Community Development Agency Capital Improvement Program TIM Fee Program Cash Proforma (by Revenue Grouping)

Size: px
Start display at page:

Download "Community Development Agency Capital Improvement Program TIM Fee Program Cash Proforma (by Revenue Grouping)"

Transcription

1 Community Development Agency Prior* 16/17 17/18 18/19 19/2 2/21 21/22-25/26 26/27-35/36 El Dorado Hills TIM Zone 8 Cash 14,38,412 5,952,818 19,991,23 Revenue 3,511,925 2,196,826 2,151,276 2,445,139 2,445,139 2,445,139 12,245,675 22,381,21 49,822,32 TIM Fair Share Transfer 199,538 2,594 2,594 2,594 2,594 1,2,969 1,883,983 3,888,866 Sources 17,55,337 2,396,364 2,351,87 2,645,733 2,645,733 2,645,733 13,248,644 3,218,2 73,72,416 Affordable 1-Affordable Housing TIM Fee Reserve % Funded: 18.2% 22,778 3,62,337 3,643,115 Appr Reimb 2-Approved Reimbursement Agreements-El Dorado Hills TIM % Funded: 1.% 9,294,868 27, , , , , ,948 13,152,126 Pend Reimb 3-Pending Reimbursement Agreements-El Dorado Hills TIM % Funded: 1.% 3, 3, Bridge Matc Bridge Program Match % Funded: 14.3% 516,15 516, Country Club Drive Extension - El Dorado Hills Blvd to Silva % Funded: 1.% 17, 488,282 1,93,26 1,751,488 Valley Parkway Country Club Drive Extension - Silva Valley Parkway to Tong % Funded: 1.% 1, 15, 7,99, 8,24, Road Country Club Drive Extension - Tong Road to Bass Lake Road % Funded: 1.% 2, 355,429 11,893,293 12,448,722 GP178 Green Valley Road Widening - Francisco to Silva Valley Parkway % Funded: 1.% 27,83 5,821,197 6,29, Green Valley Road Widening from County Line to Sophia % Funded: 2.% 422,2 422,2 Parkway Latrobe Connection % Funded: 59.1% 57,545 37, 427, Saratoga Way Extension - Phase 1 % Funded: 1.% 1,88,397 1, 8,138,272 9,326,669 GP147 Saratoga Way Extension - Phase 2 % Funded: 1.% 3,31,727 3,31,727 TIM Prog TIM Fee Program Projects % Funded: 28.8% 988, ,954 88,691 88,691 88, , ,745 1,569,67 4,81,67 Traffic Signa Traffic Signal and Intersection Operational Improvements % Funded: 29.6% 579, , , ,778 2,898,89 5,217,998 1,436, Transit Service Improvements % Funded: 24.2% 1,688, 1,688, 7133 U.S. 5/Bass Lake Road Interchange Improvements % Funded:.1% 5,32 5, U.S. 5/El Dorado Hills Boulevard Interchange Improvements - % Funded: 1.% 279,434 2,53, 5,572, 8,381,434 Phase 2B White Rock Road Widening (2 to 4 lanes) - Monte Verde Drive to US 5/Silva Valley Parkway Interchange % Funded: 1.% 4,172 1,49,1 4,568,9 5,622,172 *Prior FY includes actual revenue and expenditures through 6/3/15 plus amounts estimated through 6/3/ K 1 of 2 8/25/216 CIPProgram.mdb/Project Summary Funding TIM by RevGroup Page 1 of 17

2 El Dorado Hills TIM Zone 8 Community Development Agency Prior* 16/17 17/18 18/19 19/2 2/21 21/22-25/26 26/27-35/36 Cash 14,38,412 5,952,818 19,991,23 Revenue 3,511,925 2,196,826 2,151,276 2,445,139 2,445,139 2,445,139 12,245,675 22,381,21 49,822,32 TIM Fair Share Transfer 199,538 2,594 2,594 2,594 2,594 1,2,969 1,883,983 3,888,866 Sources 17,55,337 2,396,364 2,351,87 2,645,733 2,645,733 2,645,733 13,248,644 3,218,2 73,72,416 Expense 11,74, ,472 1,856,617 1,434,417 1,734,417 2,535,46 37,26,333 42,278,122 98,782,275 5,89,486 2,219, ,253 1,211, ,316 11,687-23,777,689-12,6,12-25,79,859 5,89,486 8,29,378 8,524,631 9,735,947 1,647,263 1,757,95-13,19,739-25,79,859 *Prior FY includes actual revenue and expenditures through 6/3/15 plus amounts estimated through 6/3/ K 2 of 2 8/25/216 CIPProgram.mdb/Project Summary Funding TIM by RevGroup Page 2 of 17

3 Developer Advance - EDH TIM Community Development Agency Prior* 16/17 17/18 18/19 19/2 2/21 21/22-25/26 26/27-35/36 Cash 275, ,177 Sources 275, , Latrobe Connection % Funded: 38.% 275, ,177 Expense 275, ,177 *Prior FY includes actual revenue and expenditures through 6/3/15 plus amounts estimated through 6/3/ K 3 of 2 8/25/216 CIPProgram.mdb/Project Summary Funding TIM by RevGroup Page 3 of 17

4 Community Development Agency Prior* 16/17 17/18 18/19 19/2 2/21 21/22-25/26 26/27-35/36 Silva Valley Interchange Set Aside Cash 51,38,472-5,952,818 45,355,654 Revenue 1,66, , ,975 1,47,917 1,47,917 1,47,917 5,239,585 9,591,93 21,256,488 TIM Fair Share Transfer 413, , , , ,859 2,79,296 3,95,761 8,62,164 Sources 52,915,33 1,166,114 1,337,834 1,463,776 1,463,776 1,463,776 7,318,881 7,544,846 74,674,36 Affordable 1-Affordable Housing TIM Fee Reserve % Funded: 7.8% 9,762 1,551,573 1,561,335 Appr Reimb 2-Approved Reimbursement Agreements-Silva Valley Interchange % Funded: 1.% 4,811,649 1,337,834 1,463,776 1,463,776 1,463,776 5,654,154 16,194,965 TIM Prog TIM Fee Program Projects % Funded: 2.6% 374,79 374, U.S. 5/Silva Valley Parkway Interchange - Phase 1 % Funded: 86.4% 43,65,449 2,874,744 16, 46,685, U.S. 5/Silva Valley Parkway Interchange - Phase 1 Landscape % Funded: 1.% 3, 1,8, 2, 2, 2, 4, 2,2, U.S. 5/Silva Valley Parkway Interchange - Phase 2 - On % Funded: 1.% 23 7,658, 7,658,23 Ramps and Auxiliary Lanes on U.S. 5 Expense 44,35,24 7,986,393 3,297,834 1,483,776 1,483,776 1,483,776 5,694,154 9,29,573 74,674,36 8,88,279-6,82,279-1,96, -2, -2, -2, 1,624,727-1,664,727 8,88,279 2,6, 1, 8, 6, 4, 1,664,727 *Prior FY includes actual revenue and expenditures through 6/3/15 plus amounts estimated through 6/3/ K 4 of 2 8/25/216 CIPProgram.mdb/Project Summary Funding TIM by RevGroup Page 4 of 17

5 Developer Advance - Silva Valley IC Set Aside Community Development Agency Prior* 16/17 17/18 18/19 19/2 2/21 21/22-25/26 26/27-35/36 Cash 5,61,755 5,61,755 Sources 5,61,755 5,61, U.S. 5/Silva Valley Parkway Interchange - Phase 1 % Funded: 1.4% 5,61,755 5,61,755 Expense 5,61,755 5,61,755 *Prior FY includes actual revenue and expenditures through 6/3/15 plus amounts estimated through 6/3/ K 5 of 2 8/25/216 CIPProgram.mdb/Project Summary Funding TIM by RevGroup Page 5 of 17

