1 Exhibit P-40, Budget Line Item Justification: PB 2016 Navy Date: February N: Aircraft Procurement, Navy / BA 05: Modification of Aircraft / BSA 1: Modification of Aircraft ID Code (A=Service Ready, B=Not Service Ready) : A Program Elements for Code B Items: Other Related Program Elements: N Resource Summary Prior Years FY 2014 FY 2015 FY 2017 FY 2018 FY 2019 FY 2020 Procurement Quantity (Units in Each) Gross/Weapon System Cost ($ in Millions) Less PY Advance Procurement ($ in Millions) Net Procurement (P1) ($ in Millions) Plus CY Advance Procurement ($ in Millions) Obligation Authority ($ in Millions) (The following Resource Summary rows are for informational purposes only. The corresponding budget requests are documented elsewhere.) Initial Spares ($ in Millions) Flyaway Unit Cost ($ in Dollars) Gross/Weapon System Unit Cost ($ in Dollars) Description: This line funds modifications to the RQ-7 Unmanned Air Vehicle (UAV) and associated support systems. The RQ-7B Shadow UAV system provides dedicated Reconnaissance, Surveillance and Target Acquisition, Intelligence, Battle Damage Assessment and Force Protection to the Marine Air-Ground Task Force. The RQ-7B Shadow UAS provides the Marine Expeditionary Force with critical battlefield intelligence and targeting information in the rapid cycle time required for success at the tactical level. The RQ-7B Shadow UAS system consists of four air vehicles each configured with an Electro-Optical/Infra-Red sensor payload, launcher, ground control stations, attrition engine, support equipment, and Government furnished equipment which includes power generation communications equipment, automated recovery equipment, remote video terminals, vehicle mounted shelters, and High Mobility Multipurpose Wheeled Vehicles with trailer(s). Each system is equipped with one maintenance section multifunctional vehicle and is supported by a mobile maintenance facility. The RQ-7B Shadow UAV system has logged over 47,000 flight hours since May Most hours were flown in support of Overseas Contingency Operations. The RQ-7B Shadow UAV system modifications are procured through the Army on the Army's Shadow Tactical Unmanned Aircraft System contracts and are identical to the Army's system. Every effort is made to ensure that the Marine Corps RQ-7B Shadow configuration matches the Army's such that combat units maintain maximum interoperability, maintainability, and combat effectiveness. Navy Page 1 of 5 P-1 Line #58 Volume 2-877

2 Exhibit P-40, Budget Line Item Justification: PB 2016 Navy Date: February N: Aircraft Procurement, Navy / BA 05: Modification of Aircraft / BSA 1: Modification of Aircraft ID Code (A=Service Ready, B=Not Service Ready) : A Program Elements for Code B Items: Other Related Program Elements: N Exhibits Schedule Prior Years FY 2014 FY 2015 Title* Exhibits ID CD (Added Capability) P-3a - / / / - - / / - - / Gross/Weapon System Cost - / / / - - / / - - / Exhibits Schedule FY 2017 FY 2018 FY 2019 FY 2020 Title* Exhibits ID CD (Added Capability) P-3a - / / - - / - - / - - / - - / Gross/Weapon System Cost - / / - - / - - / - - / - - / *Title represents 1) the Number / Title for Items; 2) the Number / Title [DODIC] for Ammunition; and/or 3) the Number / Title (Modification Type) for Modifications. Note: s in this Exhibit P-40 set may not be exact or add due to rounding. Justification: FY2014 requested supported the continuation of the Congressionally mandated Tactical Common Data Link (TCDL) and supports Pre-Planned Product Improvements (P3I), retrofit, and associated equipment for Shadow, including, but not limited to, technology insertion upgrades to improve reliability, safety and performance, weaponization, communications, target designation, and other upgrades to be determined based on operational requirements and user needs. FY2014 procured two TCDL upgrade kits, and incorporation of sixty-four (64) Small Mission Computers, to maintain United States Marine Corps RQ-7B Shadow Unmanned Air Systems interoperability with United States Army systems. FY2015 requested funding for Small Mission Computer was fully marked by Congress in the appropriations process due to FY14 unobligated balances. The RQ-7 program will procure additional Small Mission Computers, up to a quantity of sixty-four (64) in FY14 to comply with Congressional direction. FY2016 requested funding was originally planned for the procurement of forty-six (46) propulsion upgrades under development by the US Army RQ-7 program. Development of these propulsion upgrades was delayed by one (1) year and will commence in FY17. In FY16 the RQ-7 program will procure thirty-two (32) PRC-152A radios, weatherization kits, and other equipment, if so designated, to maintain Marine Corps RQ-7B Shadow Unmanned Aircraft Systems interoperability and commonality with Army systems and to permit full integration of Shadow generated information into the digital interoperability environment. FY2017 requested funding will procure the first increment of forty-six (46) propulsion system upgrades, and other equipment, if so designated to maintain Marine Corps RQ-7B Shadow UAS interoperability and commonality with Army systems and the digital environment. Navy Page 2 of 5 P-1 Line #58 Volume 2-878

