VTA s BART Silicon Valley Extension BART Phase II Project Update

Size: px
Start display at page:

Download "VTA s BART Silicon Valley Extension BART Phase II Project Update"

Transcription

1 VTA s BART Silicon Valley Extension BART Phase II Project Update December 1, 2014

2 VTA s BART Silicon Valley Alignment 2

3 VTA s BART Phase I Berryessa Extension 10-mile extension under construction Two Stations: Milpitas, near the Great Mall Berryessa, near the San Jose Flea Market Forecast opening date is Fall 2017 $2.3 billion total project cost Anticipated daily ridership for Phase I: 23,000 opening day (doubles in 15 years) 3

4 Current Project Activities Milpitas 4 Construction of Milpitas Station invert underway.

5 Current Project Activities San Jose 5 Completed Hostetter Road deck. Construction underway of BART trench at Hostetter Road in the City of San Jose. Construction underway of wayside facilities (train control S44 and substation SHO) (east of the alignment)

6 Current Project Activities San Jose Photo of a completed section of the Berryessa Aerial Guideway. 6

7 VTA s BART Phase II Project Phase II Total Project Cost in Year of Expenditure Dollars : $4.7 billion $163 million incurred to date Anticipated Daily Ridership for Phase II: 55, forecast ridership based on 2012 model forecast 7

8 Measure A Overview Measure A is a ½ cent retail sales tax in Santa Clara County Began collections in 2006 and will sunset in 2036 Devoted to specified public transit capital improvement projects and operations VTA Board of Directors determined BART Silicon Valley a priority project in December

9 Measure A Sales Tax Revenue Cumulative Forecast Projections Millions of Year-of-Receipt Dollars $16,000 $14,000 $12,000 $10,000 $8,000 $6,000 $4,000 $2, : $14.3B 2005: $9.9B 2007: $8.7B 2014: $7.4B 2009: $6.6B $

10 Measure A ½-Cent Sales Tax Uses of Funds FY2006-FY2036 8,000 7,000 Millions of Year-of-Expenditure Dollars 6,000 5,000 4,000 3,000 2,000 1,000 - Other Projects VTA s BART Silicon SVRT Valley Phase Extension 1 Phase I Cost of Debt Operating Incurred Thru 6/14 $1.5B Uses 10

11 Measure A ½-Cent Sales Tax Uses of Funds FY2006-FY2036 8,000 7,000 Millions of Year-of-Expenditure Dollars 6,000 5,000 4,000 3,000 2,000 1,000 - Other Projects VTA s BART Silicon SVRT Valley Phase Extension 1 Phase I Cost of Debt Operating Other Projects VTA s BART Silicon SVRT Valley Phase Extension 1 Phase I Cost of Debt Operating Project Commitments Incurred Thru 6/14 $3.0B $1.5B Uses 11

12 Measure A ½-Cent Sales Tax Uses of Funds FY2006-FY2036 8,000 Millions of Year-of-Expenditure Dollars 7,000 6,000 5,000 4,000 3, ,000 1,000 - Future Projects Cost Future Projects/ Debt Cost Future Projects Cost of Debt Other Projects VTA s BART Silicon SVRT Valley Phase Extension 1 Phase I Cost of Debt O perating Other Projects VTA s BART Silicon SVRT Valley Phase Extension 1 Phase I Cost of Debt Operating Remaining Measure A Funds Available Project Commitments $3.0B Incurred Thru 6/14 $2.9B $1.5B Uses TOTAL $7.4B 12

13 Measure A Phase II Funding Measure A funds constrained $2.9 billion remaining for Measure A projects and financing Additional funding needed to build Phase II VTA will pursue federal funding from the Federal Transit Administration s (FTA) New Starts Program New Starts rating for projects is based on two criteria: Project Justification (50%) and Local Financial Commitment (50%) Other funding Cap & Trade, Value Capture, etc. 13

14 Phase II Capital Costs and Sources of Funds TCRP State Funds 4.0 Shortfall $ ** New Starts Measure A ** Station Alternative (Alum Rock, Downtown, Diridon, Santa Clara)* $4.7 billion * The 4-Station Alternative cost includes a full maintenance facility at Newhall. ** Analysis of Measure A revenue forecast is underway. The results from this analysis will determine the extent of Measure A revenue that may be available for projects and estimate the Shortfall $ for SVRT Phase II. 14

15 Project History Environmental Process 2004 State clearance (CEQA) on Final Environmental Impact Report (EIR): 16-miles 2007 CEQA clearance on Final Supplemental EIR (SEIR): 16-miles 2010 Federal clearance (NEPA) on Final Environmental Impact Statement (EIS): 10-miles 2011 CEQA clearance on 2 nd SEIR: 10-miles 2015 Joint CEQA and NEPA document (SEIS/SEIR3): 6-miles 1

16 Environmental Process State (CEQA) and federal (NEPA) Environmental Process Timeline 16

17 Environmental Process Notice of Preparation (NOP) notification to state and other agencies of the project including a description, the location, and potential environmental issues Scoping an opportunity for members of the public and agencies to provide input in the proposed project, purpose and need, the various environmental topical areas related to the project, and the scope and content of the draft environmental document Record of Decision (ROD) federal environmental clearance 17

18 NEPA/CEQA & New Starts (Federal Funding Program) Milestone Schedule 18

19 Future Community Engagement Activities Ongoing community outreach and engagement during environmental process Environmental process kick-off (scoping meetings) late January/early February Focused Outreach Sessions Spring 2015, some topics may include: Economic and Community Benefits Funding Station Planning Transportation Connectivity Construction Methods 19

20 END 20

Appendix B Meeting Presentation. PowerPoint Presentation Informational Boards

Appendix B Meeting Presentation. PowerPoint Presentation Informational Boards Appendix B Meeting Presentation PowerPoint Presentation Informational Boards PowerPoint Presentation VTA s BART Silicon Valley Program VTA s BART Silicon Valley Phase II Extension Project Environmental