6 Community Development Agency Prior* 16/17 17/18 18/19 19/2 2/21 21/22-25/26 26/27-35/36 TIM Zones 1-7 Cash 2,792,38 2,792,38 Revenue 1,477,559 3,613,488 3,632,65 3,632,65 3,632,65 3,632,65 18,163,25 32,943,522 7,728,14 TIM Fair Share Transfer -613,29-616, , , ,453-3,82,265-5,789,744-11,951,3 Sources 22,269,597 3,,279 3,16,152 3,16,152 3,16,152 3,16,152 15,8,76 27,153,778 79,569,22 Affordable 1-Affordable Housing TIM Fee Reserve % Funded: 23.3% 1,174,21 3,477,339 4,651,549 Appr Reimb 2-Approved Reimbursement Agreements-TIM Zones 1-7 % Funded: 1.% 513,8 48,23 1,427, , ,984 2,465,952 6,53,946 Pend Reimb 3-Pending Reimbursement Agreements-TIM Zones 1-7 % Funded: 1.% 7,483, 7,483, Bridge Matc Bridge Program Match % Funded: 85.7% 3,11,916 3,11, Bucks Bar Road at the North Fork Cosumnes River - Bridge Replacement % Funded: 1.2% 74,516 67,14 55,4 42, , , Cameron Park Drive Widening - Palmer Drive to Hacienda Road % Funded: 1.% 36, , , ,2 1,323, Diamond Springs Parkway - Phase 1A - SR-49 Realignment % Funded: 5.4% 769, , Diamond Springs Parkway - Phase 1B % Funded: 35.5% 2,225,923 1,636,726 1,692,82 1,192,619 1,127,273 2,152,231 1,27, Green Valley Road at Indian Creek - Bridge Replacement % Funded: 9.4% 2,153 12,473 19,18 8,27 3, ,18 425, Green Valley Road at Mound Springs Creek - Bridge % Funded: 9.6% 2,543 16,746 16,964 9,91 8, , ,655 Replacement 7719 Green Valley Road at Tennessee Creek - Bridge Replacement % Funded: 7.7% 46,694 46, Green Valley Road at Weber Creek - Bridge Replacement % Funded: 7.1% 81, ,51 2,868 1,72 2,867 83, Headington Road Extension - Missouri Flat Road to El Dorado % Funded: 1.% 653,817 3,796, 4,449,817 Road Missouri Flat Road Widening - China Garden to Pleasant Valley Road/SR49 % Funded: 1.% 3,92, 3,92, 7332 Pleasant Valley Road (SR 49)/Patterson Drive Intersection % Funded: 59.5% 2,761,32 1, 2,861,32 Signalization 7618 Silver Springs Pkwy to Bass Lake Rd (south segment) % Funded: 14.7% 469,533 82,257 99,494 1,389, Sly Park Road at Clear Creek Crossing - Bridge Replacement % Funded: 11.7% 21, ,23 136,493 68,558 TIM Prog TIM Fee Program Projects % Funded: 61.8% 1,396, , ,39 211,39 211,39 986,19 1,655,255 3,739,641 8,766,1 Traffic Signa Traffic Signal and Intersection Operational Improvements % Funded: 7.4% 1,38,222 1,38,222 1,38,222 1,38,222 6,91,11 12,422,2 24,844, Transit Service Improvements % Funded: 57.4% 4,13, 4,13, *Prior FY includes actual revenue and expenditures through 6/3/15 plus amounts estimated through 6/3/ K 6 of 2 8/25/216 CIPProgram.mdb/Project Summary Funding TIM by RevGroup Page 6 of 17

7 TIM Zones 1-7 Community Development Agency Prior* 16/17 17/18 18/19 19/2 2/21 21/22-25/26 26/27-35/36 Cash 2,792,38 2,792,38 Revenue 1,477,559 3,613,488 3,632,65 3,632,65 3,632,65 3,632,65 18,163,25 32,943,522 7,728,14 TIM Fair Share Transfer -613,29-616, , , ,453-3,82,265-5,789,744-11,951,3 Sources 22,269,597 3,,279 3,16,152 3,16,152 3,16,152 3,16,152 15,8,76 27,153,778 79,569, U.S. 5/Bass Lake Road Interchange Improvements % Funded:.1% 5,321 5, U.S. 5/Cambridge Road Interchange Improvements % Funded:.% U.S. 5/Cameron Park Drive Interchange Improvements % Funded:.8% 665,92 665, U.S. 5/El Dorado Road Interchange Improvements - Ph 1 % Funded:.6% 31,635 31, U.S. 5/Ponderosa Rd Interchange - Durock Rd Realignment % Funded:.1% 7,3 7, U.S. 5/Ponderosa Rd Interchange - N. Shingle Rd Realignment % Funded:.1% 4,627 4, U.S. 5/Ponderosa Rd/So. Shingle Rd Interchange % Funded: 2.4% 55,82 55,82 Improvements Expense 11,469,62 4,65,666 4,247,134 4,752,14 4,657,632 5,628,93 19,229,762 34,469,898 89,14,945 1,799,977-1,65,387-1,23,982-1,735,988-1,641,48-2,611,941-4,149,2-7,316,12-9,535,923 1,799,977 9,149,59 7,918,68 6,182,62 4,541,14 1,929,199-2,219,83-9,535,923 *Prior FY includes actual revenue and expenditures through 6/3/15 plus amounts estimated through 6/3/ K 7 of 2 8/25/216 CIPProgram.mdb/Project Summary Funding TIM by RevGroup Page 7 of 17

8 Community Development Agency Prior* 16/17 17/18 18/19 19/2 2/21 21/22-25/26 26/27-35/36 Developer Advance TIM Cash 34,335 1,91,833 2,59,513 59,455 2,964,282 3,789,263 11,528,681 Sources 34,335 1,91,833 2,59,513 59,455 2,964,282 3,789,263 11,528, Country Club Drive Realignment - Bass Lake Road to Tierra de Dios Drive % Funded: 1.% 6, 16, 59,455 2,964,282 3,789,263 7,483, 7618 Silver Springs Pkwy to Bass Lake Rd (south segment) % Funded: 42.8% 34,335 1,841,833 1,899,513 4,45,681 Expense 34,335 1,91,833 2,59,513 59,455 2,964,282 3,789,263 11,528,681 *Prior FY includes actual revenue and expenditures through 6/3/15 plus amounts estimated through 6/3/ K 8 of 2 8/25/216 CIPProgram.mdb/Project Summary Funding TIM by RevGroup Page 8 of 17

9 Community Development Agency Prior* 16/17 17/18 18/19 19/2 2/21 21/22-25/26 26/27-35/36 Highway 5 TIM Zones 1-8 Cash 7,44,971 1,387,764 8,792,735 Revenue 1,449,982 8,266,57 8,226,784 7,711,237 7,618,621 7,618,621 38,93,15 68,881,19 147,865,597 Sources 8,854,953 8,266,57 8,226,784 7,711,237 7,618,621 7,618,621 38,93,15 7,268, ,658,332 Affordable 1-Affordable Housing TIM Fee Reserve % Funded: 5.7% 458,42 9,685,581 1,144, Pleasant Valley Road (SR 49)/Patterson Drive Intersection % Funded:.5% 25,239 25,239 Signalization TIM Prog TIM Fee Program Projects % Funded: 6.6% 935, , Transit Service Improvements % Funded: 18.4% 1,284,62 1,284,62 GP148 U.S. 5 Auxiliary Lane Eastbound - Bass Lake Road to % Funded: 1.% 8,83,5 8,83,5 Cambridge Road U.S. 5 Auxiliary Lane Eastbound - Cambridge Rd to Cameron % Funded: 1.% 8,743,5 8,743,5 Park Dr U.S. 5 Auxiliary Lane Eastbound - Cameron Park Drive to % Funded: 1.% 8,381, 8,381, Ponderosa Road U.S. 5 Auxiliary Lane Eastbound - Sacramento County Line to % Funded: 1.% 6,51,5 6,51,5 El Dorado Hills Blvd U.S. 5 Auxiliary Lane Westbound - Bass Lake Road to Silva % Funded: 1.% 5,466,5 5,466,5 Valley Parkway GP149 U.S. 5 Auxiliary Lane Westbound - Cambridge Road to Bass % Funded: 1.% 8,685,5 8,685,5 Lake Road U.S. 5 Auxiliary Lane Westbound - Ponderosa Rd to Cameron Park Dr % Funded: 1.% 8,961, 8,961, 7133 U.S. 5/Bass Lake Road Interchange Improvements % Funded: 91.3% 11,523 1,767,5 3,582,5 5,361, U.S. 5/Cambridge Road Interchange Improvements % Funded: 1.% 37, , 8,19, 8,611, U.S. 5/Cameron Park Drive Interchange Improvements % Funded: 99.2% 474,73 1, 86,43, 86,617, U.S. 5/Camino Area Safety Project % Funded: 9.1% 378, , U.S. 5/El Dorado Road Interchange Improvements - Ph 1 % Funded: 97.% 25, ,578 4,315,89 5,5, U.S. 5/El Dorado Road Interchange Phase 2 % Funded: 1.% 1,475, 1,475, U.S. 5/Ponderosa Rd Interchange - Durock Rd Realignment % Funded: 99.9% 7,3 1,28,857 8,836,695 9,872, U.S. 5/Ponderosa Rd Interchange - N. Shingle Rd Realignment % Funded: 99.9% 4,627 1,34,892 5,89,747 6,93,266 *Prior FY includes actual revenue and expenditures through 6/3/15 plus amounts estimated through 6/3/ K 9 of 2 8/25/216 CIPProgram.mdb/Project Summary Funding TIM by RevGroup Page 9 of 17

