American Recovery and Reinvestment Act Project Repair and Modernization of Administration Building 1500 at Naval Air Station Pensacola, Florida

Similar documents
Report Documentation Page

Report No. D-2011-RAM-004 November 29, American Recovery and Reinvestment Act Projects--Georgia Army National Guard

Report No. D June 16, 2011

Geothermal Energy Development Project at Naval Air Station Fallon, Nevada, Did Not Meet Recovery Act Requirements

Briefing No. D-2010-RAM-003 March 10, Repair Aircraft Parking Apron at Naval Station Norfolk

Incomplete Contract Files for Southwest Asia Task Orders on the Warfighter Field Operations Customer Support Contract

Acquisition. Air Force Procurement of 60K Tunner Cargo Loader Contractor Logistics Support (D ) March 3, 2006

World-Wide Satellite Systems Program

Independent Auditor's Report on the Attestation of the Existence, Completeness, and Rights of the Department of the Navy's Aircraft

DoD Countermine and Improvised Explosive Device Defeat Systems Contracts for the Vehicle Optics Sensor System

Report No. DODIG Department of Defense AUGUST 26, 2013

Report No. D May 14, Selected Controls for Information Assurance at the Defense Threat Reduction Agency

Information Technology

Acquisition. Diamond Jewelry Procurement Practices at the Army and Air Force Exchange Service (D ) June 4, 2003

Report No. D February 9, Internal Controls Over the United States Marine Corps Military Equipment Baseline Valuation Effort

DoD Cloud Computing Strategy Needs Implementation Plan and Detailed Waiver Process

Award and Administration of Multiple Award Contracts for Services at U.S. Army Medical Research Acquisition Activity Need Improvement

Report No. DODIG December 5, TRICARE Managed Care Support Contractor Program Integrity Units Met Contract Requirements

Review of Defense Contract Management Agency Support of the C-130J Aircraft Program

Report No. D February 22, Internal Controls over FY 2007 Army Adjusting Journal Vouchers

Report No. D July 25, Guam Medical Plans Do Not Ensure Active Duty Family Members Will Have Adequate Access To Dental Care

Financial Management

Complaint Regarding the Use of Audit Results on a $1 Billion Missile Defense Agency Contract

Report No. D August 12, Army Contracting Command-Redstone Arsenal's Management of Undefinitized Contractual Actions Could be Improved

Improving the Quality of Patient Care Utilizing Tracer Methodology

Information Technology

Naval Audit Service. Audit Report

Internal Controls Over the Department of the Navy Cash and Other Monetary Assets Held in the Continental United States

Report No. D April 9, Training Requirements for U.S. Ground Forces Deploying in Support of Operation Iraqi Freedom

DDESB Seminar Explosives Safety Training

Report No. D June 17, Long-term Travel Related to the Defense Comptrollership Program

DODIG March 9, Defense Contract Management Agency's Investigation and Control of Nonconforming Materials

Report No. D September 22, The Department of the Navy Spent Recovery Act Funds on Photovoltaic Projects That Were Not Cost-Effective

Office of Inspector General Department of Defense FY 2012 FY 2017 Strategic Plan

DOD Native American Regional Consultations in the Southeastern United States. John Cordray NAVFAC, Southern Division Charleston, SC

February 8, The Honorable Carl Levin Chairman The Honorable James Inhofe Ranking Member Committee on Armed Services United States Senate

D June 29, Air Force Network-Centric Solutions Contract

Report No. D July 30, Status of the Defense Emergency Response Fund in Support of the Global War on Terror

DOING BUSINESS WITH THE OFFICE OF NAVAL RESEARCH. Ms. Vera M. Carroll Acquisition Branch Head ONR BD 251

Chief of Staff, United States Army, before the House Committee on Armed Services, Subcommittee on Readiness, 113th Cong., 2nd sess., April 10, 2014.

