GALT JOINT UNION HIGH SCHOOL DISTRICT August 16, 2017 MEASURE E BOND UPDATE BIWEEKLY REPORT Report No: 007

Similar documents
Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents

Southern Kern Unified School District

Morgan Hill Unified School District

Massachusetts Bay Transportation Authority. POLICIES & PROCEDURES Design Build Procurement Procedures April 2016

The School Facility Program

SANTA ROSA CITY SCHOOLS DISTRICT. 211 Ridgway Avenue Santa Rosa, CA Request for Proposals For Architectural Services

Request for Qualifications (Architect / Engineer) State of Ohio Standard Forms and Documents

Owner s Meeting Minutes /03/08

AWARD OF CONSTRUCTION CONTRACT CONTRACTOR: REYES CONSTRUCTION, INC. BERTH 100 WHARF SOUTH EXTENSION AND BACKLANDDEVELOPMENT SPECIFICATION NO.

SEQUOIA UNION HIGH SCHOOL DISTRICT BACKGROUND INFORMATION FOR AGENDA ITEMS FOR 7/22/15, BOARD MEETING

You Passed Your Bond Now What? a Part 2: Conflicts of Interest, Procuring Key Team Members, and Citizens Bond Oversight Committees

PAULY ELEMENTARY SCHOOL RELOCATABLES P1-P5 & R23-R26

MICHAEL N. FEUER CITY ATTORNEY REPORT RE:

REQUEST FOR QUALIFICATIONS PROJECT AND CONSTRUCTION MANAGEMENT CONSULTANT

School Facility Program Review Fall Conference Responses from Membership SUMMARY OF NEW PROGRAM CONCEPTS COLLECTED

SCOPE OF WORK. Project No. A STATE OF NEW JERSEY Honorable Chris Christie, Governor Honorable Kim Guadagno, Lt. Governor

Attention Design Firms

Request for Qualifications and Proposals (RFQ/P) #564. for. Program and Construction Management Services

LUTHER BURBANK HIGH SCHOOL ATHLETIC SPORTS CENTER Progress Meeting 2/4/10

JOINT CONSTRUCTION OUTREACH & PROGRAM UPDATES

RESOLUTION NUMBER 2877

POLICY 6800 PROCUREMENT

Minnesota s Capital Investment Process: What Cities Should Know. Webinar for the League of MN Cities May 2, 2017

1.0 Purpose Scope Acronyms, Terms and Definitions... 3

REQUEST FOR QUALIFICATIONS AND REQUEST FOR PROPOSALS FOR ARCHITECTURAL SERVICES CROMWELL BELDEN PUBLIC LIBRARY TOWN OF CROMWELL, CONNECTICUT

REQUEST FOR QUALIFICATIONS. General Contractor Construction Manager (GC/CM) Services. Modernization Project

Long Beach Unified School District Measure K Citizens' Bond Oversight Committee 2015 Annual Report. April 7, 2016

NEW HAVEN UNIFIED SCHOOL DISTRICT REQUEST FOR BID

Chabot-Las Positas Community College District

DORMITORY AUTHORITY OF THE STATE OF NEW YORK (DASNY) on behalf of the. HIGHER EDUCATION CAPITAL MATCHING (HECap) GRANT PROGRAM BOARD

REQUEST FOR QUALIFICATIONS AS-NEEDED CONSULTING PROJECT MANAGER

Informational Workshop How to do Business with the City of Irvine March 31, 2011

LACCD BOND PROGRAM UPDATE AND PATHWAY TO THE FUTURE

Chabot-Las Positas Community College District

TOPIC: CONTRACTS STATE OF MISSISSIPPI DEPARTMENT OF EDUCATION SECTION 17.0 PAGE 1 OF 38 EFFECTIVE DATE: MAY 1, 2017 REVISION #4: MARCH 1, 2017

Below are five basic procurement methods common to most CDBG projects:

STATE UNIVERSITY CONSTRUCTION FUND P R O G R A M D I R E C T I V E S

REQUEST FOR QUALIFICATIONS. Architectural/Engineering Design Services

Mandatory Site Visit: Thursday, July 13, :00 PM (Pierson Library, Shelburne, VT)

