Exhibit R-2, RDT&E Budget Item Justification: PB 2012 Air Force DATE: February 2011 COST ($ in Millions) FY 2010 FY 2013 FY 2014 FY 2015 FY 2016 To Program Element - - 93.867-93.867 158.218 315.238 397.880 336.786 Continuing Continuing 657007: B61 LIFE EXTENSION PROGRAM 657008: LONG RANGE STAND- OFF - - 83.941-83.941 118.823 116.609 57.038 41.281 Continuing Continuing - - 9.926-9.926 39.395 198.629 340.842 295.505 Continuing Continuing Note The program funding includes reductions for acquisition excellence efficiencies in FY15 and FY16 that are not intended to impact program content. Reductions for efficiencies may be spread to other Air Force programs at a later date. Amounts of the reductions are: $7.0M/FY15 and $102.5M/FY16. In FY12 B61 LEP efforts were transferred from PE 0604222F, Nuclear Weapons Support, to PE 0101125F, Nuclear Weapon Modernization in order to support B61 LEP development. In FY12 LRSO efforts were transferred from PE 0101122F, Air Launched Cruise Missile, to PE 0101125F, Nuclear Weapon Modernization in order to support LRSO development. A. Mission Description and Budget Item Justification The purpose of this program element is to conduct and support Air Force and Joint DoD-DoE acquisition activities for the modernization and sustainment of nuclear weapons. B61 Life Extension Program (LEP): Lead the joint DoD-DoE B61 Life Extension Program (LEP) feasibility, design, cost, and down-select effort. Lead development and acquisition of B61 tail subassembly for B61 LEP. Ensure integration of B61 LEP with current and future aircraft. Long Range Stand Off (LRSO): identify viable concepts and materiel solutions to replace the legacy Air Launched Cruise Missile (ALCM) fleet in support of the Air Force s strategic deterrence and global strike mission requirements. This program is in Budget Activity 5, System Development and Demonstration (SDD) because it is conducting engineering and manufacturing development tasks aimed at meeting validated requirements prior to full-rate production. Air Force Page 1 of 12 R-1 Line Item #85
Exhibit R-2, RDT&E Budget Item Justification: PB 2012 Air Force DATE: February 2011 B. Program Change Summary ($ in Millions) FY 2010 Previous President's Budget - - 93.867-93.867 Current President's Budget - - 93.867-93.867 Adjustments - - - - - Congressional General Reductions - Congressional Directed Reductions - Congressional Rescissions - - Congressional Adds - Congressional Directed Transfers - Reprogrammings - - SBIR/STTR Transfer - - Other Adjustments - - - - - Air Force Page 2 of 12 R-1 Line Item #85
Exhibit R-2A, RDT&E Project Justification: PB 2012 Air Force DATE: February 2011 COST ($ in Millions) 657007: B61 LIFE EXTENSION PROGRAM FY 2010 657007: B61 LIFE EXTENSION PROGRAM FY 2013 FY 2014 FY 2015 FY 2016 To - - 83.941-83.941 118.823 116.609 57.038 41.281 Continuing Continuing Quantity of RDT&E Articles 0 0 0 0 0 0 0 0 0 Note In FY12 B61 LEP efforts were transferred from PE 0604222F, Nuclear Weapons Support, to PE 0101125F, Nuclear Weapon Modernization in order to support B61 LEP development. A. Mission Description and Budget Item Justification B61 Life Extension Program (LEP): The LEP of the B61 gravity weapon will extend the service life of the weapon, consolidate multiple B61 variants into one modification and improve safety, security, and use control (surety). Provides leadership, management, and oversight of the Air Force-led, joint Department of Defense (DoD) - Department of Energy (DoE) B61 Project Officer's Group (POG). Lead the joint DoD-DoE B61 LEP feasibility, design, cost, and down-select study. Provide technical oversight of the DoE nuclear package LEP activities. Develop weapons trainers, test equipment, tech data, and training for the B61 LEP. Conduct ground and flight tests and support aircraft