Western Slope CIP and TIM Fee Update Workshop

Similar documents
WESTERN SLOPE CIP AND TIM FEE UPDATE

Community Development Agency Capital Improvement Program TIM Fee Program Cash Proforma (by Revenue Grouping)

ADMINISTRATIVE CODE BOARD OF COUNTY COMMISSIONERS

1.0 EXECUTIVE SUMMARY

Long Range Transportation Plan

BABCOCK RANCH MASTER DEVELOPMENT ORDER DRI # NOTICE OF PROPOSED CHANGE

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM

South Fulton Comprehensive Transportation Plan of Fulton County Transportation Coordinating Committee August 08, 2014

PLACER COUNTY REGIONAL TRAFFIC CONGESTION AND AIR QUALITY MITIGATION FEE PROGRAM

FEDERAL LANDS ACCESS PROGRAM

Puget Sound Gateway Program

TRAFFIC IMPACT ANALYSIS IMPLEMENTATION. Richard L. Caywood, P.E. Robert W. Hofrichter

Public Meeting #5 Summary

-Recitals- - Signatures on following pages - Revised Exhibit 1 Rev MOU June 5, TEU Page 1 of 44

DRAFT Subject to modifications

NAPA COUNTY BOARD OF SUPERVISORS Board Agenda Letter

City of Lynwood MODIFIED REQUEST FOR PROPOSALS FOR

STAFF REPORT. MEETING DATE: August 21, 2008 AGENDA ITEM: 9

RESOLUTION NO. 18-XX RESOLUTION AUTHORIZING THE EXECUTIVE DIRECTOR TO EXECUTE COOPERATIVE AGREEMENT NO WITH THE CALIFORNIA DEPARTMENT OF

REQUEST FOR PROPOSALS

City Council Study Session Retail Market Analysis

Agenda. 6:00 p.m. - 6:45 p.m. - Registration & Open House. 6:45 p.m. - 6:55 p.m. - Welcome & Opening Remarks

Invitation letters were ed to 44 members of the PAG on June 23, Reminder invites were ed to PAG members on July 18, 2017.

Table of Contents. Page 2

AGENDA Rural Transportation Advisory Committee Tuesday, September 20 th, :00 p.m. Water Street Center, 401 East Water Street, Charlottesville

A RESOLUTION ADOPTING THE LADY S ISLAND CORRIDOR STUDY

Traffic Impact Analysis (TIA) POLICY

REQUEST FOR CITY COUNCIL ACTION

A. 3. Identify whether the proposed development is located in a designated special hurricane preparedness district.

EL DORADO HILLS COMMUNITY SERVICES DISTRICT

A DEFINITIONS AND ACRONYMS

Florida Statewide Regional Evacuation Study Program. Regional Evacuation Transportation Analysis

DIRECTOR S REPORT TRANSPORTATION BOARD SEPTEMBER 10, 2018

Order of Business. D. Approval of the Statement of Proceedings/Minutes for the meeting of January 24, 2018.

ITEM 11 Information July 20, Strategic Plan for the Development of the TPB Travel Demand Model

CFLHD Organizational and Program Overview FEDERAL LAND ACCESS PROGRAM (FLAP) 55 th ACE Annual Conference

TITLE: 2017 Comprehensive Plan Sub-Area Plan for the Old Fort Lake Business and Technology Park. (File No. COMP-16-04) BUDGET IMPACT: Yes No

US 50/SOUTH SHORE COMMUNITY REVITALIZATION PROJECT

VTP Highway Program. Semi-Annual Report April 2013

City of Culver City. Staff Report

COUNTY OF SACRAMENTO CALIFORNIA

A. Amend the FY LACMTA Budget to add $3,000,000 from Measure R 3% Commuter Rail funds for the Rancho Vista Grade Separation Project

Coolidge - Florence Regional Transportation Plan

Genoa Township Area Road and Bridge Projects

NATIONAL CAPITAL REGION TRANSPORTATION PLANNING BOARD 777 North Capitol Street, N.E. Washington, D.C

Travel Times. Newsletter of the Pasadena Department of Transportation

Agenda Item D.2 PRESENTATION Meeting Date: June 17, 2014

H I G H WAY D I G I TA L S IGNS L AND D E V E L O M P E N T C O D E A M E N D M E N T A DDENDUM

Corridor Advisory Committee Meeting #52. February 16, :00 PM - 8:00 PM Progress Park Downey Ave, Paramount, CA MEETING SUMMARY