DEFENSE LOGISTICS AGENCY WASTEWATER TREATMENT SYSTEMS. Report No. D March 26, Office of the Inspector General Department of Defense

Report No. D September 22, Kuwait Contractors Working in Sensitive Positions Without Security Clearances or CACs

The Fully-Burdened Cost of Waste in Contingency Operations

A udit R eport. Office of the Inspector General Department of Defense. Report No. D October 31, 2001

Comparison of Navy and Private-Sector Construction Costs

Panel 12 - Issues In Outsourcing Reuben S. Pitts III, NSWCDL

terns Planning and E ik DeBolt ~nts Softwar~ RS) DMSMS Plan Buildt! August 2011 SYSPARS

Office of the Inspector General Department of Defense

Report Documentation Page

Opportunities to Streamline DOD s Milestone Review Process

H-60 Seahawk Performance-Based Logistics Program (D )

The Navy s Management of Software Licenses Needs Improvement

Mission Assurance Analysis Protocol (MAAP)

ASAP-X, Automated Safety Assessment Protocol - Explosives. Mark Peterson Department of Defense Explosives Safety Board

DoD Scientific & Technical Information Program (STIP) 18 November Shari Pitts

Report No. DoDIG April 27, Navy Organic Airborne and Surface Influence Sweep Program Needs Defense Contract Management Agency Support

Defense Health Care Issues and Data

Report No. D December 16, Air Force Space and Missile Systems Center's Use of Undefinitized Contractual Actions

Defense Acquisition: Use of Lead System Integrators (LSIs) Background, Oversight Issues, and Options for Congress

Shadow 200 TUAV Schoolhouse Training

MILITARY MUNITIONS RULE (MR) and DoD EXPLOSIVES SAFETY BOARD (DDESB)

Report No. DODIG U.S. Department of Defense SEPTEMBER 28, 2016

Office of the Inspector General Department of Defense

Preliminary Observations on DOD Estimates of Contract Termination Liability

White Space and Other Emerging Issues. Conservation Conference 23 August 2004 Savannah, Georgia

DoD IG Report to Congress on Section 357 of the National Defense Authorization Act for Fiscal Year 2008

Report No. D January 21, FY 2007 DoD Purchases Made Through the U.S. Department of Veterans Affairs

Assessment of the DSE 40mm Grenades

Software Intensive Acquisition Programs: Productivity and Policy

USAF TECHNICAL TRAINING NAS Pensacola Florida Develop America's Airmen Today --- for Tomorrow

Information Technology Management

Munitions Response Site Prioritization Protocol (MRSPP) Online Training Overview. Environmental, Energy, and Sustainability Symposium Wednesday, 6 May

Department of Defense

Aviation Logistics Officers: Combining Supply and Maintenance Responsibilities. Captain WA Elliott

Fiscal Year 2011 Department of Homeland Security Assistance to States and Localities

US Coast Guard Corrosion Program Office

Developmental Test and Evaluation Is Back

Make or Buy: Cost Impacts of Additive Manufacturing, 3D Laser Scanning Technology, and Collaborative Product Lifecycle Management on Ship Maintenance

The Security Plan: Effectively Teaching How To Write One

Integrated Comprehensive Planning for Range Sustainability

Exemptions from Environmental Law for the Department of Defense: Background and Issues for Congress

Social Science Research on Sensitive Topics and the Exemptions. Caroline Miner

Followup Audit of Depot-Level Repairable Assets at Selected Army and Navy Organizations (D )

Report Documentation Page

Report Documentation Page


United States Army Aviation Technology Center of Excellence (ATCoE) NASA/Army Systems and Software Engineering Forum

United States Military Casualty Statistics: Operation Iraqi Freedom and Operation Enduring Freedom

Tannis Danley, Calibre Systems. 10 May Technology Transition Supporting DoD Readiness, Sustainability, and the Warfighter. DoD Executive Agent

U.S. ARMY AVIATION AND MISSILE LIFE CYCLE MANAGEMENT COMMAND

Evolutionary Acquisition an Spiral Development in Programs : Policy Issues for Congress

Report No. DODIG September 11, Inappropriate Leasing for the General Fund Enterprise Business System Office Space

Staffing Cyber Operations (Presentation)

Report No. D June 20, Defense Emergency Response Fund

Summary Report on DoD's Management of Undefinitized Contractual Actions

Navy Enterprise Resource Planning System Does Not Comply With the Standard Financial Information Structure and U.S. Government Standard General Ledger

The Air Force's Evolved Expendable Launch Vehicle Competitive Procurement

Report No. D September 25, Controls Over Information Contained in BlackBerry Devices Used Within DoD

The Military Health System How Might It Be Reorganized?