More information

VTA s Capital Projects Program & BART Phase II Procurement Opportunities. VTA s Procurement Fair and Workshop. November 1, 2016

VTA s Capital Projects Program & BART Phase II Procurement Opportunities. VTA s Procurement Fair and Workshop. November 1, 2016 VTA s Capital Projects Program & BART Phase II Procurement Opportunities VTA s Procurement Fair and Workshop November 1, 2016 Capital Projects Program Capital Projects Program Major Projects in Construction

More information

SAN IPSE CAPITAL OF SILICON VALLEY ?/2W/(T. Memorandum TO: HONORABLE MAYOR AND CITY COUNCIL. FROM: Kim Walesh Jim Ortbal

SAN IPSE CAPITAL OF SILICON VALLEY ?/2W/(T. Memorandum TO: HONORABLE MAYOR AND CITY COUNCIL. FROM: Kim Walesh Jim Ortbal CITY OF 7 S3 SAN IPSE CAPITAL OF SILICON VALLEY TO: HONORABLE MAYOR AND CITY COUNCIL STUDY SESSION: 3/30/2017 Memorandum FROM: Kim Walesh Jim Ortbal SUBJECT: DIRIDON STATION PLAN AND REGIONAL RAIL PROJECTS

More information

SILICON VALLEY RAPID TRANSIT CORRIDOR BART EXTENSION TO MILPITAS, SAN JOSE AND SANTA CLARA POLICY ADVISORY BOARD MEETING MINUTES

SILICON VALLEY RAPID TRANSIT CORRIDOR BART EXTENSION TO MILPITAS, SAN JOSE AND SANTA CLARA POLICY ADVISORY BOARD MEETING MINUTES SILICON VALLEY RAPID TRANSIT CORRIDOR BART EXTENSION TO MILPITAS, SAN JOSE AND SANTA CLARA POLICY ADVISORY BOARD MEETING Wednesday, April 25, 2007 MINUTES 1. The Regular Meeting of the Silicon Valley Rapid

More information

VTA s BART Silicon Valley Phase II Extension Project

VTA s BART Silicon Valley Phase II Extension Project VTA s BART Silicon Valley Phase II Extension Project Alum Rock Community Working Group November 15, 2017 1 Agenda Follow-up Items Phase I Update Phase II Update San Jose Diridon Integrated Station Concept

More information

2016 Measure B Program Areas

2016 Measure B Program Areas 2016 Measure B Program Areas 2016 Measure B Programwide Topics 2 Program Areas 3 2016 Measure B Program Areas Program Category BART Phase II Bicycle/Pedestrian Caltrain Corridor Capacity Improvements Caltrain

More information

VTA s BART Silicon Valley Phase II Extension Project

VTA s BART Silicon Valley Phase II Extension Project VTA s BART Silicon Valley Phase II Extension Project Downtown/Diridon Community Working Group February 6, 2018 1 Agenda Follow-up Items Phase I Update Phase II Update Financial Update San Jose Diridon

More information

VTA s BART Silicon Valley Phase II Extension Project

VTA s BART Silicon Valley Phase II Extension Project VTA s BART Silicon Valley Phase II Extension Project Alum Rock/28 th Street Community Working Group February 7, 2018 1 Follow-up Items Agenda Trails Overview Phase I Update Phase II Update Financial Update

More information

For the Fiscal Year Ended June 30, 2014

For the Fiscal Year Ended June 30, 2014 SANTA CLARA VALLEY TRANSPORTATION AUTHORITY 2000 Measure A Transit Improvement Program [A Fund of the Santa Clara Valley Transportation Authority] Independent Accountant s Report on Compliance Examination

More information

For the Fiscal Year Ended June 30, 2016

For the Fiscal Year Ended June 30, 2016 SANTA CLARA VALLEY TRANSPORTATION AUTHORITY 2000 Measure A Transit Improvement Program [A Fund of the Santa Clara Valley Transportation Authority] Independent Accountant s Report on Compliance Examination

More information

Regional Transportation Activities Report. VTA Funding Measure

Regional Transportation Activities Report. VTA Funding Measure Regional Transportation Activities Report VTA Funding Measure Transportation and Environment Committee June 6, 2016 VTA Proposed Funding Measure Funding Category BART Phase II Bicycle/Pedestrian Program

More information

2000 Measure A Transit Improvement Program

2000 Measure A Transit Improvement Program 2000 Measure A Transit Improvement Program Citizens Watchdog Committee Annual Report on Fiscal Year 2012 2000 Measure A Transit Improvement Program Citizens Watchdog Committee Annual Report on Fiscal Year

More information

VTA s BART Silicon Valley Phase II Extension Project

VTA s BART Silicon Valley Phase II Extension Project VTA s BART Silicon Valley Phase II Extension Project Downtown/Diridon Community Working Group September 12, 2017 1 Agenda Follow-up Items CWG Workplan BART Fare Setting Process & Background Future Intermodal

More information

Diridon Station Joint Policy Advisory Board MINUTES

Diridon Station Joint Policy Advisory Board MINUTES CALL TO ORDER Diridon Station Joint Policy Advisory Board Friday, December 17, 2010 MINUTES The Regular Meeting of the Diridon Station Joint Policy Advisory Board ( Committee ) was called to order at 3:06

More information

Attendees: Members in Attendance: Asn Ndiaye, Charlie Faas, Deborah Arant, Bert Weaver, Jim Goddard, Adina Levin, Scott Knies, and Jaclyn Tidwell

