THE NORTHWEST SEAPORT ALLIANCE MEMORANDUM

Similar documents
PUBLIC NOTICE Application for Permit

CHICAGO AREA WATERWAY SYSTEM (CAWS) DREDGED MATERIAL MANAGEMENT PLAN

TEXAS MARITIME UPDATE

CESAM-RD-M May 2, 2013 PUBLIC NOTICE U.S. ARMY CORPS OF ENGINEERS MOBILE DISTRICT

Jacksonville Harbor Deepening

DEPARTMENT OF THE ARMY ER U.S. Army Corps of Engineers CECW-P Washington, DC Regulation No February 2016

U.S. ARMY CORPS OF ENGINEERS BUILDING STRONG LOS ANGELES DISTRICT

TRIBAL. relations. fosters. sailors from Navy Region Northwest REGION NORTHWEST SAILORS HELP LOCAL NATIVE AMERICAN TRIBES WITH CLAM SEEDING

U.S. Army Corps of Engineers Navigation Program Update

FY 2006 CULTURAL RESOURCES TEAM AWARD NAVY REGION NORTHWEST

PUBLIC NOTICE. Section 404 of the Clean Water Act (33 U.S.C. 1344) Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C.

Land-Water Interface and Service Pier Extension

BIG RIVER COALITION LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT DRIVING THE ECONOMY

ARMY CORPS OF ENGINEERS. Action Needed to Ensure the Quality of Maintenance Dredging Contract Cost Data

Civil Works Process Overview

Appendix I: Native Americans

PUBLIC NOTICE Application for Permit

Implementing the Water Resources Development Act of 2007

CURRENT AND FUTURE STUDIES

U.S. Army Corps of Engineers Navigation Program Update

HOGANSAC th Annual Harbor Safety Committee Conference Seattle, Washington. Good Afternoon I am TF, chair of HOGANSAC

MEMORANDUM OF AGREEMENT BETWEEN THE FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION AND THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY

Appendix F: Native Americans

Shellfish Aquaculture Permitting Program Update

vessel prepares for and actively off-loads two new Post-Panamax gantry cranes to the

GENERAL ASSEMBLY OF NORTH CAROLINA SESSION 2013 SESSION LAW HOUSE BILL 484

2017 Nationwide Permit Reissuance

A history of Innovation & Entrepreneurship

Makah Tribal Council Office of Marine Affairs. EPA Region a Tribal Response Program

FIND Matching and Major Funding Requests. Mid Cycle Funding Requests

Gulf Intracoastal Waterway

USCG Roles Before, During & After a CSZ Event

Office of Coast Survey. Nautical Charting of Artificial Reefs

Contingency Planning, Emergency Management & Marine Transportation Policy Leader

PUBLIC NOTICE.

SUMMARY: By this direct final rule, the Coast Guard is removing. the regulation for the safety zone at Snake Island, also known as

BROWARD COUNTY PORT EVERGLADES

Washington Maritime Blue Strategy Overview and Process Accelerating Innovation for a Sustainable Maritime Future

Appendix C: Public Participation

Update on USACE Civil Works Program Authorities, Policies, and Guidance

WIFIA 2014 Listening Session. Chicago, IL July 22, 2014

2. The EPA provided the following information regarding EPA s activities in Newark Bay during the meeting:

MEMORANDUM OF UNDERSTANDING LANDSCAPE CONSERVATION OF NATURAL RESOURCES IN CALIFORNIA THROUGH THE CALIFORNIA CONSERVATION PARTNERSHIP

Alteration of Bridges

TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M. To: Council Members AGENDA ITEM 5L

FOREST SERVICE MANUAL NATIONAL HEADQUARTERS (WO) WASHINGTON, DC

5Native Americans. Meet its trust responsibilities. Build stable and enduring relationships with tribes through government-to-government contact