3 Resource Summary Prior Years FY 2014 FY 2015 FY 2017 FY 2018 FY 2019 FY 2020 Procurement Quantity (Units in Each) Gross/Weapon System Cost ($ in Millions) Less PY Advance Procurement ($ in Millions) Net Procurement (P1) ($ in Millions) Plus CY Advance Procurement ($ in Millions) Obligation Authority ($ in Millions) (The following Resource Summary rows are for informational purposes only. The corresponding budget requests are documented elsewhere.) Initial Spares ($ in Millions) Gross/Weapon System Unit Cost ($ in Dollars) Description: FY2014 requested supported the continuation of the Congressionally mandated Tactical Common Data Link (TCDL) and supports Pre-Planned Product Improvements (P3I), retrofit, and associated equipment for Shadow, including, but not limited to, technology insertion upgrades to improve reliability, safety and performance, weaponization, communications, target designation, and other upgrades to be determined based on operational requirements and user needs. FY2014 procured two TCDL upgrade kits, and incorporation of sixty-four (64) Small Mission Computers, to maintain United States Marine Corps RQ-7B Shadow Unmanned Air Systems interoperability with United States Army systems. FY2015 requested funding for Small Mission Computer was fully marked by Congress in the appropriations process due to FY14 unobligated balances. The RQ-7 program will procure additional Small Mission Computers, up to a quantity of sixty-four (64) in FY14 to comply with Congressional direction. FY2016 requested funding was originally planned for the procurement of forty-six (46) propulsion upgrades under development by the US Army RQ-7 program. Development of these propulsion upgrades was delayed by one (1) year and will commence in FY17. In FY16 the RQ-7 program will procure thirty-two (32) PRC-152A radios, weatherization kits, and other equipment, if so designated, to maintain Marine Corps RQ-7B Shadow Unmanned Aircraft Systems interoperability and commonality with Army systems and to permit full integration of Shadow generated information into the digital interoperability environment. FY2017 requested funding will procure the first increment of forty-six (46) propulsion system upgrades, and other equipment, if so designated to maintain Marine Corps RQ-7B Shadow UAS interoperability and commonality with Army systems and the digital environment. DEVELOPMENT STATUS/MAJOR DEVELOPMENT MILESTONE: Planned Initial Operational Capability for TCDL rescheduled from FY2014 to FY2015 Planned Initial Operational Capability for Small Mission Computers in FY2016 Navy Page 3 of 5 P-1 Line #58 Volume 2-879

4 Models of Systems Affected: RQ-7B Shadow UAV Modification Type: Added Capability Related RDT&E PEs: N Procurement Financial Plan Modification Item 1 of 1: RQ-7 UAV Retrofits (OSIP ) B Kits Recurring Prior Years FY 2014 FY 2015 FY 2017 FY 2018 FY 2019 FY 2020 (1) 1.1.1) P3I Upgrades/Retrofits - NonOrganic 7 / / / - 32 / / - 32 / / / - - / - - / - - / / Subtotal: Recurring - / / / - - / / - - / / / - - / - - / - - / - - / Non-Recurring 1.2.1) Installation Equipment N/R - Organic - / / - - / - - / - - / - - / - - / - - / - - / - - / - - / - - / Subtotal: Non-Recurring - / / - - / - - / - - / - - / - - / - - / - - / - - / - - / - - / Subtotal: RQ-7 UAV Retrofits (OSIP ) 7 / / / - 32 / / - 32 / / / - - / - - / - - / / Subtotal: Procurement, All Modification Items - / / / - - / / - - / / / - - / - - / - - / - - / Installation Modification Item 1 of 1: RQ-7 UAV Retrofits (OSIP ) - / / - - / - - / - - / - - / - - / - - / - - / - - / - - / - - / - Subtotal: Installation - / / - - / - - / - - / - - / - - / - - / - - / - - / - - / - - / - Cost (Procurement + Support + Installation) Navy Page 4 of 5 P-1 Line #58 Volume 2-880

5 Modification Item 1 of 1: RQ-7 UAV Retrofits (OSIP ) Manufacturer Information Manufacturer Name: AAI (2) Manufacturer Location: Hunt Valley, MD Administrative Leadtime (in Months): 9 Production Leadtime (in Months): 12 Dates FY 2014 FY 2015 FY 2017 FY 2018 FY 2019 FY 2020 Contract Dates Jun 2015 Jun 2016 Jun 2017 Delivery Dates Jun 2016 Jun 2017 Jun 2018 Installation Information Method of Implementation: [none specified]:: Installation Name: P3I Upgrades/Retrofits Installation Cost Prior Years FY 2014 FY 2015 FY 2017 FY 2018 FY 2019 FY 2020 Prior Years 2 / / - - / - 5 / / / / - - / - - / - - / - - / - 7 / FY / - - / - - / - 28 / - - / - 28 / - - / - - / - - / - - / - - / - 28 / - FY / - - / - - / - - / - - / - - / - - / - - / - - / - - / - - / - - / - - / - - / - - / - - / - - / - - / - 32 / - - / - - / - - / - - / - 32 / - FY / - - / - - / - - / - - / - - / - - / - 46 / - - / - - / - - / - 46 / - FY / - - / - - / - - / - - / - - / - - / - - / - - / - - / - - / - - / - FY / - - / - - / - - / - - / - - / - - / - - / - - / - - / - - / - - / - FY / - - / - - / - - / - - / - - / - - / - - / - - / - - / - - / - - / - - / - - / - - / - - / - - / - - / - - / - - / - - / - - / - - / - - / - 2 / / - - / - 33 / - - / - 33 / - 32 / - 46 / - - / - - / - - / / - Installation Schedule FY 2014 FY 2015 FY 2017 FY 2018 FY 2019 FY 2020 PYS Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 TC t In Out Footnotes: (1) FY2014 funding will procure 2 TCDL upgrade kits and 26 Small Mission Computers. FY2015 funding fully marked. FY2016 funding will procure and 32 PRC-152A radios, weatherization kits, and other equipment. FY2017 funding will procure 46 propulsion system upgrades. (2) Dollars not shown due to turn-key contract method, but quantities shown in the year that they will install. Navy Page 5 of 5 P-1 Line #58 Volume 2-881

UNCLASSIFIED. FY 2017 Base FY 2017 OCO FY 2017 OCO. FY 2017 Base

UNCLASSIFIED. FY 2017 Base FY 2017 OCO FY 2017 OCO. FY 2017 Base Exhibit P-40, Budget Line Item Justification: PB 2017 Army Date: February 2016 2031A: Aircraft Procurement, Army / BA 02: Modification of Aircraft / BSA 10: Modification of Aircraft ID Code (A=Service

More information

UNCLASSIFIED. FY 2014 FY 2014 OCO ## Total FY 2015 FY 2016 FY 2017 FY 2018

UNCLASSIFIED. FY 2014 FY 2014 OCO ## Total FY 2015 FY 2016 FY 2017 FY 2018 Exhibit P-40, Budget Item Justification Sheet: PB 2014 United States Special Operations Command Date: April 2013 Operations Command / BSA 1: Aviation Programs ID Code (A=Service Ready, B=Not Service Ready)

More information

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 8 P-1 Line #50

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 8 P-1 Line #50 Exhibit P-40, Budget Line Item Justification: PB 2017 Air Force Date: February 2016 3010F: Aircraft Procurement, Air Force / BA 05: Modification of Inservice Aircraft / BSA 5: Other Aircraft ID Code (A=Service

