Memorandum. Trinity River Corridor Project Committee Members: David A. Neumann (Chairman) Vonciel Jones Hill Steve Salazar (Vice-Chair) Delia Jasso

Similar documents
Memorandum CITY OF DALLAS. Hazardous Property Receivership and Operation Goodwill Program

US Army Corps of Engineers Periodic Inspection Report 9 Update. Dallas City Council June 3, 2009

Memorandum. CAPRA: Commission for Accreditation of Park and Recreation Agencies

REVISED AGENDA. 1. Approval of December 6, 2010 Minutes of the Economic Development Committee

Memorandum CITY OF DALLAS. February 1, Honorable Mayor and Members of the City Council

Dallas Floodway System Update

R rtf~ t:" \1 F [L. ~. ;:-" t V'\ S'tV 2012 JAN 13 PH 5: 53. CI ry SE.CRETAif { DALLAS. TEXAS

University of North Texas Libraries

SUMMARY REPORT. OPERATIONS and MAINTENANCE PLANS and CRITERIA. HOUSATONIC RIVER and NAUGATUCK RIVER FLOOD PROTECTION PROJECTS SECTION 1

REQUEST FOR PROPOSALS BIG DARBY ACCORD. Proposals Due by October 25, 2004

THE BROOKINGS INSTITUTION

Community Recovery. Pat Forbes Louisiana Office of Community Development

Panel Decision & Report. SRP MAPC Plymouth County, MA

Memorandum. Please contact me if you have any questions or need additional information. Eric D. Campbell CITY OF DALLAS

BOROUGH OF ROSELLE PUBLIC NOTICE ANNUAL NOTICE OF CALENDAR YEAR 2018 WORKSHOP SESSIONS, PRE-AGENDA MEETINGS AND REGULAR MEETINGS

Hazard Mitigation Assistance (HMA) Developing Hazard Resilient Communities February 29, 2012

Levees in the USA and the Vital Role of Local Sponsors

New Orleans Hurricane and Storm Damage Risk Reduction System Update

Please contact me or Director of Transportation Michael Rogers at (214) if you have any questions or concerns.

Better Cultural, Arts and Recreational Amenities. Trinity Watershed Management

1. Introduction..3 a. Purpose of This Procedural Review Plan...3 b. Description and Information...3 c. References...3

Memorandum CITY OF DALLAS

Memorandum CITY OF DALLAS

Memorandum. Our Product is Service Empathy Ethics Excellence Equity. DATE July 31, SUBJECT Community Centers Programming

2013 Louisiana Transportation Conference

8/30/ American Public Works Association (APWA) International Congress and Exposition. August 30, 2015

Hazard Mitigation Assistance

CITY OF DALLAS. Office of the City Auditor. Audit Report. AUDIT OF CONSTRUCTION-RELATED PROCUREMENTS (Report No. A18-001) October 20, 2017

SCIENCE ADVISORY COMMITTEE TERMS OF REFERENCE

Public Information Meeting Rahway River Basin, New Jersey Flood Risk Management Feasibility Study

Brig. Gen. Thomas W. Kula Commanding General Aug. 14, US Army Corps of Engineers BUILDING STRONG

APPENDIX D PUBLIC AND PRIVATE SECTOR PARTICIPATION PROGRESS REPORT. Hillsborough County Local Mitigation Strategy Appendix D-1

CITY OF DALLAS Bid Review # S15-001

Pre- and Post-Katrina Planning in Pearl River County. Pearl River County

Vista Ridge Project Technical Advisor

Red River Valley Association

VERMONT S RESILIENCE PROGRESS REPORT ROADMAP. August 20, 2015 BACKGROUND WHAT IS RESILIENCE? TRACKING OUR PROGRESS.