Puget Sound Gateway Program

Defense Environmental Funding

CITY OF LAREDO Environmental Services Department

MEMORANDUM. July 7, 2016

Infrastructure Month Tool Kit Talking Points

SPD Emergency Procedures and SPK Regional General Permit 8 for Emergency Actions

PUBLIC NOTICE REQUEST FOR PERMISSION TO ALTER A U.S. ARMY CORPS OF ENGINEERS PROJECT PURSUANT TO 33 U.S.C. SECTION 408

Chairman Farenthold, Ranking Member Plaskett, and Members of the Subcommittee:

Project Design Advance. Nauru: Port Development Project. Project Number: December 2015

U.S. Army Corps of Engineers FY 16 Workplan and FY 17 Budget Navigation Program Update

Corps Regulatory Program Update

USACE 2012: The Objective Organization Draft Report

Lisa Mangione is a Senior Regulatory Project Manager with the Army Corps of Engineers Los Angeles District. She has over 25 years of professional

SUMMARY: The Captain of the Port of New Orleans (COTP New. Orleans), under the authority of the Magnuson Act,, established

Steps 1 2 seek whether the project is feasible.

Direct Component Project Evaluation Form

New Draft Section 408 Policy Document EC

NATURAL RESOURCE AGENCIES

Mount St. Helens Long-Term Sediment Management Plan

Funding Principles. Years Passed New Revenue Credit Score Multiplier >3 years 0% % % % After Jan %

NORTH AND WEST ALASKA COOPERATIVE ECOSYSTEM STUDIES UNIT. AMENDMENT TWO TO COOPERATIVE and JOINT VENTURE AGREEMENT. between

Anchorage Grounds; Galveston Harbor, Bolivar Roads Channel, Galveston, Texas

Northwest Straits Marine Conservation Initiative Sustainability Plan

SANCTUARY OPERATIONS REVISED STRATEGIES AND ACTIVITIES WITH SUMMARY OF AC COMMENTS Submitted to the OCNMS Advisory Council on November 20, 2009

WHOLE WATERSHED RESTORATION INITIATIVE

Stationing and Training of Increased Aviation Assets within U.S. Army Alaska Environmental Impact Statement

jobs program earmark ban

Rational Expectations: The impacts of the Panama Canal Expansion on Gulf Coast ports

Exemptions from Environmental Law for the Department of Defense: Background and Issues for Congress

National Environmental Policy Act/California Environmental Quality Act Scoping Meeting Summary

Corps of Engineers Feasibility Studies

U.S. Army Corps of Engineers Navigation Program Update

Safety Zone; Unexploded Ordnance Detonation, Gulf of Mexico, Pensacola, FL

GAO ARMY CORPS OF ENGINEERS. Peer Review Process for Civil Works Project Studies Can Be Improved

Cleanup Successes and Challenges. James D. Werner Director, Air & Waste Management Division

Kansas AAP, KS Conveyance Progress Report

WHOLE WATERSHED RESTORATION INITIATIVE Request for Proposals for Community-based Habitat Restoration Projects in Oregon and Washington

U.S. ARMY CORPS OF ENGINEERS REPORT TO CONGRESS HOPPER DREDGES

Page 1 of NATIONWIDE PERMIT (NWP) PROGRAM - SUMMARY - ALABAMA CERTIFICATION & PRE-CONSTRUCTION INFOMATION

OSC Readiness Training November Navigating the USCG s NPFC Policies on Accessing the OSLTF

The American Merchant Marine The Missing Link in Cargo Security

Compiled by the Office of Rep. Pramila Jayapal MAY 2018

Security Zones; Naval Base Point Loma; Naval Mine Anti Submarine. SUMMARY: The Coast Guard is increasing a portion of an existing

Port of Bellingham Port Commission District 1 Candidates: Dan Robbins, Michael Shepard

DEPARTMENT OF THE ARMY CORPS OF ENGINEERS, NEW ORLEANS DISTRICT 7400 LEAKE AVE NEW ORLEANS LA September 17, 2018 PUBLIC NOTICE

CPE PROGRAM. The only program of its kind in North America is transforming the management and competitiveness of North American ports.