More information

UNCLASSIFIED. UNCLASSIFIED Army Page 1 of 13 P-1 Line #25

UNCLASSIFIED. UNCLASSIFIED Army Page 1 of 13 P-1 Line #25 Exhibit P-40, Budget Line Item Justification: PB 2015 Army Date: March 2014 2031A: Aircraft Procurement, Army / BA 02: Modification of Aircraft / BSA 10: Modification of Aircraft ID Code (A=Service Ready,

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE Exhibit R-2, RDT&E Budget Item Justification: PB 213 Navy DATE: February 212 COST ($ in Millions) FY 211 FY 212 FY 214 FY 215 FY 216 FY 217 To Complete Program Element 25.229.872.863 7.6 8.463.874.876.891.96

More information

UNCLASSIFIED. FY 2014 FY 2014 OCO ## Total FY 2015 FY 2016 FY 2017 FY 2018

UNCLASSIFIED. FY 2014 FY 2014 OCO ## Total FY 2015 FY 2016 FY 2017 FY 2018 Exhibit P-40, Budget Item Justification Sheet: PB 2014 Navy Date: April 2013 combat vehicles / BSA 2: Artillery And Other Weapons ID Code (A=Service Ready, B=Not Service Ready) : A Program Elements for

More information

UNCLASSIFIED. FY 2017 Base FY 2017 OCO

UNCLASSIFIED. FY 2017 Base FY 2017 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2017 United States Special Operations Command : February 2016 0400: Research, Development, Test & Evaluation, Defense-Wide / BA 7: Operational Systems Development

More information

UNCLASSIFIED FY 2017 OCO. FY 2017 Base

UNCLASSIFIED FY 2017 OCO. FY 2017 Base Exhibit P-40, Budget Line Item Justification: PB 2017 Navy Date: February 2016 1810N: Other Procurement, Navy / BA 04: Ordnance Support Equipment / BSA 3: Ship Missile Systems Equipment ID Code (A=Service

More information

UNCLASSIFIED. FY 2017 Base FY 2017 OCO FY 2017 OCO. FY 2017 Base

UNCLASSIFIED. FY 2017 Base FY 2017 OCO FY 2017 OCO. FY 2017 Base Exhibit P-40, Budget Line Item Justification: PB 2017 Date: February 2016 2035A: Other Procurement, / BA 01: Tactical and Support Vehicles / BSA 20: Non-Tactical Vehicles ID Code (A=Service Ready, B=Not

More information

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 7 P-1 Line #10

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 7 P-1 Line #10 Exhibit P-40, Budget Line Item Justification: PB 2017 Air Force Date: February 2016 3021F: Space Procurement, Air Force / BA 01: Space Procurement, Air Force / BSA 1: Space Programs Code (A=Service Ready,

More information

UNCLASSIFIED. FY 2017 Base FY 2017 OCO

UNCLASSIFIED. FY 2017 Base FY 2017 OCO Exhibit P-40, Budget Line Item Justification: PB 2017 Air Force Date: February 2016 3020F: Missile Procurement, Air Force / BA 03: Modification of Inservice Missiles / BSA 1: Class IV ID Code (A=Service

More information

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 9 P-1 Line #1

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 9 P-1 Line #1 Exhibit P-40, Budget Line Item Justification: PB 2017 Air Force : February 2016 3011F: Procurement of Ammunition, Air Force / BA 01: Ammunition / BSA 11: Rockets ID Code (A=Service Ready, B=Not Service

More information

UNCLASSIFIED FY 2017 OCO. FY 2017 Base

UNCLASSIFIED FY 2017 OCO. FY 2017 Base Exhibit P-40, Budget Line Item Justification: PB 2017 Air Force : February 2016 3011F: Procurement of Ammunition, Air Force / BA 01: Ammunition / BSA 16: Flares ID Code (A=Service Ready, B=Not Service

More information

UNCLASSIFIED. FY 2017 Base FY 2017 OCO. FY 2017 Base FY 2017 OCO

UNCLASSIFIED. FY 2017 Base FY 2017 OCO. FY 2017 Base FY 2017 OCO Exhibit P-40, Budget Line Item Justification: PB 2017 Army : February 2016 2035A: Other Procurement, Army / BA 02: Communications and Electronics Equipment / BSA 80: Elect Equip - Tact Int Rel Act (TIARA)

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE Exhibit R-2, RDT&E Budget Item Justification: PB 213 Army DATE: February 212 COST ($ in Millions) FY 211 FY 212 FY 214 FY 215 FY 216 FY 217 To Program Element 1.547 1.935 4.39-4.39 2.917 2.977 3.25 3.77

More information

UNCLASSIFIED. UNCLASSIFIED United States Special Operations Command Page 1 of 6 R-1 Line #208

UNCLASSIFIED. UNCLASSIFIED United States Special Operations Command Page 1 of 6 R-1 Line #208 Exhibit R-2, RDT&E Budget Item Justification: PB 2015 United States Special Operations Command Date: March 2014 0400: Research, Development, Test & Evaluation, Defense-Wide / BA 7: Operational Systems

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE Exhibit R-2, RDT&E Budget Item Justification: PB 2014 United States Special Operations Command DATE: April 2013 COST ($ in Millions) Years FY 2012 FY 2013 # Base OCO ## FY 2015 FY 2016 FY 2017 FY 2018

More information

UNCLASSIFIED. UNCLASSIFIED Army Page 1 of 12 P-1 Line #51

UNCLASSIFIED. UNCLASSIFIED Army Page 1 of 12 P-1 Line #51 Exhibit P-40, Budget Line Item Justification: PB 2017 Army : February 2016 2035A: Other Procurement, Army / BA 02: Communications and Electronics Equipment / BSA 64: Information Security ID Code (A=Service

More information

UNCLASSIFIED. UNCLASSIFIED Navy Page 1 of 7 P-1 Line #18

UNCLASSIFIED. UNCLASSIFIED Navy Page 1 of 7 P-1 Line #18 Exhibit P-40, Budget Line Item Justification: PB 2017 Navy Date: February 2016 1611N: Shipbuilding and Conversion, Navy / BA 03: Amphibious Ships / BSA 1: Amphibious Ships ID Code (A=Service Ready, B=Not