integration for the B61 LEP. Develop and acquire a B61 tail subassembly (TSA) and ensure integration of B61 LEP onto threshold aircraft. This may include weapon trainers, test equipment, tech data, training and training materials. Additionally, the program office will conduct lab, ground and flight tests, engineering studies and technology analyses, modeling and simulation, logistics evaluations, human system integration, technology maturation, and risk reduction activities in support of the required materiel solution. This program is in Budget Activity 5, System Development and Demonstration (SDD) because it is conducting engineering and manufacturing development tasks aimed at meeting validated requirements prior to full-rate production. B. Accomplishments/Planned Programs ($ in Millions) Title: B61 POG Support and B61 LEP FY 2010 - - 83.941-83.941 Description: Accomplish DoD-DoE B61 LEP effort. Develop and acquire B61 tail subassembly and ensure integration of B61 LEP onto current and future aircraft. FY 2010 Accomplishments: Plans: Plans: Air Force Page 3 of 12 R-1 Line Item #85
Exhibit R-2A, RDT&E Project Justification: PB 2012 Air Force DATE: February 2011 657007: B61 LIFE EXTENSION PROGRAM B. Accomplishments/Planned Programs ($ in Millions) FY 2010 Provide technical oversight of the DoE B61 LEP activities. Refine proposed materiel solution concepts. Refine acquisition strategy to include program development schedule and cost estimates. Prepare documentation for Technology Development phase exit criteria and Milestone B entrance criteria. Support DoD-DoE B61 POG. Plans: Accomplishments/Planned Programs Subtotals - - 83.941-83.941 C. Other Program Funding Summary ($ in Millions) Line Item FY 2010 FY 2013 FY 2014 FY 2015 FY 2016 To PE 0604222F: RDT&E 6.382 25.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 Continuing Continuing D. Acquisition Strategy Full and open competition as approved by the MDA. E. Performance Metrics Please refer to the Performance Budget Overview Book for information on how Air Force resources are applied and how those resources are contributing to Air Force performance goals and most importantly, how they contribute to our mission. Air Force Page 4 of 12 R-1 Line Item #85
Exhibit R-3, RDT&E Project Analysis: PB 2012 Air Force DATE: February 2011 Product Development ($ in Millions) Category Item Prior 657007: B61 LIFE EXTENSION PROGRAM To B61 LEP C/TBD TBD:, - - Jan 2011 39.301 Nov 2012-39.301 Continuing Continuing TBD Support ($ in Millions) Category Item Subtotal - - 39.301-39.301 Prior To B61 LEP Program Office MIPR AAC/EBD:, - - 11.169 Nov 2011-11.169 Continuing Continuing 0.000 Aircraft Integration MIPR Various:, - - 32.550 Nov 2011-32.550 Continuing Continuing 0.000 Test and Evaluation ($ in Millions) Category Item Subtotal - - 43.719-43.719 0.000 Prior To Test Oversight MIPR RTO:, - - 0.921 Nov 2011-0.921 Continuing Continuing 0.000 Management Services ($ in Millions) Category Item Subtotal - - 0.921-0.921 0.000 Prior To Subtotal - - - - - 0.000 0.000 0.000 Prior Project s - - 83.941-83.941 To Remarks Air Force Page 5 of 12 R-1 Line Item #85
Exhibit R-4, RDT&E Schedule Profile: PB 2012 Air Force DATE: February 2011 657007: B61 LIFE EXTENSION PROGRAM Air Force Page 6 of 12 R-1 Line Item #85
Exhibit R-4A, RDT&E Schedule Details: PB 2012 Air Force DATE: February 2011 657007: B61 LIFE EXTENSION PROGRAM Schedule Details Start End Events Quarter Year Quarter Year MDD and Milestone A Preparation 1 2010 3 2011 Combined Materiel Development Decision / Milestone A Decision 3 2011 3 2011 Technology Development Phase 3 2011 1 2014 Milestone B Decision 1 2014 1 2014 Air Force Page 7 of 12 R-1 Line Item #85