10 Highway 5 TIM Zones 1-8 Community Development Agency Prior* 16/17 17/18 18/19 19/2 2/21 21/22-25/26 26/27-35/36 Cash 7,44,971 1,387,764 8,792,735 Revenue 1,449,982 8,266,57 8,226,784 7,711,237 7,618,621 7,618,621 38,93,15 68,881,19 147,865,597 Sources 8,854,953 8,266,57 8,226,784 7,711,237 7,618,621 7,618,621 38,93,15 7,268, ,658, U.S. 5/Ponderosa Rd/So. Shingle Rd Interchange % Funded: 97.5% 516,951 72,852 21,457,739 22,47,542 Improvements Expense 4,161,87 172,852 1,516,327 28,418, ,268,418 4,693,866 8,93,25 8,226,784 7,711,237 7,618,621 7,618,621 27,576, ,149,198-66,61,86 4,693,866 12,787,71 21,13,855 28,725,92 36,343,713 43,962,334 71,539,112-66,61,86 *Prior FY includes actual revenue and expenditures through 6/3/15 plus amounts estimated through 6/3/ K 1 of 2 8/25/216 CIPProgram.mdb/Project Summary Funding TIM by RevGroup Page 1 of 17

11 Hwy 5 TIM-Blackstone Community Development Agency Prior* 16/17 17/18 18/19 19/2 2/21 21/22-25/26 26/27-35/36 ( FUNDING) Cash 3,92,224-1,387,764 2,514,46 Revenue 993,6 1,2,86 1,2,86 17,624 3,16,944 Sources 4,895,824 1,2,86 1,2,86 17,624-1,387,764 5,621, U.S. 5 Auxiliary Lane Westbound - El Dorado Hills Boulevard % Funded: 1.% 9,94 5,611,5 5,621,44 to Sacramento County Line Expense 9,94 5,611,5 5,621,44 4,885,92 1,2,86 1,2,86 17,624-6,999,264 4,885,92 5,888,78 6,891,64 6,999,264 6,999,264 6,999,264 6,999,264 *Prior FY includes actual revenue and expenditures through 6/3/15 plus amounts estimated through 6/3/ K 11 of 2 8/25/216 CIPProgram.mdb/Project Summary Funding TIM by RevGroup Page 11 of 17

12 Master Circulation and Funding Plan Financing Community Development Agency MC&FP Cash Proforma Prior* 16/17 17/18 18/19 19/2 2/21 21/22-25/26 26/27-35/36 Cash 7,32,796 7,32,796 Revenue 1,42,354 1,, 1,, 3,42,354 Sources 8,345,15 1,, 1,, 1,345, Diamond Springs Parkway - Phase 1A - SR-49 Realignment % Funded: 5.2% 739, , Diamond Springs Parkway - Phase 1B % Funded: 4.% 1,115,521 1,115, U.S. 5/Missouri Flat Road Interchange - Phase 1B.2 % Funded: 49.9% 266,59 799,472 1,65, U.S. 5/Missouri Flat Road Interchange Improvements - Phase % Funded: 1.% 3,738 79, 632, 34, 34, 34, 34, 1,858,738 1C Riparian Restoration Expense 2,421,549 1,589, , 34, 34, 34, 34, 4,779,21 5,923,61-589, , -34, -34, -34, -34, 5,566,129 5,923,61 5,334,129 5,72,129 5,668,129 5,634,129 5,6,129 5,566,129 5,566,129 *Prior FY includes actual revenue and expenditures through 6/3/15 plus amounts estimated through 6/3/ K 12 of 2 8/25/216 CIPProgram.mdb/Project Summary Funding TIM by RevGroup Page 12 of 17

13 Local Funds - Tribe Community Development Agency Local Funds-Tribe Cash Proforma Prior* 16/17 17/18 18/19 19/2 2/21 21/22-25/26 26/27-35/36 Cash 19,14,5 19,14,5 Revenue 2,667,968 2,6, 2,652, 2,75,4 2,759,141 2,814,324 14,938,768 3,169,385 34,36,626 Sources 21,88,468 2,6, 2,652, 2,75,4 2,759,141 2,814,324 14,938,768 3,169,385 53,447,126 RDMAINT 1-Road Maintenance % Funded: 93.7% 1,534,742 2,9, 4,434, Diamond Springs Parkway - Phase 1A - SR-49 Realignment % Funded: 67.5% 671,951 2,151,25 6,767,44 9,59, Diamond Springs Parkway - Phase 1B % Funded: 47.% 495,9 691, ,126 46,435 5,599,42 5,526,683 13,26, Overlay - Gold Hill % Funded: 1.% 535,453 5, 54, Overlay - Patterson Drive and Missouri Flat Road % Funded: 97.% 146,876 98,223 1, 1,65, U.S. 5 HOV Lanes Phase % Funded: 17.1% 2,936,563 96,274 3,32,837 Expense 5,825,585 6,556,647 7,468, ,126 46,435 5,599,42 5,526,683 31,924,769 15,982,883-3,956,647-4,816,873 2,217,914 2,298,76-2,785,96 9,412,85 3,169,385 21,522,357 15,982,883 12,26,236 7,29,363 9,427,277 11,725,983 8,94,887 18,352,972 21,522,357 *Prior FY includes actual revenue and expenditures through 6/3/15 plus amounts estimated through 6/3/ K 13 of 2 8/25/216 CIPProgram.mdb/Project Summary Funding TIM by RevGroup Page 13 of 17

14 Community Development Agency Prior* 16/17 17/18 18/19 19/2 2/21 21/22-25/26 26/27-35/36 RSTP Exchange Funds-Caltrans (STATE FUNDING) Cash 1,746,437 1,746,437 Revenue 321,99 321,99 321,99 321,99 321,99 321,99 1,69,545 2,897,181 6,438,18 Sources 2,68, ,99 321,99 321,99 321,99 321,99 1,69,545 2,897,181 8,184, Alder Drive at EID Canal - Bridge Replacement % Funded: 2.2% 34,17 34, Blair Road at EID Canal - Bridge Replacement % Funded:.5% 11,527 11, Bucks Bar Road at the North Fork Cosumnes River - Bridge % Funded:.1% 7,78 7,78 Replacement 7336 Cold Springs Road Realignment % Funded: 11.5% 234, , Green Valley Road - Class II Bikeway - Loch Way to Signalized % Funded: 4.7% 18,778 1, 19,778 Entrance to Pleasant Grove Middle School Green Valley Road at Mound Springs Creek - Bridge % Funded:.7% 32,176 32,176 Replacement 7719 Green Valley Road at Tennessee Creek - Bridge Replacement % Funded: 9.7% 583, , Green Valley Road at Weber Creek - Bridge Replacement % Funded:.7% 78,37 78, Hazel Valley Road at EID Canal - Bridge Replacement % Funded:.% Hollow Oak Road Drainage % Funded:.% OP5 Metal Beam Guardrail Installation - Various Locations % Funded: 1.% 67, 67, Mosquito Road Bridge at South Fork American River % Funded:.% 1,379 1, Newtown Road at South Fork of Weber Creek - Bridge % Funded:.2% 9,122 9,122 Replacement 7332 Pleasant Valley Road (SR 49)/Patterson Drive Intersection % Funded:.6% 3,271 3,271 Signalization Rubicon Trail at Ellis Creek - Bridge Replacement % Funded:.4% 4,134 4, Salmon Falls Road South of Glenesk Lane Realignment % Funded: 33.1% 363, , , Silva Valley Parkway/Serrano Parkway Traffic Circulation Improvement % Funded: 1.% 58,653 59, 639, Silver Fork Road at South Fork American River - Bridge % Funded:.3% 6,87 6,87 Rehabilitation Sly Park Road at Clear Creek Crossing - Bridge Replacement % Funded:.4% 22,393 22, Wentworth Springs Road at Gerle Creek - Bridge Replacement % Funded: 2.% 29,81 29,81 *Prior FY includes actual revenue and expenditures through 6/3/15 plus amounts estimated through 6/3/ K 14 of 2 8/25/216 CIPProgram.mdb/Project Summary Funding TIM by RevGroup Page 14 of 17

15 RSTP Exchange Funds-Caltrans Community Development Agency Prior* 16/17 17/18 18/19 19/2 2/21 21/22-25/26 26/27-35/36 (STATE FUNDING) Cash 1,746,437 1,746,437 Revenue 321,99 321,99 321,99 321,99 321,99 321,99 1,69,545 2,897,181 6,438,18 Sources 2,68, ,99 321,99 321,99 321,99 321,99 1,69,545 2,897,181 8,184,617 Expense 2,47, ,596 67, 2,397,333 2,69 39, ,99 321,99 321,99 321,99 1,542,545 2,897,181 5,787,284 2,69 59, ,831 73,74 1,25,649 1,347,558 2,89,13 5,787,284 *Prior FY includes actual revenue and expenditures through 6/3/15 plus amounts estimated through 6/3/ K 15 of 2 8/25/216 CIPProgram.mdb/Project Summary Funding TIM by RevGroup Page 15 of 17

