Massachusetts School Building Authority Steven Grossman Chairman, State Treasurer Jack McCarthy Executive Director MSBA Overview Associated General Contractors March 28, 2014 www.massschoolbuildings.org
Massachusetts School Building Authority Steven Grossman Chairman, State Treasurer Jack McCarthy Executive Director Our Mission Partner with Massachusetts communities to support the design and construction of educationallyappropriate, flexible, sustainable, and cost-effective public school facilities. www.massschoolbuildings.org
Massachusetts School Building Authority Steven Grossman Chairman, State Treasurer Jack McCarthy Executive Director Building With Us www.massschoolbuildings.org/building
MSBA Resources www.massschoolbuildings.org 4
MSBA Resources www.massschoolbuildings.org 5
MSBA Resources (Continued) www.massschoolbuildings.org 6
MSBA Resources (Continued) www.massschoolbuildings.org 7
Roundtable Discussion Roundtables: Owner s Project Manager Designer Contractor www.massschoolbuildings.org
Who We Work With Massachusetts School Building Authority 9
Schematic Design www.massschoolbuildings.org 10
Bid Data www.massschoolbuildings.org 11
Accelerated Repair Program www.massschoolbuildings.org 12
2013 Statements of Interest (SOIs) Overview www.massschoolbuildings.org 13
Accelerated Repair Program: Roofs, Windows, & Boilers (anticipated bids) 7 Boiler bids estimated at $6,793,747 31 Roof bids estimated at $60,525,783 12 Window bids estimated at $13,678,617
FY 2014 SOI Process FY 2014 SOI Process opened on Friday, January 10, 2014 Accelerated Repair Closed on February 14, 2014 Core Program The SOI closing date for districts submitting under the Core Program will be April 11, 2014 www.massschoolbuildings.org 15
Accelerated Repair Program Review of the 117 SOIs are currently underway Hard Copy Submission Requirements Complete Content Review Underway Site Visits and other due diligence through April and May Anticipate ARP Invites at June 2014 Board Meeting www.massschoolbuildings.org 16
Accelerated Repair Program District selected scope of work: 33 Roof 26 Windows 25 Boiler 15 Roof & Boilers 7 Roof, Windows, & Boilers 6 Roof & Windows 2 Windows & Boilers 3 Other (Carpet Replacement, Retaining Wall, Emergency Generator) www.massschoolbuildings.org 17
Accelerated Repair Program Close to 60% of the 117 ARP SOIs were filed by 13 Districts: 16 - Springfield 7 - Brockton 6 - Lowell & Taunton 5 - Hampden-Wilbraham 4 - Quincy & Worcester 3 - Auburn, Middleborough, Mohawk Trail, Randolph, Uxbridge, and Winchendon www.massschoolbuildings.org 18
Core Program April 11, 2014 Deadline 19 Core SOIs have been received 8 - Addition/Renovation 6 - Repair 5 - New School Construction Core Review Hard copy SOI review through mid May Content review, site visits, and Senior Studies through the Summer into early Fall Anticipate invites into Eligibility Period at Fall/Winter Board meetings www.massschoolbuildings.org 19
Our Programs and Initiatives Model Schools 18 model schools approved, 7 out of the 8 remaining will complete construction this year Science Lab 8 projects approved; 6 completed, 2 in construction Accelerated Repair At March 2014 Board meeting, final 2013 ARP SOIs approved for PFA 2014 ARP SOI due diligence underway www.massschoolbuildings.org 20
Massachusetts School Building Authority Steven Grossman Chairman, State Treasurer Jack McCarthy Executive Director Approved Projects, Bids and Buildings
2007-2012 149 Core Program Projects approved Grants - $3.096 billion OPM fees - $147.5 million Designer fees - $371 million Construction - $4.052 billion Massachusetts School Building Authority 22
400 Total Projects PROJECT TYPE: NEW MODEL ADDITION/RENOVATION ACCELERATED REPAIR MAJOR REPAIR TO BE DETERMINED All Projects (includes active and inactive)
Design Development 30 Projects ($602 million) 17 Accelerated Repair projects 13 New Program Projects 4 Elementary Schools Athol-Royalston, Gloucester, Newton, South Hadley 5 Middle Schools Chicopee, Lynn, North Adams, Peabody, Wachusett Regional 4 High Schools Greater Lawrence Regional Voc/Tech, Lunenberg, Winchester, Winthrop Massachusetts School Building Authority 24
Construction Projects 45 projects in construction ($1.802 billion) 6 Accelerated Repair Program Projects 2 Science Lab Initiative Projects 37 New Program and Waitlist Projects 9 Elementary Schools Andover, Georgetown, Newburyport (Breshnahan), Revere, Springfield (Brookings), Webster, Westfield, Weston, Williamsburg 9 Middle and Middle/High Schools Auburn, Douglas, Greenfield, Hingham, Newburyport (Nock) Oxford, Stoneham, Sutton, Wakefield 19 High Schools Add/Reno Assabet Valley Regional Tech Ayer Shirley Regional Dracut Greater Lowell Regional Voc/Tech Greater New Bedford Voc/Tech Add/Reno Methuen Norfolk County Agric North Reading Southern Worcester Reg. Voc/Tech Southwick-Tolland- Granville New Concord-Carlisle Regional Essex North Shore Agric and Tech West Bridgewater Wilmington Models Duxbury Franklin Marshfield Monomoy Regional Somerset-Berkley Reg Massachusetts School Building Authority 25
Summary of Bid Data Year Number of Projects Design Basis for Enrollment Project Budget Construction Budget 2009 11 8,188 $205.6 M $171.5 M 2010 33 26,184 $1.37 B $1.07 B 2011 20 16,113 $896.6 M $688.6 M 2012 25 21,157 $1.28 B $979.2 M *2013 30 23,598 $1.16B $972.0M 2014 13 10,815 $972.6M $493.0 M 2015 1 970 $80.2M $62.0M Grand Total 133 107,025 $5.96 B $4.44 B Note: These numbers are based on preliminary information received from the District and are subject to further review and calculation. www.massschoolbuildings.org 26