More information

UNCLASSIFIED. UNCLASSIFIED Army Page 1 of 8 P-1 Line #33

UNCLASSIFIED. UNCLASSIFIED Army Page 1 of 8 P-1 Line #33 Exhibit P-40, Budget Line Item Justification: PB 2017 Army Date: February 2016 2034A: Procurement of Ammunition, Army / BA 02: Ammunition Production Base Support / BSA 10: Production Base Support ID Code

More information

ARMY RDT&E BUDGET ITEM JUSTIFICATION (R-2 Exhibit)

ARMY RDT&E BUDGET ITEM JUSTIFICATION (R-2 Exhibit) COST (In Thousands) FY1999 Actual FY 2002 FY 2003 FY2004 FY2005 to Army Joint STARS (TIARA) 5316 25676 17898 17713 12833 14372 11527 Continuing Continuing A. Mission Description and Justification: The

More information

UNCLASSIFIED. FY 2016 Base FY 2016 OCO

UNCLASSIFIED. FY 2016 Base FY 2016 OCO Exhibit R2, RDT&E Budget Item Justification: PB 2016 Navy : February 2015 1319: Research, Development, Test & Evaluation, Navy / BA 7: Operational Systems Development COST ($ in Millions) Years R1 Program

More information

UNCLASSIFIED. UNCLASSIFIED Navy Page 5 of 10 P-1 Line #11

UNCLASSIFIED. UNCLASSIFIED Navy Page 5 of 10 P-1 Line #11 Exhibit P-27, Ship Production Schedule: PB 2017 Navy Date: February 2016 Ship Shipbuilder Fiscal Year Contract Award Start of Construction Delivery Date LCS 7 LOCKHEED MARTIN 2011 Mar 2011 Apr 2012 Jun

More information

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 5 R-1 Line #213

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 5 R-1 Line #213 COST ($ in Millions) Prior Years FY 2013 FY 2014 Base OCO # Total FY 2016 FY 2017 FY 2018 FY 2019 Cost To Complete Total Program Element - 12.205 13.491 13.516-13.516 13.767 14.037 14.311 14.584 Continuing

More information

Department of Defense Fiscal Year (FY) 2016 President's Budget Submission

Department of Defense Fiscal Year (FY) 2016 President's Budget Submission Department of Defense Fiscal Year (FY) 2016 President's Budget Submission February 2015 Department of Defense Education Activity Defense Wide Justification Book Volume 1 of 1 Procurement, Defense-Wide

More information

ARMY RDT&E BUDGET ITEM JUSTIFICATION (R2 Exhibit)

ARMY RDT&E BUDGET ITEM JUSTIFICATION (R2 Exhibit) Budget Item Justif ication Exhibit R-2 0604633A ARMY RDT&E BUDGET ITEM JUSTIFICATION (R2 Exhibit) COST (In Thousands) Actual Estimate Estimate to AIR TRAFFIC CONTROL 11676 14167 7578 Continuing Continuing

More information

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 8 R-1 Line #211

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 8 R-1 Line #211 Exhibit R-2, RDT&E Budget Item Justification: PB 2015 Air Force Date: March 2014 3600: Research, Development, Test & Evaluation, Air Force / BA 7: Operational Systems Development COST ($ in Millions) Prior

More information

CLASSIFICATION: UNCLASSIFIED

CLASSIFICATION: UNCLASSIFIED Exhibit P-40, BUDGET ITEM JUSTIFICATION APPROPRIATION/BUDGET ACTIVITY Aircraft Procurement, Navy/APN-5 Aircraft Modifications Program Element for Code B Items: P-1 ITEM NOMENCLATURE 051100, EA-6 SERIES

More information

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE N: Air Control

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE N: Air Control Exhibit R-2, RDT&E Budget Item Justification: PB 212 Navy DATE: February 211 COST ($ in Millions) FY 21 FY 211 PE 6454N: Air Control FY 213 FY 214 FY 215 FY 216 To Complete Program Element 6.373 5.665

More information

ARMY RDT&E BUDGET ITEM JUSTIFICATION (R-2 Exhibit)

ARMY RDT&E BUDGET ITEM JUSTIFICATION (R-2 Exhibit) COST (In Thousands) ARMY COMMON GROUND STATION (CGS) (TIARA) FY 2000 FY 2001 FY 2002 FY 2003 FY 2004 FY 2005 FY 2006 FY 2007 Cost to Total Cost Actual Estimate Estimate Estimate Estimate Estimate Estimate

More information

ARMY RDT&E BUDGET ITEM JUSTIFICATION (R-2 Exhibit)

ARMY RDT&E BUDGET ITEM JUSTIFICATION (R-2 Exhibit) ARMY RDT&E BUDGET ITEM JUSTIFICATION (R-2 Exhibit) COST (In Thousands) FY1998 Actual FY 2002 FY 2003 FY2004 FY2005 to Army Joint STARS (TIARA) 6464 5463 11535 26871 25227 10752 16437 130 Continuing Continuing

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE. FY 2014 FY 2014 OCO ## Total FY 2015 FY 2016 FY 2017 FY 2018

UNCLASSIFIED R-1 ITEM NOMENCLATURE. FY 2014 FY 2014 OCO ## Total FY 2015 FY 2016 FY 2017 FY 2018 Exhibit R-2, RDT&E Budget Item Justification: PB 2014 Navy DATE: April 2013 COST ($ in Millions) Years FY 2012 FY 2013 # ## FY 2015 FY 2016 FY 2017 FY 2018 To Program Element 174.037 11.276 8.610 1.971-1.971

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2013 United States Special Operations Command DATE: February 2012 COST ($ in Millions) FY 2011 FY 2012 Total FY 2014 FY 2015 FY 2016 FY 2017 To Complete

More information

UNCLASSIFIED UNCLASSIFIED

UNCLASSIFIED UNCLASSIFIED EXHIBIT R-2, RDT&E Budget Item Justification APPROPRIATION/BUDGET ACTIVITY R-1 ITEM NOMENCLATURE RESEARCH DEVELOPMENT TEST & EVALUATION, NAVY / BA-7 0305192N - JOINT MILITARY INTELLIGENCE PROGRAM Prior