16 Community Development Agency Prior* 16/17 17/18 18/19 19/2 2/21 21/22-25/26 26/27-35/36 RSTP Exchange Funds-Rural-EDCTC (STATE FUNDING) Cash 2,852,31 2,852,31 Revenue 423,119 45, 45, 45, 45, 45, 2,25, 4,5, 8,973,119 Sources 3,275,429 45, 45, 45, 45, 45, 2,25, 4,5, 11,825,429 RDMAINT 1-Road Maintenance % Funded: 6.3% 13, ,37 3, Alder Drive at EID Canal - Bridge Replacement % Funded:.2% 3,36 3, Bucks Bar Road at the North Fork Cosumnes River - Bridge % Funded:.9% 78,543 78,543 Replacement 7336 Cold Springs Road Realignment % Funded: 13.7% 28,9 28, Green Valley Road at Indian Creek - Bridge Replacement % Funded: 11.2% 21,8 31,4 24,4 22,65 13,9 12,15 38, 56, Green Valley Road at Mound Springs Creek - Bridge % Funded: 1.6% 3,9 24, 22,1 13,6 11,9 378, 48,5 Replacement 7719 Green Valley Road at Tennessee Creek - Bridge Replacement % Funded: 1.9% 116, , Green Valley Road at Weber Creek - Bridge Replacement % Funded: 7.8% 94,416 94, Green Valley Road Widening from County Line to Sophia % Funded: 4.3% 9, 9, Parkway Newtown Road at South Fork of Weber Creek - Bridge % Funded: 11.% 4,119 67,68 26,932 73, ,92 62,698 Replacement Salmon Falls Road South of Glenesk Lane Realignment % Funded: 15.% 266, , U.S. 5/Camino Area Safety Project % Funded: 15.2% 248,131 27,86 64,68 22,42 83,53 182,71 629, U.S. 5/El Dorado Road Interchange Improvements - Ph 1 % Funded: 2.4% 124, 124, Expense 1,817, ,355 14,12 14, ,932 26,76 758, 4,4,752 1,457, ,355 39,988 39,153-73, ,24 1,492, 4,5, 7,424,677 1,457,583 1,94,228 1,44,216 1,713,369 1,639,437 1,882,677 3,374,677 7,424,677 *Prior FY includes actual revenue and expenditures through 6/3/15 plus amounts estimated through 6/3/ K 16 of 2 8/25/216 CIPProgram.mdb/Project Summary Funding TIM by RevGroup Page 16 of 17

17 Community Development Agency Prior* 16/17 17/18 18/19 19/2 2/21 21/22-25/26 26/27-35/36 RSTP Match Funds-Caltrans ( FUNDING) Cash 53,177 53,177 Revenue 1, 1, 1, 1, 1, 1, 5, 9, 2,, Sources 63,177 1, 1, 1, 1, 1, 5, 9, 2,53, Bucks Bar Road at the North Fork Cosumnes River - Bridge % Funded:.6% 51,983 51,983 Replacement 7336 Cold Springs Road Realignment % Funded: 9.1% 186, , Green Valley Road at Indian Creek - Bridge Replacement % Funded:.4% 16,77 16, Green Valley Road at Tennessee Creek - Bridge Replacement % Funded: 1.7% 95,344 1,434 1,434 1,433 99, Green Valley Road at Weber Creek - Bridge Replacement % Funded:.% 3,444 3, Newtown Road at South Fork of Weber Creek - Bridge % Funded: 1.2% 68,71 68,71 Replacement Rubicon Trail at Ellis Creek - Bridge Replacement % Funded:.6% 7,31 7, Salmon Falls Road South of Glenesk Lane Realignment % Funded: 7.5% 37,564 95, 132, Sly Park Road at Clear Creek Crossing - Bridge Replacement % Funded: 1.2% 71,59 71,59 Expense 538,249 96,434 1,434 1, ,55 91,928 3,566 98,566 98,567 1, 1, 5, 9, 1,892,627 91,928 95, ,6 292, , , ,627 1,892,627 *Prior FY includes actual revenue and expenditures through 6/3/15 plus amounts estimated through 6/3/ K 17 of 2 8/25/216 CIPProgram.mdb/Project Summary Funding TIM by RevGroup Page 17 of 17

18 K 18 of 2

19 Revenue Sources and Potential Uses State Highway Users Tax (aka Gas Tax ): Provided for under the Streets and Highway Code, Sections Most of this funding is calculated by formula based on the number of licensed vehicles and maintained mileage. Road District Tax: A percentage of property taxes. Public Utility Franchise Fees: Provided for under the Streets and Highway Code, Sections Public utility companies have entered into franchise agreements that provide for the payment of franchise fees to the County based on a percentage of power sales. General Fund: Can be used for anything the Board directs the Division to use it for, including capital overlays, road maintenance, matching funds for bridge grants, etc. Federal/State Grants: Grants awarded for various types of (primarily) capital projects. Local Tribe Funds: These funds can only be used in the specific area as defined in the Amendment of Memorandum of Understanding and Intergovernmental Agreement between the County of El Dorado and Shingle Springs Band of Miwok Indians. MC&FP: Master Circulation and Funding Plan: A portion of the sales and property tax collected in the Missouri Flat MC&FP district, which is to be used to fund roadway capital improvement projects inside the district (e.g., Missouri Flat Interchange, Diamond Springs Parkway). TIM Fees: Capital projects in Exhibit B of the most current Board adopted TIM Fee Resolution Zone 8 TIM: (formerly known as El Dorado Hills/Salmon Falls Area RIF ) Traffic Impact Mitigation fees to fund road improvements in the El Dorado Hills area (TIM Fee Program Zone 8) Highway 5 TIM: Traffic Impact Mitigation fees collected in all Zones to fund road improvements along the Highway 5 Corridor Zones 1-7 TIM: Traffic Impact Mitigation Fees to fund road improvements in the remainder of the county (TIM Fee Program Zones 1-7), excluding El Dorado Hills and Tahoe. RSTP: Regional Surface Transportation Program: This program was established by California State Statute utilizing Surface Transportation Program Funds that are identified in Section 133 of Title 23 of the United States Code. Various types of projects are eligible for funding from the RSTP including, but not limited to: construction, reconstruction, rehabilitation, resurfacing, restoration, and operational improvements on Federal-aid highways and bridges; safety improvements on public roads of all functional classifications; capital costs for transit projects eligible for assistance under the Federal Transit Act; etc. Urban RSTP: Can only be used in the urbanized area based on the Sacramento Urbanized Area Map 21. Can only be used in the urbanized area based on the Sacramento Urbanized Area Map 21. The Sacramento Urbanized Area Map was developed by the FHWA based on 21 census data K 19 of 2

20 Revenue Sources and Potential Uses Road Fund: Used mostly in road maintenance, but occasionally used for Capital Overlay and Rehabilitation Program projects. Rural RSTP: Can only be used in areas that are outside those identified as Urban on the Sacramento Urbanized Area Map. Accumulative Capital Outlay: Can be used for capital outlays including the construction and maintenance of capital facilities. In the CIP, this funding is used for matching funds for Federal Aviation Administration grants for Airport projects K 2 of 2

Western Slope CIP and TIM Fee Update Workshop

Western Slope CIP and TIM Fee Update Workshop Western Slope CIP and TIM Fee Update Workshop Board of Supervisors Study Session May 5, 2015 14-0245 8K 1 of 39 Agenda 1. Brief Background 2. Receive and file: Traffic Analysis Methodology 3. BOS Direction:

More information

WESTERN SLOPE CIP AND TIM FEE UPDATE

WESTERN SLOPE CIP AND TIM FEE UPDATE WESTERN SLOPE CIP AND TIM FEE UPDATE 12/6/16 BOARD OF SUPERVISORS STUDY SESSION B O A R D S T U D Y S E S S I O N # 8 2015 14-0245 Revised 22M 1 of 53 AGENDA 1. Background 2. Programmatic EIR 3. General

More information

Presentation to Roseville City Council April 15, 2015

Presentation to Roseville City Council April 15, 2015 Regional Transportation Projects in South Placer County Presentation to Roseville City Council April 15, 2015 Completed Regional Transportation Projects Lincoln Bypass 2014 SR 65/Ferrari Ranch Rd 2012

More information

FEDERAL LANDS ACCESS PROGRAM

FEDERAL LANDS ACCESS PROGRAM FEDERAL LANDS ACCESS PROGRAM CEAC Transportation Policy Committee Presentation Wednesday, November 30, 2016 Chris Longley, CFLHD FLAP Program Manager CENTRAL FEDERAL LANDS HIGHWAY DIVISION 2 Overview Who

More information

DIRECTOR S REPORT TRANSPORTATION BOARD SEPTEMBER 10, 2018

DIRECTOR S REPORT TRANSPORTATION BOARD SEPTEMBER 10, 2018 DIRECTOR S REPORT TRANSPORTATION BOARD SEPTEMBER 10, 2018 1 EMERGENCY OPERATIONS MAINTENANCE FORCES IN DISTRICTS 2 AND 3 CLOSED ROADS DUE TO WILDFIRES FLOODING IN SOUTHERN NEVADA DUE TO MONSOON SEASON

More information

Newton County. Impact Fee Annual Update FY2011

Newton County. Impact Fee Annual Update FY2011 Newton County Impact Fee Annual Update FY2011 Newton County STWP Update 2011-2015 PLAN ELEMENT ITEM (ED, NOR OR ) General General DESCRIPTION Implement a Capital Improvement Plan Develop a comprehensive

More information

Coolidge - Florence Regional Transportation Plan

Coolidge - Florence Regional Transportation Plan Coolidge - Florence Regional Transportation Plan A Partnership Among the City of Coolidge, Town of Florence, and ADOT FINAL REPORT Kimley-Horn Kimley Kimley-Horn and and Associates, Associates, Inc. Inc.