DEPARTMENT OF THE ARMY. U.S. Army Corps of Engineers, Los Angeles District. Regulatory Division

December 21, 2004 NATIONAL SECURITY PRESIDENTIAL DIRECTIVE NSPD-41 HOMELAND SECURITY PRESIDENTIAL DIRECTIVE HSPD-13

Dave (Sanford) always good to see you again. Ladies & Gentlemen, I m glad to be here

FOSC Prince William Sound January 31, CDR Michael. R. Franklin CG Marine Safety Unit Valdez

Department of Army Permit Evaluation Process

e-navigation Projects

HARBOR INFRASTRUCTURE INVENTORIES Calumet Harbor, Illinois and Indiana

Transcription:

THE NORTHWEST SEAPORT ALLIANCE MEMORANDUM MANAGING MEMBERS Item No. 4B BRIEFING ITEM Date of Meeting December 5, 2017 DATE: November 27, 2017 TO: FROM: Managing Members Ralph Graves, Sr. Director Capital Development, The Port of Seattle Presenter: Bari Bookout, Non-Federal Sponsor Project Liaison SUBJECT: US Army Corps of Engineers Seattle Harbor Navigation Improvement Project A. BRIEFING REQUESTED Status of feasibility study and project timing for the US Army Corps of Engineers Seattle Harbor Navigation Improvement Project B. BACKGROUND As part of the strategic plan for gateway competitiveness, the Port of Seattle partnered with the US Army Corps of Engineers to initiate a deepening project for the Seattle navigation channels. This project will allow the North Harbor terminals to handle the big containerships that are already being deployed in the transpacific trade and accommodate growth for the next 50 years. The project has three distinct stages: Feasibility Study, Preconstruction Engineering & Design, and Construction. The project is nearing the end of the Feasibility Study. C. CURRENT STATUS Industry Trends The shipping industry is rapidly increasing the size of ships to realize savings through economies of scale. These large ships can carry more containers with the same amount of fuel burned by smaller ships. Smaller, less efficient ships have become obsolete and been scrapped. Within the last 10 years, has seen an increase in average ship size, and now sees regular calls of ships in the 10-14,000 TEU range. Almost all of the new ship capacity coming on line are 10,000 TEU and larger ships. The industry is also consolidating to fewer, larger shipping lines. The top 5 shipping lines now control 79% of fleet capacity of ships 9000 TEU and larger. Ports in North America are investing in infrastructure to handle these ships efficiently, and the evolution of ship size is likely to mean consolidation of the industry to fewer, larger terminals that can handle large ships efficiently. These ships have drafts up to 54. With the additional 10% of draft under keel required by the Puget Sound Pilots for safe transit, channel depth needed for a fully laden ship is -57 at Mean Lower Low Water (MLLW). Currently the berths and navigation channels in the North Harbor are 45-50 MLLW.

Page 2 of 5 The Port of Prince Rupert has 60 of water or deeper at berth, and the Ports of LA and Long Beach have either completed, or are in the planning process to construct deeper channels and berths at a majority of their terminals. Because the Pacific Northwest is rich in export cargo like seafood, agricultural and forest products which are very heavy, ships need to be able to arrive and depart our port at their fully laden draft. If ships are restricted in movement by depth, they must either depart without a full payload of cargo, or wait on the tide for enough water. These measures create financial and operational impacts through less efficient ship and terminal operations. Less efficient ship economics could mean our gateway loses future business to those ports with water depth to handle them. USACE Feasibility Study Deepening of Federal Navigation Channels in the United States is performed by the US Army Corps of Engineers. There are three distinct phases to channel deepening, and the process can take 10 years or longer. The stages are (1) Feasibility Study & Environmental Assessment (2) Preconstruction Engineering and Design, and (3) Construction. Each phase requires federal authorization and appropriation of funding, as well as a cost-share agreement by the non-federal sponsor. The Port of Seattle is the non-federal sponsor of this project. In anticipation of increases in ship size and to remain competitive as a gateway, in 2012 the Port of Seattle requested that the US Army Corps of Engineers conduct a feasibility study to evaluate deepening of the navigation channels in the Seattle Harbor. The federal channel in the West Waterway is currently only authorized at -34 and the East Waterway at -50 to -34 in sections, which means there is no obligation on the Corps to do any maintenance dredging at depths greater than the authorization. The Seattle Harbor Navigation Improvement Feasibility Study and Environmental Assessment was federally authorized in 2014, and is expected to be completed by May 2018. The cost share obligation of the Port for the study was $1.5M, with some of the funds contributed as work in kind. Cost Share for Feasibility Study and Environmental Assessment Cost- Description Share Obligation Expenditures to Date Remaining $1.5M $1.1M $400K US Army Corps of Engineers $1.5M $1.2M $300K Total Feasibility Study Expenditure $3 Million $2.3M $700K The US Army Corps of Engineers modeled the economic cost/benefit of deepening the channels by forecasting vessel and trade activity over the next 50 years, and by conducting a detailed simulation of vessel traffic under different depth scenarios. They used a design vessel assumption equivalent to an 18,000 TEU ship with a draft of 52. When the study was begun, this ship size seemed unlikely to be deployed on the West Coast for a number of years. However, in 2016 the CMA CGM Benjamin Franklin, an 18,000 TEU ship, called Seattle on a test run.