Attendees: Members in Attendance: Asn Ndiaye, Charlie Faas, Deborah Arant, Bert Weaver, Jim Goddard, Adina Levin, Scott Knies, and Jaclyn Tidwell Downtown/Diridon Community Working Group Meeting Date of Meeting: June 12, 2018 (4:00 p.m. to 6:00 p.m.) Attendees: Members in Attendance: Asn Ndiaye, Charlie Faas, Deborah Arant, Bert Weaver, Jim Goddard,

More information

May 17, To: From: Subject: Program continues to. Overview. Step Two. fixed-guideway. Program. for. Background

May 17, To: From: Subject: Program continues to. Overview. Step Two. fixed-guideway. Program. for. Background May 17, 2010 To: From: Subject: Transportation 2020 Committee Will Kempton, Chief Executive Officer Go Local Fixed-Guideway Program Update Overview The Go Local Fixed-Guidewaof the program, the City of

More information

SAN JOSE CAPITAL OF SILICON VALLEY

SAN JOSE CAPITAL OF SILICON VALLEY CITY OF SAN JOSE CAPITAL OF SILICON VALLEY TO: HONORABLE MAYOR AND CITY COUNCIL COUNCIL AGENDA: 1-12-16 ITEM: 7.2 Memorandum FROM: Toni J. Taber, C City Clerk SUBJECT: SEE BELOW DATE: December 18, 2015

More information

VTA s BART Silicon Valley Phase II Extension Santa Clara Community Working Group

VTA s BART Silicon Valley Phase II Extension Santa Clara Community Working Group VTA s BART Silicon Valley Phase II Extension Santa Clara Community Working Group October 15, 2015 1 Agenda Follow-up Items and Work Plan BART System Operating and Maintenance VTA s BART Silicon Valley

More information

VTA s BART Silicon Valley Phase II Extension Project

VTA s BART Silicon Valley Phase II Extension Project VTA s BART Silicon Valley Phase II Extension Project Alum Rock Community Working Group September 13, 2017 1 Agenda Follow-up Items CWG Work Plan Five Wounds Trail Discussion BART Fare Setting Process &

More information

Santa Clara Valley Transportation Authority Disadvantaged Business Enterprise (DBE) Program

Santa Clara Valley Transportation Authority Disadvantaged Business Enterprise (DBE) Program Santa Clara Valley Transportation Authority Disadvantaged Business Enterprise (DBE) Program Three-Year Overall Goal and Methodology Report For Federal Fiscal Years 2017 2019 I. Goal Setting Methodology

More information

CONNECTING AND TRANSFORMING CALIFORNIA. Ben Tripousis, Northern California Regional Director SPUR Tuesday, October 25, 2016 San Jose, California

CONNECTING AND TRANSFORMING CALIFORNIA. Ben Tripousis, Northern California Regional Director SPUR Tuesday, October 25, 2016 San Jose, California CONNECTING AND TRANSFORMING CALIFORNIA Ben Tripousis, Northern California Regional Director SPUR Tuesday, October 25, 2016 San Jose, California HIGH-SPEED RAIL STATEWIDE OVERVIEW 2 CONNECTING CALIFORNIA

More information

Public and Agency Involvement. 8.1 Scoping Meetings and Noticing. Chapter 8

Public and Agency Involvement. 8.1 Scoping Meetings and Noticing. Chapter 8 8.1 Scoping Meetings and Noticing Chapter 8 As described in Chapter 1, Section 1.7, Scope and Content of this Environmental Impact Report, the scoping process for this EIR was formally initiated on June

More information

Central City Line Kick-off and Tour

Central City Line Kick-off and Tour Central City Line Kick-off and Tour Phase C Preliminary Engineering, Environmental Documentation and Small Starts Submittal Kickoff Meeting Agenda Time Item 1:00 PM Welcome, Introductions and Agenda Review

More information

SUBJECT: SEE BELOW DATE: May 26, 2016

SUBJECT: SEE BELOW DATE: May 26, 2016 COUNCIL AGENDA: 06-07-16 ITEM: A. CI CITY OF C: 3- SAN JOSE CAPITAL OF SILICON VALLEY TO: HONORABLE MAYOR AND CITY COUNCIL Memorandum FROM: Barry Ng SUBJECT: SEE BELOW DATE: Approved IL2_PS^ Date 5 ^ lip

More information

Action / Decisions Pending / Follow up

Action / Decisions Pending / Follow up Meeting Location Via Telephone 70 W. Hedding Street Lower Level Conference Room Meeting Date and/or Time 03.08.2017 Meeting Subject Community Meeting #02 Meeting Number 1 File 1MN This is page 1 of 5 Present

More information

August 9, Re: DBE Program Triennial Goal Concurrence - Recipient ID #1674. Dear Mr. Smith:

August 9, Re: DBE Program Triennial Goal Concurrence - Recipient ID #1674. Dear Mr. Smith: U.S. Department of Transportation Federal Transit Administration REGION IX Arizona, California, Hawaii, Nevada, Guam American Samoa, Northern Mariana Islands 201 Mission Street Suite 1650 San Francisco,

More information

Memorandum Plans and Programs Committee June 21, 2016

Memorandum Plans and Programs Committee June 21, 2016 Memorandum 06.15.16 Plans and Programs Committee June 21, 2016 Plans and Programs Committee: Commissioners Tang (Chair), Farrell (Vice Chair), Avalos, Breed, Peskin and Wiener (Ex Officio) Eric Cordoba

More information

Peninsula Corridor Joint Powers Board Legislative Program

Peninsula Corridor Joint Powers Board Legislative Program Peninsula Corridor Joint Powers Board 2018 Legislative Program Purpose Legislative and regulatory actions have the potential to significantly benefit Peninsula Corridor Joint Powers Board (JPB) programs

More information

Subject: Request for Proposal Route 99 Interchanges at Hammett Road and Kiernan Avenue

Subject: Request for Proposal Route 99 Interchanges at Hammett Road and Kiernan Avenue DEPARTMENT OF PUBLIC WORKS Matt Machado Director 1010 10 th Street, Suite 3500, Modesto, CA 95354-0847 Phone: 209.525.6550 Date «FirstName» «LastName» «Company» «Address1» «City», «State» «PostalCode»