More information

South Fulton Comprehensive Transportation Plan of Fulton County Transportation Coordinating Committee August 08, 2014

South Fulton Comprehensive Transportation Plan of Fulton County Transportation Coordinating Committee August 08, 2014 South Fulton Comprehensive Transportation Plan of Fulton County Transportation Coordinating Committee August 08, 2014 www.southfultonctp.org 1 What is a Comprehensive Transportation Plan (CTP)? Guiding

More information

City of Culver City. Staff Report

City of Culver City. Staff Report City of Culver City City Hall 9770 Culver Blvd. Culver City, CA 90232 (310) 253-5851 Staff Report File #: 18-0499, Version: 1 CC - Approval of Professional Services Agreement with Tetra Tech for the Design

More information

Transportation Funding Terms and Acronyms Unraveling the Jargon

Transportation Funding Terms and Acronyms Unraveling the Jargon Funding Terms and Acronyms Unraveling the Jargon Every profession has its own acronyms and jargon. The shorthand wording makes it easier and quicker for professionals in any given field to communicate

More information

NASHVILLE AREA MPO FY TIP - ADOPTED DECEMBER

NASHVILLE AREA MPO FY TIP - ADOPTED DECEMBER WILSON NASHVILLE AREA MPO FY -2017 TIP - ADOPTED DECEMBER 11, 2013 Beckwith Road/Eastern Connector TIP # 2008-71-038 New Road Mt. Juliet Wilson Length 5.00 Regional Plan ID 1072-132 Air Quality Status

More information

FFY Transportation Improvement Program

FFY Transportation Improvement Program Lawton Metropolitan Planning Organization DRAFT FFY 2018-2021 Transportation Improvement Program Approved, 2017 The Federal Fiscal Years (FFY) 2018-2021 Transportation Improvement Program (TIP) is updated

More information

Special State Funding Programs Breakout Session #5C Funding Programs Track. October 25, 2012

Special State Funding Programs Breakout Session #5C Funding Programs Track. October 25, 2012 Special State Funding Programs Breakout Session #5C Funding Programs Track October 25, 2012 SPECIAL STATE FUNDING PROGRAMS - REVENUE SHARING Debbi Webb-Howells Revenue Sharing Program Manager Local Assistance

More information

Annual Listing of Projects with Federal Funding for Federal Fiscal Year 2014/15

Annual Listing of Projects with Federal Funding for Federal Fiscal Year 2014/15 Annual Listing of Projects with Federal Funding for Federal Fiscal Year 2014/15 210 N. Church Street, Suite B Visalia, CA 93291 Phone: (559) 623-0450 Fax: (559) 733-6720 Website: www.tularecog.org Purpose

More information

RESOLUTION FOR APPROVAL OF AMENDMENTS TO THE TRANSPORTATION IMPROVEMENT PROGRAM (TIP) AND 2040 REGIONAL TRANSPORTATION PLAN (RTP)

RESOLUTION FOR APPROVAL OF AMENDMENTS TO THE TRANSPORTATION IMPROVEMENT PROGRAM (TIP) AND 2040 REGIONAL TRANSPORTATION PLAN (RTP) TPC Agenda Item 6A Mailout 10/20/16 RESOLUTION FOR APPROVAL OF AMENDMENTS TO THE 2017-2020 TRANSPORTATION IMPROVEMENT PROGRAM (TIP) AND 2040 REGIONAL TRANSPORTATION PLAN (RTP) Amendment Summary Amendment

More information

Major in FY2013/2014 (By and ing Source) Municipal Building Acquisition and Operations Balance $1,984, Contributions from Real Estate

Major in FY2013/2014 (By and ing Source) Municipal Building Acquisition and Operations Balance $1,984, Contributions from Real Estate Major in FY2013/2014 (By and ing Source) Environmental Services Solid Waste 4200 4200 06CON 4200 SWM01 Balance $13,753,504.00 Balance $4,631,754.00 Balance $2,738,918.00 ing Source Total: $21,124,176.00

More information

Georgia s Operational Improvement Program. Paul DeNard, P.E., PTOE State Traffic Operations Manager

Georgia s Operational Improvement Program. Paul DeNard, P.E., PTOE State Traffic Operations Manager Georgia s Operational Improvement Program Paul DeNard, P.E., PTOE State Traffic Operations Manager How do you address Capacity? We can t build our way out of the congestion problem Widening projects cost

More information

Section 4.2 Tahoe EIP Individual Project Summaries

Section 4.2 Tahoe EIP Individual Project Summaries Section 4.2 Tahoe EIP Individual Project Summaries Page 1 of 63 Angora Creek Road Damage CIP Project Summary Project No: 78723 Type: Emergency Click for Interactive Map Project Description: Angora Creek

More information

Transportation Needs and Funding Role of Impact Fees. January 6, 2015 BoCC Workshop

Transportation Needs and Funding Role of Impact Fees. January 6, 2015 BoCC Workshop Transportation Needs and Funding Role of Impact Fees January 6, 2015 BoCC Workshop 1 Impact Fees Provide Facilities for: Roads* Schools Parks Fire EMS *Most significant element 2 Discussion Topics Current

More information

APPENDIX 5. Funding Plan

APPENDIX 5. Funding Plan STUDY: FINAL REPORT APPENDIX 5 Funding Plan May 2015 V:\2073\active\2073009060\report\DRAFT Final Report\rpt_MalPCH_DRAFTFinalReport-20150515.docx Pacific Coast Highway Safety Study: Funding Plan City

More information

Route 58 PPTA Project Finance Plan Annual Update Hillsville to Stuart Corridor. Submitted By:

Route 58 PPTA Project Finance Plan Annual Update Hillsville to Stuart Corridor. Submitted By: Route 58 PPTA Project Finance Plan Annual Update Hillsville to Stuart Corridor Submitted By: Robert P. Williams District Construction Engineer Salem District Virginia Department of Transportation Submitted

More information

Genoa Township Area Road and Bridge Projects

Genoa Township Area Road and Bridge Projects Genoa Township Area Road and Bridge Projects Delaware County Engineer s Office May 18, 2017 Delaware County Engineer s Office 2016 Construction Highlights Biggest construction year in Delaware County Engineer

More information

CFLHD Organizational and Program Overview FEDERAL LAND ACCESS PROGRAM (FLAP) 55 th ACE Annual Conference

CFLHD Organizational and Program Overview FEDERAL LAND ACCESS PROGRAM (FLAP) 55 th ACE Annual Conference CFLHD Organizational and Program Overview FEDERAL LAND ACCESS PROGRAM (FLAP) 55 th ACE Annual Conference - 2016 Topics to Share Federal Lands Access Program History Funding Type of Projects PDC FLMA Coordination

More information

Planning Phase (Route Study and Pond Siting Analysis & Report) Determines Preferred Alignment Public Workshop and Board Approval Required Completion:

Planning Phase (Route Study and Pond Siting Analysis & Report) Determines Preferred Alignment Public Workshop and Board Approval Required Completion: 2 Planning Phase (Route Study and Pond Siting Analysis & Report) Determines Preferred Alignment Public Workshop and Board Approval Required Completion: 270 Days Design/Permitting Phase Engineering Plans

More information

Agenda Item D.2 PRESENTATION Meeting Date: June 17, 2014

Agenda Item D.2 PRESENTATION Meeting Date: June 17, 2014 Agenda Item D.2 PRESENTATION Meeting Date: June 17, 2014 TO: FROM: SUBJECT: Mayor and Councilmembers Rosemarie Gaglione, Interim Public Works Director Capital Improvement Program Update RECOMMENDATION:

More information

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM Date of Meeting: July 3, 2018 # 5 BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM SUBJECT: ELECTION DISTRICT(S): Smart Scale Project Selection for the Commonwealth Transportation Board Six Year Improvement

More information

WACOG FY Transportation Improvement Program STP PROJECTS AT A GLANCE

WACOG FY Transportation Improvement Program STP PROJECTS AT A GLANCE FY - Transportation Improvement Program PROJECTS AT A GLANCE TIP TIP ID # PROJECT PROJECT PROJECT LENGTH TYPE OF Functional LANES LANES FED AID FEDERAL FEDERAL ADOT LOCAL OTHER OTHER HURF TOTAL YEAR TRAC's

More information

REPORT TO MAYOR AND COUNCIL

REPORT TO MAYOR AND COUNCIL AGENDA ITEM NO..d REPORT TO MAYOR AND COUNCIL TO THE HONORABLE MAYOR AND COUNCIL: DATE: July, SUBJECT: ADOPT RESOLUTION NOS. -, -, -, - AND -0 OF LOCAL SUPPORT AUTHORIZING THE FILING OF APPLICATIONS FOR

More information

Puget Sound Gateway Program

Puget Sound Gateway Program Puget Sound Gateway Program SR 509 Completion Project PSRC FAST Committee October 11, 2017 MIKE RIGSBY, PE ANDREY CHEPEL, PE DEPUTY PROGRAM ADMINISTRATOR SR 509 PROJECT ENGINEER 1 Puget Sound Gateway Program

More information

2018 POLICY FRAMEWORK FOR PSRC S FEDERAL FUNDS

2018 POLICY FRAMEWORK FOR PSRC S FEDERAL FUNDS 2018 POLICY FRAMEWORK FOR PSRC S FEDERAL FUNDS TABLE OF CONTENTS Section 1: Background... 3 A. Policy Framework... 3 B. Development of the 2019-2022 Regional Transportation Improvement Program (TIP)..