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE PE F: SPECIAL TACTICS/COMBAT CONTROL

UNCLASSIFIED R-1 ITEM NOMENCLATURE PE F: SPECIAL TACTICS/COMBAT CONTROL Exhibit R-2, RDT&E Budget Item Justification: PB 2012 Air Force DATE: February 2011 COST ($ in Millions) FY 2013 FY 2014 FY 2015 FY 2016 To Complete Program Element 9.693 17.670 7.118-7.118 7.538 7.651

More information

Exhibit R-2, RDT&E Budget Item Justification February 2008

Exhibit R-2, RDT&E Budget Item Justification February 2008 PE NUMBER: 41318F PE TITLE: CV-22 Exhibit R-2, RDT&E Budget Item Justification February 28 5 System Development and Demonstration (SDD) 41318F CV-22 ($ in Millions) 413 Total Program Element (PE) CV-22

More information

UNCLASSIFIED UNCLASSIFIED

UNCLASSIFIED UNCLASSIFIED : February 26 Exhibit R2, RDT&E Budget Item Justification: PB 27 24: Research, Development, Test & Evaluation, / BA 7: Operational Systems Development COST ($ in Millions) R Element (Number/Name) PE 6735A

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE Exhibit R-2, RDT&E Budget Item Justification: PB 2013 Navy DATE: February 2012 COST ($ in Millions) FY 2011 FY 2012 Total FY 2014 FY 2015 FY 2016 FY 2017 To Complete Total Total Program Element - 15.000

More information

UNCLASSIFIED FY This program develops and demonstrates advanced technologies, including Electromagnetic (EM) Rail Gun for naval weapon systems.

UNCLASSIFIED FY This program develops and demonstrates advanced technologies, including Electromagnetic (EM) Rail Gun for naval weapon systems. Exhibit R-2, RDT&E Budget Item Justification: PB 2015 Navy Date: March 2014 1319: Research, Development, Test & Evaluation, Navy / BA 3: Advanced Development (ATD) COST ($ in Millions) Prior Years FY 2013

More information

UNCLASSIFIED. FY 2017 Base FY 2017 OCO

UNCLASSIFIED. FY 2017 Base FY 2017 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2017 Navy Date: February 2016 1319: Research, Development, Test & Evaluation, Navy / BA 3: Advanced Technology Development (ATD) COST ($ in Millions) Prior

More information

ARMY RDT&E BUDGET ITEM JUSTIFICATION (R-2 Exhibit)

ARMY RDT&E BUDGET ITEM JUSTIFICATION (R-2 Exhibit) ARMY RDT&E BUDGET ITEM JUSTIFICATION (R-2 Exhibit) COST (In Thousands) FY1999 Actual FY 2002 FY 2003 FY2004 FY2005 to Program Element (PE) 352217 463124 614041 764621 738441 762673 407979 Continuing Continuing

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2013 Air Force DATE: February 2012 COST ($ in Millions) FY 2011 FY 2014 FY 2015 FY 2016 FY 2017 To Program Element 42.067 6.509 5.000-5.000 41.500 30.000

More information

UNCLASSIFIED. Cost To Complete Total Program Element Continuing Continuing EF4: Integrated Broadcast System

UNCLASSIFIED. Cost To Complete Total Program Element Continuing Continuing EF4: Integrated Broadcast System Exhibit R-2, RDT&E Budget Item Justification: PB 2016 Army : February 2015 2040: Research, Development, Test & Evaluation, Army / BA 7: Operational Systems Development COST ($ in Millions) Years FY 2014

More information

RDT&E BUDGET ITEM JUSTIFICATION SHEET (R-2 Exhibit) MAY 2009 APPROPRIATION / BUDGET ACTIVITY RDT&E, DEFENSE-WIDE / 7

RDT&E BUDGET ITEM JUSTIFICATION SHEET (R-2 Exhibit) MAY 2009 APPROPRIATION / BUDGET ACTIVITY RDT&E, DEFENSE-WIDE / 7 RDT&E BUDGET ITEM JUSTIFICATION SHEET (R-2 Exhibit) DATE MAY 2009 APPROPRIATION / BUDGET ACTIVITY RDT&E, DEFENSE-WIDE / 7 R-1 ITEM NOMENCLATURE / PROJECT NO. PE 1160404BB Special Operations (SO) Tactical

More information

UNCLASSIFIED. FY 2016 Base FY 2016 OCO. Quantity of RDT&E Articles

UNCLASSIFIED. FY 2016 Base FY 2016 OCO. Quantity of RDT&E Articles Exhibit R-2, RDT&E Budget Item Justification: PB 2016 Air Force : February 2015 COST ($ in Millions) Years FY 2017 FY 2018 FY 2019 FY 2020 To Program Element - 6.021 8.312 7.963-7.963 8.046 8.146 8.194

More information

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 6 R-1 Line #62

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 6 R-1 Line #62 COST ($ in Millions) Prior Years FY 2013 FY 2014 Base OCO # Total FY 2016 FY 2017 FY 2018 FY 2019 Cost To Complete Total Program Element - 0.051-3.926-3.926 4.036 4.155 4.236 4.316 Continuing Continuing

More information

OVERSEAS CONTINGENCY OPERATIONS (OCO)

OVERSEAS CONTINGENCY OPERATIONS (OCO) OVERSEAS CONTINGENCY OPERATIONS (OCO) OVERVIEW submitted to the Congress in June 2014. The Navy and Marine Corps approach to support the comprehensive strategy to degrade, and ultimately, defeat, the Islamic

More information

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE F: Specialized Undergraduate Pilot Training. FY 2011 Total Estimate. FY 2011 OCO Estimate

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE F: Specialized Undergraduate Pilot Training. FY 2011 Total Estimate. FY 2011 OCO Estimate Exhibit R-2, RDT&E Budget Item Justification: PB 2011 Air Force DATE: February 2010 COST ($ in Millions) FY 2009 Actual FY 2010 FY 2012 FY 2013 FY 2014 FY 2015 To Complete Program Element 11.801 10.862

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2013 Army DATE: February 2012 COST ($ in Millions) FY 2011 FY 2012 Total FY 2014 FY 2015 FY 2016 FY 2017 To Complete Total Total Program Element - 2.885