REQUEST FOR PROPOSAL FOR PARKING CONSULTANT TO THE LIBERTY STATION COMMUNITY ASSOCIATION SEPTEMBER 26 TH, 2017

Fairfax County FY 2019 Advertised Budget The 2018 Economic Outlook Summit April 12, 2018 w w w. f a i r f a x c o u n t y. g o v / b u d g e t

CITY OF ELK GROVE CITY COUNCIL STAFF REPORT

PINELLAS COUNTY DEO#12-1ESR

COUNTY OF SACRAMENTO CALIFORNIA

Nassau County 2030 Comprehensive Plan. Public School Facilities Element (PSF) Goals, Objectives and Policies. Goal

Welcome back. Welcome to our second public exhibition for Cheshunt Lakeside. We are now presenting our updated and more detailed proposals.

Transport NI York Street Interchange APPENDIX A PROJECT BRIEF

Economic Development Element of the Arroyo Grande General Plan. Prepared by the City of Arroyo Grande Community Development Department

The Atlanta Region s Plan RTP/ FY TIP Amendment #4. Transportation Coordinating Committee January 5, 2018

LAKE~SUMTER MPO 2035 TRANSPORTATION PLAN & LAND USE WORKSHOP

Board of Supervisors' Agenda Items

KANSAS CITY REGIONAL TIGER PROJECT PMOC PROGESS REPORT 2014 Fiscal Quarter 1 October 1 December 31, 2013

I-66 Inside the Beltway Initial Traffic Analysis and Framework Agreement

APPENDIX I LADOT Traffic Assessment

Report No. D July 25, Guam Medical Plans Do Not Ensure Active Duty Family Members Will Have Adequate Access To Dental Care

Transit Operations Funding Sources

Overall Work Program, Budget, and Goals and Objectives

TRANSPORTATION AD HOC COMMITTEE

REPORT. To the Honorable Mayor and City Council From the City Manager. May 9, 2016

INSTITUTE OF TRANSPORTATION ENGINEERS

CRENSHAW/LAX PILOT BUSINESS SOLUTION CENTER (BSC} and METRO'S PILOT BUSINESS INTERRUPTION FUND (BIF} MONTHLY REPORT

ORTEGA HIGHWAY: UNNECESSARY DELAYS HAVE COST US MILLIONS

Hurricane Evacuation Clearance Workshop Meeting 3 April 30, 2012 Minutes 10am 6:00pm

City of Norwood Young America

SOUTHWEST LRT (METRO GREEN LINE EXTENSION)

Planning Phase (Route Study and Pond Siting Analysis & Report) Determines Preferred Alignment Public Workshop and Board Approval Required Completion:

3. Award and execute contract modifications for up to $1,200,000.

ATTACHMENT A PDA PLANNING GRANT PROGRAM Information and Evaluation Criteria

Local Taxes and Highway Tolls: The New Normal

2018 Regional Transportation Improvement Program

The Council entered into an executive session at 5:10 p.m. Motion to adjourn R Eck, second D Johnson

Human Resources Policies Traffic Control. Category: Health and Safety Sub-Category: General Policy Statement

Nevada Department of Transportation Traffic Operations Policy Memorandum Traffic Signal Warrant Approval Process

Exhibit B. Plumas County Non-Motorized Transportation Plan SCOPE OF WORK

INTRODUCTION. RTPO Model Program Guide February 27, 2007 Page 1

Logan Square Corridor Development Initiative Final Report Appendix

Eastside Transit Corridor Phase 2 Draft EIS/EIR Public Hearings

Sponsorship Opportunities Events

Public-Private Partnerships for Transportation

AMENDMENT TO CODIFIED ORDINANCES OF THE CITY OF NEGAUNEE, CHAPTERS 1260, 1271, 1272, 1273, AND 1285 REPEALER

Lake Norman Regional Transportation Commission AGENDA March 8, 2017

Highway 156 Improvement Project Ad Hoc Committee

APPENDIX 5. Funding Plan

REQUEST FOR PROPOSALS

MARATHON COUNTY ENVIRONMENTAL IMPACT FUND

Dulles Corridor Metrorail Project

Public-Private Partnership Program May 2015 Transit Coalition Update

INDIAN RIVER COUNTY METROPOLITAN PLANNING ORGANIZATION

REQUEST FOR PROPOSAL TO PROVIDE AS-NEEDED ENGINEERING SERVICES FOR THE IMPLEMENTATION OF

BUDGETING WITH AN EYE ON

Transcription:

Western Slope CIP and TIM Fee Update Workshop Board of Supervisors Study Session May 5, 2015 14-0245 8K 1 of 39

Agenda 1. Brief Background 2. Receive and file: Traffic Analysis Methodology 3. BOS Direction: TIM Fee Zone Geography Options 4. BOS Discussion: Land Use Categories 5. Receive and file: Existing and Future Deficiency Analysis 6. BOS Direction: Land Use Scenario (General Plan vs. TGPA-ZOU) 7. Receive and file: Alternative Funding 8. Receive and file: Summary of Public Outreach Phase One 14-0245 8K 2 of 39

Last BOS TIM Fee Study Session Confirmed the project purpose and goals Confirmed the baseline assumptions Confirmed the four (4) TIM Fee Zone Geography options presented are appropriate for further analysis Confirmed the approach to public outreach Confirmed the project schedule 14-0245 8K 3 of 39

Work Completed Since BOS TIM Fee Study Session Developed Traffic Analysis Methodology (Memo 2-1) Completed Review of Mitigation Fee Act Best Practices (Memo 3-1) TIM Fee Zone Geography (Processing for GP and TGPA)(Memo 2-2) Existing and Future Roadway Deficiency Analysis (GP and TGPA) (Memo 2-3) Developed Outreach Tools (branding, website, web-based tools, Focus Group rosters, contact lists, e-blast lists) Completed 1 st Round of Public Outreach (5 Focus Group Workshops, 2 Public Workshops and continuous Virtual Webbased Workshop materials) 14-0245 8K 4 of 39

Traffic Analysis Methodology Describes TIM Fee Analysis Framework Data Data Sources Analysis Methodology Analysis Tools/Software Assumptions Level of Service Criteria (Measure of Effectiveness) Consistent with General Plan Policy TC-Xd Consistent with Measure Y 14-0245 8K 5 of 39

Traffic Analysis Methodology Annual Average Weekday Conditions (Tues-Thurs during Spring or Fall) Published Volumes by Caltrans and US 50 PeMs Data Traffic Counts on County roadways Interregional traffic on US 50 50% weekdays 70% weekends/pk season 14-0245 8K 6 of 39

Traffic Analysis Methodology Operational Methods Highway Capacity Manual 2010 State Highways (US 50, SR 49, SR 193) Green Valley Road Peak Hour Planning Methods Highway Capacity Manual 2010 Local County Roadways Green Valley Road Technical Memorandum 2-1 Posted on Project Website 14-0245 8K 7 of 39

TIM Fee Benefit Zone Geography Options Examine Alternative Fee Geographies Proposed Options for BOS Consideration: Existing 8-Zone Structure 8-Zone Structure Smoothed 5-Zone Structure based on Population 4-Zone Structure based on combining zones with similar fees Technical Memorandum 2-2 Posted on Project Website 14-0245 8K 8 of 39

Option 1 Existing 8-Zone Structure TIM Fee Benefit Zone Geography Options Option 1 Existing 8-Zone Structure 14-0245 8K 9 of 39

Option 2 Existing 8-Zone Structure Smoothed TIM Fee Benefit Zone Geography Options Option 2 8-Zone Structure Smoothed 14-0245 8K 10 of 39

Option 3 5 Zone Structure Population Equivalency TIM Fee Benefit Zone Geography Options Option 3 5-Zone Structure Population Equivalency 14-0245 8K 11 of 39

Option 4 4-Zone Structure Fee Equivalency TIM Fee Benefit Zone Geography Options Option 4 4-Zone Structure Fee Equivalency 14-0245 8K 12 of 39

TIM Fee Benefit Zone Geography Options BOS Action: Final confirmation to move forward with the four (4) TIM Fee Zone geography options for further analysis. 14-0245 8K 13 of 39

Land Use Categories: Residential Current Single Family Multi-family Age-restricted Single Family Age-restricted Multi-Family Proposed (no changes) Single Family Multi-family Age-restricted Single Family Age-restricted Multi-Family 14-0245 8K 14 of 39

Land Use Categories: Nonresidential Current High Trip Commercial General Commercial Gas Station Office Industrial Warehouse Church Golf Course Campground Bed & Breakfast (None) Proposed Retail / Commercial Office Industrial / Warehouse Church (Delete) (Delete) Hotel / Motel Per Trip Fee 14-0245 8K 15 of 39

Land Use Categories: Proposed Residential Single Family Multi-family Age-restricted Single Family Age-restricted Multi-Family Nonresidential Retail / Commercial Hotel / Motel Church Office Industrial / Warehouse Per Trip Fee BOS Action: Provide Input 14-0245 8K 16 of 39