Human Capital. DoD Compliance With the Uniformed and Overseas Citizens Absentee Voting Act (D ) March 31, 2003

Transcription:

Memorandum No. D2010-RAM-010 June 11, 2010 American Recovery and Reinvestment Act Project Repair and Modernization of Administration Building 1500 at Naval Air Station Pensacola, Florida

Report Documentation Page Form Approved OMB No. 0704-0188 Public reporting burden for the collection of information is estimated to average 1 hour per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to a penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. 1. REPORT DATE 11 JUN 2010 2. REPORT TYPE 3. DATES COVERED 00-00-2010 to 00-00-2010 4. TITLE AND SUBTITLE American Recovery and Reinvestment Act Project - Repair and Modernization of Administration Building 1500 at Naval Air Station Pensacola, Florida 5a. CONTRACT NUMBER 5b. GRANT NUMBER 5c. PROGRAM ELEMENT NUMBER 6. AUTHOR(S) 5d. PROJECT NUMBER 5e. TASK NUMBER 5f. WORK UNIT NUMBER 7. PERFORMING ORGANIZATION NAME(S) AND ADDRESS(ES) Department of Defense Inspector General,400 Army Navy Drive (Room 801),Arlington,VA,22202-4704 8. PERFORMING ORGANIZATION REPORT NUMBER 9. SPONSORING/MONITORING AGENCY NAME(S) AND ADDRESS(ES) 10. SPONSOR/MONITOR S ACRONYM(S) 12. DISTRIBUTION/AVAILABILITY STATEMENT Approved for public release; distribution unlimited 13. SUPPLEMENTARY NOTES 14. ABSTRACT 11. SPONSOR/MONITOR S REPORT NUMBER(S) 15. SUBJECT TERMS 16. SECURITY CLASSIFICATION OF: 17. LIMITATION OF ABSTRACT a. REPORT unclassified b. ABSTRACT unclassified c. THIS PAGE unclassified Same as Report (SAR) 18. NUMBER OF PAGES 14 19a. NAME OF RESPONSIBLE PERSON Standard Form 298 (Rev. 8-98) Prescribed by ANSI Std Z39-18

Additional Copies To obtain additional copies of this report, visit the Web site of the Department of Defense Inspector General at http://www.dodig.mil/audit/reports or contact the Secondary Reports Distribution Unit at (703) 604-8937 (DSN 664-8937) or fax (703) 604-8932. Suggestions for Audits To suggest or request audits, contact the Office of the Deputy Inspector General for Auditing by phone (703) 604-9142 (DSN 664-9142), by fax (703) 604-8932, or by mail: ODIG-AUD (ATTN: Audit Suggestions) Department of Defense Inspector General 400 Army Navy Drive (Room 801) Arlington, VA 22202-4704 Acronyms and Abbreviations FAR Federal Acquisition Regulation NAS Naval Air Station NAVFAC Naval Facilities Engineering Command OMB Office of Management and Budget PWD Public Works Department QMAD Quantitative Methods and Analysis Division

INSPECTOR GENERAL DEPARTMENT OF DEFENSE 400 ARMY NAVY DRIVE ARLINGTON, VIRGINIA 22202-4704 JUN 11 2010 MEMORANDUM FOR NAVAL INSPECTOR GENERAL COMMANDING OFFICER, NAVAL FACILITIES ENGINEERING COMMAND SOUTHEAST COMMANDING OFFICER, NAVAL AIR STATION PENSACOLA PUBLIC WORKS DEPARTMENT SUBJECT: American Recovery and Reinvestment Act Project- Repair and Modernization of Administrative Building 1500 at Naval Air Station Pensacola, Florida (Memorandum No. D2010-RAM-OIO) We are providing this report for your information and use. We performed this audit in response to the requirements ofpublic Law 111-5, "American Recovery and Reinvestment Act of2009," February 17,2009. We considered management comments on a discussion draft of the report when preparing the final report. No additional comments are required. We appreciate the courtesies extended to the staff. Please direct questions to Mr. Timothy Wirnette at (703) 604-8876 (DSN 664-8876). (h~~- Alice F. Carey Assistant Inspector General Readiness, Operations, and Support