#NLCU. Lessons Learned from Crisis Leadership

MEETING SOLE SOURCE REQUIREMENTS UNDER PROPOSITION 39 SOLE SOURCE PROCESS UNCERTAINTIES

North Dakota State University. Minard Hall Project Status Summary As of September 30, 2011

ARCHITECTURAL, LANDSCAPE, AND ENGINEERING CONSULTING SERVICES

Request for Proposals Architectural Services Re: Fremont High School (RFP No date advertised July 17, 2014) ADDENDUM No. 2 (AUGUST 7, 2014)

City of Batavia Downtown Improvement Grant

REQUEST FOR PROPOSALS PROFESSIONAL ARCHITECTURAL FIRM FOR DESIGN & CONSTRUCTION MANAGEMENT SERVICES

Request for Qualifications. On-Call Landscape Architectural Services. In the City of Dublin, Alameda County. Responses Due:

TOPIC: CONTRACTS STATE OF MISSISSIPPI DEPARTMENT OF EDUCATION SECTION 17.0 PAGE 1 OF 49 EFFECTIVE DATE: JULY 1, 2018 REVISION #4: JULY 1, 2018

A Guide to. Starting a Business. Auburn, GA

Request for Proposals: Non-Profit Housing Corporation Property Acquisition and Renovation

School Board of Brevard County, Florida Half-Cent Sales Surtax Internal Audit Fiscal Year

- j / <-, rei BOARD OF AIRPORT COMMISSIONERS. e:t. Flin hief Executive Officer REPORT TO THE

Request for Qualifications (Architect / Engineer) State of Ohio Standard Forms and Documents

SECTION 9: FORMAL PROCEDURES

TRANSMITTAL TO CATE COUNCIL FILE NO Deborah Flint. Executive Director Department of Airports

This request for qualifications seeks the following type of service providers:

COMMUNITY CONSOLIDATED SCHOOL DISTRICT West Dundee Road Wheeling, IL REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT SERVICES

Request for Proposals Construction Services Workplace Excellence Project

REQUEST FOR PROPOSALS

UNIVERSITY OF THE VIRGIN ISLANDS ADMINISTRATION AND CONFERENCE CENTER ST. THOMAS CAMPUS 9:00 A.M. CONSENT AGENDA

WEST VIRGINIA HIGHER EDUCATION POLICY COMMISSION REQUEST FOR PROPOSALS VERIFICATION AND DOCUMENT MANAGEMENT SERVICES RFP #19007.

Office of Business and Financial Services Procurement and Contracts Division Section SUBJECT: PROCUREMENT OF CONSTRUCTION SERVICES

CHAPTER Committee Substitute for Committee Substitute for Committee Substitute for House Bill No. 865

REGULAR MEETING OF THE CITIZENS OVERSIGHT COMMITTEE

POOL ACCOUNT CHART ACCOUNT CODE ACCOUNT TITLE. Page 1 of 6

OVERVIEW OF GRANTS ADMINISTRATION PROCESS

2016 Leroy F. Greene Design + Planning Awards. Submittal Guidelines

Salida School District, R-32-J Central Administration Office 310 East 9 th Street Salida, Colorado 81201

REQUEST FOR QUALIFICATIONS (RFQ) AIRPORT ARCHITECTURAL AND ENGINEERING SERVICES AGREEMENT MINOT INTERNATIONAL AIRPORT

PROCUREMENT PLAN N/A. Date of First Procurement Plan: 31 May 2017 Date of this Procurement Plan: 3 September 2018, Version 2

Before we begin, the OCR has a new website format that has changed how the CDBG section is accessed. Once on the main HCR website you will first

Request for Qualifications Construction Manager

RESTORE Program - Residential Emergency Services to Offer (Home) Repairs to the Elderly Program Year 2014 Request for Proposals (RFP)

Measure H Update CITIZEN S BOND OVERSIGHT COMMITTEE (CBOC) JANUARY 11, 2016

Request for Qualifications (RFQ) Indefinite Delivery Indefinite Quantity (IDIQ) Athletic Facility Architectural Services

REQUEST FOR PROPOSALS ROCHESTER SCHOOLS MODERNIZATION PROGRAM (PHASE 2) PROGRAM MANAGEMENT SERVICES

Southern Dallas GO Bond Program Public/Private Partnership Amendment

Denver Public Schools 2008 Bond Program

Duwayne Brooks Murdoch, Walrath & Holmes

DOING BUSINESS WITH THE. Orange County Board of County Commissioners. Orange County Procurement Division