More information

Eastside Transit Corridor Phase 2 Draft EIS/EIR Public Hearings

Eastside Transit Corridor Phase 2 Draft EIS/EIR Public Hearings Eastside Transit Corridor Phase 2 Draft EIS/EIR Public Hearings Agenda Registration/Open House (30 minutes) Draft EIS/EIR Presentation (30 minutes) Public Comment (90 minutes) 1 Purpose of Today s Meeting

More information

Measure A Strategic Plan Update Citizens Advisory Committee July 1, 2014

Measure A Strategic Plan Update Citizens Advisory Committee July 1, 2014 Measure A Strategic Plan Update 2014-2018 Citizens Advisory Committee July 1, 2014 Presentation Outline Review Program Elements & Past Performance Discuss County Demographics and Travel Trends Review Program

More information

VTP Highway Program. Semi-Annual Report April 2013

VTP Highway Program. Semi-Annual Report April 2013 VTP Highway Program Semi-Annual Report April 2013 VTP Highway Program Semi-Annual Progress Report April 2013 Table of Contents TABLE OF CONTENTS Section Title Page 1 EXECUTIVE SUMMARY A Background... 1-2

More information

SUBJECT: AMENDED AND RESTATED AGREEMENT WITH CREATV SAN JOSE FOR PUBLIC AND EDUCATIONAL ACCESS CHANNEL MANAGEMENT

SUBJECT: AMENDED AND RESTATED AGREEMENT WITH CREATV SAN JOSE FOR PUBLIC AND EDUCATIONAL ACCESS CHANNEL MANAGEMENT CITY OF SAN JOSE CAPITAL OF SILICON VALLEY TO: HONORABLE MAYOR AND CITY COUNCIL COUNCIL AGENDA: 9/1/15 ITEM: Memorandum FROM: David Vossbrink SUBJECT: SEE BELOW DATE: Approved Date SUBJECT: AMENDED AND

More information

MOBILITY PARTNERSHIP AGENDA

MOBILITY PARTNERSHIP AGENDA 1. CALL TO ORDER/ROLL CALL MOBILITY PARTNERSHIP Wednesday, October 11, 2017 9:00 a.m. to 10:30 a.m. Gilroy City Council Chambers 7351 Rosanna Street, Gilroy, CA AGENDA 2. PUBLIC PRESENTATIONS: This portion

More information

To: From: Subject: Program continues to. Overview. the City of. Background. began the. As part of with both

To: From: Subject: Program continues to. Overview. the City of. Background. began the. As part of with both September 8, 2010 To: From: Subject: Transportation 2020 Committee Will Kempton, Chief Executive Officer Go Local Fixed-Guideway Program Update Overview The Go Local Fixed-Guideway Program continues to

More information

Federal Public Transportation Program: In Brief

Federal Public Transportation Program: In Brief Federal Public Transportation Program: In Brief William J. Mallett Specialist in Transportation Policy December 2, 2013 Congressional Research Service 7-5700 www.crs.gov R42706 Contents Introduction...

More information

Public-Private Partnership Program May 2015 Transit Coalition Update

Public-Private Partnership Program May 2015 Transit Coalition Update Public-Private Partnership Program May 2015 Transit Coalition Update Los Angeles County Metropolitan Transportation Authority Mark Linsenmayer Director Presentation Agenda Overview of Metro Public Private

More information

Planning Committee STAFF REPORT October 7, 2015 Page 2 of 6 Changes from Committee Background MTC began preparing its 2017 RTP Update earlier this yea

Planning Committee STAFF REPORT October 7, 2015 Page 2 of 6 Changes from Committee Background MTC began preparing its 2017 RTP Update earlier this yea Planning Committee STAFF REPORT Meeting Date: October 7, 2015 Subject Summary of Issues Approval of Resolution 15-4-G and Transmittal of Recommended Project Lists to the Metropolitan Transportation Commission

More information

SAFETY, SECURITY, AND TRANSIT PLANNING AND OPERATIONS AGENDA

SAFETY, SECURITY, AND TRANSIT PLANNING AND OPERATIONS AGENDA SAFETY, SECURITY, AND TRANSIT PLANNING AND OPERATIONS Thursday, February 16, 2017 3:00 PM VTA Conference Room B-106 3331 North First Street San Jose, CA AGENDA CALL TO ORDER 1. ROLL CALL 2. PUBLIC PRESENTATIONS:

More information

Meeting Minutes. Project: Subject: Date: Wednesday, December 16, 2015 Location: Attendees:

Meeting Minutes. Project: Subject: Date: Wednesday, December 16, 2015 Location: Attendees: Meeting Minutes Project: Subject: DART D2 Stakeholder Work Group for D2 Date: Wednesday, December 16, 2015 Location: Attendees: DART, 1401 Pacific Avenue, Dallas, TX Steve Salin, DART Ernie Martinez, DART

More information

The goal of the program is to enable transit-oriented housing and employment growth in Santa Clara County s Priority Development Areas (PDAs).

