Exhibit R-2, RDT&E Budget Item Justification: PB 2011 Air Force DATE: February 2010 COST ($ in Millions) FY 2009 Actual FY 2010 FY 2012 FY 2013 FY 2014 FY 2015 Program Element 13.322 9.915 9.933 0.000 9.933 10.061 10.224 10.366 10.524 Continuing Continuing 674137: Launch and Test Range System 13.322 9.915 9.933 0.000 9.933 10.061 10.224 10.366 10.524 Continuing Continuing A. Mission Description and Budget Item Justification The Eastern Range (ER) at Patrick Air Force (AFB)/Cape Canaveral Air Force Station, FL, and the Western Range (WR) at Vandenberg AFB, CA, make up the Spacelift Range System (SLRS), also known as LTRS. They provide tracking, telemetry, communications, flight safety, and other capabilities to safely conduct: national security, civil, and commercial spacelift operations; ballistic missile and missile defense evaluations; and aeronautical and guided weapons tests. Decreasing reliability of aging range systems forces the AF to use redundant assets during launches to ensure range availability, increasing operations and maintenance costs. The AF is addressing range deficiencies in FY11 via multiple contracts. The Range Standardization and Automation (RSA) IIA contract (OPAF only in FY11) modernizes control/display and communications systems. The SLRS (SLRSC) modernizes command, telemetry, and radar instrumentation; and provides systems engineering, architecture management, and system level testing. RSA IIA and SLRSC end in FY11. The AF awarded a follow-on systems engineering and integration contract in Dec 09 and will award a follow-on modernization and sustainment contract in FY11. Planned communications system upgrades will comply with OSD policies and standards for netcentricity, global information grid interface, information assurance, and test/training enabling architecture. These upgrades to fielded systems are categorized as Budget Activity 7, Operational Systems Development. Air Force Page 1 of 11
Exhibit R-2, RDT&E Budget Item Justification: PB 2011 Air Force DATE: February 2010 B. Program Change Summary ($ in Millions) FY 2009 FY 2010 Previous President's Budget 12.322 9.957 0.000 0.000 0.000 Current President's Budget 13.322 9.915 9.933 0.000 9.933 Adjustments 1.000-0.042 9.933 0.000 9.933 Congressional General Reductions -0.042 Congressional Directed Reductions 0.000 Congressional Rescissions 0.000 0.000 Congressional Adds 0.000 Congressional Directed Transfers 0.000 Reprogrammings 0.000 0.000 SBIR/STTR Transfer 0.000 0.000 Other Adjustments 1.000 0.000 9.933 0.000 9.933 Change Summary Explanation FY09: AF increase of $1M for systems engineering. Air Force Page 2 of 11
Exhibit R-2A, RDT&E Project Justification: PB 2011 Air Force DATE: February 2010 COST ($ in Millions) FY 2009 Actual 674137: Launch and Test Range System FY 2010 FY 2012 FY 2013 FY 2014 FY 2015 13.322 9.915 9.933 0.000 9.933 10.061 10.224 10.366 10.524 Continuing Continuing Quantity of RDT&E Articles 0 0 0 0 0 0 0 0 0 A. Mission Description and Budget Item Justification The Eastern Range (ER) at Patrick Air Force (AFB)/Cape Canaveral Air Force Station, FL, and the Western Range (WR) at Vandenberg AFB, CA, make up the Spacelift Range System (SLRS), also known as LTRS. They provide tracking, telemetry, communications, flight safety, and other capabilities to safely conduct: national security, civil, and commercial spacelift operations; ballistic missile and missile defense evaluations; and aeronautical and guided weapons tests. Decreasing reliability of aging range systems forces the AF to use redundant assets during launches to ensure range availability, increasing operations and maintenance costs. The AF is addressing range deficiencies in FY11 via multiple contracts. The Range Standardization and Automation (RSA) IIA contract (OPAF only in FY11) modernizes control/display and communications systems. The SLRS (SLRSC) modernizes command, telemetry, and radar instrumentation; and provides systems