Project Implementation: From RFP to Project Closeout

Original Revision Total Project Budget: $14,530,000 $47,700,000 $62,230,000 District Funding Commitment Anticipated State Match: $14,530,000 $N/A

Request for Proposal (RFP) The Klamath Tribes Youth Fitness Center Klamath Tribes Housing Department (KTHD) RFP # 09-KTHD17

Pierce Joint Unified School District P.O. Box 239 Arbuckle CA (530) Fax (530)

CAMPBELL UNION HIGH SCHOOL DISTRICT

Attachment A. Procurement Contract Submission and Conflict of Interest Policy. April 23, 2018 (revised)

CHAPTER House Bill No. 5013

Agenda (Items may be taken out of order) IV. SUMMARY NEXT MEETING... Ernest H. Moreno

SONOMA COUNTY JUNIOR COLLEGE DISTRICT. RFQ #1054 for Engineering & Design Services For Districtwide Energy Management/Sustainability Projects

Galt Joint Union High School District Marengo Rd Galt, CA Elizabeth Kaufman, Superintendent REQUEST FOR QUALIFICATIONS / PROPOSALS

Attention Design Firms

MEMORANDUM. July 7, 2016

REQUEST FOR PROPOSAL FOR DESIGN (ARCHITECTURAL & ENGINEERING) SERVICES

Community Development Block Grant Applicant Guide

Agenda (Items may be taken out of order)

REQUEST FOR PROPOSAL FOR BUILDING LEASE

Page 1 of 10 Chicago Infrastructure Trust Joint Public Safety Training Academy - RFQ Clarifications - November 9, 2017

REQUEST FOR PROPOSALS (RFP) For Electrical Engineering Design Services City Hall Switchgear Replacement October 28, 2016

CITY OF PORT ARANSAS, TEXAS REQUEST FOR PROPOSAL (RFP) FIRE STATION TEMPORARY FACILITY NOTICE TO BIDDERS

REQUEST FOR PROPOSAL For East Bay Community Energy Technical Energy Evaluation Services

Transcription:

GALT JOINT UNION HIGH SCHOOL DISTRICT August 16, 2017 MEASURE E BOND UPDATE BIWEEKLY REPORT Report No: 007 SUMMARY Program refinement of the Master Plan is nearing completion. LHRS stadium is out to bid and Galt HS Phase 1 modernization plans are being developed. Prop 39 Energy projects are underway. The team continues progress in setting up program controls, project planning, bid preparation, coordination and setting up general procedures. 1. Initial Project Sequencing A. Preliminary Projects 1. Temporary Bleachers GHS - The bleacher vendor installed a 12 Wide x 24 Long platform on the upper section of seating to serve as a press box. This platform will be in place until the bleachers are shipped back in November. Maintenance and Operations has restored power to the platform and has activated the scoreboard and clock. A temporary sound system will be in place prior to the first game. 2. Uninhabited Portables @ GHS a. Abatement: Synergy Environmental completed abatement. b. Hazmat Consultant: Terracon/RGA Environmental was responsible for inspection and monitoring. The consultant has monitored the abatement scope and is completing closeout documentation. Abatement is complete. c. Demolition: An informal bid package was released for demolition under the Uniform Public Construction Cost Accounting Act (UPCCAA) procedures. Three Bids were received on July 12 th ($72,000, $81,770 and $149,800). The second bidder protested the low bidder who failed to submit a couple of affidavit forms with their bid (Non Collusion Declaration, Prevailing Wage Certification and Workman Compensation Certification). District counsel reviewed the matter and assisted in issuing a letter to the second bidder indicating that their complaint is without merit and that the district intended to award. The contractor issued a second letter indicating their objection and wanted to defer the matter to their attorney. District council issued a second letter elaborating on the District s determination and cited applicable case law. As of Wednesday morning (8/2) no further objection was received and counsel advised the District to proceed with award. The contractor was mobilized and completed the demolition prior to start of school on August 15 th. Final cleanup and site restoration is yet to be completed. d. Site Restoration: Rainforth Grau provided a basic concept plan for site restoration for the area currently occupied by portables based on input provided by the GHS Principal and Plant Manager during a site walk. The current Scope includes irrigation, grass and some fencing across the

