SOUTH DENALI IMPLEMENTATION PROGRESS REPORT

Similar documents
HATCHER PASS RECREATIONAL AREA ACCESS, TRAILS. AND TRANSIT FACILITIES FAQs

County of Sonoma Agenda Item Summary Report

COMMUNITY LEADERSHIP & COMMUNICATION

MIDPENINSULA REGIONAL OPEN SPACE DISTRICT GENERAL COUNSEL

Grand Forks Growth Fund, A Jobs Development Authority Staff Report

Committee Report. Community Development Committee. Business Item No Proposed Action. Summary of Committee Discussion/Questions

The Bluffs concept is all about helping to change these perceptions.

Annual Plan

MAT-SU VALLEY SOUTH GATEWAY VISITOR CENTER. Preliminary Feasibility Study June Agnew::Beck Consulting, LLC Wolf Architecture RECON, LLC

Community Development Committee Meeting date: December 15, 2014 For the Metropolitan Council meeting of January 14, 2015

Subject: Park Acquisition Opportunity Fund Grant Request for Big Marine Park Reserve (17980 Margo Avenue), Washington County

Meadow Lakes Comprehensive Plan

TABLE OF CONTENTS EXECUTIVE SUMMARY

LODGING TAX FACILITIES GRANT PROGRAM

Asset-Based Economic Development and Building Sustainable Rural Communities

Professional Planning Services to Complete Recreation Plan Update

Metropolitan Parks and Open Space Commission

URBAN DEVELOPMENT CORPORATION INFORMATION MORANDUM DOCUMENT GREEN GROTTO CAVES- LAKE AREA RECREATIONAL ACTIVITIES

SPECIAL MEETING OF THE METROPOLITAN PARKS AND OPEN SPACE COMMISSION Tuesday, February 9, 2016

4. IMPLEMENTATION. 4.1 Implementation Matrix

OPEN SPACE, RECREATION, BAY AND WATERSHED PROTECTION BONDS 2004 OPEN SPACE BOND AUTHORIZATION $70,000,000 (Chapter 595 Public Laws 2004) PENDING

2012 Heritage Action Plan Grant Program Schuylkill River Heritage Towns & Tours

REPORT TO THE 2002 HAWAII STATE LEGISLATURE

UNIFIED GOVERNMENT OF ATHENS-CLARKE COUNTY GEORGIA GREENSPACE ACQUISITION PROGRAM POLICY AND PROCEDURES

Present Leonard Boord, Chair Justo L. Pozo, Vice Chair Cesar L. Alvarez Dean C. Colson Natasha Lowell Marc D. Sarnoff Kathleen L.

US 50/SOUTH SHORE COMMUNITY REVITALIZATION PROJECT

KNIGHTSEN TOWN COMMUNITY SERVICES DISTRICT

Guidelines for the Hudson River Valley National Heritage Area 2018 Heritage Development Grant Program

Lancaster County Smart Growth Transportation Program (Updated March 2017)

SOUTHWEST LRT (METRO GREEN LINE EXTENSION)

Chisago County, Minnesota

Request for Redevelopment Proposal 102 N. Broadway, City of De Pere

Funding Application Portal Contents March 2018

Minnesota Department of Natural Resources. Recreation & Conservation Grants. Traci Vibo. Grant Coordinator Division of Parks and Trails

STUDY AND ARCHITECTURAL DESIGN SERVICES

Funding Guidelines and Criteria March 2017

Florida Job Growth Grant Fund Public Infrastructure Grant Proposal

CITY OF DANA POINT AGENDA REPORT

American Farmland Trust Conference October 20-23, 2014 Lexington, KY

Rural Grants Program (

CONTENT 1 INTRODUCTION 2 WHAT

N E W B U I L D I N G S A T A U B U R N R E S E A R C H P A R K

July 5, JOINT PUBLIC NOTICE Savannah District/State of Georgia

ATTACHMENT AAAaAAAA. Washington DIRECTOR OF FINANCE $110,335 - $155,915. Plus Excellent Benefits OPEN UNTIL FILLED

DeKalb County Government Sycamore, Illinois. Economic Development Committee Minutes May 6, 2014

DEPARTMENT OF THE ARMY SAVANNAH DISTRICT, CORPS OF ENGINEERS 1104 NORTH WESTOVER BOULEVARD, UNIT 9 ALBANY, GEORGIA SEPT 1ER