The goal of the program is to enable transit-oriented housing and employment growth in Santa Clara County s Priority Development Areas (PDAs). PDA PLANNING GRANTS PROGRAM The Santa Clara Valley Transportation Authority (VTA) has created a planning grant program for Santa Clara County jurisdictions that will provide significant support for Priority

More information

ATTACHMENT A: DRAFT PROPOSED SCOPE OF WORK

ATTACHMENT A: DRAFT PROPOSED SCOPE OF WORK 6 Harris Court Monterey, CA 93940 831 649-5225 Fax 831 373-5065 ATTACHMENT A: DRAFT PROPOSED SCOPE OF WORK FORA has prepared this proposed scope of work to be used as a guide for consultants as they submit

More information

City of Palo Alto (ID # 6831) City Council Staff Report

City of Palo Alto (ID # 6831) City Council Staff Report City of Palo Alto (ID # 6831) City Council Staff Report Report Type: Consent Calendar Meeting Date: 4/11/2016 Summary Title: Draft Comment Letter on Draft 2016 CHSRA Business Plan Title: Approval of a

More information

Corridor Management Committee. September 5, 2012

Corridor Management Committee. September 5, 2012 Corridor Management Committee September 5, 2012 2 Today s Topics SWLRT DEIS Process Overview and Outreach Preliminary Engineering Services Procurement Update Communications and Outreach Update BAC Report

More information

Annual Report on Funding Recommendations

Annual Report on Funding Recommendations Annual Report on Funding Recommendations Fiscal Year 2019 Capital Investment Grants Program Report of the Secretary of Transportation to the United States Congress Pursuant to 49 USC 5309(o)(1) and Section

More information

THE PENINSULA ECONOMY

THE PENINSULA ECONOMY Economic Update THE PENINSULA ECONOMY July 2017 SILICON VALLEY INSTITUTE for REGIONAL STUDIES Prepared by Stephen Levy This publication is one in a series of periodic updates on the local economy published

More information

Corridor Management Committee. March 28, 2018

Corridor Management Committee. March 28, 2018 Corridor Management Committee March 28, 2018 1 Today s Topics Chair s Update Proposed Corridor Protection Wall Update Environmental Update 2018 Look Ahead Eden Prairie Video 2 Chair s Update 3 Recent Activities

More information

Shaping Investments for San Francisco s Transportation Future The 2017 San Francisco Transportation Plan (SFTP) Update

Shaping Investments for San Francisco s Transportation Future The 2017 San Francisco Transportation Plan (SFTP) Update SAN FRANCISCO COUNTY TRANSPORTATION AUTHORITY Shaping Investments for San Francisco s Transportation Future The 2017 San Francisco Transportation Plan (SFTP) Update Provide world-class infrastructure and

More information

Public School Building Capital Fund

Public School Building Capital Fund Public School Building Capital Fund 1 Key Takeaways School capital funding is traditionally a local school district responsibility The Public School Building Capital Fund is one of few State supports for

More information

VTA Board of Directors and VTA Advisory Committee Members:

VTA Board of Directors and VTA Advisory Committee Members: From: Board.Secretary Sent: Wednesday, January 14, 2015 3:18 PM To: VTA Board of Directors; VTA Advisory Committee Members Subject: January is Human Trafficking Prevention Month VTA Board of Directors

More information

San Francisco to San Jose (Caltrain) / HNTB

San Francisco to San Jose (Caltrain) / HNTB Progress Report February 2013 Regional Consultant Monthly Progress Report San Francisco to San Jose (Caltrain) / HNTB Prepared By: Chuck Morganson Period: January 26, 2013 through February 22, 2013 ENVIRONMENTAL

More information

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY THIS PRINT COVERS CALENDAR ITEM NO. : 10.7 SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY DIVISION: Finance and Information Technology BRIEF DESCRIPTION: Resolution authorizing the San Francisco Municipal

More information

San Francisco Transportation Plan (SFTP) and Early Action Plan

San Francisco Transportation Plan (SFTP) and Early Action Plan San Francisco Transportation Plan (SFTP) and Early Action Plan October 2013 SAN FRANCISCO COUNTY TRANSPORTATION AUTHORITY Purpose of the San Francisco Transportation Plan (SFTP) Regional Transportation

More information

TABLE OF CONTENTS EXECUTIVE SUMMARY

TABLE OF CONTENTS EXECUTIVE SUMMARY TABLE OF CONTENTS EXECUTIVE SUMMARY v SECTION 1 BACKGROUND. 1 Coalfields Expressway.. 1 Route 460 Connector... 3 Corridor Q. 4 Project History.. 5 Current Activities.. 7 Project Implementation Schedule.

More information

Long Range Campus Plan 3.0 December 4, 2015

Long Range Campus Plan 3.0 December 4, 2015 Long Range Campus Plan 3.0 December 4, 2015 Campus Aerial View 2 Overview 3 333 Golden Gate Avenue Updates CEQA Project Delivery Student Housing Updates University of California San Francisco 198 McAllister/50

More information

The Economic Impact During FY 2015 of New Mexico's Business Incubators

The Economic Impact During FY 2015 of New Mexico's Business Incubators The Economic Impact During FY 2015 of New Mexico's Business s March 11, 2016 Prepared for: New Mexico Economic Development Department 1100 St. Francis Drive Joseph Montoya Building Santa Fe, NM 87505 Prepared

More information

SB202 MSO Community Action Plan SSPA Region 3

SB202 MSO Community Action Plan SSPA Region 3 SB202 MSO Community Action Plan SSPA Region 3 PRIORITY OVERVIEW FROM SSPA-3 PLAN REQUEST FOR PROPOSAL FOR FISCAL YEAR 2017-2018 THIS OVERVIEW CONTAINS THE INFORMATION IN ALL RFPS FOR SB 202 FUNDING AND

More information

Capitol Expressway Light Rail Project SCOPING SUMMARY REPORT. Federal Transit Administration Santa Clara Valley Transportation Authority

Capitol Expressway Light Rail Project SCOPING SUMMARY REPORT. Federal Transit Administration Santa Clara Valley Transportation Authority Capitol Expressway Light Rail Project SCOPING SUMMARY REPORT Federal Transit Administration Santa Clara Valley Transportation Authority January 2010 TABLE OF CONTENTS Introduction... 1 General Description

More information

Members of the Board of Directors. Wendy Knowles, Clerk of the Board. Update on the California High-Speed Rail Program Revised 2012 Business Plan

