NAVAJO - GALLUP WATER SUPPLY PROJECT QUARTERLY REPORT: APRIL JUNE, 2014

Similar documents
NAVAJO - GALLUP WATER SUPPLY PROJECT QUARTERLY REPORT: JULY -SEPTEMBER, 2014

NAVAJO - GALLUP WATER SUPPLY PROJECT QUARTERLY REPORT: OCTOBER - DECEMBER, 2014 February 11, 2015 Navajo Nation Water Management Branch

Appendix F: Native Americans

2012 Annual Tribal Self-Governance Department of the Interior and Department of Health and Human Services Conference

EXHIBIT A for RFP. Navajo Nation Environmental Protection Agency Air Quality Control/Operating Permit Program. Scope of Work

Navajo Nation Integrated Justice Information Sharing Project

ARRA Overview. ATTWG Symposium Anchorage, AK April 7, 2009

Annual Performance Report

FAQs on DELEP Governance and the National Estuary Program (NEP) March 2017

Colorado Revised Statute, Part 5 of Article 37.5 of Title 24. STATEMENT OF MUTUAL INTERESTS, BENEFITS AND CONSIDERATION

SUBJECT: May Update of Implementation Plan for Public Law

Appendix I: Native Americans

SUMMARY OF THE GROW AMERICA ACT As Submitted to Congress on April 29, 2014

Land and Water Conservation Fund: Appropriations for Other Purposes

Summary of. Overview. existing law. to coal ash. billion in FY. funding in FY 2013 FY 2014

Demonstration Projects to End Childhood Hunger 2016 Annual Report to Congress

Digital comments may be ed to

Sanitary Engineering Department Greene County, Ohio Request for Proposals

Request for Proposals

IMPLEMENTATION AN OVERVIEW OF THE ARIZONA WATER SETTLEMENTS ACT IN NEW MEXICO OF LEGAL CONSIDERATIONS

BUTTE COUNTY DEPARTMENT OF WATER AND RESOURCE CONSERVATION REQUEST FOR PROPOSALS TO

Commitment, CHDO Reservation, and Expenditure Deadline Requirements for the HOME Program. Table of Contents

VETERANS TRUST FUND NOTICE OF FUNDING ANNOUNCEMENT

FY2018 Tribal Transportation Improvement Program Presentation

REQUEST FOR PROPOSAL

STATEMENT OF PRINCIPAL REASONS FOR ADOPTION OF RULES

Presenter. Changes to Federal Programs & Single Audits (A-87, A-21, A-122, A-102, A-110, A-89, A-133 & A-50) The New OMB Uniform Guidance

STATEMENT OF COLORADO RIVER ENERGY DISTRIBUTORS ASSOCIATION Regarding S a bill to authorize the Bureau of Reclamation to provide cost sharing

SOUTHERN UTE INDIAN TRIBE REQUEST FOR PROPOSALS (RFP) FOR ENVIRONMENTAL CONSULTING SERVICES FOR

Per the requirements of ARRA, all. themselves before asking any question in order to have themselves and the question/answer shown on

45 CFR 75 Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Health and Human Services Awards

FOR REINVESTMENT ACT. NILAH DEVANEY NWRO, AWARDING OFFICIAL

DOING RESEARCH IN THE GRAND CANYON 1 MONITORING AND GRAND CANYON MONITORING AND RESEARCH CENTER US DEPARTMENT OF THE INTERIOR FLAGSTAFF, AZ

Base Year - July 01, 2016 June 30, 2017, with optional renewal at Board s sole. (520)

HOME Investment Partnerships Program

Food Safety Issues on the Jicarilla Apache Reservation

FINAL DRAFT Programmatic Agreement Among The Bureau of Land Management The Arizona State Historic Preservation Officer

Navajo Nation Partnership Quarterly Steering Committee Meeting February 26, :00-3:30 p.m. ADOT Flagstaff District Training Room