King County Flood Control District 2017 Work Program

Update on USACE Civil Works Program Authorities, Policies, and Guidance

Expedited Bridge Replacement Program

Prosperity for Butte County

Democratic Presidential Primary Spending Analysis Update Barack Obama

Mark A. Doctor, PE CAREER PATH

DEPARTMENT OF ENVIRONMENTAL CONSERVATION SELECTED ASPECTS OF THE DAM SAFETY PROGRAM. Report 2006-S-61 OFFICE OF THE NEW YORK STATE COMPTROLLER

Natalie Jaresko Executive Director. Dear Mr. Majority Leader, Mr. Speaker, Mr. Minority Leader, and Ms. Democratic Leader:

CITY OF SPOKANE VALLEY Request for Council Action

Emergency Management THERE WHEN YOU NEED US

Memorandum. Our Product is Service Empathy Ethics Excellence Equity. DATE January 8, 2018

jobs program earmark ban

Learning from the Hurricane Harvey Relief Fund: Considerations for the Future August 2018

Independent Auditor s Report on Applying Agreed-Upon Procedures for the Fiscal Year 2013 # 3 Weapons Destruction

Memorandum. RIGHT Care Pilot Program

Sewer System Improvement Program

Proposed Connector between Airline Highway (US 61) and Interstate 10 in St. John the Baptist Parish

THE NATIONAL RESILIENCE INITIATIVE REQUEST FOR PARTNERSHIP. The Foundation for the American Institute of Architects

Fundraising Opportunities in Your Community

KANATA HIGHLANDS URBAN EXPANSION STUDY TERMS OF REFERENCE

Recent Career Highlights: University of Maryland, Center for Disaster Resilience WaterWonks LLC Prior Career Highlights

Y CARRIED I LOST TOWN OF CALEDON. Project Update and Proposed Revisions to the Work Program be received

Council. Jill A. Jordan, RE., Assistant Joey Zapata, Assistant M.

Water Resources Reform and Development Act (WRRDA) of Section Vertical Integration and Acceleration of Studies. Interim Report to Congress

REGIONAL WATER & SEWER DISTRICT FEASIBILITY STUDY, PETITION, AND PLAN OF OPERATION REQUEST FOR PROPOSALS

Sept.16, National CED conference

Income Eligible Procurement. February

Seawall Earthquake Safety + Disaster Prevention Program Community Meeting June 21, 2018

Florida Community Development Block Grant Disaster Recovery (CDBG DR) Hurricane Irma Unmet Needs Assessment

December 1999 Report No

Mississippi Development Authority. Katrina Disaster Assistance Program. Modification # 17 Program Funding Allocation. CDBG Disaster Recovery Program

Aging Infrastructure: Dam Safety

ATLANTIC CAPE COMMUNITY COLLEGE GRANTS DIRECTORY FISCAL YEAR 2013 JUNE 30, 2013

Board of Supervisors San Joaquin County AGENDA

ACEC Environmental Business & Funding Sources Conference September 15, Camille Meiners, PE

Bowen Island Municipality. Bowen Island Community Centre. Project Briefing Note


During the 4 Years: December, December, 1994 * TOTAL INDUSTRY JOBS LOST (30,800) -1.9%

Funding the Federal-Aid Highway Program

City of Ephrata Tourism Grant Funding 2017 APPLICATION

Beth Day Director, FTA Office of Project Planning RailVolution October 2011

GREAT LAKES STORMWATER COLLABORATIVE WORKPLAN (APRIL 2018 MARCH 2019)

Florida Community Development Block Grant Disaster Recovery (CDBG DR) Hurricane Irma

The Fiscal 2018 Omnibus Spending Bill

CAMDEN COUNTY SOIL CONSERVATION DISTRICT 423 COMMERCE LANE, SUITE #1 WEST BERLIN, NJ (FAX) MEETING AGENDA

Task Force Meeting January 12, 2018

ALTERNATIVE SOURCES OF FUNDING FOR

OVERVIEW Chapter Responsibilities Infrastructure Capital Improvement Plan Project Authorization-after funding

SUMMARY OF MINUTES PUBLIC WORKS COMMITTEE. 6:00 p.m., Tuesday, July 14, 2015 COMMITTEE ROOM. Room 239, City Hall

Tuesday, April 24, 2018

County Transportation Infrastructure Fund Grant Program Frequently Asked Questions

Implementation Status & Results Benin ebenin Project (P113370)

Welcome and Introductions

ALBERTA TRANSPORTATION North Central Region Edson Area Instrumentation Monitoring Results

INLAND RAIL - PARKES TO NARROMINE (P2N) INDUSTRY BRIEFING

PERFORMANCE MANAGEMENT MEETING. Health Department:

REQUEST FOR QUALIFICATIONS (RFQ)

Accreditation Support for Ohio Local Health Districts Request for Training or Technical Assistance - Round 1 The Ohio Department of Health