Members of the Board of Directors. Wendy Knowles, Clerk of the Board. Update on the California High-Speed Rail Program Revised 2012 Business Plan BOARD COMMITTEE TRANSMITTAL May 14, 2012 To: From: Subject: Members of the Board of Directors Wendy Knowles, Clerk of the Board Update on the California High-Speed Rail Program Revised 2012 Business Plan

More information

Community Advisory Panel Meeting #

Community Advisory Panel Meeting # Community Advisory Panel Meeting # 3 10.10.18.. Agenda Welcome and Introductions Community Conversations Review mailing in anticipation of next two community meetings Work Plan / Schedule Alternatives

More information

Strategic Plan Update Q1(July 2017 September 2017)

Strategic Plan Update Q1(July 2017 September 2017) Strategic Plan Update 18 Q1(July 17 September 17) Year 3 Initiatives Enrollment 1. Deliver Strategic Enrollment Plan by December 17 2. Deliver Academic Master Plan by April 18 3. Deliver The Armory new

More information

SAN JOSE CAPITAL OF SILICON VALLEY

SAN JOSE CAPITAL OF SILICON VALLEY PSFSS AGENDA: 9/17/2015 ITEM: (d) 6 CITY OF SAN JOSE CAPITAL OF SILICON VALLEY TO: PUBLIC SAFETY, FINANCE, AND STRATEGIC SUPPORT COMMITTEE Memorandum FROM: Curtis P. Jacobson SUBJECT: FIRE DEPARTMENT EMERGENCY

More information

Corridor Management Committee. May 4, 2016

Corridor Management Committee. May 4, 2016 Corridor Management Committee May 4, 2016 1 Today s Topics Chair s Update New Starts Update Station Design Update Corridor Development Update Next Steps CAC/BAC Reports 2 Chair s Update 3 2016 Legislative

More information

CHAPTER 6 PUBLIC AND AGENCY OUTREACH

CHAPTER 6 PUBLIC AND AGENCY OUTREACH CHAPTER 6 PUBLIC AND AGENCY OUTREACH This chapter documents the Westside Purple Line Extension Project (the Project) Public Participation Plan for the Draft Supplemental Environmental Impact Statement

More information

Memorandum. P:\Lifeline Program\2014 Lifeline Program\Call for Projects\LTP Cycle 4 Call - Memo.doc Page 1 of 7

Memorandum. P:\Lifeline Program\2014 Lifeline Program\Call for Projects\LTP Cycle 4 Call - Memo.doc Page 1 of 7 Memorandum Date: 10.29.14 To: Prospective Project Sponsors From: Seon Joo Kim Senior Transportation Planner Through: Amber Crabbe Assistant Deputy Director Subject: Cycle 4 Lifeline Transportation Program

More information

REQUEST FOR QUALIFICATIONS G ELLUCIAN (Datatel) COLLEAGUE CONVERSION TO MS SQL AND RELATED UPGRADES PROJECT

REQUEST FOR QUALIFICATIONS G ELLUCIAN (Datatel) COLLEAGUE CONVERSION TO MS SQL AND RELATED UPGRADES PROJECT SAN JOSE/EVERGREEN COMMUNITY COLLEGE DISTRICT 4750 San Felipe Road, San Jose, CA 95135 REQUEST FOR QUALIFICATIONS G2010.0069 ELLUCIAN (Datatel) COLLEAGUE CONVERSION TO MS SQL AND RELATED UPGRADES PROJECT

More information

JARC Grant Application

JARC Grant Application JARC Grant Application 2015 JOB Access Reverse Commute (JARC) Program Fund Federal Transit Administration (FTA) Section 5307 Winston-Salem Urban Area Metropolitan Planning Organization City of Winston

More information

Plans and Programs Committee: Commissioners Campos (Chair), Chu (Vice Chair), Avalos, Chiu, Wiener and Mirkarimi (Ex Officio)

Plans and Programs Committee: Commissioners Campos (Chair), Chu (Vice Chair), Avalos, Chiu, Wiener and Mirkarimi (Ex Officio) 10.14.11 Plans and Programs Committee October 18, 2011 Plans and Programs Committee: Commissioners Campos (Chair), Chu (Vice Chair), Avalos, Chiu, Wiener and Mirkarimi (Ex Officio) Maria Lombardo Chief

More information

THE REDEVELOPMENT AGENCY OF THE CITY OF SAN JOSE PROPOSED FY CAPITAL BUDGET FY OPERATING BUDGET

THE REDEVELOPMENT AGENCY OF THE CITY OF SAN JOSE PROPOSED FY CAPITAL BUDGET FY OPERATING BUDGET San Jose Innovation Center Brocade Communication Systems Campus in North San Jose San Jose BioCenter Adobe Headquarters THE REDEVELOPMENT AGENCY OF THE CITY OF SAN JOSE PROPOSED FY 2011-2012 CAPITAL BUDGET

More information

$5.2 Billion Transportation Funding Deal Announced, includes $1.5 Billion for Local Streets and Roads

$5.2 Billion Transportation Funding Deal Announced, includes $1.5 Billion for Local Streets and Roads 1400 K Street, Suite 400 Sacramento, California 95814 Phone: (916) 658-8200 Fax: (916) 658-8240 www.cacities.org $5.2 Billion Transportation Funding Deal Announced, includes $1.5 Billion for Local Streets

More information

CEDARS-SINAI MEDICAL CENTER WEST TOWER PROJECT

CEDARS-SINAI MEDICAL CENTER WEST TOWER PROJECT A. PROPOSED PROJECT A. PROPOSED PROJECT The Cedars-Sinai Medical Center (CSMC or the Applicant ) proposes to develop a new inpatient/medical support facility on the approximately 24.1-acre CSMC Campus

More information

In-Step, In Line, On Time. Robert F. Tally Jr. FHWA Indiana Division Administrator Monday, November 16, 2009