THE ARRA AND SRF QUESTIONS AND ANSWERS Volume 1 March 17, 2009

REQUEST FOR PROPOSAL FOR. Document Management System for a Tribal Governmental Organization PROPOSAL NO. FY2012/041

Alteration of Bridges

42 USC 2991b-3. NB: This unofficial compilation of the U.S. Code is current as of Jan. 4, 2012 (see

Objectives for Financial Control over Grant Programs

Subject: Financial Management Policy for Workforce Investment Act Funds

Request for Qualifications PIKE ROAD VOLUNTEER FIRE PROTECTION AUTHORITY

FTA and Tribal Transit Program Past, Present, and Future

Report to Congress on Distribution of Department of Defense Depot Maintenance Workloads for Fiscal Years 2015 through 2017

Kansas AAP, KS Conveyance Progress Report

ORDER OF PROCEEDINGS SPECIAL PERTH TOWN COUNCIL 1:00 PM, Thursday, February 27, 2014

I. INTRODUCTION AND BACKGROUND

BACKGROUND POSITION DESCRIPTION ACCOMPLISHMENTS

Southwest Minnesota Emergency Communications Board

Best Practice: Multi agency Memorandum of Understanding

Department of Defense INSTRUCTION

TEX Rail Corridor Memorandum of Agreement 1

Water Infrastructure Financing: History of EPA Appropriations

Funding Principles. Years Passed New Revenue Credit Score Multiplier >3 years 0% % % % After Jan %

State of Michigan Civil Service Commission Capitol Commons Center, P.O. Box Lansing, MI POSITION DESCRIPTION. 12. Unit

UNIFORM GUIDANCE - IMPLEMENTATION 2 CFR 200 SUMMARY. Office of Contracts and Grants December, 2014

SEPTIC MAINTENANCE PROGRAM RULES (ARTICLE 10)

United States Department of the Interior BUREAU OF INDIAN AFFAIRS Northwest Regional Office 911 NE 11th Avenue Portland, Oregon

The Border Environment Cooperation Commission

RECOMMENDATIONS TO THE SECRETARY


MEMBERS PRESENT: Dedrick Denton Chair Scott Warren Vice Chair Jerry Barnes (Pinal County) (Gila County) (Globe)

SCDOT MINORITY BUSINESS ENTERPRISE UTILIZATION PLAN

COLORADO PLATEAU COOPERATIVE ECOSYSTEM STUDIES UNIT. AMENDMENT TWO TO COOPERATIVE and JOINT VENTURE AGREEMENT. between

MEMORANDUM OF UNDERSTANDING COOPERATIVE ECOSYSTEM STUDIES UNITS NETWORK

ARIZONA ASSOCIATION OF CONSERVATION DISTRICTS STRATEGIC PLAN P age 75 Years of Locally Led Conservation

REQUIREMENTS FOR CERTIFICATION CONSTRUCTION CONTRACTING. [ ] General Contractor - Lic. # Class. [ ] Special Trades - Lic. # [ ] Subcontractor

Minority Business Enterprise and Women-Owned Business Enterprise Certification Program (Act 1456 of 2003, as amended) Rules

INFORMATION TECHNOLOGY ASSESSMENT & PLANNING CONSULTANT REQUEST FOR PROPOSALS (RFP)

IPM. Western Region GUIDELINES FOR PROPOSAL PREPARATION AND SUBMISSION FOR FISCAL YEAR 2000

Stakeholder Guidance American Recovery and Reinvestment Act (ARRA) of 2009 March 3, 2009

COMPARISON OF FEDERAL REGULATIONS, VIRGINIA CODE AND VIRGINIA PART C POLICIES AND PROCEDURES RELATED TO INFRASTRUCTURE DRAFT

Tribal Declarations Pilot

Caring for Mother Earth, Plants and Animals

Partnership Grant Program

Abandoned Mine Drainage Abatement and Treatment

SunZia Southwest Transmission Project. September. EUCI 2017 Western Transmission Summit SunZia Project Case Study February 27, 2017.