engineering, architecture management, and system level testing. RSA IIA and SLRSC end in FY11. The AF awarded a follow-on systems engineering and integration contract in Dec 09 and will award a follow-on modernization and sustainment contract in FY11. Planned communications system upgrades will comply with OSD policies and standards for netcentricity, global information grid interface, information assurance, and test/training enabling architecture. These upgrades to fielded systems are categorized as Budget Activity 7, Operational Systems Development. B. Accomplishments/Planned Program ($ in Millions) Major Thrust: Modernize timing and safety systems to complete activation of Western Range (WR) Operations Control Center. Modernize telemetry, radar, and command destruct instrumentation on WR and... FY 2009 FY 2010 12.776 9.340 3.685 0.000 3.685 Air Force Page 3 of 11
Exhibit R-2A, RDT&E Project Justification: PB 2011 Air Force DATE: February 2010 B. Accomplishments/Planned Program ($ in Millions) FY 2009 Accomplishments: In FY 2009: Continued critical design reviews, system security accreditations, system integration testing, antenna pointing system software development, and preparations for operational testing. FY 2010 Plans: In FY 2010: Continued critical design reviews, system security accreditations, system integration testing, antenna pointing system software development, and preparations for operational testing. Plans: In : d critical design reviews, system security accreditations, system integration testing, antenna pointing system software development, and preparations for operational testing. Transitioned efforts to operational testing/acceptance. Plans: In : N/A FY 2009 FY 2010 Major Thrust: Conduct independent systems engineering and integration (SE&I) effort starting in FY10. Continue systems engineering efforts previously accomplished under SLRSC. FY 2009 Accomplishments: In FY 2010: Initiated follow-on, separate systems engineering and integration effort. 0.000 0.175 5.948 0.000 5.948 FY 2010 Plans: In : Continue follow-on, separate systems engineering and integration effort. Support completion of SLRSC and transition to follow-on modernization/ improvement contract. Plans: In : N/A Air Force Page 4 of 11
Exhibit R-2A, RDT&E Project Justification: PB 2011 Air Force DATE: February 2010 B. Accomplishments/Planned Program ($ in Millions) Plans: In : Not Applicable. FY 2009 FY 2010 Major Thrust: Provide program support, to include System Program Office operations, SETA, and FFRDC. FY 2009 Accomplishments: In FY 2009: Continued engineering support from Aerospace (FFRDC). 0.546 0.400 0.300 0.000 0.300 FY 2010 Plans: In FY 2010: Continued engineering support from Aerospace (FFRDC). Plans: In : Continue engineering support from Aerospace (FFRDC). Plans: In : N/A Accomplishments/Planned Programs Subtotals 13.322 9.915 9.933 0.000 9.933 C. Other Program Funding Summary ($ in Millions) Line Item FY 2009 FY 2010 FY 2012 FY 2013 FY 2014 FY 2015 PE 0305182F: Spacelift Range 99.086 99.975 91.004 0.000 91.004 107.629 106.619 104.514 106.412 0.000 0.000 System Space, OPAF 2.948 2.948 2.978 0.000 2.978 3.032 3.082 3.126 3.178 0.000 0.000 Air Force Page 5 of 11
Exhibit R-2A, RDT&E Project Justification: PB 2011 Air Force DATE: February 2010 C. Other Program Funding Summary ($ in Millions) Line Item FY 2009 FY 2010 PE 0305182F (1): Spares and Repair Parts, OPAF FY 2012 FY 2013 FY 2014 FY 2015 D. Acquisition Strategy The AF is using two competitively awarded, complementary contracts, managed by the Space and Missile Systems Center, to modernize the ranges on a minimalinterference basis as they continue to support operational launches and tests. The AF competitively awarded a follow-on systems engineering and integration contract in Dec 09 and will competively award a follow-on modernization/improvement contract in late FY11. E. Performance Metrics Please refer to the Performance Budget Overview Book for information on how Air Force resources are applied and how those resources are contributing to Air Force performance goals and most importantly, how they contribute to our mission. Air Force Page 6 of 11