More information

Arkansas State Highway and Transportation Department. Garland County Tea Party

Arkansas State Highway and Transportation Department. Garland County Tea Party Arkansas State Highway and Transportation Department Garland County Tea Party October 16, 2013 About AHTD The Facts: 12 th Largest System in USA 43 rd Highway Revenue Per Mile How We Compare State Mileage

More information

Regional Transportation Plan: APPENDIX B

Regional Transportation Plan: APPENDIX B Regional Transportation Plan: 2007-2030 Appendix B APPENDIX B POTENTIAL FUNDING SOURCES Funding sources for transportation improvement projects are needed if the recommended projects of the Transportation

More information

KEY TAKEAWAYS THE STIMULUS BREAKDOWN

KEY TAKEAWAYS THE STIMULUS BREAKDOWN S T I M U L U S F O R G R E A T E R P H I L A D E L P H I A : W H A T I T M E A N S F O R T R A N S P O R T A T I O N I N V E S T M E N T I N T H E R E G I O N KEY TAKEAWAYS Greater Philadelphia will likely

More information

Purpose. Funding. Eligible Projects

Purpose. Funding. Eligible Projects SMART SCALE is a statewide program that distributes funding based on a transparent and objective evaluation of projects that will determine how effectively they help the state achieve its transportation

More information

Project Budget and Schedule Status

Project Budget and Schedule Status Program Management Project Budget and Schedule Status Highway Program Planning & Programming Committee June 19, 2013 Highway Program Project Schedules EIR/EIS Construction Various project stages Engineering

More information

Draft for approval by TCC on 8/8; TAQC on 8/14 and ARC on 8/27/14

Draft for approval by TCC on 8/8; TAQC on 8/14 and ARC on 8/27/14 Draft for approval by TCC on 8/8; TAQC on 8/14 and ARC on 8/27/14 DATE: August 27, 2014 ISSUE SUMMARY: PLAN 2040 RTP/TIP Amendment #1 FROM: Tom Worthan, Transportation & Air Quality Committee IMPORTANCE:

More information

2016 Measure B Program Areas

2016 Measure B Program Areas 2016 Measure B Program Areas 2016 Measure B Programwide Topics 2 Program Areas 3 2016 Measure B Program Areas Program Category BART Phase II Bicycle/Pedestrian Caltrain Corridor Capacity Improvements Caltrain

More information

The Atlanta Region s Plan RTP/ FY TIP Amendment #4. Transportation Coordinating Committee January 5, 2018

The Atlanta Region s Plan RTP/ FY TIP Amendment #4. Transportation Coordinating Committee January 5, 2018 The Atlanta Region s Plan RTP/ FY 2018-2023 TIP Amendment #4 Transportation Coordinating Committee January 5, 2018 What s in Amendment #4? 2017 TIP Project Solicitation Funding Commitments Exempt projects

More information

Georgia DOT Local Maintenance Improvement Grant Program. Todd Long, P.E., Deputy Commissioner

Georgia DOT Local Maintenance Improvement Grant Program. Todd Long, P.E., Deputy Commissioner Georgia DOT Local Maintenance Improvement Grant Program Todd Long, P.E., Deputy Commissioner GDOT Local Assistance Programs Funded by State Motor Fuel Tax Collections Prior to 2009: Governor and General

More information

A RESOLUTION ADOPTING THE LADY S ISLAND CORRIDOR STUDY

A RESOLUTION ADOPTING THE LADY S ISLAND CORRIDOR STUDY A RESOLUTION ADOPTING THE LADY S ISLAND CORRIDOR STUDY WHEREAS, Beaufort County, in conjunction with the City of Beaufort, had a corridor study prepared for the Sea Island Parkway corridor on Lady s Island;

More information

Expected Roadway Project Crash Reductions for SMART SCALE Safety Factor Evaluation. September 2016

Expected Roadway Project Crash Reductions for SMART SCALE Safety Factor Evaluation. September 2016 Expected Roadway Project Crash Reductions for SMART SCALE Safety Factor Evaluation September 2016 SMART SCALE Safety Factors Evaluation 1. Using Crash Modification Factors for SMART SCALE Safety Evaluation

More information

CAPITAL IMPROVEMENT PROGRAM I - 1

CAPITAL IMPROVEMENT PROGRAM I - 1 CITY OF SACRAMENTO TRANSPORTATION PROGRAM OVERVIEW INTRODUCTION The 2014-2019 Transportation Program reflects the City s funding strategy for delivering transportation improvements, which will improve

More information

SCOTT COUNTY COMMUNITY SERVICES DIVISION

SCOTT COUNTY COMMUNITY SERVICES DIVISION SCOTT COUNTY COMMUNITY SERVICES DIVISION PHYSICAL DEVELOPMENT 600 COUNTRY TRAIL EAST JORDAN, MN 55352-9339 (952) 496-8346 Fax: (952) 496-8365 www.co.scott.mn.us MITCHELL J. RASMUSSEN, P.E. COUNTY ENGINEER

More information

Regional Planning Partnership

Regional Planning Partnership Regional Planning Partnership Item #3 Action February 21, 2018 Amendment #20 to the 2017-20 Metropolitan Transportation Improvement Program Issue: Should the Regional Planning Partnership Committee recommend

More information

APPENDIX A PROGRAMMATIC AGREEMENT FOR MINOR TRANSPORTATION PROJECTS

APPENDIX A PROGRAMMATIC AGREEMENT FOR MINOR TRANSPORTATION PROJECTS APPENDIX A PROGRAMMATIC AGREEMENT FOR MINOR TRANSPORTATION PROJECTS PROGRAMMATIC AGREEMENT AMONG THE FEDERAL HIGHWAY ADMINISTRATION THE PENNSYLVANIA DEPARTMENT OF TRANSPORTATION, THE PENNSYLVANIA STATE

More information

VTP Highway Program. Semi-Annual Report April 2013

VTP Highway Program. Semi-Annual Report April 2013 VTP Highway Program Semi-Annual Report April 2013 VTP Highway Program Semi-Annual Progress Report April 2013 Table of Contents TABLE OF CONTENTS Section Title Page 1 EXECUTIVE SUMMARY A Background... 1-2

More information

Association of Metropolitan Planning Organizations Fixing America s Surface Transportation (FAST) Act

Association of Metropolitan Planning Organizations Fixing America s Surface Transportation (FAST) Act Association of Metropolitan Planning Organizations Fixing America s Surface Transportation (FAST) Act General Overview Total authorizations (Highway Trust Fund, HTF, Contract Authority plus General Funds

More information

Board of Supervisors' Agenda Items

Board of Supervisors' Agenda Items A. Roll Call COUNTY OF SAN DIEGO BOARD OF SUPERVISORS REGULAR MEETING MEETING AGENDA WEDNESDAY, APRIL 13, 2016, 9:00 A.M. BOARD OF SUPERVISORS NORTH CHAMBER 1600 PACIFIC HIGHWAY, ROOM 310, SAN DIEGO, CALIFORNIA

More information

Transportation Improvement Program

Transportation Improvement Program Transportation Improvement Program Transportation Conformity Check List The Transportation Improvement Program (TIP) and all amendments must include a conformity report. The conformity report must address

More information

Transportation Improvement Program for Lake, Porter, and LaPorte Counties, Indiana for

Transportation Improvement Program for Lake, Porter, and LaPorte Counties, Indiana for Transportation Improvement Program for Lake, Porter, and LaPorte Counties, Indiana for 2012-2015 Part II: TIP Development and Project Selection Processes MPO Planning Process The NIRPC Board of Commissioners

More information

Overall Work Program, Budget, and Goals and Objectives

Overall Work Program, Budget, and Goals and Objectives Overall Work Program, Budget, and Goals and Objectives Fiscal Year 2016/2017 Draft: March 3, 2016 Prepared by: El Dorado County Transportation Commission 2828 Easy Street, Suite 1, Placerville, CA 95667

More information

FY16 Annual Report WHAT IS GTIB? WHO ADMINSTERS GTIB? Summary of GTIB Funding Through FY16

FY16 Annual Report WHAT IS GTIB? WHO ADMINSTERS GTIB? Summary of GTIB Funding Through FY16 FY16 Annual Report PROVIDING FUNDS TO IMPROVE MOBILITY, SUSTAIN DEVELOPMENT AND ENHANCE COMMUNITIES THROUGHOUT GEORGIA WHAT IS GTIB? The Georgia Transportation Infrastructure Bank (GTIB) provides financial

