CONTRACT BRIEF WORKER ACCOMMODATION MARCH 4, The Worker Accommodation RFQ can be found on BC Bid at document number 1807.

Similar documents
Project Brief. for. Kitsilano Secondary School Renewal

City of Fort St. John Special Council 1:30 pm Council Chambers October 31, 2011

Aboriginal Group Communication Plan Annual Report. Site C Clean Energy Project

Project Report: Achieving Value for Money Charles Jago Northern Sport Centre

ABORIGINAL CONSULTATION PLAN FOR THE NANTICOKE SOLAR PROJECT

First Nations Energy Education Exchange Workshop

GEORGE MASSEY TUNNEL REPLACEMENT PROJECT

Northline Solar Project

Conrad Grebel University College. Kitchen and Dining Room Expansion and Renovation Architectural Feasibility Study

Powering Our Communities. Grant Guidelines

Office of Climate Change Guyana September, TRANSITIONING TO NATIONAL ENERGY SECURITY: Bartica as a Model Green Town TERMS OF REFERENCE

General Contractor Services - Small Projects

Innovation Grants REQUEST FOR PROPOSAL (RFP)

Request for Statements Qualifications(RFQ) For

Request for Proposals and Specifications for a Community Solar Project

FEED-IN TARIFF POLICY APPLICATION AND IMPLEMENTATION GUIDELINES

Ab o r i g i n a l Operational a n d. Revised

City of Coquitlam. Request for Expressions of Interest RFEI No Workforce Scheduling Software

Title 35-A: PUBLIC UTILITIES

Coastal First Nations Art Installation - Regional District of Nanaimo Administration Building

Project Application Webinar

Request for Expressions of Interest

Capital Project Plan Royal Columbian Hospital Redevelopment Project Phases 2 & 3 May 2, 2017

Biosolids Forest Fertilization Program

NEWS RELEASE. New economic development strategy to build on rural advantages on North Vancouver Island

Q. Why a new hospital?

First Nations Clean Energy Business Fund. Guidelines for Funding

CONSUMERS ENERGY COMPANY REQUEST FOR PROPOSALS SOLAR GENERATION PROJECTS. Bids Due: July 28, :00 noon EPT (Jackson, MI) Issued.

INVENERGY LLC Meeting Summary Report Severn Sun Solar Project

CONTENT 1 INTRODUCTION 2 WHAT

City of Waterloo, Wisconsin. Request for Proposals. Municipal Engineering Services

Capital Project Plan Royal Inland Hospital Patient Care Tower Project March 1, 2017

Invitation for Business Cases / Request for Funding For Building Repairs & Small Capital Replacement

Industrial Optimization Program: Feasibility Study

Low-Carbon Building Skills Training Fund for Ontario Non-College Training Delivery Agents

Canada-British Columbia Clean Water and Wastewater Fund

HANDBOOK FOR THE INDIGENOUS ECONOMIC DEVELOPMENT FUND. January 2018

Request for Proposal (RFP) Architectural Services for Interior Renovations

Bowen Island Municipality

Invitation to Submit Expression of Interest and Proposal

Generator Replacement at the Garden River Power Plant

Practice Review Guide April 2015

Everyone s Environment Grants Guidelines. Cleaning up our backyards round one

Open Call Engineering Artist-In-Residence INVITATION TO ARTISTS TO APPLY FOR AN ENGINEER ARTIST-IN-RESIDENCE

EL DORADO IRRIGATION DISTRICT 2018 CLASS/PAY LISTING

SMALL COMMUNITIES FUND PROGRAM GUIDELINES MUNICIPAL AFFAIRS.

Project Overview and Description. August Overview. Project Description. Monitoring and Evaluation. Reporting Arrangements.

