REACTOR OPERATIONS AT SAFARI-1. JWH Vlok 1 Manager: Reactor Operations SAFARI-1 Research Reactor NECSA South Africa ABSTRACT

Similar documents
NATIONAL NUCLEAR REGULATOR

Functions important to nuclear power plant safety, and training and qualification of personnel

Licensing of Nuclear Installations

ASME Nuclear Conformity Assessment. Bernard E. Hrubala Sr. Vice President Code and Standards October 7, 2008

Statement of Owner Expectations NSW TAFE COMMISSION (TAFE NSW)

Certification of Persons Working at Nuclear Power Plants

NEI [Revision 0] Guidelines for a Certified Fuel Handler Training and Retraining Program

SOUTH AFRICAN NURSING COUNCIL

P O L I C Y F O R A C C R E D I T A T I O N C L I N I C A L D E P A R T M E N T S F O R T H E

CHAPTER 82 WARFARE BRANCH PHYSICAL TRAINING CONTENTS

Regional Jobs and Investment Packages

REVIEW PROCESS AND LICENSING FOR RESEARCH REACTOR DECOMMISSIONING ACTIVITIES IN ROMANIA

RECRUITMENT AND VETTING CHECKS POLICY

Background and initial problem

Anaesthesia Fellow. Position Description. Department : Department of Anaesthesia & Perioperative Medicine

Job Description. Basic Grade Pharmacy Technician

MANCOSA BURSARY FUND Information Pack 2018

IRISH AID IRISH AID IDEAS PROGRAMME: STRAND II

TIPPERARY COUNTY COUNCIL POST OF SENIOR ENTERPRISE DEVELOPMENT OFFICER QUALIFICATIONS

STATUTORY INSTRUMENTS SUPPLEMENT No th June, 2016 STATUTORY INSTRUMENTS SUPPLEMENT

KENYATTA NATIONAL HOSPITAL VACANCIES EXTERNAL ADVERTISEMENT

Call for Submission of Proposals

DIRECTIVES. COUNCIL DIRECTIVE 2009/71/EURATOM of 25 June 2009 establishing a Community framework for the nuclear safety of nuclear installations

PROGRAMME SPECIFICATION(POSTGRADUATE) 1. INTENDED AWARD 2. Award 3. Title 28-APR NOV-17 4

Revalidation Annual Report

Overview of the Regulatory Framework for the Safety of Nuclear Power Plants in Romania

Request for Proposals (RFP)

CHAPTER 4 : VALUE SYSTEM AND VALUE CHAIN OVERVIEW 4.1 THE VALUE SYSTEM FOR SOUTH AFRICAN NATIONAL DEFENCE

Qualification details

WORKPLACE LEARNING PROCEDURES AND STANDARDS

PLANNING AND PROGRESS FOR DECOMMISSIONING OF HEAVY WATER RESEARCH REACTOR

International Research Fee Scholarships for China (UWA China Scholarships) * [F19680]

ES-301 Administrative Topics Outline Form ES-301-1

EXTRAORDINARY PUBLISHED BY AUTHORITY. ISLAMABAD, THURSDAY, March 1, 2012

OVERSEAS TERRITORIES AVIATION REQUIREMENTS (OTARs)

Generating cash from Irish R&D activities

LEGISLATIVE ACTS AND OTHER INSTRUMENTS COUNCIL DIRECTIVE establishing a Community framework for the nuclear safety of nuclear installations

Australian Medical Council Limited

Report on SAPC HOPS Meeting 5 April The SAPC met with Heads of Pharmaceutical Services from both the public and private sectors.

Our community nursing roles

Version 1, March 2015

Good Practice Principles:

Page 1 of 5 SOUTH AFRICAN QUALIFICATIONS AUTHORITY REGISTERED QUALIFICATION: National Certificate: Medical Equipment Maintenance

Technical Meeting on the International Project on Decommissioning of Small Facilities

BY-LAWS. Current Revision Amended on February per Resolution R50-62 through R50-68

Request for Proposals and Specifications for a Community Solar Project

Discretionary Grants: Call for Applications for Non-Governmental Organisation (NGOs) to upskill their employees in short skills programmes

Financial information 2016 $

The Characteristics of an Effective Nuclear Regulator

POSITION PROFILE: 1801 HEALTH CENTRE MANAGER

Quality and Patient Safety, Project Manager Children s Hospital Group. Job Specification and Terms & Conditions. Quality and Safety, Project Manager

Procedures and criteria relating to delegation of authority

Subject: Appointment to the post of Mission Director of AUSC project on Contractual basis

North West Universities: NMP collaboration

Job Description. Biochemistry Laboratory Temple Street Children s University Hospital Temple Street Dublin 1.