2017 Supporting Native Arts Grants Grant Application Q&A

Department of Defense Regional Council for Small Business Education and Advocacy Charter

FRAMEWORK FINANCING AGREEMENT. (National Highway Development Sector Investment Program Project 1) between ISLAMIC REPUBLIC OF PAKISTAN.

POLICIES RELATING TO FEDERAL HIGHWAY FUNDING

Brownsville Treatment Plant after 1 million gallon per day upgrade. 100,000 gallon Storage Tank behind Office Building on KY 259 N.

Yucca Mountain and Interim Storage Proposed Appropriation Language

Federally Supported Water Supply and Wastewater Treatment Programs

Report to Congress. June Deputy Under Secretary of Defense (Installations and Environment)

Lands and Investments, Office of

LEGISLATIVE BILL 275

ROCKY MOUNTAINS COOPERATIVE ECOSYSTEM STUDIES UNIT. AMENDMENT FIVE TO COOPERATIVE and JOINT VENTURE AGREEMENT. between

AZSITE Consortium Annual Report to the Governor s Office For the period July 1, 2010, through June 30, 2011

Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (New Uniform Guidance)

MEMORANDUM OF UNDERSTANDING LANDSCAPE CONSERVATION OF NATURAL RESOURCES IN CALIFORNIA THROUGH THE CALIFORNIA CONSERVATION PARTNERSHIP

CAP FARM WATER SUPPLY PROGRAM Terms and Conditions

REQUEST FOR PROPOSALS. Advanced Metering Infrastructure Planning, Specification Writing and Project Management Services

DOT FUNDING OPPORTUNITIES FOR TRANSPORTATION ASSETS

Transition Review of the Greater Fort Lauderdale Convention & Visitors Bureau

REQUEST FOR PROPOSALS FOR REPLACEMENT OF GENERATOR AT LAKE HILLS 1860 BOOSTER PUMP STATION

Program Management Plan

Transcription:

NAVAJO - GALLUP WATER SUPPLY PROJECT QUARTERLY REPORT: APRIL JUNE, 2014 July 21, 2014 Navajo Nation Water Management Branch (Modified from USBOR Update) I. Background/Purpose/Beneficiaries a. Authorized for construction in March 2009 (PL 111-11) b. Cornerstone of Navajo San Juan River in New Mexico Water Rights Settlement between the Navajo Nation, the State of New Mexico, and the United States of America. c. Will provide a long-term, sustainable water supply from the San Juan River to over 40 chapters on the Navajo reservation; the southwest area of the Jicarilla Apache reservation, and the City of Gallup, New Mexico. II. Scope a. Two main laterals (pipelines) i. Cutter Lateral Serving the far eastern side of the Navajo Reservation and providing a tap to serve the Jicarilla Apache Reservation near Highway 550. ii. San Juan Lateral Starting at the San Juan River near Nenahnezad, NM and extending southward, roughly following US Hwy 491 through Gallup; with extensions to Window Rock, AZ, and near to Crown Point, NM. b. 2 Water Treatment Plants, numerous pumping plants and storage tanks c. Designed to serve a 2040 population of approximately 250,000 III. Construction Schedule a. Project has been divided into 27 Reaches for construction. (see map) b. Construction has begun (first contract awarded April 2012 on Reach 12A) c. Groundbreaking was June 2, 2012. d. Legislated deadline to complete construction is 2024 IV. Construction Sequencing a. In order to meet legislated deadline, simultaneous construction will occur at sections (reaches) throughout the Project area by various Project Participants. Reclamation is the lead construction agency and has developed Financial Assistance Agreements with partners to assist in construction various Reaches. b. Memorandums of Understanding have been developed with Project Participants that accomplish the following: i. Provide for a flexible approach to project design and construction to allow for consideration of delivering water to existing or future distribution systems. ii. Provide for structured process for making modifications. iii. Require that costs must be maintained within authorization ceiling. iv. Identify responsibilities of the Project participants, designers, and construction entities for various reaches. c. Initial facilities will be constructed to convey water to areas that have immediate needs. Demands will be met in short term by existing groundwater wells. i. Reclamation starting near the Navajo community of Twin Lakes, north of Gallup 1