Page 3 of 5 The NWSA is already seeing regular calls of 13,000 TEU sized ships and these ships also have a maximum draft of 52. The shipping line deploying these ships recently raised concern about depth of our berth and channels, which are currently 50 in Seattle. The study is expected to be completed in May 2018, with the issuance of the signed Chief s Report. The US Army Corps of Engineers recommended authorization of a National Economic Development Plan (NED) of -56 MLLW and supported authorization of a Locally Preferred Plan (LPP) of (-57 ). To maximize future benefit, the Port of Seattle, in coordination with the NWSA, submitted a letter requesting the Locally Preferred Plan granting an authorization of -57 MLLW. The final Feasibility Report and Environmental Assessment has been completed and the remaining milestone is the Civil Works Review Board, which will take place in January of 2018. If all goes well, the final authorization recommended in the Chief s Report will be -57 MLLW in both the East and West Waterways. The Chief s Report will only be issued if all decision-making authorities including the Federal Government, the EPA, Department of Ecology and the Tribes agree on the recommended authorization. Environmental Review A full environmental assessment was performed by the US Army Corps of Engineers as part of the feasibility study, and was made available for public review and comment. The NWSA and Port of Seattle contributed review and comments at multiple points during the study. Elements of the review included habitat, benthic organisms and other wildlife, water quality, air quality, hydrology, cultural resources, hazardous & toxic waste, and public health and safety. Construction of the Corps channel deepening project will not take place until the other remediation projects in the waterways are completed. These are the East Waterway CERCLA cleanup in the East Waterway and the Lockheed Martin Shipyard CERCLA cleanup project in the West Waterway. Contaminated sediment will be removed from the waterways during these cleanups. For the remaining project area, a preliminary analysis of sediment characteristics was performed during the Feasibility stage and a more detailed analysis will be carried out during design. Any remaining sediment that is unsuitable for open water disposal under DMMP will be transported to upland disposal sites. Mitigation of Impact to Treaty Reserved Fishing Access In addition to economic benefit, the Feasibility Study and Environmental Assessment measures impacts to the environment, including Indian Trust assets and cultural resources. The Muckleshoot Indian Tribe and the Suquamish Tribe are both signatories to the Point Elliott Treaty of 1855, which guarantees the rights of taking fish at usual and accustomed grounds and stations. The usual and accustomed grounds for both tribes overlap the project area, where they harvest salmon and other seafood. Tribes have the authority to participate in all decision making with potential to affect protected treaty fishing. After the Draft Feasibility Report and Environmental Assessment was released for public comment (NEPA) in August 2016, the Muckleshoot Indian Tribe requested a government to government meeting and formally opposed the project due to impact to usual and accustomed treaty fishing, and requested clarification on other elements of the study. The Suquamish Tribe raised similar concerns in a comment letter. The US Army Corps of Engineers will not issue a final Chief s Report, or proceed with construction of the project if objections are raised by Native American tribal interests or other federal agencies.