Exhibit R-3, RDT&E Project Analysis: PB 2011 Air Force DATE: February 2010 Product Development ($ in Millions) Category Item Range Standardization and Automation IIA Spacelift Range System Follow-on modernization and improvement contract Separate systems engineering and integration contract Remarks Method & Type C/CPAF C/CPAF C/CPIF C/CPIF Performing Activity & Location Lockheed Martin Santa Maria, CA ITT Industries Cape Canaveral, FL TBD TBD Booz Allen and Hamilton McLean, VA Prior Years FY 2010 Target Value of 335.704 0.000 0.000 0.000 0.000 0.000 335.704 349.469 169.084 9.340 Oct 2009 3.685 Oct 2010 0.000 3.685 0.000 182.109 Continuing 0.000 0.000 0.000 0.000 0.000 Continuing Continuing Continuing 0.000 0.175 Dec 2009 5.948 Oct 2010 0.000 5.948 Continuing Continuing Continuing Subtotal 504.788 9.515 9.633 0.000 9.633 Support ($ in Millions) Category Item SPO Program Support (FFRDC, SETA, SPO Ops) Method & Type Various Performing Activity & Location Various Various Prior Years FY 2010 Air Force Page 7 of 11 Target Value of 36.917 0.400 Oct 2009 0.300 Oct 2010 0.000 0.300 Continuing Continuing Continuing Various Various 34.353 0.000 0.000 0.000 0.000 0.000 34.353 Continuing
Exhibit R-3, RDT&E Project Analysis: PB 2011 Air Force DATE: February 2010 Support ($ in Millions) Category Item California Space Infrastructure Program Method & Type Performing Activity & Location Various Prior Years FY 2010 Target Value of Subtotal 71.270 0.400 0.300 0.000 0.300 Remarks Prior Years FY 2010 Project s 576.058 9.915 9.933 0.000 9.933 Target Value of Remarks Prior Years may include only FY 2009 data. Air Force Page 8 of 11
Exhibit R-4, RDT&E Schedule Profile: PB 2011 Air Force DATE: February 2010 Air Force Page 9 of 11
Exhibit R-4A, RDT&E Schedule Details: PB 2011 Air Force DATE: February 2010 Schedule Details Event Quarter Year Quarter Year - WR Comm Timing Mgmt System Ops Testing 1 2009 2 2009 - WR Comm Timing Mgmt System Ops Fix, Retest, Acceptance, and Turnover 1 2010 4 2011 - WR Mission Flight Control Center Ops Testing 1 2009 2 2009 - WR Mission Flight Control Center Ops Fix, Retest, Acceptance, and Turnover 1 2010 4 2011 - WR Ops Control Center (WROCC) Ops Testing 1 2009 2 2009 - WR Ops Control Center (WROCC) Ops Fix, Retest, Acceptance, and Turnover 1 2010 4 2011 - Metric Tracking (Telemetry) Final Critical Design Review 1 2009 1 2009 - Metric Tracking (Telemetry) Final Developmental Test 2 2010 3 2010 - Metric Tracking (Telemetry) 1st Site Ops Testing, Acceptance, and Turnover 3 2009 4 2010 - Metric Tracking (Telemetry) 2nd Site Ops Testing, Acceptance, and Turnover 3 2010 4 2010 - Metric Tracking (Telemetry) 3rd Site Ops Testing, Acceptance, and Turnover 3 2010 1 2011 - Metric Tracking (Telemetry) 4th Site Ops Testing, Acceptance, and Turnover 3 2010 2 2011 - Metric Tracking (Radar Open System Architecture) 1st Site Ops Testing, Acceptance, and Turnover - Metric Tracking (Radar Open System Architecture) 2nd Site Ops Testing, Acceptance, and Turnover Start End 1 2009 2 2010 3 2010 2 2011 - Command Destruct (Vehicle Uplink) Final Critical Design Review 1 2009 3 2009 - Command Destruct (Vehicle Uplink) Final Developmental Test 1 2010 4 2010 - Command Destruct (Vehicle Uplink) 1st Site Ops Testing, Acceptance, and Turnover 3 2010 1 2011 Air Force Page 10 of 11
Exhibit R-4A, RDT&E Schedule Details: PB 2011 Air Force DATE: February 2010 Start End Event Quarter Year Quarter Year - Command Destruct (Vehicle Uplink) 2nd Site Ops Testing, Acceptance, and Turnover 4 2010 1 2011 - Command Destruct (Vehicle Uplink) 3rd Site Ops Testing, Acceptance, and Turnover 1 2011 2 2011 - Command Destruct (Vehicle Uplink) 4th Site Ops Testing, Acceptance, and Turnover 3 2011 4 2011 Air Force Page 11 of 11