ii. City of Gallup will be upgrading portions of their system in order to deliver Project water through City facilities to neighboring Navajo communities, and eventually to receive Project water from the San Juan River to meet their projected water demands. iii. IHS will be constructing Reach 14 which will take Project water delivered through the City of Gallup s system and deliver it to communities east, south, and west of Gallup. Interagency Acquisition awarded to IHS in May 2013 for construction of Reach 14.1 and Reach 14.2. IHS is moving forward with additional Reaches for construction in coordination with Project participants. iv. Navajo Nation will be extending the Project on the Cutter Lateral side by tying into their existing Eastern Navajo Pipeline Project to provide Project water to the communities on the eastern portions of the Navajo Reservation. d. The PCC has agreed to work on constructing the San Juan Lateral from Twin Lakes, NM north and from the San Juan River south at the same time and meet in the middle. V. Construction Status a. The pilot water treatment plant completed testing for treating San Juan River water during the 2012. Information gained from the pilot project will be used in the procurement and final design process of the water treatment plant. Hogback Irrigation Intake may be the suggested location for the San Juan Lateral. b. On April 16, 2012, a contract for $10.75M was awarded to McMillen, LLC, for the construction of Reach 12A consisting of 4 miles of 42-inch water supply pipeline c. The City of Gallup, NTUA and Navajo Nation are cooperating on the construction of Project 4 near Tohlakai, NM using NM funds. A storage tank is being constructed on the west side of Highway 491. The City of Gallup is the fiscal agent but the project and rightof-way will be transferred to NTUA after construction. Project 4 is an upgrade of the Twin Lakes NTUA system that will receive water from this Project via Reach 12A and Tohlakai Pumping Plant. d. Currently Reclamation s contractor is constructing of Tohalakai Hill Pumping Plant, located on the east side of highway 491 between Reach 12A and 12B (see map). Reclamation anticipates awarding construction contracts for Reach 12b in 2015, Reach 22a in 2015, and Reach 12.1 in FY 2015, Reach 12.2 in 2015 (see map). e. Construction contracts are anticipated to be awarded in FY2014 for other project reaches to be constructed by the Navajo Nation, Indian Health Service and the City of Gallup under respective financial assistance agreements with Reclamation. i. Navajo Nation will issue a request for bids for Reaches 24.1 and 25 in July 2014. ii. City of Gallup will be upgrading portions of their system (Reaches 13 and 27). Portions to begin construction in 2014. iii. IHS has been moving forward with investigations and design data collection for Reach 14.1 and Reach 14.2. Construction is anticipated to begin in FY 2014. VI. Predecessor to Construction Documents a. Completed Agreements/Contracts i. Environmental Impact Statement and Record of Decision ii. San Juan River Basin in New Mexico, Navajo Nation Water Rights Settlement Agreement 2