More information

Department of Defense Fiscal Year (FY) 2017 Request for Additional Appropriations

Department of Defense Fiscal Year (FY) 2017 Request for Additional Appropriations Department of Defense Fiscal Year (FY) 2017 Request for Additional Appropriations March 2017 Air Force Justification Book Volume 1 of 1 Procurement of Ammunition, Air Force THIS PAGE INTENTIONALLY LEFT

More information

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 8 R-1 Line #156

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 8 R-1 Line #156 Exhibit R-2, RDT&E Budget Item Justification: PB 2016 Air Force : February 2015 3600: Research, Development, Test & Evaluation, Air Force / BA 7: Operational Systems Development COST ($ in Millions) Years

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE Exhibit R-2, RDT&E Budget Item Justification: PB 2013 Navy DATE: February 2012 COST ($ in Millions) FY 2011 FY 2012 FY 2014 FY 2015 FY 2016 FY 2017 Navy Page 1 of 8 R-1 Line #83 To Program Element - -

More information

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE F: MQ-9 Development and Fielding. FY 2011 Total Estimate. FY 2011 OCO Estimate

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE F: MQ-9 Development and Fielding. FY 2011 Total Estimate. FY 2011 OCO Estimate Exhibit R-2, RDT&E Budget Item Justification: PB 2011 Air Force DATE: February 2010 COST ($ in Millions) FY 2009 Actual FY 2010 FY 2012 FY 2013 FY 2014 FY 2015 To Complete Program Element 57.205 93.145

More information

UNCLASSIFIED. FY 2017 Base FY 2017 OCO

UNCLASSIFIED. FY 2017 Base FY 2017 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2017 Air Force : February 2016 COST ($ in Millions) Years FY 2018 FY 2019 FY 2020 FY 2021 To Program Element - 4.208 2.245 5.830 0.000 5.830 17.932 35.734

More information

UNCLASSIFIED. Cost To Complete Total Program Element Continuing Continuing : Physical Security Equipment

UNCLASSIFIED. Cost To Complete Total Program Element Continuing Continuing : Physical Security Equipment COST ($ in Millions) Prior Years FY 2013 FY 2014 Base OCO # Total FY 2016 FY 2017 FY 2018 FY 2019 Cost To Complete Total Program Element - 3.350 3.874 - - - 1.977 - - - Continuing Continuing 645121: Physical

More information

UNCLASSIFIED. FY 2017 Base FY 2017 OCO

UNCLASSIFIED. FY 2017 Base FY 2017 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2017 Air Force : February 2016 3600: Research, Development, Test & Evaluation, Air Force / BA 7: Operational Systems Development COST ($ in Millions) (+)

More information

UNCLASSIFIED. FY 2016 Base FY 2016 OCO

UNCLASSIFIED. FY 2016 Base FY 2016 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2016 Air Force : February 2015 3600: Research, Development, Test & Evaluation, Air Force / BA 7: Operational Systems Development COST ($ in Millions) FY

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE Exhibit R-2, RDT&E Budget Item Justification: PB 2013 Air Force DATE: February 2012 COST ($ in Millions) FY 2011 FY 2012 Base OCO Total FY 2014 FY 2015 FY 2016 FY 2017 Cost To Complete Total Cost Total

More information

UNCLASSIFIED UNCLASSIFIED

UNCLASSIFIED UNCLASSIFIED : February 216 Exhibit R2, RDT&E Budget Item Justification: PB 217 24: Research, Development, Test & Evaluation, / BA 5: tem Development & Demonstration (SDD) COST ($ in Millions) FY 215 FY 216 R1 Program

More information

UNCLASSIFIED UNCLASSIFIED. EXHIBIT R-2, RDT&E Budget Item Justification February 2007 RESEARCH DEVELOPMENT TEST & EVALUATION, NAVY / BA-7

UNCLASSIFIED UNCLASSIFIED. EXHIBIT R-2, RDT&E Budget Item Justification February 2007 RESEARCH DEVELOPMENT TEST & EVALUATION, NAVY / BA-7 EXHIBIT R-2, RDT&E Budget Item Justification APPROPRIATION/BUDGET ACTIVITY R-1 ITEM NOMENCLATURE RESEARCH DEVELOPMENT TEST & EVALUATION, NAVY / BA-7 0305204N TACTICAL UNMANNED AERIAL VEHICLES COST ($ in

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2013 Air Force DATE: February 2012 COST ($ in Millions) Total FY 2014 FY 2015 FY 2016 FY 2017 Air Force Page 1 of 14 R-1 Line #147 Cost To Complete Total

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2013 Air Force DATE: February 2012 COST ($ in Millions) Total Program Element 0.912 2.292 2.095-2.095 3.633 4.555 - - Continuing Continuing 671325: HH-60G

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE COST ($ in Millions) FY 2011 FY 2012 Base OCO Total FY 2014 FY 2015 FY 2016 FY 2017 Cost To Complete Total Cost Total Program Element 11.589 20.727 63.853-63.853 60.995 19.248 19.291 15.230 Continuing

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE Exhibit R-2, RDT&E Budget Item Justification: PB 2013 Air Force DATE: February 2012 COST ($ in Millions) Total Program Element - 9.967 8.117-8.117 50.084 104.866 132.174 229.912 Continuing Continuing 675346:

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE Exhibit R-2, RDT&E Budget Item Justification: PB 2013 Army DATE: February 2012 COST ($ in Millions) FY 2011 FY 2012 FY 2014 FY 2015 FY 2016 FY 2017 To Program Element 19.610 5.856 8.660-8.660 14.704 14.212

More information

ARMY RDT&E BUDGET ITEM JUSTIFICATION (R-2 Exhibit)

ARMY RDT&E BUDGET ITEM JUSTIFICATION (R-2 Exhibit) COST (In Thousands) Actual FY 2002 FY 2003 FY2004 FY 2005 to Force XXI Battle Command, Brigade & Below (FBCB2) 52003* 65176 63601 37699 29154 12179 0 0 264137 * Database presently shows 56328. Internal