INVENERGY LLC Meeting Summary Report Northline Solar Project

REQUEST FOR QUALIFICATIONS (RFQ)

KWS/GIMCO/EOI/52/

Request for Proposals Emergency Response Plan, Training and Vulnerability Assessment

BC Rural Dividend Program Guide

PHILADELPHIA ENERGY AUTHORITY

Practice Review Guide

Request for Information and Qualifications RFIQ No Facility Asset Management Consulting Services

New Building Canada Fund: Provincial-Territorial Infrastructure Component National and Regional Projects

Business Plan: Corporate Investments & Partnerships

Papua New Guinea: Implementation of the Electricity Industry Policy

2014 New Building Canada Fund: Provincial-Territorial Infrastructure Component National and Regional Projects

Clean Water and Wastewater Fund. Program Guidelines

Lessons Learned for a Transit Public-Private Partnership. Phillip A. Washington, General Manager Regional Transportation District

BC Parks Volunteer Strategy

BC Rural Dividend Program Guide

BC Hydro writes to provide the BCUC with its second errata to the Addendum to Assessment Report No. 6 (Addendum) filed on September 30, 2013.

REQUEST FOR PROPOSALS PROFESSIONAL ARCHITECTURAL FIRM FOR DESIGN & CONSTRUCTION MANAGEMENT SERVICES

Introducing the Renewed Federal Gas Tax Agreement In British Columbia

FACT SHEET: Environmental Approvals and Licences

Regional Growth Fund Frequently Asked Questions

Massachusetts Bay Transportation Authority. POLICIES & PROCEDURES Design Build Procurement Procedures April 2016

OVERVIEW OF THE CFP PROCESS Co-Financing Grants for Commercial Renewable Energy Projects in Indonesia. Jakarta, 3 rd February 2015

PROJECT PREPARATORY TECHNICAL ASSISTANCE

Call for Applications for the development of pre-commercial clean-energy projects and technologies

Request for Qualifications to Certify Qualified Providers for the Arkansas Energy Performance Contracting Program

BUTTE COUNTY DEPARTMENT OF WATER AND RESOURCE CONSERVATION REQUEST FOR PROPOSALS TO

Guidelines. Ministry of Natural Resources and Forestry Land Stewardship and Habitat Restoration Program (LSHRP) Ontario.

Agricultural Waste Control Regulation Intentions Paper Response Form

Aboriginal Community Capital Grants Program Guide

Currant Lake Telecommunication Tower

Local Energy Challenge Fund

Quarterly Progress Report on Corporate Strategic Initiatives

City of Coquitlam. REQUEST FOR PROPOSALS RFP No

The Village requests that responses be submitted by: 4:00 p.m. Pacific Time on Thursday, August 30, 2012.

FIPN COMPLEMENTARY DETAILS FONDS D INITIATIVES DU PLAN NORD (FIPN)

DISCUSSION ITEM EXECUTIVE SUMMARY

Fiji Electricity Authority. MR 323/2017 Feasibility Study of Pumped Storage Hydropower at Monasavu Request for Prices

Attention Design Firms

Energy. Request For Proposals for Renewable Power Supply Resources

Alberta Education/ASBOA Bootcamp 101

INDUSTRIAL ENERGY OPTIMIZATION PROGRAM

REQUEST FOR QUALIFICATIONS AS-NEEDED CONSULTING PROJECT MANAGER

Project # LI

POLICY 6800 PROCUREMENT

Page 1 of 10 Chicago Infrastructure Trust Joint Public Safety Training Academy - RFQ Clarifications - November 9, 2017

Request for Qualifications DRPA Solar Photovoltaic Systems

COUNTY OF PERTH. Chief Administrative Officer. Clerk s Office Business Plan. January 2017

THIS IS A SAMPLE APPLICATION ONLY ALL APPLICANTS MUST APPLY AND SUBMIT APPLICATIONS ONLINE

REQUEST FOR EXPRESSIONS OF INTEREST AND REQUEST FOR PROPOSALS FOR DESIGN SERVICES OF A NEW RONALD MCDONALD HOUSE IN HALIFAX, NS

Heritage Energy Retrofit Grant Terms and Conditions Sept Oct 2018

NEXT NGA WEST (N2W) PROGRAM ACQUISITION INFORMATION BRIEF

ARCHITECTURAL/ENGINEERING SERVICES

Transcription:

CONTRACT BRIEF WORKER ACCOMMODATION MARCH 4, 2014 The RFQ can be found on BC Bid at www.bcbid.gov.bc.ca, document number 1807.