In-Step, In Line, On Time. Robert F. Tally Jr. FHWA Indiana Division Administrator Monday, November 16, 2009 In-Step, In Line, On Time Robert F. Tally Jr. FHWA Indiana Division Administrator Monday, November 16, 2009 I-69 Corridor 1 I-69 Corridor I-69 is expected to create more than 27,000 new jobs by 2025, resulting

More information

I-25 GAP COALITION MEETING #3 August 24, 2017 Douglas County Fairgrounds Main Event Center 500 Fairgrounds Blvd., Castle Rock MEETING SUMMARY

I-25 GAP COALITION MEETING #3 August 24, 2017 Douglas County Fairgrounds Main Event Center 500 Fairgrounds Blvd., Castle Rock MEETING SUMMARY I-25 GAP COALITION MEETING #3 August 24, 2017 Douglas County Fairgrounds Main Event Center 500 Fairgrounds Blvd., Castle Rock MEETING SUMMARY Attendees Dale Anderson Rachel Beck Linda Black Representative

More information

SUBJECT: FIREWORKS ORDINANCE DATE: April 1,2016

SUBJECT: FIREWORKS ORDINANCE DATE: April 1,2016 CITY OF 2 SANjOSE CAPITAL OF SILICON VALLEY TO: HONORABLE MAYOR AND CITY COUNCIL COUNCIL AGENDA: 4/12/16 ITEM: 8.1 Memorandum FROM: Curtis P. Jacobson SUBJECT: FIREWORKS ORDINANCE DATE: Approved " _ /

More information

FIVE YEAR FORECAST FY THROUGH FY

FIVE YEAR FORECAST FY THROUGH FY FIVE YEAR FORECAST FY 2014-15 THROUGH FY 2018-19 NOVEMBER 19, 2013 Catheryn Whitesell, Director Budget and Management Services Farrell Hanzaker, Chief Financial Officer Virginia Beach City Public Schools

More information

California s Current Section 1115 Waiver & Its Impact on the Public Hospital Safety Net

California s Current Section 1115 Waiver & Its Impact on the Public Hospital Safety Net February 2010 California s Current Section 1115 Waiver & Its Impact on the Public Hospital Safety Net Executive Summary The current Section 1115 Medicaid waiver, which was intended to stabilize California

More information

SUBJECT: LOS LAGOS GOLF COURSE DATE: May 16, 2016 LAND USE PUBLIC OUTREACH

SUBJECT: LOS LAGOS GOLF COURSE DATE: May 16, 2016 LAND USE PUBLIC OUTREACH COUNCIL AGENDA: 6/7/16 ITEM NO: 0... CITY OF SAN JOSE CAPITAL OF SILICON VALLEY Memorandum TO: HONORABLE MAYOR AND CITY COUNCIL FROM: Angel Rios, Jr. SUBJECT: LOS LAGOS GOLF COURSE DATE: LAND USE PUBLIC

More information

Special Meeting Agenda

Special Meeting Agenda Special Meeting Agenda Thursday, April 14, 2016 Time: 9:00 a.m. to 10 a.m. THIS IS A PHONE CONFERENCE MEETING Teleconference Number: 1-712- 432-1212 Participant Code: 432-600- 639 A. CALL TO ORDER AND

More information

Connecting and Transforming California

Connecting and Transforming California Connecting and Transforming California DRAFT 2016 BUSINESS PLAN FEBRUARY 18, 2016 www.hsr.ca.gov 2 Ca li f o rni a Hi gh-s p e e d Ra i l Au thori t y w w w. hsr. ca. gov Board of Directors The California

More information

National Environmental Policy Act/California Environmental Quality Act Scoping Meeting Summary

National Environmental Policy Act/California Environmental Quality Act Scoping Meeting Summary Redwood City Harbor Navigation Improvement Integrated Feasibility Study & EIS/EIR Appendix K National Environmental Policy Act/California Environmental Quality Act Scoping Meeting Summary December 2014

More information

Chapter 8. Glossary and Index. Chapter 8

Chapter 8. Glossary and Index. Chapter 8 Chapter 8 Glossary and Index Chapter 8 89 Chapter 8 Glossary and Index 1976 Measure A: A permanent, local half-cent sales tax approved by the voters of Santa Clara County exclusively for public transit

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS ENGINEERING/ARCHITECTURAL DESIGN SERVICES FOR THE NORTHEAST STOCKTON LIBRARY AND RECREATION CENTER CITY PROJECT NO. PW1724 City of Stockton Public Works Department 22 E. Weber Avenue,

More information

Santa Clara County County Home Page http://www.sccgov.org/portal/site/scc of Planning and Planning Office Services Office Building Inspection Office County Clerk/Recorder s Office Municipal/County Code

More information

Association of Fundraising Professionals Silicon Valley Collegiate Chapter. Request for Proposals Development Internship Opportunity

Association of Fundraising Professionals Silicon Valley Collegiate Chapter. Request for Proposals Development Internship Opportunity Association of Fundraising Professionals Silicon Valley Collegiate Chapter Request for Proposals Development Internship Opportunity Application Deadline: Tuesday, October 11, 2011 Submit via email to:

More information

THE ROSE GARDEN LIBRARY CLOSES AT 7:00PM

THE ROSE GARDEN LIBRARY CLOSES AT 7:00PM THE ROSE GARDEN LIBRARY CLOSES AT 7:00PM If you are parked in the library s garage, PLEASE MOVE YOUR CAR TO THE STREET, right away, so your car doesn t get locked in the garage until the library opens

More information

Economic Contribution of the North Dakota University System in 2015

Economic Contribution of the North Dakota University System in 2015 Agribusiness and Applied Economics Report No. 729 May 2017 Economic Contribution of the North Dakota University System in 2015 Randal C. Coon Dean A. Bangsund Nancy M. Hodur Department of Agribusiness