More information

Exhibit R-2, RDT&E Budget Item Justification

Exhibit R-2, RDT&E Budget Item Justification PE NUMBER: 0604261F PE TITLE: Personnel Recovery Exhibit R-2, RDT&E Budget Item Justification BUDGET ACTIVITY PE NUMBER AND TITLE ($ in Millions) FY 2006 FY 2007 FY 2008 FY 2009 FY 2010 FY 2011 FY 2012

More information

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 9 R-1 Line #94

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 9 R-1 Line #94 Exhibit R-2, RDT&E Budget Item Justification: PB 2015 Air Force Date: March 2014 3600: Research, Development, Test & Evaluation, Air Force / BA 5: System Development & Demonstration (SDD) COST ($ in Millions)

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE Exhibit R-2, RDT&E Budget Item Justification: PB 2014 Air Force DATE: April 2013 COST ($ in Millions) # ## FY 2015 FY 2016 FY 2017 FY 2018 To Program Element - 108.021 21.000 3.000-3.000 3.000 2.000 0.000

More information

UNCLASSIFIED. UNCLASSIFIED Navy Page 1 of 8 R-1 Line #77

UNCLASSIFIED. UNCLASSIFIED Navy Page 1 of 8 R-1 Line #77 Exhibit R2, RDT&E Budget Item Justification: PB 2015 Navy Date: March 2014 1319: Research, Development, Test & Evaluation, Navy / BA 4: Advanced Component Development & Prototypes (ACD&P) COST ($ in Millions)

More information

ARMY RDT&E BUDGET ITEM JUSTIFICATION (R-2 Exhibit)

ARMY RDT&E BUDGET ITEM JUSTIFICATION (R-2 Exhibit) BUDGET ACTIVITY ARMY RDT&E BUDGET ITEM JUSTIFICATION (R-2 Exhibit) PE NUMBER AND TITLE 5 - System Development and Demonstration 0604223A - COMANCHE COST (In Thousands) FY 2002 FY 2003 FY 2004 FY 2005 FY

More information

UNCLASSIFIED UNCLASSIFIED. EXHIBIT R-2, RDT&E Budget Item Justification RESEARCH DEVELOPMENT TEST & EVALUATION, NAVY / BA-7

UNCLASSIFIED UNCLASSIFIED. EXHIBIT R-2, RDT&E Budget Item Justification RESEARCH DEVELOPMENT TEST & EVALUATION, NAVY / BA-7 CLASSIFICATION: EXHIBIT R-2, RDT&E Budget Item Justification APPROPRIATION/BUDGET ACTIVITY RESEARCH DEVELOPMENT TEST & EVALUATION, NAVY / BA-7 R-1 ITEM NOMENCLATURE 0305205N Endurance Unmanned Aerial Vehicles

More information

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE D8Z: Central Test and Evaluation Investment Program (CTEIP) FY 2013 OCO

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE D8Z: Central Test and Evaluation Investment Program (CTEIP) FY 2013 OCO COST ($ in Millions) FY 2011 FY 2012 FY 2013 Base FY 2013 OCO FY 2013 Total FY 2014 FY 2015 FY 2016 FY 2017 Cost To Complete Total Cost Total Program Element 157.971 156.297 144.109-144.109 140.097 141.038

More information

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 8 R-1 Line #86

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 8 R-1 Line #86 Exhibit R-2, RDT&E Budget Item Justification: PB 2017 Air Force : February 2016 3600: Research, Development, Test & Evaluation, Air Force / BA 5: System Development & Demonstration (SDD) COST ($ in Millions)

More information

UNCLASSIFIED. FY 2016 Base FY 2016 OCO

UNCLASSIFIED. FY 2016 Base FY 2016 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2016 Air Force : February 2015 3600: Research, Development, Test & Evaluation, Air Force / BA 7: Operational Systems Development COST ($ in Millions) FY

More information

UNCLASSIFIED. Cost To Complete Total Program Element S750: Mission Training and Preparation Systems FY 2015

UNCLASSIFIED. Cost To Complete Total Program Element S750: Mission Training and Preparation Systems FY 2015 Exhibit R-2, RDT&E Budget Item Justification: PB 2015 United States Special Operations Command Date: March 2014 0400: Research, Development, Test & Evaluation, Defense-Wide / BA 7: Operational Development

More information

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE F: Multi-Platform Electronics

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE F: Multi-Platform Electronics Exhibit R-2, RDT&E Budget Item Justification: PB 2012 Air Force DATE: February 2011 COST ($ in Millions) FY 2010 FY 2013 FY 2014 FY 2015 FY 2016 To Program Element 14.370 15.574 - - - - - - - Continuing

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE Exhibit R-2, RDT&E Budget Item Justification: PB 2013 United States Special Operations Command DATE: February 2012 COST ($ in Millions) FY 2011 FY 2012 Total FY 2014 FY 2015 FY 2016 FY 2017 To Complete

More information

Department of Defense Fiscal Year (FY) 2014 Amended Budget Estimates

Department of Defense Fiscal Year (FY) 2014 Amended Budget Estimates Department of Defense Fiscal Year (FY) 2014 Amended Budget Estimates May 2013 Air Force Justification Book Volume 1 of 1 Other Procurement, Air Force THIS PAGE INTENTIONALLY LEFT BLANK Air Force Amended

More information

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE BB: Special Operations Aviation Systems Advanced Development

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE BB: Special Operations Aviation Systems Advanced Development Exhibit R-2, RDT&E Budget Item Justification: PB 2013 United States Special Operations Command DATE: February 2012 COST ($ in Millions) FY 2011 FY 2012 Total FY 2014 FY 2015 FY 2016 FY 2017 To Complete

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE Exhibit R-2, RDT&E Budget Item Justification: PB 2013 Air Force DATE: February 2012 COST ($ in Millions) FY 2011 FY 2012 Base OCO Total FY 2014 FY 2015 FY 2016 FY 2017 Cost To Complete Total Cost Total

More information

UNCLASSIFIED. UNCLASSIFIED Navy Page 1 of 10 R-1 Line #98

UNCLASSIFIED. UNCLASSIFIED Navy Page 1 of 10 R-1 Line #98 Exhibit R2, RDT&E Budget Item Justification: PB 2015 Navy : March 2014 1319: Research, Development, Test & Evaluation, Navy / BA 5: System Development & Demonstration (SDD) COST ($ in Millions) Years FY