Memorandum No. D2010-RAM-010 (Project No. D2009-D000LH-0313.000) June 11, 2010 Results in Brief: American Recovery and Reinvestment Act Project Repair and Modernization of Administrative Building 1500 at Naval Air Station Pensacola, Florida What We Did Our overall objective was to evaluate DOD s implementation of Public Law 111-5, American Recovery and Reinvestment Act of 2009, February 17, 2009. Specifically, we determined whether Navy personnel adequately planned, funded, executed, tracked, and reported Project RM55-01, to repair and modernize Administrative Building 1500 at Naval Air Station Pensacola, Florida, to ensure the appropriate use of Recovery Act funds. What We Found We determined that Project RM55-01 was justified and met the Recovery Act goals regarding accountability and transparency. Personnel at the Naval Facilities Engineering Command Southeast Public Works Department at Naval Air Station Pensacola, Florida, planned, funded, executed, and had procedures in place to track and report the project as required by the Recovery Act and implementation guidance. Administrative Building 1500 at Naval Air Station Pensacola, Florida Although the contract initially omitted four required Federal Acquisition Regulation clauses, contracting personnel subsequently issued contract modifications to include the clauses. What We Recommend This report contains no recommendations. Management Comments The Commander, Naval Facilities Engineering Command Southeast Public Works Department at Naval Air Station Pensacola, Florida, had no comments on the discussion draft report and agreed with our results and conclusions. We do not require any formal comments. Basement of Administrative Building 1500 at Naval Air Station Pensacola, Florida i

Introduction Objective Our overall objective was to evaluate DOD s implementation of Public Law 111-5, American Recovery and Reinvestment Act of 2009, February 17, 2009 (Recovery Act). We reviewed the implementation of the DOD Recovery Act plans at the Service and installation levels to determine whether individual projects were managed to achieve the accountability and transparency goals of the Recovery Act. Specifically, we determined whether personnel at Naval Air Station (NAS) Pensacola, Florida adequately planned, funded, executed, tracked, and reported to ensure the appropriate use of Recovery Act funds for Project RM55-01 for the design, repair, and modernization of Administrative Building 1500 at NAS Pensacola. See the appendix for a discussion of the audit scope and methodology related to the audit objective. Background In passing the Recovery Act, Congress provided supplemental appropriations to preserve and create jobs; promote economic recovery; assist those most impacted by the recession; provide investments to increase economic efficiency by spurring technological advances in science and health; and invest in transportation, environmental protection, and other infrastructure. The Recovery Act also established unprecedented efforts to ensure the responsible distribution of funds for its purposes and to provide transparency and accountability of expenditures by informing the public of how, when, and where tax dollars were being spent. Further, the Recovery Act states that the President and heads of the Federal departments and agencies were to expend these funds as quickly as possible, consistent with prudent management. DOD received approximately $6.8 billion 1 in Recovery Act funds to be used for projects that support the Act s purpose. In March 2009, DOD released expenditure plans for the Recovery Act, which list DOD projects that will receive Recovery Act funds. The Department of the Navy received $1.928 billion in Recovery Act funds for Operations and Maintenance; Military Construction; and Research, Development, Test and Evaluation. Table 1 provides specific funds allocated to each appropriation. Table 1. Department of the Navy Program-Specific Recovery Act Appropriations Appropriations Amount (millions) Operations and Maintenance $916 Military Construction 937 Research, Development, Test and Evaluation 75 Total $1,928 1 The $6.8 billion does not include $4.6 billion for the U.S. Army Corps of Engineers or $555 million for the Homeowners Assistance Fund. 1

Of the $1.928 billion, the Department of Navy allocated approximately $10.6 million (Operations and Maintenance) to support the repair and modernization of Administrative Building 1500 at NAS Pensacola. This project consists of repairs and modernization of fire safety systems; interior electrical distribution; heating, ventilation, and air conditioning; interior plumbing; exterior and interior finishes; windows; telecommunications system; electrical supply; and physical security. This project also includes asbestos and lead paint removal and installation of an elevator and handicap ramp to comply with the Americans with Disabilities Act. NAS Pensacola s mission is to enhance readiness of the U.S. Navy and the other Services by fully supporting the operational and training missions of tenant commands assigned. NAS Pensacola provides support to 89 DOD and 30 non-dod tenant commands, the majority of which are dedicated to training Navy, Marine Corps, and Coast Guard personnel in naval aviation. 2