back. GHS Agriculture department has voiced interest in using the site. Final decision regarding restoration will be coordinated with Kelly Beck. Fencing bids have been received. A fencing contractor is set up and scheduled to install fencing in mid-september. A temporary safety fence has been installed. Site restoration/landscape and permanent fencing to begin in September. B. Prop 39 Energy Projects 1. Three separate bid packages were issued for Galt HS: a. Lighting Retrofit Project was rebid. Bids were due on July 13 th. Three bids were received from bidders who responded to the prior bid and withdrew for errors. Bids were: $153,403, $167,682.40 and $185,000. Award went to Green Energy @ $153,403 and contractor has begun work. The energy expenditure plan covered 20% of the ballast replacement to encumber the balance of the grant. Additional ballast will be purchased under the grant as replacement stock. b. HVAC Replacements The Project has been tentatively awarded. Contracts and Bonds are in process. Equipment Submittals for the new equipment and pre construction procurement activities are also in process. The Prop 39 Energy consultant and contractor are evaluating equipment options. After looking at various equipment, all new equipment options appear to exceed the weight of the current equipment, so structural analysis and approval by DSA will become necessary. Contractor, Cooper Oates, has provided a price proposal for their structural engineer to review and provide calculations for $1,500. The structural engineer has completed calculations necessary to substantiate that there are no structural impacts to the buildings. Contracts, bond forms and insurance requirements have been issued to the contractor. Once executed, a Notice to Proceed will be issued and work can commence. c. Energy Management Control (EMS) Upgrades - The Project has been awarded. Contractor has been on site setting up and evaluating existing conduit runs, adding new raceways and pulling wires. The energy expenditure plan only covered certain equipment to encumber the balance of the grant. To connect the entire campus, additional zones can be added to the contract or deferred to modernization phases. We are currently reviewing options. C. New Grandstands 1. Bids were received for both Galt HS and Liberty Ranch HS (LRHS) and were awarded at the June 20 th Board meeting. 2. The Architect has contacted Southern Bleacher Company to discuss some Value Engineering options to try to reduce costs. VE options have been reviewed and discussed at the past Board meeting and are being implemented. 3. Southern Bleachers is completing their engineered drawings and specifications for DSA submittal. D. Field Improvements 1. Design documents are being completed by Rainforth Grau and Lloyd Civil and Sports Engineering for LRHS athletic field.

2. DSA approval of the Increment 1 site package (including grading, field, track and paving) has been obtained. Increment 2 grandstands and lights are tentatively scheduled to be submitted to DSA for normal review process in late August. 3. The increment 1 Bid has been issued. Bids are due August 29 th. However it is likely the bid date will be delayed in order to accommodate any questions from bidders through issuance of addenda as needed. 4. Construction tentatively scheduled to begin in October 2017. E. Galt High School Core Building Modernization Phase 1 1. Development of detailed scope is ongoing. Phase 1 work focuses on roofing and HVAC of shops / historic buildings as well as replacement of northern windows. Additionally, work as required for ADA improvements in admin parking lot, path of travel and around buildings is part of this scope. Scope to be finalized by funding availability. Hazmat testing of the subject buildings is currently being coordinated. 2. Construction documents are ongoing. 3. DSA submittal is currently scheduled for September 2017. F. Galt High School - Science Technology Engineering Building 1. Floor plans have been developed with Site Planning Group and building development is ongoing. 2. Site Planning Group has provided direction on preferred building configuration based on need for best line of sight and visual control. 3. RGA, Facilities and RGM to meet with Meehleis Modular Buildings Incorporated (MMBI). 4. RGA has met with MMBI and provided schematic design documents for pricing. MMBI will provide budget costs as well as engineering costs in August. 2. Program Development A. Planning 1. Continue Master Plan refinement and coordination. 2. Develop Master Education Specifications. 3. Develop Design Standards (Board resolution is required for any identified proprietary products or vendors). 4. Refine master program schedule as stakeholder engagement and design evolves. B. Cash Flow Analysis / State Funding Opportunities School Facility Consultants attended the July 7 team planning meeting and provided an update to the State funding program, process and the District s eligibility. 1. Team continues to review bond sale options and cash flow analysis as the master plan and schedules are being refined. 2. School Facility Consultants will continue to update the District on State funding prospects for Growth and Modernization. a. Explore grant augmentation options (for GHS infrastructure support). 3. Team will explore additional funding opportunities for Career Technology Education (CTE) Program Grants. 4. Team will review Facility Hardship Program funding options.