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE COST ($ in Millions) FY 2011 FY 2012 Base OCO Total FY 2014 FY 2015 FY 2016 FY 2017 Cost To Complete Total Cost Total Program Element 22.756 - - - - - - - - Continuing Continuing 675043: Fighter Tactical

More information

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE A: Joint Air-to-Ground Missile (JAGM) FY 2012 OCO

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE A: Joint Air-to-Ground Missile (JAGM) FY 2012 OCO Exhibit R2, RDT&E Budget Item Justification: PB 212 Army DATE: February 211 24: Research, Development, Test & Evaluation, Army COST ($ in Millions) FY 21 FY 211 PE 6545A: Joint AirtoGround Missile Total

More information

UNCLASSIFIED. UNCLASSIFIED Office of Secretary Of Defense Page 1 of 8 R-1 Line #163

UNCLASSIFIED. UNCLASSIFIED Office of Secretary Of Defense Page 1 of 8 R-1 Line #163 Exhibit R-2, RDT&E Budget Item Justification: PB 2015 Office of Secretary Of Defense Date: March 2014 0400: Research, Development, Test &, Defense-Wide / BA 6: RDT&E Management Support COST ($ in Millions)

More information

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 6 R-1 Line #231

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 6 R-1 Line #231 COST ($ in Millions) Prior Years FY 2013 FY 2014 Base OCO # Total FY 2016 FY 2017 FY 2018 FY 2019 Cost To Complete Total Program Element - 76.569 97.134 83.773-83.773 56.172 55.168 66.032 67.486 Continuing

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE PE A: RADAR DEVELOPMENT

UNCLASSIFIED R-1 ITEM NOMENCLATURE PE A: RADAR DEVELOPMENT Exhibit R-2, RDT&E Budget Item Justification: PB 2012 Army DATE: February 2011 COST ($ in Millions) FY 2010 FY 2011 Total FY 2013 FY 2014 FY 2015 FY 2016 Army Page 1 of 10 R-1 Line Item #116 To Complete

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2013 Air Force DATE: February 2012 COST ($ in Millions) FY 2011 FY 2012 FY 2014 FY 2015 FY 2016 FY 2017 Air Force Page 1 of 16 R-1 Line #227 To Program

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 213 Navy DATE: February 212 COST ($ in Millions) FY 211 FY 212 FY 214 FY 215 FY 216 FY 217 To Program Element 147.268 6.751 61.163-61.163 94.537 369.826

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2013 Air Force DATE: February 2012 COST ($ in Millions) FY 2011 FY 2014 FY 2015 FY 2016 FY 2017 To Program Element 65.844 127.925 21.000-21.000 8.000 -

More information

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 5 R-1 Line #146

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 5 R-1 Line #146 COST ($ in Millions) Prior Years FY 2013 FY 2014 Base OCO # Total FY 2016 FY 2017 FY 2018 FY 2019 Cost To Complete Total Program Element - 0.992 0.350 0.883-0.883 0.791 0.637 0.650 0.662 Continuing Continuing

More information

UNCLASSIFIED. FY 2016 Base FY 2016 OCO

UNCLASSIFIED. FY 2016 Base FY 2016 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2016 Defense Information Systems Agency : February 2015 0400: Research, Development, Test & Evaluation, Defense-Wide / BA 7: Operational Systems Development

More information

UNCLASSIFIED UNCLASSIFIED

UNCLASSIFIED UNCLASSIFIED EXHIBIT R-2, RDT&E Budget Item Justification APPROPRIATION/BUDGET ACTIVITY R-1 ITEM NOMENCLATURE RESEARCH DEVELOPMENT TEST & EVALUATION, NAVY / BA-7 0305206N Airborne Reconnaissance Advanced Development

More information

UNCLASSIFIED FY 2016 OCO. FY 2016 Base

UNCLASSIFIED FY 2016 OCO. FY 2016 Base Exhibit R2, RDT&E Budget Item Justification: PB 2016 Navy Date: February 2015 1319: Research, Development, Test & Evaluation, Navy / BA 6: RDT&E Management Support COST ($ in Millions) Prior Years R1 Program

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE Exhibit R-2, RDT&E Budget Item Justification: PB 213 Navy DATE: February 212 COST ($ in Millions) FY 211 FY 212 FY 213 Base FY 213 OCO FY 213 Total FY 214 FY 215 FY 216 FY 217 Navy Page 1 of 5 R-1 Line

More information

UNCLASSIFIED. Cost To Complete Total Program Element : DIGITAL BATTLEFLD COMM.

UNCLASSIFIED. Cost To Complete Total Program Element : DIGITAL BATTLEFLD COMM. Exhibit R-2, RDT&E Budget Item Justification: PB 2016 Army Date: February 2015 2040: Research, Development, Test & Evaluation, Army / BA 3: Advanced Technology Development (ATD) FY 2017 FY 2018 FY 2019

More information

UNCLASSIFIED. FY 2016 Base FY 2016 OCO

UNCLASSIFIED. FY 2016 Base FY 2016 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2016 Air Force : February 2015 3600: Research, Development, Test & Evaluation, Air Force / BA 7: Operational Systems Development COST ($ in Millions) FY

More information

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE BB: SOF Underwater Systems

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE BB: SOF Underwater Systems Exhibit R-2, RDT&E Budget Item Justification: PB 2012 United States Special Operations Command DATE: February 2011 COST ($ in Millions) FY 2010 FY 2011 Total FY 2013 FY 2014 FY 2015 FY 2016 To Complete

More information

Unmanned Aerial Vehicle Operations

Unmanned Aerial Vehicle Operations MCWP 3-42.1 Unmanned Aerial Vehicle Operations U.S. Marine Corps DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited PCN 143 000141 00 DEPARTMENT OF THE NAVY Headquarters United

More information

KC-46A Tanker DoD Budget FY2013-FY2017. RDT&E U.S. Air Force

KC-46A Tanker DoD Budget FY2013-FY2017. RDT&E U.S. Air Force KC-46A Tanker DoD Budget FY2013-FY2017 RDT&E U.S. Air Force Exhibit R-2, RDT&E Budget Item Justification: PB 2013 Air Force DATE: February 2012 FY 2013 FY 2013 FY 2013 Cost To COST ($ in Millions) FY 2011

More information