Audit Results We determined that Project RM55-01 met the goals regarding accountability and transparency as provided in the Recovery Act. This project was justified, and the Naval Facilities Engineering Command (NAVFAC) Southeast Public Works Department at NAS Pensacola (the PWD) personnel planned, funded, and executed the project in order to achieve the goals of the Recovery Act. In addition, PWD personnel had procedures in place to track and report the project as required by the Recovery Act. Although the contract was initially missing four Federal Acquisition Regulation (FAR) clauses required by Recovery Act implementation guidance, contracting personnel issued contract modifications to include the clauses. Planning PWD personnel appropriately planned the project, which we determined to be justified. According to planning documents, Hurricane Ivan struck NAS Pensacola in 2004 causing severe damage to Building 1500, which is a unique, historically-registered building. As a result of the hurricane damage, the building presents many health hazards. The planning documents state that this project will bring the building up to a safe and usable condition to house command and support staff and allow the command to be in closer proximity to the Admiral s building. The project will also make the building compliant with the National Preservation Act. Upon project completion, the Command and staff will move from Building 624 into Building 1500. NAS Pensacola will then convert Building 624 into barracks for military personnel attending classes on base. PWD personnel appropriately planned the project by obtaining a detailed cost estimate and economic analysis. The cost estimate was based on the number of square feet requiring repair and modernization and upgrades needed to meet requirements of the Americans with Disabilities Act and Anti-terrorism Force Protection policy. The economic analysis considered possible alternatives to house command and support staff, such as status quo, leasing, renovation, and new construction. PWD personnel determined that renovation was the best option because it was less expensive than new construction and because it: provided a Command building closer to the Admiral s building and apart from the training campus at NAS Pensacola, permitted completion of renovations without having to temporarily relocate tenants, vacated Building 624 for renovation into barracks for training campus students, and preserved a historically-registered building. Funding Navy personnel distributed Recovery Act funds to the Building 1500 repair and modernization project in a timely manner, and funding documents properly identified a Recovery Act designation. Navy Region Southeast personnel distributed Recovery Act 3

funds to NAVFAC on September 11, 2009, and NAVFAC Southeast personnel awarded the contract subsequent to receiving the funds. Funding documents indicated that $10,598,586 was distributed for the project and identified the correct Recovery Act appropriation in the line of accounting. Execution PWD personnel adequately performed initial project execution of the Recovery Act project. In our evaluation of initial project execution, we determined whether the contracts were competitively solicited and awarded, with full transparency, and whether they contained the clauses the FAR requires for Recovery Act contract actions. PWD personnel awarded the contract competitively at a firm fixed price of approximately $10.6 million on September 18, 2009, which was one month earlier than the milestone from the DOD s Recovery Act expenditure plan. PWD personnel issued the request for proposal competitively and eight companies responded. The PWD s source selection board evaluated the proposals based on price and six technical factors. PWD personnel determined that the proposal from Greenhut Construction Co. provided the best value to the Government. Greenhut Construction Co. tied with two other companies for the highest technical evaluation scores. However, Greenhut Construction Co. had a lower price than the other two companies did. Greenhut Construction Co. registered on the Central Contractor Registration web page, and the Excluded Parties List System did not include them as a debarred contractor. Contracting personnel properly recorded contract actions to facilitate full transparency. Office of Management and Budget (OMB) Memorandum M-09-15, Updated Implementing Guidance for the American Recovery and Reinvestment Act of 2009, April 3, 2009, describes requirements for reporting Recovery Act funded actions in the Federal Procurement Data System and publicizing actions on Federal Business Opportunities. Contracting personnel properly reported the contract award in the Federal Procurement Data System and announced the solicitation and contract award on the Federal Business Opportunities website. The contract was originally missing four FAR clauses. However, PWD personnel modified the contract to include these clauses. PWD contracting personnel included most of the required Recovery Act FAR clauses, including those for whistleblower protection, reporting, the Davis-Bacon Act, and the Buy American Act. However, we identified one missing subcontracting clause 52.244-6, Subcontracts for Commercial Items and three clauses required by FAR Part 23, Environment, Energy, and Water Efficiency, Renewable Energy Technologies, Occupational Safety, and Drug-free Workplace. FAR part 23 prescribes policies and procedures for protecting and improving the quality of the 4