5. Team will develop Cash Flow Analysis to align projects and projected expenditures with bond issuances and potential state funding. 6. Team also exploring the opportunity for obtaining QZAB funding opportunities that may help bridge the gap waiting for State Prop 51 funds. C. Project Designs 1. Upon final Master Plan refinement, Architects will advance all project designs through the Division of State Architect (DSA) regulatory and CDE review, necessary to apply for state funding with OPSC. 2. Rainforth Grau will provide updated schedule upon completion of the MP refinement as they get their consultants engaged in developing the project plans. 3. Bid and Contract Documents - Procurement Procedures A. Documents from Counsel 1. Bid and Contract Documents have been received from Legal counsel. a. Baseline templates for all projects and various delivery methods including Lease Leaseback (LLB), traditional formal and informal bidding, General and Special Conditions, and project procedures and coordination requirements (Division 1) are being prepped. 2. Lease Leaseback a. Currently developing LLB process and schedule for issuing Request for Proposal(s) (RFPs). This will be done in conjunction with the District s prequalification process. 3. Liberty Ranch Field a. LRHS field project will be a formal competitive public bid process. 4. Galt High School Core Building Modernization Phase 1 a. At this time, project will be a formal competitive public bid process. 5. Prequalification Criteria Counsel will amend the Board resolution to include traditional and informal bidding since it is currently limited to just Lease Leaseback (LLB). Team anticipates bringing a resolution to the board to amend the current process to include informal and formal bidding. A Prequalification process will be initiated in September to identify a pool of qualified prime and Mechanical, Plumbing and Electrical trade contractors pursuant to newly adopted regulations. 6. CEQA Environmental Processing On June 20 th, the Board approved engaging an environmental specialist, Planning Dynamics Group (PDG), to review the previous EIR for the LRHS stadium lighting and other improvements, and guide the District through an environmental review process to renew implementation of scope approved in the previous EIR. Contracts and initial engagement are in place. Other bond projects appear to qualify for an exemption. The initial study report draft was circulated on August 4 th for District, RGA and RGM input. It has been updated, printed and is being submitted to the State Clearinghouse for publication and agency review. The document continues to be in public review period.

It is anticipated that Board action on the environmental documents will occur at the September 12 th, 2017 meeting and will coincide with awarding of the LRHS field construction contract. 7. Communications and Coordination 8. Scheduling A. Responsibility Matrix 1. Team is currently developing a matrix to better define roles and responsibilities between District, Architect, PM and other key participants and stakeholders. B. Communications 1. Team has initiated discussions for communications including website updates, posting bid and RFQ opportunities, project design updates, and to promote community and stakeholder meetings. Development of the Master Program Schedule will be initiated shortly and will outline planning, procurement, design, and construction activities in accordance with the proposed Implementation Plan. As programing is being completed and project packaging and phases are being determined and developed, more detailed schedules will be provided. 9. Budgets and Estimating A. After completion of the master plan refinement, a preliminary probable cost estimate will be updated for each project and reconciled with the facilities master plan estimates, as well as other program-related costs. B. To check scope and cost trends, detailed estimating will be conducted as each design progresses. C. Master and individual project budgets will be developed to include construction, soft costs, IT, furniture and equipment, and contingencies. 10. Expenditure Tracking Financial Reporting The District is reviewing software options for developing expenditures, formats, account codes and reporting summaries for internal, Board and CBOC. 11. California Uniform Public Construction Cost Accounting Act (CUPCCAA) Informal Bid Procedures The District adopted the CUPCCAA procedures for informal bidding by Board resolution in March. Under the adopted procedures, the District will develop a list of vendors to contact with each informal bid opportunity. As the list is being developed, the District will post to designated plan rooms and trade journals in lieu of newspaper advertising. END OF REPORT