More information

Section 6. The Transportation Plan

Section 6. The Transportation Plan Section 6. The Transportation Plan Like the areas it covers, the needs and opportunities identified in the 2035 Plan are diverse economic development projects, highways and bridges, transit facilities

More information

Transportation Projects for Which Federal Funds. Were Obligated During FY 2016/17. November 2017

Transportation Projects for Which Federal Funds. Were Obligated During FY 2016/17. November 2017 Transportation Projects for Which Federal Funds Were Obligated During FY 2016/17 November 2017 (This page intentionally left blank) Transportation Projects for which Federal Funds Were Obligated During

More information

Amendments to FY Transportation Improvement Program of the Coastal Region Metropolitan Planning Organization (CORE MPO) October 2017

Amendments to FY Transportation Improvement Program of the Coastal Region Metropolitan Planning Organization (CORE MPO) October 2017 Amendments to FY 2018-2021 Transportation Improvement of the Coastal Region Metropolitan Planning Organization (CORE MPO) October 2017 The Transportation Improvement (TIP) is the MPO s short-range programming

More information

Appendix 5 Freight Funding Programs

Appendix 5 Freight Funding Programs 5. Chapter Heading Appendix 5 Freight Programs Table of Contents 4.1 Surface Transportation Block Grant (STBG);... 5-1 4.2 Transportation Investment Generating Economic Recovery Discretionary Grant Program

More information

County Executive Office/Legislative Affairs. County of Orange Report on Grant Applications/Awards

County Executive Office/Legislative Affairs. County of Orange Report on Grant Applications/Awards AttachmentA County Executive Office/Legislative Affairs DRAFT September 27, 2016 Item No. 41 Vol. XXXlX, No. 17 County of Orange Report on Grant Applications/Awards The Grants Report is a condensed list

More information

MEMORANDUM AGENDA ITEM #6k

MEMORANDUM AGENDA ITEM #6k South Florida Regional Planning Council MEMORANDUM AGENDA ITEM #6k DATE: SEPTEMBER 8, 2008 TO: FROM: SUBJECT: COUNCIL MEMBERS STAFF TOWN OF MEDLEY PROPOSED COMPREHENSIVE PLAN AMENDMENT Introduction On

More information

Transportation. Fiscal Research Division. March 24, Justification Review

Transportation. Fiscal Research Division. March 24, Justification Review Fiscal Research Division Hiighway Fund and Hiighway Trust Fund Secondary Roads Program Transportation Justification Review March 24, 2007 The General Assembly should eliminate or reduce funding for the

More information

Public Meeting #5 Summary

Public Meeting #5 Summary Public Meeting #5 Summary Pulaski County, Arkansas February 4, 2016 TABLE OF CONTENTS 1.0 Introduction... 1 2.0 Public Meeting #5... 1 2.1 Public Meeting Advertising and Outreach... 2 2.2 Public Meeting

More information

ACTION TRANSMITTAL No

ACTION TRANSMITTAL No Transportation Advisory Board of the Metropolitan Council of the Twin Cities DATE: March 6, 2017 TO: FROM: ACTION TRANSMITTAL No. 2017-08 Transportation Advisory Board Technical Advisory Committee PREPARED

More information

Appendix E: Grant Funding Sources

Appendix E: Grant Funding Sources Appendix E: Grant Funding Sources Federal Programs The majority of public funds for bicycle, pedestrian, and trails projects are derived through a core group of federal and state programs. Federal funding

More information

2018 Regional Transportation Improvement Program

2018 Regional Transportation Improvement Program 2018 Regional Transportation Improvement Program Fiscal Years 2018/19 through 2022/2023 Adopted November 15, 2017 Stanislaus Council of Governments 1111 I Street Suite 308 Modesto, CA 95354 www.stancog.org

More information

FUNDING POLICY GUIDELINES

FUNDING POLICY GUIDELINES FUNDING POLICY GUIDELINES Revised and Approved May 25, 2017 Akron Metropolitan Area Transportation Study 806 CitiCenter 146 South High Street Akron, Ohio 44308 This document was prepared by the Akron Metropolitan

More information

Wisconsin DNR Administered Programs. Aids For The Acquisition And Development Of Local Parks (ADLP)

Wisconsin DNR Administered Programs. Aids For The Acquisition And Development Of Local Parks (ADLP) Wisconsin DNR Administered Programs Community Service Specialist Rhinelander Service Center 107 Sutliff Ave Rhinelander WI 54501 Acquisition Of Development Rights Grants (ADR) Helps to buy development

More information

Transportation Projects for Which Federal Funds. Were Obligated During FY 2014/15. November 2015

Transportation Projects for Which Federal Funds. Were Obligated During FY 2014/15. November 2015 Transportation Projects for Which Federal Funds Were Obligated During FY 2014/15 November 2015 Transportation Projects for which Federal Funds Were Obligated During FY 2014/15 This document contains a

More information

SMALL CITY PROGRAM. ocuments/forms/allitems.

SMALL CITY PROGRAM.  ocuments/forms/allitems. SMALL CITY PROGRAM The Small City Program provides Federal funds to small cities with populations from 5,000 to 24,999 that are NOT located within Metropolitan Planning Organizations' boundaries. Currently

More information

NORTH DAKOTA SIDE TRANSPORTATION IMPROVEMENT PROGRAM

NORTH DAKOTA SIDE TRANSPORTATION IMPROVEMENT PROGRAM NORTH DAKOTA SIDE TRANSPORTATION IMPROVEMENT PROGRAM 2018-2021 December, 2017 The preparation of this report was partially financed by FHWA/FTA Planning funds through the North Dakota Department of Transportation

More information

City of Creve Coeur CAPITAL FUND

City of Creve Coeur CAPITAL FUND City of Creve Coeur To: Mayor and City Council From: Mark Perkins, City Administrator Date: February 21, 2017 Re: Capital Improvement Program Update FY2018-2022 The proposed Capital Improvement Program

More information

2018 Call for Projects Guidebook

2018 Call for Projects Guidebook 2018 Call for Projects Guidebook Project Selection for the NFRMPO CMAQ, STBG, and TA Programs in FY2022 and FY2023 October 8, 2018 Table of Contents Introduction... 2 Section 1 - Call Overview... 2 1.1

More information

NORTH DAKOTA SIDE TRANSPORTATION IMPROVEMENT PROGRAM

NORTH DAKOTA SIDE TRANSPORTATION IMPROVEMENT PROGRAM NORTH DAKOTA SIDE TRANSPORTATION IMPROVEMENT PROGRAM 2018-2021 December, 2017 The preparation of this report was partially financed by FHWA/FTA Planning funds through the North Dakota Department of Transportation

More information

National Capital Region Transportation Planning Board

National Capital Region Transportation Planning Board National Capital Region Transportation Planning Board 777 North Capitol Street, N.E., Suite 300, Washington, D.C. 20002-4290 (202) 962-3310 Fax: (202) 962-3202 Item #5 MEMORANDUM January 8, 2010 To: From:

More information

VERMONT AGENCY OF TRANSPORTATION. FY2018 Budget. Joe Flynn, Secretary of Transportation House Appropriations Committee February 27, 2017

VERMONT AGENCY OF TRANSPORTATION. FY2018 Budget. Joe Flynn, Secretary of Transportation House Appropriations Committee February 27, 2017 VERMONT AGENCY OF TRANSPORTATION FY2018 Budget Joe Flynn, Secretary of Transportation House Appropriations Committee February 27, 2017 Today s Presentation FY2018 Governor s Recommended overview and program

More information

Appendix E Federal and State Funding Categories

Appendix E Federal and State Funding Categories Appendix E Federal and State Funding Categories This page left blank intentionally. Federal and State Funding Categories Appendix E E 3 Appendix E Federal and State Funding Categories Highway Programs

More information

Operational cuts were made while managing to secure $15 million in local funds for capital projects.