Existing & Future Deficiency Analysis Based on the Traffic Analysis Methodology Existing Condition LOS Analysis based on: Caltrans PeMs Data for portions of US 50 (2014) Caltrans Published Volumes on State Highways (2014) County Traffic Counts for County Roadways (2013-15) All counts reflect average weekday AM and PM peak hour conditions during non-peak seasons 14-0245 8K 17 of 39

Existing & Future Deficiency Analysis The Travel Demand Model was updated to a 2015 Baseline year by: Updating land use based on constructed & occupied building permits issued between 2010 & 2015 Updating roadway network with facilities constructed or in construction by 1/1/15 Two future Land Use Scenarios: 2035 General Plan Land Use Scenario 2035 Targeted General Plan and Zoning Ordinance Update (TGPA-ZOU) Land Use Scenario 14-0245 8K 18 of 39

Existing & Future Deficiency Analysis Travel Model Forecasts Unique to TIM Fee due to: Updated 2015 Baseline Land Use Application of 2015 Network for 2035 Forecast (No Build) Updated Traffic Counts and focus on Average Weekday Traffic Caltrans US 50 TCR/CSMP Forecasts Different Baseline Volumes Different Model (based on SACOG Model Forecasts) Prior GP and TGPA-ZOU Forecasts 2010 Baseline Did Not Include Different Roadway Network Assumptions Outside of EDC Did Not Include CIP Projects initiated and completed between 2010-2015 14-0245 8K 19 of 39

Existing & Future Deficiency Analysis Identification of Deficient Roadways County Adopted LOS Standards State Highways (US 50, SR 49, SR 193): Spanning 60 segments County Roadways: 57 County Roadways spanning 150 segments Identification of Deficient Interchanges Relied on more detailed operational studies Compared peak hour model volumes to previous forecasts by predecessor model for confirmation 14-0245 8K 20 of 39

Existing & Future Deficiency Analysis Facility Type Baseline Roadway 2035 General Plan Roadway 2035 TGPA-ZOU Roadway State Highways None 1. US 50 (El Dorado/ Sacramento County Line to Latrobe Road) 2. US 50 (Latrobe Road to Bass Lake Road) 3. US 50 (Bass Lake Road to Cambridge Road) 1. US 50 (El Dorado/ Sacramento County Line to Latrobe Road) 2. US 50 (Latrobe Road to Bass Lake Road) 3. US 50 (Bass Lake Road to Cambridge Road) Total: 0 segment Total: 3 segments Total: 3 segments Local Roads 1. Green Valley Road (west of Sophia Parkway) 1. Cameron Park Drive (south of Hacienda Drive) 2. Green Valley Road (west of Sophia Parkway) 3. Green Valley Road (west of Lotus Road) 4. Latrobe Road (north of Golden Foothill Parkway) 5. White Rock Road (west of Windfield Way) 6. White Lock Road (at El Dorado/Sacramento County Line) 1. Cameron Park Drive (south of Hacienda Drive) 2. Green Valley Road (west of Sophia Parkway) 3. Green Valley Road (west of Lotus Road) 4. Latrobe Road (north of Golden Foothill Parkway) 5. Missouri Flat Road (south of China Garden Road) 6. White Rock Road (west of Windfield Way) 7. White Rock Road (at El Dorado/Sacramento County Line) Total: 1 segment Total: 6 segments Total: 7 segments 14-0245 8K 21 of 39

Existing & Future Deficiency Analysis US 50 Interchanges (7) El Dorado Hills Boulevard Interchange Silva Valley Parkway Interchange (by virtue of deficiencies at both El Dorado Hills and Bass Lake Road interchanges Bass Lake Road Interchange Cambridge Road Interchange Cameron Park Drive Interchange Ponderosa Road Interchange El Dorado Road Interchange 14-0245 8K 22 of 39

Existing & Future Deficiency Analysis Next Steps Identify Needed Improvements to Remedy Deficiency Explore parallel capacity facilities Identify Logical Project Limits Update Per Unit Infrastructure Cost Estimates Develop improvement cost estimates Perform Fair Share modeling analysis of deficient roadway and interchange facilities Determine Fair Share costs to new development Technical Memorandum 2-3 Posted on Website 14-0245 8K 23 of 39