Specialised Commissioning Oversight Group. Terms of Reference

The Green Initiative Fund

Employee Assistance Professionals Association of South Africa: an Association for Professionals in the field of Employee Assistance Programmes

Incentive Guidelines Knowledge Transfer

Memorandum of Understanding. between. The General Teaching Council for Scotland. and. The Scottish Social Services Council

Powering Our Communities. Grant Guidelines

The Code of Conduct on the Safety of Research Reactors

Life Extension of Nuclear Power Plants

Health Research Cluster Tactical Research Project Applications Guidelines for Applicants

Workforce Development Fund

Northeast Power Coordinating Council, Inc. Regional Standards Process Manual (RSPM)

The Assistant Director-General for External Relations and Cooperation

LEEUW MINING AND EXPLORATION (PTY) LIMITED VAALKRANTZ COLLIERY ( LME ) Outline of University of Technology Bursary Scheme

Guidance Notes NIHR Clinical Trials Fellowship Round 6 June 2017

Programme Specification ( ): PG Diploma in Mental Health

BRIEFING TO THE PORTFOLIO COMMITTEE ON POLICE SAPS Basic Training Learning Programme SOUTH AFRICAN POLICE SERVICE

MISSION REPORT ON THE INTEGRATED NUCLEAR INFRASTRUCTURE REVIEW (INIR)

The Organization requires the services of qualified individuals in its Cape Town Regional Office for the following lnternship programme:-

Rural and remote ultrasound scholarship 2018 APPLICATION PACK

National VET Data Policy

QCF. Health and Social Care. Centre Handbook. Level 2 Certificate in Dementia Care Level 3 Certificate in Dementia Care Scheme codes 05920, 05922

CLOSING DATE: 13 th December 2013

Towards Quality Care for Patients. National Core Standards for Health Establishments in South Africa Abridged version

Attention: Suncorp Solar Potential Investors and Shareholders SMALL IPP PROGRAM SOUTH AFRICA RENEWABLE ENERGY MARKET

Health and Safety Policy

Registered Manager. To be responsible for shaping and delivering the residential home s Statement of Purpose and managing a team to achieve the same.

Ministry of Social Affairs and Health, Finland N.B. Unofficial translation. Legally binding only in Finnish and Swedish. No.

PNG. Civil Aviation Rules. Part 129. Foreign Air Operator Certification

Asbestos identification, risk assessment approaches, asbestos register and asbestos management plan

Qualifications and Apprenticeships

CORK COUNTY COUNCIL SANITARY CARETAKER GRADE 5 WATER SERVICES ZONE 3 (SOUTH EAST)

NHS Governance Clinical Governance General Medical Council

Career Information. Switchboard: Bernicia House Goldcrest Way Newburn Riverside NEWCASTLE 1 UPON TYNE NE15 8NY

1-E. HSE HR Circular 013/2006. Re: Roman Catholic Hospital Chaplains

ICO International Guidelines for Accreditation of Ophthalmology Training Programs

Guidance to Workplace Experience Level 4 Diploma in Therapeutic Counselling (TC-L4)

School of Law Graduate Scholarship

3.3 Facilitate sharing and understanding of: Key nuclear environment, radiological, industrial, safety, health, security, safeguards

Careers. Aviation Training Academy ATS Instructors Engineering Instructors Simulator Support Officers Course Administrators Instructional Designers

Employer Guidance for 2016 GAP Grant

National Policing Improvement Agency Circular

IRDG R&D Tax Credit Clinic. 19 th January 2016 Radisson Blu, Dublin Airport

Request for Proposals (RFP) The provision of transport law specialist services for subsidised public transport contracts for the CSIR

WIB incentivize faculty to join these discussion so to educate industry on the needs (e.g., Videotape or live feed for broader access shared online

New Zealand Scholarship Conditions

Transcription:

REACTOR OPERATIONS AT SAFARI-1 JWH Vlok 1 Manager: Reactor Operations SAFARI-1 Research Reactor NECSA South Africa ABSTRACT A vigorous commercial programme of isotope production and other radiation services has been followed by the SAFARI-1 research reactor over the past ten years superimposed on the original purpose of the reactor to provide a basic tool for nuclear research, development and education to the country at an institutional level. A combination of the binding nature of the resulting contractual obligations and tighter regulatory control has demanded an equally vigorous programme of upgrading, replacement and renovation of many systems in order to improve the safety and reliability of the reactor. Not least among these changes is the more effective training and deployment of operations personnel that has been necessitated as the operational demands on the reactor evolved from five days per week to twenty four hours per day, seven days per week, with more than 300 days per year at full power. This paper briefly sketches the operational history of SAFARI-1 and then focuses on the training and structuring currently in place to meet the operational needs. There is a detailed step-by-step look at the operator s career plan and pre-defined milestones. Shift work, especially the shift cycle, has a negative influence on the operator s career path development, especially due to his unavailability for training. Methods utilised to minimise this influence are presented. The increase of responsibilities regarding the operation of the reactor, ancillaries and experimental facilities as the operator progresses with his career are discussed. 1 Presenter & Author: JWH Vlok South African Nuclear Energy Corporation (NECSA) PO Box 582 Pretoria 0001 South Africa Tel: +27 12 305 5390 Fax: +27 12 305 5956 E-mail: wvlok@aec.co.za

1 Introduction SAFARI-1 is an MTR type tank-in-pool research reactor with a licensed operating power of 20 MW and is located at Pelindaba, Pretoria, South Africa. The reactor is a major producer of medical and industrial isotopes for both domestic and international consumption, the production of which is organized on a commercial and contractual basis. The reactor has been operational for ~37 years and has been affected in this time, as many research reactors have, by extreme swings in reasons and purpose for its existence, outdated or obsolete technology, aging of components and personnel, politics, changing public and regulatory demands regarding safety and risk of operation and numerous other factors of varying impact. 2 Reactor History. Figure 1 depicts the power history of the reactor from 1965 to date. The SAFARI-1 reactor project was first initiated in September 1960 and construction started in 1961. The reactor was commissioned in March 1965. Initially the secondary cooling capacity was 6.75MW and the reactor was operated as such. During 1968, significant upgrades were made to the reactor secondary circuit, allowing the maximum reactor power to be increased to 20MW. In 1976 an embargo was placed on the supply of fuel to SAFARI-1. The operating power was reduced to 5MW and the operating hours greatly curtailed (at one stage four days every week) in order to conserve fuel stocks while a local enrichment and fuel manufacture capability was developed. In 1981 the first locally produced fuel assemblies became available and the reactor was operated for five days a week at 5MW until 1993. In 1993 the focus of SAFARI-1 operations was shifted to commercial applications. The nominal power level was increased initially to 10MW with gradually more frequent operation at 20MW for the development and implementation of commercial programmes. During the first half of 1988, the reactor was shut down for 6 months to repair a pool leak. The reactor is currently operated at the minimum power level required to meet commercial requirements, at an annual average of 17.8MW. It is worthwhile to note that the reactor reached its 1 st million MWH in December 1994 after 29 years of operation. The 2 nd million MWH milestone will probably be reached late in the third quarter this year (2003) after only 9 further years of operation. The reactor is currently run with availability approaching 90%. QUARTERLY (MWh) SAFARI-1 POWER HISTORY 40000 35000 30000 25000 20000 15000 10000 5000 0 6566676869707172737475767778798081828384858687888990919293949596979899000102 YEAR Quarterly Cumulative 2000000 1800000 1600000 1400000 1200000 1000000 800000 600000 400000 200000 0 CUMULATIVE (MWh) Figure 1: SAFARI-1 Power History. 3 Training and career path To operate the facility reliably for more than 300 days per year requires a well-trained and dedicated operations team. Specialised training staff, consisting of two members, does all training of Reactor Operations (RO) personnel in-house. One member is a dedicated to the theoretical subjects and the