USF Board of Trustees Finance & Audit Workgroup October 10, 2005

RECREATION & CULTURE

South Dakota Transportation Alternatives

FROM: CITY MANAGER DEPARTMENT: COMMUNITY SERVICES

Milwaukee Railroad Shops Historic District ~ Sioux City, Iowa. Prepared by Larry Obermeyer, Executive Secretary

Transportation Alternatives Program Guidance

Public Notice U.S. ARMY CORPS OF ENGINEERS, GALVESTON DISTRICT AND TEXAS COMMISSION ON ENVIRONMENTAL QUALITY

City of Edina, Minnesota GrandView Phase I Redevelopment, 5146 Eden Avenue Request for Interest for Development Partner

State Project No. XXXXXX City Project No. c401807

City of Terrace Economic Development Strategy

REQUEST FOR PROPOSALS (RFP)

SAFETEA-LU. Overview. Background

Application for Wenatchee Lodging Tax Funds

GROUNDWORK FIRST ANNUAL REPORT OF THE FOOTHILLS CONSERVATION ADVISORY COMMITTEE. May, 2002

TRANSPORTATION FUNDING PROGRAMS

Economic Development ANNUAL REPORT. Innovate. Prosper. Grow.

2012 Capital Improvement Budget Library Department

KITSAP COUNTY LODGING TAX ADVISORY COMMITTEE ALLOCATION PROCESS

CITY OF MARYVILLE, MISSOURI REQUEST FOR QUALIFICATIONS (RFQ) ARCHITECTURAL DESIGN SERVICES FOR WELCOME CENTER AT MOZINGO LAKE RECREATION PARK

STAR ATTRACTIONS DESIGNATION PROGRAM General Guidelines

City Council Study Session Retail Market Analysis

REQUEST FOR QUALIFICATIONS/PROPOSALS SUBASE NEW LONDON JOINT LAND USE STUDY (JLUS) IMPLEMENTATION PROJECT

Economic Development Strategic Plan Executive Summary Delta County, CO. Prepared By:

4.b. 6/22/2017. Local Agency Formation Commission. George J. Spiliotis, Executive Officer

FOREST SERVICE MANUAL NATIONAL HEADQUARTERS (WO) WASHINGTON, DC

Job announcement: Executive Director. $79,000 - $112,000; plus excellent benefit package

DEVELOPMENT AUTHORITY OF CLAYTON COUNTY REQUEST FOR PROPOSALS MASTER PLANNING CONSULTING SERVICES

Appendix C: Public Participation

Request for Proposals

Business Ready Community Grant and Loan Program Allocation Plan

December 1999 Report No

Business Events Bid Fund Program - Prospectus. Financial Year 2018/19

Department of Natural Resources Recreation Grant Programs 2017 Workshop.

Metropolitan Parks and Open Space Commission

City of Lansing Application #2 River Trail West (Near Elm St) - Wall and Pavement Repair

Capital Budget and Program Fiscal Year 2014

Regional Parks. Policy Plan Amended June 12, 2013

REQUEST FOR PROPOSALS (RFP)

Federal Programs for Heritage and Cultural Tourism

Frankfort Historic Landmarks Arts Center

Activity Recreation Cultural Center

REQUEST FOR CITY COUNCIL ACTION

Boston Harbor Islands National and State Park

AMERICA BIKES SIDE-BY-SIDE COMPARISON OF BICYCLE AND PEDESTRIAN PROGRAMS SAFETEA LU VS. MAP 21

Oregon John A. Kitzhaber, M.D., Governor

Fiscal Year 2014 TRANSPORTATION ALTERNATIVES PROGRAM (TAP) INSTRUCTIONS AND GUIDELINES

Executive Summary. Purpose

Kendall Corridor Development Miami, Florida

Etna Riverfront Park and Trail: Design and Engineering RFP

Arkansas Transportation Alternatives Program (TAP-2015) & Recreational Trails Program (RTP-2015) Application Seminars

Transportation Alternatives (TA) Northeast Minnesota Workshop

KLAMATH COUNTY TOURISM TRADITIONAL GRANT PROGRAM APPLICATION

REPORT. To the Honorable Mayor and City Council From the City Manager. May 9, 2016

The Matanuska-Susitna Borough

Transcription:

SOUTH DENALI IMPLEMENTATION PROGRESS REPORT PROGRESS TO DATE: For over 40 years there has been a shared vision among public land managers in the South Denali region that the south side of Denali should receive greater use and development for visitors. However, the issues related to such development have historically generated extensive public controversy. A thorough public process associated with the South Denali Implementation Plan and EIS (2004-2006) yielded a well vetted and supported visitor center location within Denali State Park on Curry Ridge. This was in direct contrast to earlier planning efforts where locations identified in the Peters Hills area generated a lot of public controversy. The EIS was followed by a Record of Decision supporting the EIS in 2007. The first development phase was acquisition of high resolution imagery and LIDAR, to have the best design aids in hand. A Master Interpretive Plan was completed in 2009 followed by design work for the access road including survey, geotechnical and environmental reports. Trails planning, scenic byway planning and corridor studies are ongoing. The state is working closely with the MatSu Borough on revising land use regulations for the Special Use District that encompasses all of Denali State Park. A traffic design was completed through a local engineering firm for the Parks Highway intersection; this study will be amended to include the new proposed access road north of the original location. The Center for Economic Development at the University of Alaska has just begun work on a feasibility study for the proposed visitor center. The state has entered into an agreement with UCI, a subsidiary of the Sea Lion Corporation, in which UCI will donate 130 acres of their 160 acre inholding in the park. The state has completed a Phase I environmental study on the proposed donation parcel. This donation will provide a better access to the South Denali project. Additional road design, geotechnical, and environmental studies will be conducted on this newly acquired property in spring and summer, 2011. Pending funding, the state will contract for the design of the South Denali facilities and their subsequent construction in 2011-2013. EXPENDITURES: Progress and approximate expenditures include: $100K Master Interpretive Plan development and production $25K consultant coordination $400K geotechnical and wetlands delineation, Dowl HKM $100K engineering and consultant coordination

$50K electrical extension study, MEA $15K consultant coordination $60K South Denali special assistant $60K imagery and LIDAR collection, Aerometrics $25K mapping and technical assistance for 130 acre land donation, Sea Lion Corporation $75K Feasibility Study ongoing, UA Center for Economic Development $107K planning team, agency coordination, site planning, environmental, preliminary design, public meetings, and administration personal services and travel. $1,017K APPROXIMATE TOTAL EXPENDITURES TO DATE TIMELINE: Below is a timeline for the South Denali project. This timeline is dependent upon receiving Visitor Center design funding in 2011 and construction funding in 2012.

South Denali Visitor Center Design and Construction FY2012 Request: AP/AL: Appropriation Project Type: Construction Category: Natural Resources Location: Matanuska-Susitna Borough (Rural Mat- House District: Rural Mat-Su (HD 15) Su) Impact House District: Rural Mat-Su (HD 15) Contact: Jean Davis Estimated Project Dates: 07/01/2011-06/30/2016 Contact Phone: (907)465-2422 Brief Summary and Statement of Need: The funding will be used to complete the design of the South Denali Visitors Center. With the completion of the EIS and the Interpretive plan we are ready to move forward with design and construction. The total amount of state funding needed to complete the project is $25.0 million. This project will provide access to public lands, boost the local economy and is estimated to receive approximately 280,000 annual visits. Total remaining state project costs include: $3 million for design of the visitor center and the transportation system $13 million for the construction of the visitor center $3 million for construction of the transportation system $6 million to extend power to the site Funding: FY2012 FY2013 FY2014 FY2015 FY2016 FY2017 Total Gen Fund $22,000,000 $25,000,000 Total: $22,000,000 $0 $0 $0 $0 $25,000,000 State Match Required One-Time Project Phased - new Phased - underway On-Going 0% = Minimum State Match % Required Amendment Mental Health Bill Operating & Maintenance Costs: Amount Staff Project Development: 0 0 Ongoing Operating: 0 0 One-Time Startup: 0 Totals: 0 0 Additional Information / Prior Funding History: Previous Funding: CIP SLA 2008/CH 29 $8,900,000 (GO Bonds) for access road design and construction SLA 2007/CH 30/Sec18 (a) $100,000 SDPR for master interpretive plain Project Description/Justification: Detailed Project Justification: Purpose: Year round visitor center on Curry Ridge in Denali State Park approximately three miles east of the Parks Highway at mile post 135 Facilities will include 15,000 square foot visitor center, transportation center, campground, trails, interpretive displays, and parking FY2012 Governor Amended 2/16/11 3:32:08 PM Page 1