Operational cuts were made while managing to secure $15 million in local funds for capital projects. Cumulative cuts: Total operational budget cuts Total eliminated positions 135 $8.5 million Operational cuts were made while managing to secure $15 million in local funds for capital projects. Other strategic

More information

2004 Transportation Expenditure Plan

2004 Transportation Expenditure Plan 2004 Transportation Expenditure Plan - Developed with extensive public input - Approved by the San Mateo County Transportation Authority, San Mateo County Board of Supervisors, each of the 20 cities within

More information

STAFF REPORT. MEETING DATE: August 21, 2008 AGENDA ITEM: 9

STAFF REPORT. MEETING DATE: August 21, 2008 AGENDA ITEM: 9 STAFF REPORT SUBJECT: Draft Regional Transportation Plan MEETING DATE: August 21, 2008 AGENDA ITEM: 9 STAFF CONTACT: Aubrey Spilde, Michael Powers RECOMMENDATION: Hold public hearing to receive public

More information

NAPA Overview. Dan Gallagher, Chairman National Asphalt Pavement Association 2017 WAPAConference

NAPA Overview. Dan Gallagher, Chairman National Asphalt Pavement Association 2017 WAPAConference NAPA Overview Dan Gallagher, Chairman National Asphalt Pavement Association 2017 WAPAConference View from the Hill: Legislative Outlook Jay Hansen, Executive Vice President Ashley Jackson, Director of

More information

Overview of the Regional Transportation Improvement Program

Overview of the Regional Transportation Improvement Program Overview of the 2017-2020 Regional Transportation Improvement Program Table of Contents What is the Puget Sound Regional Council (PSRC)?... 1 What is the Transportation Improvement Program (TIP)?... 1

More information

INDIAN RIVER COUNTY METROPOLITAN PLANNING ORGANIZATION

INDIAN RIVER COUNTY METROPOLITAN PLANNING ORGANIZATION 2016 PRIORITY PROJECTS REPORT INDIAN RIVER COUNTY METROPOLITAN PLANNING ORGANIZATION This document was produced in cooperation with the Florida Department of Transportation and the Federal Highway Administration

More information

Special Purpose Local Option Sales Tax 2005 Program. Citizen Review Committee April 22, 2005

Special Purpose Local Option Sales Tax 2005 Program. Citizen Review Committee April 22, 2005 Special Purpose Local Option Sales Tax 2005 Program Citizen Review Committee April 22, 2005 1 Georgia s SPLOST Law Qualified cities are entitled to a share of the SPLOST. Cities are qualified if they provide

More information

9. REVENUE SOURCES FEDERAL FUNDS

9. REVENUE SOURCES FEDERAL FUNDS 9. REVENUE SOURCES This Chapter summarizes multimodal revenue sources and estimates that are applicable to the City of Coolidge and the Town of Florence, together with financial constraints and opportunities

More information

Memorandum. Date: RE: Plans and Programs Committee

Memorandum. Date: RE: Plans and Programs Committee Memorandum Date: 02.05.09 RE: Plans and Programs Committee February 10, 2009 To: From: Through: Subject: Summary Plans and Programs Committee: Commissioners Chu (Chair), Campos (Vice Chair), Chiu, Elsbernd,

More information

Transportation Alternatives Program Application For projects in the Tulsa Urbanized Area

Transportation Alternatives Program Application For projects in the Tulsa Urbanized Area FFY 2015-2016 Transportation Alternatives Program Application For projects in the Tulsa Urbanized Area A Grant Program of Moving Ahead for Progress in the 21st Century (MAP-21) U.S. Department of Transportation

More information

RCTC Toll Program and Projects

RCTC Toll Program and Projects RCTC Toll Program and Projects for CMAA Southern California Chapter October 13, 2011 Presenta(on Agenda I 15 Corridor Improvement Project SR 91/71 Interchange Improvements Project SR 91 Corridor Improvement

More information

RESOLUTION OF THE BOARD OF DIRECTORS OF THE OHIO KENTUCKY INDIANA REGIONAL COUNCIL OF GOVERNMENTS

RESOLUTION OF THE BOARD OF DIRECTORS OF THE OHIO KENTUCKY INDIANA REGIONAL COUNCIL OF GOVERNMENTS OKI 2015 RESOLUTION OF THE BOARD OF DIRECTORS OF THE OHIO KENTUCKY INDIANA REGIONAL COUNCIL OF GOVERNMENTS CONCERNING AMENDMENT #1 OF THE FISCAL YEARS 2016 2019 TRANSPORTATION IMPROVEMENT PROGRAM WHEREAS,

More information

In-Step, In Line, On Time. Robert F. Tally Jr. FHWA Indiana Division Administrator Monday, November 16, 2009

In-Step, In Line, On Time. Robert F. Tally Jr. FHWA Indiana Division Administrator Monday, November 16, 2009 In-Step, In Line, On Time Robert F. Tally Jr. FHWA Indiana Division Administrator Monday, November 16, 2009 I-69 Corridor 1 I-69 Corridor I-69 is expected to create more than 27,000 new jobs by 2025, resulting

More information

ORANGE COUNTY TRANSPORTATION AUTHORITY. Measure M2 Progress Report for January 2012 Through March Staff Report

ORANGE COUNTY TRANSPORTATION AUTHORITY. Measure M2 Progress Report for January 2012 Through March Staff Report ORANGE COUNTY TRANSPORTATION AUTHORITY Measure M2 Progress Report for January 2012 Through March 2012 Staff Report May 14, 2012 To: From: Subject: Members of the Board of Directors Will Kempton, Chief

More information

CHAPTER ONE PURPOSE AND NEED. 1.1 Context

CHAPTER ONE PURPOSE AND NEED. 1.1 Context CHAPTER ONE PURPOSE AND NEED This Final Environmental Impact Statement/Report (FEIS/R) incorporates the entire South Access to the Golden Gate Bridge - Doyle Drive Project Draft Environmental Impact Statement/Report

More information

Approved Capital Budget and Program

Approved Capital Budget and Program Approved F I S C A L Y E A R Steve Schuh County Executive 2 0 1 6 Project Title Page AACC B&A Connector 119 ADA ROW Compliance 122 Arundel Mills LDC Roads 121 Brock Bridge/MD 198 112 Cap St Claire Rd

More information

Federal Public Transportation Program: In Brief

Federal Public Transportation Program: In Brief Federal Public Transportation Program: In Brief William J. Mallett Specialist in Transportation Policy December 2, 2013 Congressional Research Service 7-5700 www.crs.gov R42706 Contents Introduction...

More information

2013 Louisiana Transportation Conference

2013 Louisiana Transportation Conference February 20, 2013 Baton Rouge River Center 2013 Louisiana Transportation Conference Partnerships for Progress in Transportation Mega Projects Session (I-12 to Bush) I-12 to Bush Agenda Inclusion into TIMED

More information

SBCAG STAFF REPORT. Senate Bill 1 (SB1) State Funding Strategy for U.S. 101 High Occupancy Vehicle (HOV) Lane and Parallel Projects

SBCAG STAFF REPORT. Senate Bill 1 (SB1) State Funding Strategy for U.S. 101 High Occupancy Vehicle (HOV) Lane and Parallel Projects SBCAG STAFF REPORT SUBJECT: Senate Bill 1 (SB1) State Funding Strategy for U.S. 101 High Occupancy Vehicle (HOV) Lane and Parallel Projects MEETING DATE: October 19, 2017 AGENDA ITEM: 6 STAFF CONTACT:

More information

Click to edit Master title style

Click to edit Master title style Customer-Driven Customer First Mr. Greg Slater, Administrator 7/11/2018 1 1 Customer-Driven Customer First THIS MORNING S PRESENTATION MDOT/SHA Fifth Focus level Current state of our delivery and travel

More information

Caltrans Sustainable Transportation Planning Grant Program

Caltrans Sustainable Transportation Planning Grant Program Caltrans Sustainable Transportation Planning Grant Program FY 2017-18 Strategic Partnerships & Sustainable Communities Presented by California Department of Transportation (Caltrans) FY 2017-18 Update

More information

Urban Stuff Breakout Session # 3. September 19, 2018 Moderator Michael Fulcher Program Manager, VDOT Staunton District

Urban Stuff Breakout Session # 3. September 19, 2018 Moderator Michael Fulcher Program Manager, VDOT Staunton District Urban Stuff Breakout Session # 3 September 19, 2018 Moderator Michael Fulcher Program Manager, VDOT Staunton District Urban Program Overview Urban Maintenance Program Weldon Cooper Center Eligible Maintenance

More information

Order of Business. D. Approval of the Statement of Proceedings/Minutes for the meeting of August 2, 2017.

Order of Business. D. Approval of the Statement of Proceedings/Minutes for the meeting of August 2, 2017. COUNTY OF SAN DIEGO BOARD OF SUPERVISORS REGULAR MEETING MEETING AGENDA WEDNESDAY, SEPTEMBER 13, 2017, 9:00 AM BOARD OF SUPERVISORS NORTH CHAMBER 1600 PACIFIC HIGHWAY, SAN DIEGO, CALIFORNIA Order of Business

More information

Funding the plan. STBG - This program is designed to address specific issues

Funding the plan. STBG - This program is designed to address specific issues Iowa DNR Solid Waste Alternatives Program USDA Rural Development Solid Waste Grants Hazard Mitigation Grant Program (HMGP) Pre-Disaster Mitigation (PDM) Flood Mitigation Assistance (FMA) Water Quality

More information

Finance Committee October 18, 2011

Finance Committee October 18, 2011 10.13.11 Finance Committee October 18, 2011 Finance Committee: Commissioners Mar (Chair), Elsbernd (Vice Chair), Cohen, Farrell, Kim and Mirkarimi (Ex Officio) Leroy Saage Deputy Director for Capital Projects

More information

MPO Staff Report MPO Technical Advisory Committee: February 14, 2018 MPO Executive Board: February 21, 2018

MPO Staff Report MPO Technical Advisory Committee: February 14, 2018 MPO Executive Board: February 21, 2018 MPO Staff Report MPO Technical Advisory Committee: February 14, 2018 MPO Executive Board: February 21, 2018 RECOMMENDED ACTION: Make a Recommendation on the Urban Grant, Regional and Urban Program Candidate

More information