Exhibit R-2A, RDT&E Project Justification: PB 2012 Air Force DATE: February 2011 COST ($ in Millions) 657008: LONG RANGE STAND- OFF FY 2010 657008: LONG RANGE STAND-OFF FY 2013 FY 2014 FY 2015 FY 2016 To - - 9.926-9.926 39.395 198.629 340.842 295.505 Continuing Continuing Quantity of RDT&E Articles 0 0 0 0 0 0 0 0 0 Note In FY12 LRSO efforts were transferred from PE 0101122F, Air Launched Cruise Missile, to PE 0101125F, Nuclear Weapon Modernization in order to support LRSO development. A. Mission Description and Budget Item Justification Long Range Stand Off (LRSO) seeks to identify viable concepts and materiel solutions to replace the legacy Air Launched Cruise Missile (ALCM) fleet in support of the Air Force s strategic deterrence and global strike capabilities. This effort will analyze the areas of survivability, lethality, reliability and affordability. Funding supports Materiel Solution Analysis (MSA) phase activities and associated engineering studies and technology analyses, requirements definition, technology maturation, and risk reduction activities. This program is in Budget Activity 5, System Development and Demonstration (SDD) because it is conducting engineering and manufacturing development tasks aimed at meeting validated requirements prior to full-rate production. B. Accomplishments/Planned Programs ($ in Millions) Title: LRSO FY 2010 - - 9.926-9.926 Description: Conduct LRSO Materiel Solution Analysis (MSA) phase. Identify and refine viable materiel solution concepts for LRSO. FY 2010 Accomplishments: Plans: Plans: LRSO Analysis of Alternatives (AoA). Refine concepts for viable materiel solutions. Develop technology development strategy and refine program schedule and cost estimate. Prepare documentation for Milestone A decision. Plans: Accomplishments/Planned Programs Subtotals - - 9.926-9.926 Air Force Page 8 of 12 R-1 Line Item #85
Exhibit R-2A, RDT&E Project Justification: PB 2012 Air Force DATE: February 2011 657008: LONG RANGE STAND-OFF C. Other Program Funding Summary ($ in Millions) Line Item FY 2010 FY 2013 FY 2014 FY 2015 FY 2016 To PE 0101122F: RDT&E 3.219 3.300 0.000 0.000 0.000 0.000 0.000 0.000 0.000 Continuing Continuing D. Acquisition Strategy During MSA phase, an AoA will be completed. Multiple contracts will be awarded to refine materiel solution concepts. A technology development strategy will be developed during the MSA phase. E. Performance Metrics Please refer to the Performance Budget Overview Book for information on how Air Force resources are applied and how those resources are contributing to Air Force performance goals and most importantly, how they contribute to our mission. Air Force Page 9 of 12 R-1 Line Item #85
Exhibit R-3, RDT&E Project Analysis: PB 2012 Air Force DATE: February 2011 Product Development ($ in Millions) Category Item Prior 657008: LONG RANGE STAND-OFF To Subtotal - - - - - 0.000 0.000 0.000 Support ($ in Millions) Category Item LRSO Materiel Solution Analysis Phase activities Prior To TBD Various:, - - 9.926 Nov 2011-9.926 Continuing Continuing 0.000 Subtotal - - 9.926-9.926 0.000 Test and Evaluation ($ in Millions) Category Item Prior To Subtotal - - - - - 0.000 0.000 0.000 Management Services ($ in Millions) Remarks Category Item Prior To Subtotal - - - - - 0.000 0.000 0.000 Prior To Project s - - 9.926-9.926 0.000 Air Force Page 10 of 12 R-1 Line Item #85
Exhibit R-4, RDT&E Schedule Profile: PB 2012 Air Force DATE: February 2011 657008: LONG RANGE STAND-OFF Air Force Page 11 of 12 R-1 Line Item #85
Exhibit R-4A, RDT&E Schedule Details: PB 2012 Air Force DATE: February 2011 657008: LONG RANGE STAND-OFF Schedule Details Start End Events Quarter Year Quarter Year Materiel Development Decision Preparation 1 2010 2 2011 Materiel Development Decision 2 2011 2 2011 Materiel Solutions Analysis Phase 2 2011 3 2013 Milestone A Decision 3 2013 3 2013 Technology Development Phase 3 2013 4 2016 Air Force Page 12 of 12 R-1 Line Item #85