Core Program Construction Estimate vs. 2014 Bid Amount Two bids received in 2014 Of the two projects, one bid came in within the estimated budget Total $55,750,603 $53,558,496 $2,192,107 - $1,857,869 District School Scope Project Type Bid Date Construction Estimate ** Bid Amount ** Variance from Construction Estimate Reimbursement Rate Potential Grant Variance * Revere William McKinley ES New DBB Jan-14 $33,897,336 $31,575,000 $2,322,336 80.00% $1,857,869 North Adams Conte MS New DBB Mar-14 $21,853,267 $21,983,496 -$130,229 80.00% $0 *These numbers are based on preliminary information received from the district and are subject to further review and calculation. **The construction estimate and bid amount do not include pre-construction services and alternatives. www.massschoolbuildings.org 27
2014: The Year Ahead Eligibility Period 14 projects in Eligibility Period Capital Pipeline 328 Projects 5 projects in Consultant Selection 57 projects in Feasibility Study/Schematic Design 30 projects in Design Development 13 projects scheduled to bid in 2014 and 1 in 2015 45 Projects in Construction 129 Projects in Closeout or Complete 46 Final Audits Recently Approved Massachusetts School Building Authority 28
Module 6 Detailed Design Massachusetts School Building Authority 29
Module 6 Detailed Design Commissioning MSBA requires & pays for commissioning Commissioning Agent engaged during early phase of design development Benefits: Improved coordination between design, construction and occupancy Fewer deficiencies at turnover Energy savings and improved indoor environmental quality Massachusetts School Building Authority 30
Module 7 Construction Massachusetts School Building Authority 31
Module 7 Construction PFA Bid Amendment MSBA Plan: Apply bid savings to fund additional needs throughout the state Provisions of Section 2.3 of the PFA are there to protect state taxpayers money Bid savings to District Based on project scope, budget and schedule documented in the PFA, GCs SOV or GMP, and evaluation of scope changes during detailed design. Massachusetts School Building Authority 32
Module 7 - Construction PFA Bid Amendment PEAK Massachusetts School Building Authority 33
Module 7 Construction Change Orders Project Advisory 22, October 2013 New Change Order Funding Allowance Policy Effective for all projects approved by the MSBA Board of Directors on or after January 29, 2014 New Projects Up to 1% of the Construction Budget Addition/Renovation Projects Up to 2% of Construction Budget Massachusetts School Building Authority 34
Module 7 Construction Change Orders Change Orders District must submit a Budget Revision Request to use its construction contingency for change orders Not all change orders will be eligible, for example: Owner added scope is not eligible Changes required by third party may not be eligible for reimbursement Site work change orders beyond the 8% sitework cap established in the PFA are not eligible MSBA reviews for eligibility for reimbursement only Massachusetts School Building Authority 35
Module 7 Construction Change Order Spreadsheet Massachusetts School Building Authority 36
Module 8 Completing the Project Closeout Process Massachusetts School Building Authority 37
Module 8 Completing the Project Closeout Activities PFA Amendment Budget entered in Pro-Pay Change Order Review Budget Revision Requests Reclassifications Commissioning MA CHPS review and certification (if applicable) Submission of 100% of project costs and final request for reimbursement via Pro-Pay Mark last payment FINAL Massachusetts School Building Authority 38
Module 8 Completing the Project Audit Acceptance Process Draft Audit Report District Acceptance Completion of Closeout Forms MSBA Board Approval Final Payment Massachusetts School Building Authority 39
Massachusetts School Building Authority Steven Grossman Chairman, State Treasurer Jack McCarthy Executive Director MSBA Resources www.massschoolbuildings.org
Geographic Information System (GIS) Geographic Information System (GIS) a comprehensive mapping tool allowing the user to view individual and overview project information across the Commonwealth www.massschoolbuildings.org
Statements of Interest (SOIs) 2014 Statements of Interest Submitting an SOI is the first step in the MSBA s program On this page you can: Get an overview of the SOI process Learn when the SOI process opens/closes per fiscal year View previously submitted SOIs View FAQ s Find out about next steps
Your School Your School Tool www.massschoolbuildings.org
MSBA Calendar The MSBA Website calendar is a great resource. You can find: Meetings Events and tours State-wide site visits and senior studies www.massschoolbuildings.org
Contractor Roundtable Contractor Roundtables Bi-monthly meetings for contractors working on or wishing to work on MSBA funded school construction projects. The agendas are developed based on input from the participants www.massschoolbuildings.org
New Business Opportunities Board Meetings Approved Projects Board Meeting Power Point Presentation www.massschoolbuildings.org
New Business Opportunities Building With Us (Home Page) - Estimated Bid Schedule - Estimated Construction & Total Project Cost Data at Schematic Design - Bid Results for Awarded Construction Contracts with Executed PFA Amendments www.massschoolbuildings.org