other, who is a licensed operator, is dedicated to the practical training on the plant and experimental facilities. A certain degree of training is also received on shift and is mostly coordinated by the shift supervisor. All training in the facility is done under the control of the Reactor Training Committee. Shift work has some negative effects on the availability of personnel for training and special provisions are in place to minimise this effect. Trainees receive practical training worksheets that must be completed while on normal shift duty. The trainee may not partake in any examinations before these worksheets are completed. The shift roster itself is set up in such a way that it allows four days of the cycle for training purposes. If training does not require all this time, the personnel are utilised to do specific low-frequency maintenance tasks. 3.1 Reactor Training Committee A Reactor Training Committee (RTC) was established with the primary responsibility of participating in the assessment of the training, development and evaluation of personnel and to oversee the effective training and re-training of SAFARI-1 reactor operators and other personnel. The RTC has set a pass-mark of 70% on all theoretical examinations and 80% on practical or panel examinations. A diploma, endorsed by the Manager: SAFARI-1 Research Reactor is issued to all levels of RO personnel upon obtaining a specific licence or qualification. The RTC may withdraw a candidate's certificate of qualification if he is guilty of any misconduct, negligence, or the wilful violation of any operating procedure or licence condition. The RTC may specify conditions that the candidate must fulfil before his certificate can be re-instated (e.g. retraining, re-examination, etc.). The expected conditions of achievement with respect to required standards of examination are issued in a training manual made available to each shift worker. The requirements of these training programmes are assessed and approved by the local National Nuclear Regulator. 3.2 Staff Selection and Career Path RO staff is appointed from the available workforce after extensive psychometric testing and interviews. All training is presented in-house and no university or college qualification is required. The career of the operator is subdivided into the following well-defined steps: - Learner reactor operator - Plant operator - Licensed reactor operator - Senior licensed operator - Shift leader - Probational shift supervisor - Shift supervisor - Assistant head RO - RO Manager are trained in a chain of progression through the various steps, each step being a prerequisite of the following. 3.2.1 Learner Reactor Operator To be appointed, the candidate must comply with a minimum requirement of a secondary school certificate or equivalent with appropriate symbols in Science and Mathematics, unless otherwise recommended by the RTC. A learner reactor operator is appointed on a contract basis for the first 9 months of training. The learner has no defined plant related responsibilities other than to study. He may however perform selective tasks under direct supervision in order to gain experience. 3.2.2 Plant Operator To qualify as plant operator, the learner reactor operator must acquaint himself with 28 subjects that are further sub-divided into 75 modules. Most of these are written examination subjects and include all reactor processes and experimental facilities. On successful completion of the theoretical training, the candidate receives a financial recognition for his effort. The increment received is based on the aggregate of the theoretical subjects and is applied as follows: Aggregate in the range 70-80% 7% increase Aggregate in the range 80-90% 10% increase Aggregate in the range 90-100% 12% increase After completion of the theoretical training the candidate is subjected to a period of not more than 15 months practical training. During this time (when the candidate is ready), core members of the RTC

verbally examine the candidate during a physical walk-through of the plant. On successful completion of this examination, the candidate is appointed as a plant operator with the responsibility of operating / manipulating all plant related equipment and selective experimental facilities. The larger and more complicated experimental facilities are still operated under supervision. The average time to qualify as a plant operator is 12 months. On obtaining the plant operators qualification, the candidate is again rewarded financially as described before. In addition to the financial incentive, he is promoted to the next post level. 3.2.3 Licensed Reactor Operator The qualified plant operator undergoes a further period of not less than six months and not more than nine months, theoretical and practical training covering eight subjects in 47 modules. After completion of the required theoretical examinations, core members of the RTC verbally examine the candidate during a panel examination, to satisfy themselves that the candidate possesses the required knowledge and also essential understanding of the subjects. After successful completion of the theoretical and practical training, the candidate must execute a reactor start-up examination to prove his ability in the control room. When successful, the candidate is appointed as a Licensed Reactor Operator, with the added responsibility of manning the control room and performing the necessary manipulations. At this level, most tasks can be performed without supervision, if the operating procedure of the facility does not specify otherwise. The licensed operator must supervise the Learner- and Plant when performing tasks as a team. On obtaining an operating license, the candidate is again rewarded financially as described before. In addition to the financial incentive, he is promoted to the next post level. All operators in SAFARI-1 must be fully licensed operators as no allowance is made for dedicated reactor operators or experimental operators, only all-rounders. Therefore, a maximum limit of 9 months is placed on the obtaining of an operating license, after obtaining plant operator status. Should an operator not be able to obtain an operating licence in this period, his career is re-evaluated by the RTC and he may be reallocated to another department. 3.2.4 Senior Licensed Reactor Operator A licensed reactor operator may, after gaining experience for a minimum period of two years, take part in the senior training programme. In this programme, 13 subjects are covered in 37 modules. After successful completion, the candidate may be appointed as Senior Licensed Operator. The senior operator may act as shift leader, should the shift leader not be present. On completion of this phase, the operator is promoted to the next post level with financial recognition as previously described. 3.2.5 This level is a special level applicable to candidates who have been identified by the RTC as potential trainees for the position of shift supervisor. To qualify as a shift leader, the senior licensed operator must have at least two years experience as a senior reactor operator. In addition to this, he must pass an entrance examination established by the RTC in the form of a panel examination that will test the candidates knowledge on the process plant and reactor operations, in readiness for further training as a Shift. After qualification, the shift leader has the added responsibility to arrange the day-to-day running of his shift on behalf of the supervisor. This gives him the exposure required to broaden his thinking and develop planning abilities. On completion of this phase, the operator is promoted to the next post level with financial recognition as previously described. 3.2.6 Probational Shift (PSS) Although the teaching of theoretical subjects commences after completion of senior training, training as a PSS will generally only commence if a vacancy exists. At the discretion of the RTC, a licence may be granted without the existence of a vacancy, for selective purposes. To qualify for the final PSS examination, the shift leader must pass an entrance examination in the form of a panel and/or a theoretical examination with a minimum pass mark of 80%. The candidate must also complete additional theoretical courses and have at least three years experience as a shift leader or senior reactor operator