TABLE OF CONTENTS 1.0 PURPOSE OF THE CONTRACT BRIEF... 3 2.0 THE BUSINESS OPPORTUNITY... 4 3.0 THE CONTRACT... 5 3.1 BACKGROUND... 5 3.2 OBJECTIVES... 5 3.3 SITE... 5 3.4 SCOPE... 7 3.5 REGULATORY APPROVALS AND PERMITTING... 7 3.6 ADVANCE WORK... 7 3.7 GENERAL RESPONSIBILITIES... 8 3.8 PROJECT TEAM... 9 4.0 THE COMPETITIVE SELECTION PROCESS...10 4.1 TRANSPARENCY OF THE COMPETITIVE SELECTION PROCESS...10 4.2 PARTIAL COMPENSATION...11 5.0 CONTRACT SCHEDULE...12 2

1.0 PURPOSE OF THE CONTRACT BRIEF This, and all comments included in it, is intended only as a convenient summary describing the Site C Clean Energy Project Contract (the Contract ), the business opportunity, and the anticipated competitive selection process. The Site C Clean Energy Project ( Site C ) requires environmental certification and other regulatory permits and approvals before it can proceed to construction. The is not included as part of the Request for Qualifications ( RFQ ) or Request for Proposals ( RFP ), and it is not intended to be included with, or referred to in any way in interpreting the requirements of, the RFQ, the RFP, the Contract, or to in any way define or describe any party s rights with respect to the Contract. 3

2.0 THE BUSINESS OPPORTUNITY BC Hydro is seeking to enter into a contract with a qualified entity for the design, construction, partial financing, operation and maintenance for the Site C (the Contract ). The Contract is also anticipated to include the design, construction and construction financing of the following ancillary buildings: materials testing labs, BC Hydro offices and an emergency response building, and potential maintenance of some of the ancillary buildings. The Contract will be procured using a Design Build Finance Operate Maintain ( DBFOM ) approach. BC Hydro expects the Contract will be with a single entity (a firm, partnership or consortium) that will be responsible to provide these integrated services, assuming and sharing defined risks and participating in the financing of the Contract. BC Hydro believes that the Contract is an opportunity for participants to form a qualified entity ( Project Co ) consisting of an experienced, highly qualified, multi-disciplinary team supported by the appropriate financial and corporate commitment, resources and experience necessary to undertake the Contract. Features of the opportunity are anticipated to include: an approximately eight year operating term structured with payment linked to availability and performance; an interactive competitive selection process in which short-listed teams and BC Hydro will have the opportunity to discuss procurement issues and key elements of the Contract including design, and provisions of the Contract such as appropriate risk allocation and payment mechanism; a limited notice to proceed to allow fabrication activities to proceed for any modular units at an early stage; a phasing approach for construction that will be flexible to respond to variations in the number of workers required, including in terms of timing and capacity; and an approach to realizing potential residual value of assets through effective allocation of residual value risk between BC Hydro and Project Co. Site C requires environmental certification and other regulatory permits and approvals before it can proceed to construction. 4

3.0 THE CONTRACT 3.1 BACKGROUND Site C is a proposed third dam and hydroelectric generating station on the Peace River in northeast B.C. BC Hydro is proposing Site C to help meet the long-term electricity needs of the province. Subject to approvals, Site C would provide 1,100 megawatts of dependable capacity, and about 5,100 gigawatt hours of electricity each year enough energy to power the equivalent of about 450,000 homes per year in B.C. More information on Site C can be found at: www.sitecproject.com. Worker accommodation is a key component of BC Hydro s labour strategy to provide the housing and recreational facilities necessary to attract and retain workers engaged on Site C. Construction of Site C would be undertaken in what is expected to be a period of high demand for skilled workers. Therefore, the quality of worker accommodation is key to workforce attraction, retention and well-being of workers. 3.2 OBJECTIVES The objectives for the Contract include: (a) safety for public and workers; (b) workforce attraction, retention, and well-being of workers; (c) Site C construction productivity, cost, and schedule; (d) being appropriately timed and scaled to meet occupancy requirements; and (e) support the Site C project objectives, including providing economic opportunities for Aboriginal groups, northern communities and the province. 3.3 SITE The site is located approximately seven kilometres southwest from the City of Fort St. John in northeastern B.C. Worker accommodation camps are proposed for both sides of the Peace River to provide the safest and most efficient work site access. 5