THE IAEA FUKUSHIMA REPORT AND THE IMPLICATIONS FOR NUCLEAR SAFETY AND EMERGENCY PREPAREDNESS

49 USC NB: This unofficial compilation of the U.S. Code is current as of Jan. 4, 2012 (see

5/25/2017 FUNDING STORMWATER PROJECTS OVERVIEW PROJECT FUNDING BRIDGE KNOWN PROBLEMS KNOWN SOLUTIONS

Embedded Physician-Scholar Program

APHL Position Statement

Transcription:

Memorandum DATE October 7, 2010 TO Trinity River Corridor Project Committee Members: David A. Neumann (Chairman) Vonciel Jones Hill Steve Salazar (Vice-Chair) Delia Jasso Mayor Pro Tern Dwaine Caraway Linda Koop Deputy Mayor Pro Tem Pauline Medrano Ann Margolin Carolyn R. Davis CITY OF DALLAS SUBJECT Dallas Floodway System Update 100-Year Levee Remediation The attached briefing will be presented at the Trinity River Corridor Project Committee meeting on October 12, 2010 at 9:30 A.M. This briefing provides an update of the progress to date for retaining FEMA certification for our levees for the 100-year flood, and outlines the steps, including the estimated timeline and funding sources, for making the 100-year levee fixes Please contact me if you have questions. U Jil A. Jordan, RE. Assistant City Manager Attachment C: Honorable Mayor and Members of the City Council Mary K. Suhm, City Manager Ryan S. Evans, First Assistant City Manager A.C. Gonzalez, Assistant City Manager Forest E. Turner, Assistant City Manager Jeanne Chipperfield, Chief Financial Officer Deborah A. Watkins, City Secretary Thomas P. Perkins, Jr., City Attorney Craig D. Kinton, City Auditor Judge C. Victor Lander Helena Stevens-Thompson, Asst. to the City Manager Frank Librio, Director, Public Information Office Kelly High, Director, Trinity Watershed Management Rebecca Rasor, P.E., Managing Director, Trinity River Corridor Project Dallas, the City that works: diverse, vibrant, and progressive

Dallas Floodway System Update 100-Year Levee Remediation Presented to Trinity River Corridor Project Committee October 12, 2010

In Summary The City and Corps are committed to protecting people and property FEMA s latest schedule for releasing revised flood maps has been adjusted from August 2011 to December 2011 As part of the design of the 100-year levee fixes it was determined soil strength testing is necessary The City and Corps are committed to conducting the tests on an aggressive schedule, staying committed to meeting FEMA s remapping schedule If it appears FEMA s remapping schedule will not be met, new solutions for a path forward will be brought to Council for consideration in January 2011 2

Outline Purpose Overview FEMA Remapping 100-year Levee Remediation Plan Fully Softened Shear Strength Test Parallel Initiatives that May Affect Remapping Next Steps 3

Purpose of Briefing Provide an update of the progress to date for retaining FEMA certification that the Dallas Floodway System Levees can withstand the 100-year flood (flood that has a 1% chance of being equaled or exceeded in a given year) Outline the steps, including the estimated timeline and funding sources, for making the 100-year levee fixes 4

Dallas Floodway System Map 5

Overview Flood Protection is of critical importance to the City Dallas Floodway System protects billions of dollars of property value Dallas Floodway System historically received good, very good or excellent ratings on annual and periodic (every 5 years) inspections Our levees still meet the standards to which they were built by the Corps in the 1950 s 6

Overview (cont d) After Hurricane Katrina, a National Levee Safety Program was instituted resulting in more rigorous and nationally uniform criteria for inspecting levee systems Dallas Floodway Levee System was one of first levee systems in a major American City to be inspected based on new rating criteria As of 2008, over 200 US levees failed inspection by the Corps Those cities/local flood control districts will have to bear entire cost of correction unless they are in a cost sharing partnership with the Corps most are not City is currently in a cost sharing partnership with the Corps for the Dallas Floodway Environmental Impact Statement (EIS) 7

Overview (cont d) Under this new criteria, the Corps issued Periodic Inspection Report 9 (PI #9) in March 2009 and rated the Dallas Levee System unacceptable Deficiencies of two types were identified: Operations & Maintenance (O&M) such as vegetation, siltation and erosion To date approximately, 181 of the 198 items have been addressed System wide issues such as levee height, seepage and stability Levee height and stability issues were the fundamental drivers for the Trinity River Corridor Project and the partnership with the Corps since 1993 8