South Denali Visitor Center Design and Construction FY2012 Request: Meet Alaskans and visitors demand for additional interpretation, outdoor recreation, and access to public lands Provide opportunities for viewing Mt. McKinley, learning about Alaska, accessing the subalpine ridge and lake 1787 Meet growing demand for a Denali experience within one days drive of Anchorage Enhance opportunities for snow machining, skiing, hiking, camping, school groups, and education Boost local economy Provide the basic infrastructure that will support and encourage responsible private sector development of services and activities for visitors and Alaska residents Enhance four-season tourism opportunities in the region which will increase economic opportunities for businesses in local communities Economic Impact: Economic Impact Study completed in 2008 by the Institute of Social and Economic Research Estimated annual visitation of Alaskans, cruise passengers, independent and business travelers between 250,000 and 350,000 annually Visitor Center construction and related construction activities will provide employment for 116-213 people, over a period of 2-3 years Ongoing employment created by the Visitor Center and related activities, including additional hotel rooms, would be 221-549 jobs Over a 2-3 year period, Visitor Center construction related income will range from $6.8 million to $12.4 million Ongoing Visitor Center related employment income, including additional hotel facilities, etc., will range from $7.6 million to $18.6 million per year Tourism expenditures stimulated by the existence of the Visitor Center will range from $17.8 million to $44.8 million per year Funding: Total construction cost is $37 million. State of Alaska funding to date includes $9 million from state general fund for the road design and construction. Other (non-state) funding commitments include $1 million federal Scenic Byways Grant to be used primarily for the transportation system, a $1 million commitment from Princess Tours towards the cost of extending power to the site, and a $1 million UCI ( native village of Hooper Bay) donation of land as an access parcel to the project Additional state general fund needs total $25 million with this FY12 capital request funding $ 3 million for facility design, and FY13 capital requests of $13 million for facility construction, $ 3 million for the transportation system construction, and $ 6 million for the extension of power to the location. Timeline: 2011 finish road design and permitting, start visitor center design 2012 construct road, complete visitor center design and permitting 2013 visitor center construction 2014 finish construction and open visitor center Process: FY2012 Governor Amended 2/16/11 3:32:13 PM Page 2

South Denali Visitor Center Design and Construction FY2012 Request: A new visitor destination in this area has been discussed since the 1960s South Denali Implementation Plan and EIS 2006 Denali State Park Management Plan 2006 Winter trail system development 2007 Parks Highway Scenic Corridor Plan 2008 Interpretive Master Plan 2009 Road alignment, geotechnical survey, and preliminary road design completed 2010 Public support has switched from very contentious to almost unanimous support with a handful of folks from Talkeetna still voicing opposition Public Partners: The Final South Denali Implementation Plan and Environmental Impact Statement represents the culmination of more than 13 years of partnership planning between the State of Alaska, the Matanuska-Susitna Borough, and the National Park Service Operations costs will be self sustaining with a combination of gate receipts, Matsu Borough contribution, and the National Park Service operating budget Private Partners: In 2008, UCI, a wholly owned subsidiary of the native village of Hooper Bay purchased a 160 acre tract immediately adjacent to the project site for $1.2m Access across the UCI tract provides the most ideal access to the visitor center site. UCI has proposed donating 130 acres of the site to; o Facilitate the access road o Prohibit unwanted piecemeal development adjacent to the state park. o Preserve view shed for the park and visitor center UCI would retain 30 acres for development of private sector lodging experience within the park. The development would; o Adhere to restrictive covenants preserving the park environment. o Adhere to view shed restrictions making the lodge a discrete experience from the visitor center experience o Provide private sector improvements to complement the public park experience. The Lodge would add o $20-35m of private sector investment to the area and the tax base. o Long term jobs. o Long term investment return for the shareholders of Hooper Bay Why is this Project Needed Now?: This project has been talked about for 40 years. With completion of the EIS and Interpretive Plan it is time to move forward with design and construction. During the current economic times the cost of construction is very reasonable and it expected to increase in the future. The value of this project to the local economy, locals, visitors, and the tourism industry is very important and the project is needed now to meet those demands. FY2012 Governor Amended 2/16/11 3:32:13 PM Page 3

South Denali Visitor Center Design and Construction FY2012 Request: Specific Spending Detail: LINE ITEM DOLLAR AMOUNT DESCRIPTION (text) Personal Services $ 400,000 Staff preparation and oversight of design contract. Services $2,600,000 Contract for design. FY2012 Governor Amended 2/16/11 3:32:13 PM Page 4