environment. According to OMB Memorandum M-09-15, agencies must comply with the requirements of FAR part 23 when acquiring supplies and services 2 using Recovery Act funds. The contract was missing the following clauses required by FAR part 23: FAR 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts, FAR 52.223-14, Toxic Chemical Release Reporting, and FAR 52.223-17, Affirmative Procurement of EPA-designated Items in Service and Construction Contracts. Without these clauses, Navy officials could not hold contractors accountable for all Recovery Act requirements or ensure the protection and improvement of the environment. Since we identified this issue, PWD contracting personnel modified the contract to include the four missing clauses. Tracking and Reporting Although repair and modernization of Building 1500 had not commenced at the time of our review, the PWD had adequate personnel and procedures in place to track project schedules, address non-conformances, and ensure the contractor met contract requirements. PWD personnel stated that the construction manager and engineering technician will review daily quality control reports, attend weekly quality control meetings, and perform inspections to ensure the contractor has an adequate quality control program in place and is following all contract requirements. PWD personnel also had procedures in place to ensure the contractor reported required Recovery Act information. FAR clause 52.204-11, American Recovery and Reinvestment Act Reporting Requirements, requires contractors for Recovery Act projects to report project information at http://www.federalreporting.gov. The contracting officer and public works officer for this project stated that they planned to register on the website to ensure the contractor is reporting as required. For the first and second quarters of FY10, Greenhut Construction Co. reported the number of jobs and total dollar value for the project as required. Conclusion We concluded that need for the repair and modernization of Administrative Building 1500 was justified. NAVFAC Southeast officials adequately planned, funded, and executed, the project. NAVFAC Southeast personnel had procedures in place to track and report Project RM55-01 in accordance with the accountability and transparency goals of the Recovery Act. Although the contract was originally missing four FAR clauses, PWD personnel modified the contract to include these clauses. Therefore, this report contains no recommendations. 2 According to the definition of an acquisition in FAR Subpart 2.101, construction is a service. 5

Appendix. Scope and Methodology We conducted this performance audit from October 2009 through June 2010. We interviewed key personnel from the NAVFAC Southeast Regional Engineer Office and the NAVFAC PWD at NAS Pensacola. We reviewed documentation including the official contract file, economic analysis, cost estimate, DD Form 1391, Military Construction Project Data, and associated support, and process for tracking and reporting Recovery Act projects. We also conducted a site visit to tour Building 1500. We reviewed Federal, DOD, Navy, and NAS Pensacola guidance, and compared this guidance to our audit results. We conducted this audit in accordance with generally accepted government auditing standards. Those standards require that we plan and perform the audit to obtain sufficient, appropriate evidence to provide a reasonable basis for our findings and conclusions based on our audit objectives. We believe that the evidence obtained provides a reasonable basis for our findings and conclusions based on our audit objectives. Use of Computer-Processed Data We used computer-processed data from the Federal Procurement Data System, Central Contractor Registration, Excluded Parties List System, Federal Business Opportunities, www.federalreporting.gov, and other systems. However, our use of computer-processed data did not materially affect our audit results, findings, or conclusions, and the information we used was obtained from sources generally recognized as appropriate. Therefore, we did not evaluate the reliability of the computer-processed data we used. Use of Technical Assistance Before selecting DOD Recovery Act projects for audit, personnel in the Quantitative Methods and Analysis Division (QMAD) of the DOD Office of Inspector General analyzed all DOD agency-funded projects, locations, and contracting oversight organizations to assess the risk of waste, fraud, and abuse associated with each. QMAD personnel selected most audit projects and locations using a modified Delphi technique, which allowed them to quantify the risk based on expert auditor judgment, and other quantitatively developed risk indicators. Initially, QMAD personnel selected 83 projects with the highest risk rankings. Auditors chose some additional projects at the selected locations. QMAD personnel did not use classical statistical sampling techniques that would permit generalizing results to the total population because there were too many potential variables with unknown parameters at the beginning of this analysis. The predictive analytic techniques employed provided a basis for logical coverage not only of Recovery Act dollars being expended, but also of types of projects and types of locations across the Military Services, Defense agencies, National Guard units, and public works projects managed by the U.S. Army Corps of Engineers. 6

Prior Audit Coverage The Government Accountability Office, the Department of Defense Inspector General, and the Military Departments have issued reports and memoranda discussing DOD projects funded by the Recovery Act. You can access unrestricted reports at http://www.recovery.gov/accountability. 7