Overview (cont d) As a part of our partnership with the Corps, the City and the Corps expanded the scope of the current EIS to include study of levee deficiencies. This is called the System Study (800-Year Levee project) System Study is underway to identify and address system-wide deficiencies City has preliminary design identifying 100-year levee issues and fixes In August 2010, the Draft Master Plan of the 100-year levee fixes and Draft Environmental Assessment document were submitted to the Corps 9

FEMA Remapping After PI #9, the Corps withdrew a letter used to support the technical certification of the Dallas levees, and FEMA began its deaccreditation process in April 2009 FEMA is remapping the area around Dallas Floodway as if levees are not there If remapping occurs, ramifications include: Existing structures within the remapped areas that have federally backed mortgages will have to carry flood insurance No new building permits unless on fill or elevated Lending institutions may require flood insurance prior to FEMA s final effective maps 10

FEMA Remapping FEMA has been working closely with the City FEMA s schedule for the release of the revised finalized flood maps have been adjusted by four months FEMA Actions Original Schedule Latest Schedule Preliminary revision to current maps released for public comments September 2010 February 2011 (90 day period to submit concerns about map begins) Revised flood maps finalized (Depends on resolution of public comments) Final effective maps in place August 2011 December 2011 (This is the Date to Beat) February 2012 June 2012 11

This Map Approximates What FEMA s Remapping Could Look Like Assuming no levee protection Zaragoza 12

FEMA Remapping To prevent remapping, City would have to: Complete levee repairs by December 2011 100-Year Levee Remediation Submit 100-year flood certification information to FEMA for floodway/levees by December 2011 The City must fix 3 levee systems 1.Central Wastewater Treatment Plant (CWWTP) 2.Rochester 3.Dallas Floodway (East and West levees) 13

100-Year Levee Remediation Plan Funding plan for construction of 100-year flood improvements have been previously briefed to City Council in April 2010 consisting of: Re-allocation of Flood Protection Bond Program projects Stormwater Funds Dallas Water Utility (DWU) Funds Potential Corps Funds 14

1. Central Wastewater Treatment Plant - 100-Year Levee Remediation Plan No issues related to slope stability or under seepage known at this time 100-year levee fix is to address multiple utility levee crossings 15

2. Rochester Levee 100-Year Levee Remediation Plan No issues related to slope stability or under seepage known at this time 100-year levee fixes may include: Addressing multiple utility levee crossings Addressing the existing MSE (Mechanical Stabilized Earth) wall with the following options: Install interim measures involvin g repairs to the wall or Incorporate into the Dallas Floodway Extension project A separate briefing will be forthcoming to address long term levee improvements 16

3. Dallas Floodway Levees (East and West) 100- Year Levee Remediation Plan 100-year levee fixes may include: Measures to address multiple utility levee crossings Cut-off walls or relief wells to address under seepage Levee fattening to address stability 17

Schedule: 100-Year Levee Remediation Plan Original Schedule: Feb 2010: Submitted Draft Levee Remediation Plan Apr 2010: Completed geotechnical field investigations May 2010: Began design of proposed fixes Jun 2010: Submitted lab test results Aug 2010: Submitted design analyses and Draft Master Plan for the 100-year levee fixes Aug 2010: Submitted Draft Environmental Assessment document Sept 2010: Advertise Construction Nov 2010: Corps Approval and Construction Begins Indicates completed task 18

Schedule: 100-Year Levee Remediation Plan Schedule Changes: As part of the Corps analysis of the geotechnical information, it was determined that it may be necessary to perform site specific testing for fully softened shear strengths The methodology the consultant utilized to determine these strengths was based on a correlation rather than testing The Corps and City held a meeting of various experts in the geotechnical field on August 25-26, 2010 to determine the necessary path forward At the workshop it was agreed upon to complete additional testing specifically for fully softened shear strengths 19

Schedule: 100-Year Levee Remediation Plan Schedule Changes: - Sept 2010 : Soil samples identified - Oct 2010: First of soil samples collected and shipped Subsequent soil samples to be sent throughout the month - Oct 2010: Fully softened shear strength testing begins - Jan 2011: Mid-point of testing - Mar 2011: Testing and Results Complete - Advertisement of 100-year improvements, Corps Approval and Construction start are delayed a minimum of 4 to 6 months 20