After successful completion of the written final examination, he undergoes a stringent panel examination in which an assessment of the trainee's knowledge on the full plant will be made. Special attention is given to the candidates in-depth knowledge and understanding of the plant. After qualification, the PSS may act as supervisor on his own or another shift, when a shift supervisor is not present. The PSS is also promoted to the next post level and receives financial recognition as previously described. 3.2.7 Shift (SS) Appointment as a SS can generally only be made if a vacancy exists. Six months experience, as a PSS, is required before a candidate can be considered for promotion. The RTC will assess the candidate and make a final recommendation to line management regarding an appointment as shift supervisor. Upon appointment the SS is promoted to the next post level and receives an increment in salary. The shift supervisor is responsible, directly to the RO Manager, for the safe and effective operation of the facility in accordance with set targets and within the scope of the licence. All work carried out on the reactor or ancillaries may only be performed after obtaining permission, in the form of a works permit, from the SS and only after he has evaluated the influence a task may have on the rest of the plant and facilities. 4 Re-training In order to maintain the high levels of competence, all RO personnel are subject to a continuous retraining and qualification programme. To enforce this programme, all RO licenses issued by the RTC are valid for a maximum period of two years. All RO personnel are required to be re-examined and relicensed before their licenses expire. During this two-year period, practical worksheets have to be completed in order to gain admittance to a panel examination. Should an operator fail to obtain a licence during re-examination, his level of authorisation is reduced to the next lower level. A second attempt is allowed within one month. If unsuccessful, his licence is withdrawn and he must repeat the appropriate training programme to regain his qualification. If he continues to be unsuccessful, the operator may ultimately be reallocated to another department through formal disciplinary steps. 5 Shift Structure The RO department consists of one manager, an assistant head and 30 other members. Details of the structure of the department are given in figure 2. Manager: Reactor Operations Assistant Head Hot Cell Operations Technician Operational Assistant Decontamination Workers Shift A Shift B Shift C Shift D Shift E Figure 2: RO Organisational Structure Each shift consists of a, Shift Senior, and three other members ranging from Senior Licensed to Learner operators. One member of each shift is a qualified Radiation Protection Monitor, who is authorised to monitor small radiological tasks as required from time to time.

6 Shift Cycle The RO personnel are allocated on a five-shift system with a shift cycle of 35 days, ensuring continuous manning. The shift cycle is graphically displayed in figure 3. A normal shift is 8.5 hours long, and is from 06:45 to 15:15 (dayshift); 14:45 to 23:15 (afternoon shift); 22:45 to 07:15. The 30-minute overlap of shifts allows time for shift changeover to ensure a seamless transition. Week 1 Week 2 Week 3 Week 4 Week 5 DAY AFTERNOON OFF NIGHT TRAIN OFF Denotes weekends Figure 3: SAFARI-1 Shift Cycle The longer periods on a specific shift are found to allow more physical stability, giving personnel a day or two to adjust to the new hours after every shift change. The shift selections are made to specifically balance shift abilities and to manage personality incompatibilities. 7 Conclusion The efforts put into the training of reactor operations personnel has been shown to have a positive contribution to the efficient operation of SAFARI-1. Operator training is done in-house at a high standard. All theoretical examinations and practical tests have high pass requirements and all efforts of the students are recognised financially. The unique shift structure allows continuous retraining as well as greater stability and flexibility. The multitasking of personnel results in increased personnel economy. SAFARI-1 has regularly demonstrated its success in the dual role of providing reliable services as a national asset to South Africa, at the same time, providing neutrons for the backbone of a very successful commercial enterprise. This has been achieved by careful evaluation of operational needs and the implementation of supportive development of operators according to the desired technical standards.