Figure 1 presents the general location of the north and south bank worker accommodation camps. Figure 1 General Location of North and South Bank Camps North Bank Camp The north bank camp is planned to be built in the first year of construction and to operate through to the end of the Site C construction phase, with a capacity for approximately 500 workers. In addition to the camp facilities, the site would include general and commuter parking, offices and shuttle stops. South Bank Camp The south bank camp is planned to be built following the north bank camp and to operate through to the end of Site C construction phase as required. The peak work force at the south bank camp is anticipated to be 1,200 workers. In addition to the camp facilities, this site would include supporting facilities, restricted parking, offices and shuttle stops. Where possible, workers would be housed in the north or south camp based on the location of their work site. 6

3.4 SCOPE The camps are anticipated to be self-sustaining and typically include the elements listed in the following table. Table 1 Anticipated Camp Elements Accommodation Operations Services* Maintenance Services Bedrooms Washrooms Kitchen and dining facilities Washing and laundry facilities Recreation and leisure facilities Offices Transportation stops Parking Roads Grid electricity and other fuel supply Water supply, treatment, and distribution Wastewater Landscaping Perimeter fencing Food services Recreation services Housekeeping Commissary Fire protection and fire-fighting Medical services and first-aid Security Water supply, treatment and distribution Solid waste management (recycling and disposal) Liquid waste management Telecommunications Shuttle service Pest control Help desk services General management Grounds maintenance and landscaping Utilities maintenance * The items listed in the table relate to the Contract and not to Site C construction activities. Both camp utilities and infrastructure are to be planned to accommodate the potential peak occupancy. 3.5 REGULATORY APPROVALS AND PERMITTING Site C is undergoing a cooperative environmental assessment by the federal and provincial environmental assessment agencies, which includes a Joint Review Panel process. The environmental assessment process for Site C started in August 2011 and is anticipated to take approximately three years to complete; Site C is currently in the Joint Review Panel stage. Site C requires environmental certification and other regulatory permits and approvals before it can proceed to construction. 3.6 ADVANCE WORK BC Hydro anticipates engaging third party contractors to clear, grub and strip the north camp and south camp sites. BC Hydro also anticipates providing the north camp and the south camp with connection points to the electricity grid, a central communications system and road access to the camp locations. 7

3.7 GENERAL RESPONSIBILITIES Table 2 identifies and describes the elements of the Contract that will be delivered by Project Co, and the elements that will be delivered, managed or owned by BC Hydro. Table 2 General Responsibilities Responsibility Description Elements delivered by Project Co Design and Construction Design, construction and commissioning of the accommodation and site servicing elements identified in Table 1 including site preparation and obtaining all permits and approvals necessary for construction excluding permits obtained by BC Hydro Operations Provide the operations services listed in Table 1. Facilities Maintenance Services Provide the maintenance services listed in Table 1. Furniture and Equipment Finance End of Term Elements delivered by BC Hydro Approvals Power supply Payments Supply and installation of furniture and equipment, including equipment that is integral to the design such as building mechanical, electrical, telecommunications, security and other systems. It is anticipated that BC Hydro will make no payments during construction of the worker accommodation infrastructure. Following completion of construction of the worker accommodation infrastructure, BC Hydro intends to make a substantial completion payment for the majority of the construction costs and Project Co will be required to provide all other required financing. Decommissioning and removal of temporary facilities and reclamation of the site. Obtaining environmental certification and other regulatory permits and approvals, and decisions to proceed. BC Hydro grid electricity supply for heating, lighting and other systems for the operations period. Substantial completion payments to Project Co for eligible construction costs following construction of the worker accommodation infrastructure and service payments commencing when the worker accommodation is available for use. 8