More information

2125 O NEL DRIVE HIGHWAY 101 IDENTITY 100% LEASED WITH NEAR TERM UPSIDE SAN JOSE, CA NORTH FIRST STREET 104,657 SF OFFICE/R&D BUILDING

2125 O NEL DRIVE HIGHWAY 101 IDENTITY 100% LEASED WITH NEAR TERM UPSIDE SAN JOSE, CA NORTH FIRST STREET 104,657 SF OFFICE/R&D BUILDING NORTH FIRST STREET 104,657 SF OFFICE/R&D BUILDING HIGHWAY 101 IDENTITY 100% LEASED WITH NEAR TERM UPSIDE 2125 O NEL SAN JOSE, CA EXECUTIVE SUMMARY This offering provides the exceptional opportunity to

More information

CASE STUDY: OVERVIEW OF A UNIVERSITY PROGRAM

CASE STUDY: OVERVIEW OF A UNIVERSITY PROGRAM CASE STUDY: OVERVIEW OF A UNIVERSITY PROGRAM Example of Option #1: Pre-Tax Benefits Plus Secondary Measures (secondary measures not required with Option #1) San Jose State University (SJSU) is a public

More information

Local Control Funding Formula Spending Regulations Comparison and Feedback Response Chart

Local Control Funding Formula Spending Regulations Comparison and Feedback Response Chart Page 1 of 11 Local Control Funding Formula Spending Comparison and Response Chart Overview At the November 6-7, 2013, State Board of Education (SBE) meeting, Agenda Item 13 presented a preliminary draft

More information

UC MERCED. Sep-2017 Report. Economic Impact in the San Joaquin Valley and State (from the period of July 2000 through August 2017 cumulative)

UC MERCED. Sep-2017 Report. Economic Impact in the San Joaquin Valley and State (from the period of July 2000 through August 2017 cumulative) UC MERCED Economic Impact in the Valley and State (from the period of July 2000 through August 2017 cumulative) Update # 57 9/27/2017 Sep-2017 Report UC Merced employees as of August 2017 totals 3587 (includes

More information

City of Lynwood MODIFIED REQUEST FOR PROPOSALS FOR

City of Lynwood MODIFIED REQUEST FOR PROPOSALS FOR City of Lynwood MODIFIED REQUEST FOR PROPOSALS FOR AN URBAN PLANNING FIRM TO PREPARE A SPECIFIC PLAN AMENDMENT TO THE LYNWOOD TRANSIT AREA SPECIFIC PLAN AND REQUIRED CEQA SUPPORTING DOCUMENTS (SUPPLEMENTAL

More information

United Fresh Start Foundation Joins Silicon Valley Leaders at 3 rd Annual 5K Run to Support Salad Bars for California Schools

United Fresh Start Foundation Joins Silicon Valley Leaders at 3 rd Annual 5K Run to Support Salad Bars for California Schools NEWS RELEASE For Immediate Release, March 15, 2016 Contact: Andrew Marshall amarshall@unitedfresh.org (202) 303-3407 United Fresh Start Foundation Joins Silicon Valley Leaders at 3 rd Annual 5K Run to

More information

Modernization Program Peninsula Corridor Electrification Project (PCEP) 3 rd Quarter FY 2016 Progress Report

Modernization Program Peninsula Corridor Electrification Project (PCEP) 3 rd Quarter FY 2016 Progress Report Modernization Program Peninsula Corridor Electrification Project (PCEP) 3 rd Quarter FY 2016 Progress Report January 1, 2016 to March 31, 2016 Funding Partners FTA Core Capacity FTA Section 5307/5337 (Environmental

More information

Memorandum Plans and Programs Committee February 12, 2013

Memorandum Plans and Programs Committee February 12, 2013 Memorandum 02.06.13 Plans and Programs Committee February 12, 2013 Plans and Programs Committee: Commissioners Mar (Chair), Kim (Vice Chair), Breed, Campos, Yee and Avalos (Ex Officio) Lee Saage Deputy

More information

Local Taxes and Highway Tolls: The New Normal

Local Taxes and Highway Tolls: The New Normal Local Taxes and Highway Tolls: The New Normal Los Angeles County Metropolitan Transportation Authority Public-Private Partnership Program August 16, 2012 Transportation and Infrastructure Summit Michael

More information

California Department of Public Health Safe Drinking Water State Revolving Fund. The American Recovery and Reinvestment Act of 2009 (ARRA)

California Department of Public Health Safe Drinking Water State Revolving Fund. The American Recovery and Reinvestment Act of 2009 (ARRA) California Department of Public Health Safe Drinking Water State Revolving Fund The American Recovery and Reinvestment Act of 2009 (ARRA) 1 ARRA Temporarily Creates a Distinct Program Within the Base SRF

More information

CDEM Resilience Fund Information for the CDEM sector [IS 11/16] March 2016 ISBN

CDEM Resilience Fund Information for the CDEM sector [IS 11/16] March 2016 ISBN CDEM Resilience Fund Information for the CDEM sector [IS 11/16] March 2016 ISBN 978-0-478-43514-6 Published by the Ministry of Civil Defence & Emergency Management This document is not copyright and may

More information

Transportation Needs and Funding Role of Impact Fees. January 6, 2015 BoCC Workshop

Transportation Needs and Funding Role of Impact Fees. January 6, 2015 BoCC Workshop Transportation Needs and Funding Role of Impact Fees January 6, 2015 BoCC Workshop 1 Impact Fees Provide Facilities for: Roads* Schools Parks Fire EMS *Most significant element 2 Discussion Topics Current

More information

San Francisco Transportation Task Force 2045

San Francisco Transportation Task Force 2045 San Francisco Transportation Task Force 2045 June 5, 2017 Meeting Welcome from the Chairs Welcome and thank you for joining this effort Why we are here Process outline and role of task force members Summary

More information