Fully Softened Shear Strength Test Clay soils, like those found in and under the Dallas Floodway levees, exhibit a wide range of strengths depending on soil saturation, flood levels and flood duration This strength determines the soil s ability to resist failure These soils can lose strength over time Fully softened shear strength represents a strength value that takes these factors into account and provides a high level of certainty that the levees can be designed to perform as intended for many years 21

Fully Softened Shear Strength Test The Corps offered to have its Engineering Research and Development Center (ERDC) perform the tests, analyze the results and provide approved strength values. ERDC will: Complete all tests and analyses in 6 months at a cost of $958K, shared by the Corps and City Make this their number one priority project Provide results to the City throughout the testing period, with initial results available within 30 days Provide quality-assured data, thereby reducing future technical review processes related to the testing 22

Minor Changes to the Current 100-Year Levee Remediation Plan If the results of the preliminary testing indicate that the proposed Draft Master Plan for the 100-year levee fixes requires minor changes of this document, then plan will meet latest FEMA schedule The 100-year levee fixes will address multiple utility levee crossings and construction of cut-off walls Based on these fixes, the construction could begin in July 2011 and end by December 2011 The fixes would be funded as originally proposed from the reallocation of the 2006 Bond Program, DWU funds and Stormwater Funds City Consultant would certify the levees for 100-year event and submit plans to FEMA for accreditation upon completion of fixes 23

Extensive Changes to the Current 100-Year Levee Design Fixes If the results of the preliminary testing indicate that the proposed Draft Master Plan for the 100-year levee fixes requires extensive changes of this document, then the City would not likely meet FEMA s latest remapping schedule If this occurs, staff will brief the Council in January 2011 on the preliminary testing results and the various strategies and their impacts to the schedule of 100-year levee fixes 24

Impacts to Ongoing Projects There is likely a 4 to 6 month impact to the following project schedules currently under design: Baker Pump Station Sylvan Avenue Bridge Project Balanced Vision Plan 25

Parallel Initiatives that May Affect Remapping FEMA National Levee Issues Alliance (LIA) Since the post-katrina inspections have created levee issues nationally, concerned civic and business leaders have joined the National Levee Issues Alliance The purpose of the LIA is to: Reduce the adverse effects of levee decertification and flood zone re-designation; and Identify resources and methodologies to assist local sponsors in expediting correction of flood protection project deficiencies. Membership includes entities from Illinois, Louisiana, Mississippi and Texas (where initial Corps inspections occurred); additional membership is anticipated US Chamber of Commerce has begun meeting with the LIA to address wide-spread concerns from the business community 26

Parallel Initiatives that May Affect Remapping (cont d) FEMA National Levee Issues Alliance (LIA) (cont d) Dallas participates in the LIA The LIA is working on a number of national initiatives related to levee decertification Creation of a Congressional Levee Caucus Legislation related to levee certification and FEMA remapping Seeking language that recognizes good faith efforts toward levee repair/interior drainage improvements and slows remapping activities Congress is expected to take up legislation addressing the National Flood Insurance Program (NFIP) which could provide the best opportunity in the new Congress (112 th Congress) to address FEMA re-mapping 27

Parallel Initiatives that May Affect Remapping (cont d) The LIA will be monitoring the November elections and plans to meet before the end of the year to discuss strategy and next steps for the 112 th Congress Efforts undertaken by the LIA will focus on the 112 th Congress 28

Next Steps November 2010 through January 2011 Launch Information Campaign November 2010 - Brief TRCP Committee on the update of the Dallas Floodway Extension Project December 2010 Obtain Council authorization to supplement Consultant s (Jacobs) design contract for additional work on Baker and Pavaho Pump Stations January 2011 - Brief the TRCP Committee on the preliminary look of the fully softened shear strength test results and its impact to the schedule and cost of the 100-year levee fixes 29

In Summary The City and Corps are committed to protecting people and property FEMA s latest schedule for releasing revised flood maps has been adjusted from August 2011 to December 2011 As part of the design of the 100-year levee fixes it was determined soil strength testing is necessary The City and Corps are committed to conducting the tests on an aggressive schedule, staying committed to meeting FEMA s remapping schedule If it appears FEMA s remapping schedule will not be met, new solutions for a path forward will be brought to Council for consideration in January 2011 30

DISCUSSION