Page 4 of 5 The Corps worked with the tribes to revise the report language in areas where questions were raised. Under federal policy, it is the non-federal sponsor s responsibility to work through financial impact claims. Since 1995, all Port of Seattle capital port development and marine facility improvement projects within the harbor have included agreements to compensate Treaty tribes for adverse in-water effects on Treaty fishing in instances where displacement of fishing access could not be avoided or minimized. Compensation measures linked with port development have in most cases consisted of payments to the Muckleshoot and Suquamish Indian tribes. The tribes requested mitigation to impacts to Treaty fishing for both the T5 Modernization Project and the North Harbor Deepening Project before allowing either to proceed. The agreements were negotiated simultaneously. The T5 tribal mitigation agreement was approved by Managing Members on August 4, 2017. The mitigation agreement for Seattle Harbor Deepening was reached with the Muckleshoot Indian Tribe and the Suquamish Tribe as described in the attached action memo. Once the agreements are signed, the Tribes will transmit letters to the US Army Corps of Engineers giving their approval for the Chief s Report to be issued and permission for design and construction to move forward. Mitigation payments will become part of the internal project authorization amount and will be brought forward for approval by Managing Members at the same time that construction costshare funds are requested. Our obligation for payment to the tribes is 30 days in advance of construction. Remaining Project Timeline and Estimated Cost The Corps process for deepening includes three distinct phases, each of which requires federal appropriations and authorization before they begin. Cost-share for each phase will be made by the non-federal sponsor. In the case of the Feasibility Study, the remainder of the $1.5m budget was transferred to the Alliance upon formation. Managing Members will have not made a policy decision about funding of harbor navigation projects, but will do so at a future date. Phase 1 Feasibility: Authorized in 2014 and will be concluded in May 2018 with the issuance of a signed Chief s Report. The remaining budget for the $1.5M cost-share obligation was placed in the NWSA budget upon formation of the Alliance. Phase 2 - Preconstruction Engineering and Design (PED): Will begin in October of 2019 if funding is appropriated in the FY19 Army Corps Work Plan or a congressional appropriations bill. Congressional authorization must then be granted either through the next WRDA bill in 2018 or another appropriations bill. During this phase, the project design will be completed and bid documents will be prepared. The Non-Federal Sponsor will sign a Design Agreement to cost share PED. Phase 3 Construction: The Non-Federal Sponsor will sign a Public Partnership Agreement for cost-share of the project. Construction must first receive authorization under the 2018 WRDA bill, and must receive funding in the President s Budget. If all goes well,

Page 5 of 5 funding will start in the FY22 President s budget. Construction for the West Waterway is expected to take two seasons and at the earliest would be completed by 2024. It is expected that the Lockheed Cleanup project will be completed by the start of West waterway construction in 2022. The East Waterway will take one season, but timing is dependent upon the completion of the separate CERCLA cleanup project in that waterway. Current timing estimate would mean earliest completion by 2031. Cost Share Estimate for Phase 2 (PED) and Phase 3 (Construction) of Locally Preferred Plan (-57 MLLW) in 2016 dollars, including Tribal Mitigation Non-Federal Seattle Harbor Project Estimate Total Cost Federal (Port) East Waterway (EWW) $10M $2.5M $8M West Waterway (WWW) $50M $20.5M $29M TOTAL Both Waterways $60 Million $23 Million $37 Million Tacoma Harbor Deepening Feasibility Study The Port of Tacoma, as non-federal sponsor, has requested that the Corp undertake a Feasibility Study to determine if there is a federal interest in deepening the channels in the South Harbor. This study was not included in the 2017 President s budget and Corp work plan. The corps and the port internal team, are lobbying for inclusion in the FY2018 budget and work plan as a new start. The Tacoma Harbor Deepening Feasibility Study and Deepening Project would follow the same process as Seattle Harbor. The first cost-share commitment is for the Feasibility Study, which is $1.5M over three years. Some of the $1.5M will be contributed as work in kind, including staff time for data analysis, research, meetings and review. If the study is funded, expected earliest completion of the full project would be 2027 or later.