3.8 PROJECT TEAM 3.8.1 BC Hydro BC Hydro is a Crown corporation owned by the Province of British Columbia. BC Hydro was created to generate and deliver clean, reliable and competitively priced electricity to its 1.9 million customers. BC Hydro serves 95 per cent of B.C. s population and invests in the electrical system and in energy conservation to meet the needs of its customers. BC Hydro operates 31 hydroelectric facilities and three thermal generating plants, totalling approximately 12,000 megawatts (MW) of installed generating capacity. Additional information about BC Hydro is available at: www.bchydro.com 3.8.2 Partnerships BC Partnerships British Columbia Inc. ( Partnerships BC ) is managing the Competitive Selection Process on behalf of BC Hydro for the Contract. Additional information about Partnerships BC is available at www.partnershipsbc.ca. 9

4.0 THE COMPETITIVE SELECTION PROCESS BC Hydro intends the competitive selection process to be a two-stage process as follows: Request for Qualifications ( RFQ ) Request for Proposals ( RFP ) Table 3 provides an outline of the competitive selection process. Table 3 Competitive Selection Process Stage Request for Qualifications Request for Proposals Description Identify and select respondents who will be invited to respond to the RFP. The RFQ sets out the information requested from respondents, and the evaluation criteria that will be used to evaluate responses. BC Hydro intends to shortlist a maximum of three respondent teams who will then be invited to submit proposals based on the specifications that will be included in the RFP. Proponents will be invited to submit proposals based on the performance specifications, the final draft contract, and requirements included in the RFP. The RFP will detail the business opportunity to which proponents will be invited to submit proposals. It is anticipated that a technical submission addressing technical aspects of the RFP will be submitted in advance of the financial submission. Collaborative Discussion Process: o o o Contract: o o o BC Hydro expects the RFP process to include a series of collaborative meetings with each proponent. The purpose of such meetings is to aid proponents in submitting quality proposals that effectively address the needs of BC Hydro. Meetings will typically include: program, design, operations, maintenance and commercial/legal. The draft contract will be included with the RFP. Proponents will be invited to provide comments on the draft contract and BC Hydro will respond to these comments while the RFP is open. Prior to the close of the RFP, BC Hydro will issue a contract in final form to which the proponents will be expected to provide a proposal. 4.1 TRANSPARENCY OF THE COMPETITIVE SELECTION PROCESS The RFQ and RFP will be public documents, although only respondents short-listed through the RFQ process will be invited to respond to the RFP. The number of respondents and the names of the shortlisted teams will be made public. 10

A fairness advisor will issue reports documenting the procurement process from a fairness perspective and provide an unbiased opinion on the fairness of the entire competitive selection process. The fairness advisor s reports will be publicly available. The entire process is subject to the Freedom of Information and Protection of Privacy Act (FOIPPA). 4.2 PARTIAL COMPENSATION BC Hydro will not pay any partial compensation during the RFQ stage. BC Hydro intends to offer partial compensation in the amount of $200,000 to a maximum of three unsuccessful proponents in accordance with the terms of the RFP. 11

5.0 CONTRACT SCHEDULE Table 4 provides BC Hydro s estimated timeline for the Contract competitive selection process. Activity Table 4 Estimated Contract Timeline Timeline RFQ issue date Respondent Information Meeting March 12, 2014 RFQ Submission Time April 30, 2014 Due Diligence Period May 2014 Announce Proponents June 2014 Issue RFP and Draft Project Agreement to Proponents June 2014 Collaborative Meetings Summer 2014 Issue Final Draft Project Agreement October 2014 Submission Time for Technical Submissions October 2014 Submission Time for Financial Submissions December 2014 Selection of Preferred Proponent January 2015 Fabrication Commences (Limited Notice to Proceed) January 2015 Financial Close March 2015 Substantial completion of phase one Summer/Fall 2015 The RFQ for the Contract can be found on BC Bid at www.bcbid.gov.bc.ca, document number 1807. 12