VII. VIII. iii. Settlement Contract Between the United States and the Navajo Nation iv. Cost Share Agreement Between the United States and the State of New Mexico v. Repayment Contract with the City of Gallup vi. Water Delivery Contract Between Jicarilla Apache Nation and City of Gallup vii. Repayment Contract with the Jicarilla Apache Nation viii. Cultural Resources Programmatic Agreement ix. Financial Assistance Agreement with Navajo Nation for Reaches 24, 25 and 26 x. Financial Assistance Agreement with Navajo Area IHS for Reach 14.1 and 14.2. xi. Financial Assistance Agreement with City of Gallup for Reaches 13 and 27 b. Right of Ways with NEPA and Cultural Resource Compliance Cultural Resources Compliance a. A Programmatic Agreement was signed to ensure compliance with the National Historic Preservation Act during construction that will guide the agencies and tribes in the proper handling of the cultural resources. b. The Programmatic Agreement has been transmitted to consulting agencies and tribes who have the opportunity to sign as concurring parties. c. Cultural Resources contractor has been hired and working in accordance with the PA. In September 2011, a contract for $5.5 million was awarded to Paleo West for cultural resources work necessary to support construction of the Project. Work continues under this contract in the form of pre-construction surveys, ethnographic studies, monitoring during construction, and data recover and treatment of cultural sites. Additional contracts are being compiled as needed for Project. d. The PA requires Reclamation to fund an independent Project Manager to assist with the coordination of all reviews and deliverables required under the terms of the PA. e. The Project Participants are requesting a congressional technical correction to amend the amount allocated for cultural resources from 2 percent to 4 percent. Budget/Funding a. Project Authorization Ceiling was $870 million at 2007 price level i. Subject to adjustments as indicated by engineering cost indices b. Current Project Authorization Ceiling at the October, 2013 price is $1.041 billion. c. U.S. Discretionary (Appropriated) Funding i. Through FY 2012 - $38.1 million; FY 2013: $26.886 million ii. FY 2014 Budget Request: $ 60.497 million d. State of New Mexico Cost Share i. To date, the State has contributed approximately $44 million toward its agreed $50 million cost share by applying for a credit of approximately $30.2 million for pipelines constructed using State funding and sending $13.6 million in cash to Reclamation. e. Mandatory Funding Project is eligible to receive i. P.L. 111-291 provides for total of $180 million in FY 2012 through FY 2014 1. FY 2014 will be last year of mandatory funding under this authority. 2. Funds are available until expended. ii. P.L. 111-11 provides for mandatory funding starting again in FY 2020 3

iii. Navajo Nation and partners need to lobby for funds for Fiscal Years 2015-2019 IX. Federal Infrastructure Projects Permitting Dashboard a. NGWSP is one of the 14 high-priority infrastructure projects identified by President Obama in 2011 to be expedited through the permitting/review process to create jobs. i. Reclamation is working with other federal agencies (BLM, BIA, IHS), Navajo Nation and other Project Participants to explore ways to streamline the permitting and review processes associated with the Project. ii. Progress on the permitting and review process can be tracked on Federal website: http://permits.performance.gov/ iii. The expediting process will not relieve responsibilities to comply with environmental laws and regulations. X. Operation, Maintenance & Replacement a. Navajo Tribal Utility Authority (NTUA) has been identified as the operator for the Project through the Operations MOU of 2012, with the exception of the portion of the Project that the City of Gallup will operate (Reaches 13 and 27) will be operated by the City. b. Through the OMR Transfer Contract (pending), it is envisioned that the Project will be brought on-line as facilities and reaches are completed (rather than waiting until the entire pipeline is completed). This will allow groundwater to be delivered through the pipeline in the interim to certain communities that have immediate needs for the water. c. The right of way and project facilities that are will be transferred to the Navajo Nation/NTUA or City of Gallup depending on Reach through a title transfer agreements. d. The Navajo Nation is working in coordination with NTUA to establish an emergency reserve and replacement fund for this project and other NTUA facilities that will need approval by the Navajo Nation Council. XI. Public Outreach / Coordination with Project Participants a. In addition to the Project Construction Committee (PCC) and Project Operations Committee (POC), Reclamation conducts regular (individual) coordination meetings with the Navajo Nation Division of Natural Resource programs, the City of Gallup, Bureau of Indian Affairs, and Bureau of Land Management, respectively. b. Reclamation staff participates in Navajo chapter meetings to provide information relating to ongoing or planned construction work associated with the Project. c. Reclamation can conduct tours of ongoing construction for Project Participants, other interested agencies, and the media. d. Additional information: http://www.usbr.gov/uc/rm/navajo/nav-gallup/index.html e. Contact information: i. Jason John, Branch Manager, Navajo Nation Water Management Branch, P.O. Box 678, Fort Defiance, AZ 86504, jasonjohn@navajo-nsn.gov, 928-729-4004. ii. Pat Page, P.E., Deputy Construction Engineer, Bureau of Reclamation Four Corners Construction Office, ppage@usbr.gov, (505) 324-5027. 4

5