2035 Land Use Scenario Options Options: 1. Continue both GP & TGPA-ZOU Scenarios Requires contract amendment & minor schedule delay 2. Continue with only the 2035 GP Scenario Staff Recommendation 3. Stop work until BOS has made a determination on the TGPA-ZOU 4. Continue with only the TGPA-ZOU Scenario 14-0245 8K 24 of 39

Alternative Funding CIP History FY2004-2014 Total = $448,000,000 $111,000,000 25% CIP Projects Without TIM Fee Funding CIP Projects With TIM Fee Funding $337,000,000 75% 14-0245 8K 25 of 39

Alternative Funding CIP History TIM Fee Projects Only Total = $337,000,000 $94,000,000 $25,000,000 7% Other Local State & Federal Funding TIM Fee Funding $218,000,000 65% 14-0245 8K 26 of 39

West Slope Transportation CIP FY 2004 14: Top 10 TIM Fee Projects U.S. 50/Missouri Flat Rd. Interchange Improvements U.S. 50/Silva Valley Parkway Interchange U.S. 50 HOV Lane: El Dorado Hills to Bass Lake Grade Latrobe Rd. Widening Green Valley Rd. Widening U.S. 50/El Dorado Hills Blvd. Interchange El Dorado Hills Reimbursement White Rock Rd. Realignment & Widening White Rock Rd. Widening Bass Lake Rd. Realignment 14-0245 8K 27 of 39

Public Outreach Summary Multi-level approach and branding to maximize participation. Focus Groups to explore topic specific concerns. Web-based communications to ensure access and availability of data. Traditional workshops in multiple locations. Multiple Board presentations and study sessions. Summary reports documenting participation and comments. 14-0245 8K 28 of 39

Public Outreach Process 14-0245 8K 29 of 39

Brand Development Project team developed a specific brand to identify the Western Slope CIP and TIM Fee effort as unique among County programs and initiatives. County staff was presented a selection of options. The Brand is used on all materials. 14-0245 8K 30 of 39

Focus Groups The outreach effort included gathering four focus groups representing diverse viewpoints in the County to discuss the proposed approach and methodology for the CIP and TIM Fee Update. Groups were: Residents Economic Interests Development Community Public Agencies Recruitment was done through enews, media relations and social media and included former TIM Fee members. 14-0245 8K 31 of 39

Focus Groups The County received 65 applications and determined that rather than exclude anyone, a second resident based focus group was formed. Focus Group sessions were held March 26 th and 27 th resulting in valuable feedback and information about concerns and potential CIP projects. Notes and comments are in your staff report. 14-0245 8K 32 of 39

Web-Based Tools The project team developed a comprehensive project website which includes: All information relevant to the project, Background documents and deliverables, Meeting and workshop information, Online comments, Virtual Workshop and Online CIP mapping tools. 14-0245 8K 33 of 39

Web-Based Tools We have documented: 2,300 Page Views 1,500 Individual sessions 663 Active users 90+ participants in our Virtual Workshop 14-0245 8K 34 of 39

enewsletters We have sent 12 enewsletters out to our database. Currently 1,400 subscribers. 38 local news agencies. All 65 Focus Group members. Averaging a 35% open rate. 14-0245 8K 35 of 39

Online Mapping Tool Our online mapping tool was launched in February. Allows user to identify current and future deficiencies. 20+ comments received thus far. 14-0245 8K 36 of 39

Public Workshops Three rounds each in two locations. First round was held April 8 th and 9 th. Combination of presentation, exhibits and click-polling Sixty-five percent of attendees strongly agreed or agreed that the workshops were useful and informative with 30% neutral and 5% that disagreed. Summary notes and results in your Staff Report 14-0245 8K 37 of 39

Next Steps Second round of Focus Groups to review proposed CIP and TIM Fee structure August 2015 enewsletters Second round of Public Workshops September 2015 Launch of second Virtual Workshop September 2015 Board presentation - October 2015 14-0245 8K 38 of 39

Recap and Requests for Direction 1. Staff provided a brief background on the Major CIP/TIM Fee Update 2. Receive and file information on the Traffic Analysis Methodology 3. Staff is Requesting Final BOS Confirmation on the TIM Fee Zone Geography Options 4. Staff is Requesting BOS Discussion and preliminary feedback on the Land Use Categories 5. Receive and file information on the Existing and Future Deficiency Analysis 6. Staff is Requesting BOS Direction on proceeding with a Land Use Scenario (General Plan vs. TGPA-ZOU) 7. Receive and file information on Alternative Funding 8. Receive and file the Summary of Public Outreach Phase One 14-0245 8K 39 of 39