REGIONAL TRANSIT FEASIBILITY PLAN

Size: px
Start display at page:

Download "REGIONAL TRANSIT FEASIBILITY PLAN"

Transcription

1 REGIONAL TRANSIT FEASIBILITY PLAN The Regional Transit Feasibility Plan continues to make progress, having completed Steps One and Two of the process to evaluate opportunities for premium transit within the urbanized areas of Hillsborough, Pasco, and Pinellas Counties. The schedule is defined in two phases. The first is a three-step process to identify where the best connections are located, the best type of transit to serve those connections, and an implementation plan that identifies the catalyst project or projects that could be the starting point for building regional transit in the Tampa Bay area. The second phase will vet the Draft Implementation Plan with the public through a comprehensive and intense community outreach effort. work completed so far Workshops were held in Hillsborough, Pasco, and Pinellas Counties in August to talk with the community about the plan and the initial technical results of Step Two. The workshops are discussed on page 10. Pasco County Workshop, August 22, 2017 Hillsborough County Workshop, August 24, 2017 The first step of the effort identified the Regional Transit Vision (shown on page 2). To identify the Vision, more than 65 connections were evaluated for their ability to do three things: 1) serve key regional activity centers and regional travel needs, 2) provide access to jobs and redevelopment areas, and 3) serve community amenities. This Vision outlines the connections where premium regional transit are most needed in Tampa Bay. It also presents the transit network that is the basis for the Draft Implementation Plan. Pinellas County Workshop, August 29, 2017 The top five performing connections from the Vision were then advanced to Step Two. For more information on Step One, check out Technical Bulletin #2 on the documents page of the website, Technical Bulletin #3 October 2017 Page 1

2 Regional Transit Vision To be successful, projects must be part of a complete network of regional transit service. Components of the Regional Transit Vision include: Step One Top Performing Connections (dark blue): hhwestshore to Brandon hhdowntown Tampa to USF hhwesley Chapel, USF, Tampa, St. Petersburg hhclearwater, Gateway, St. Petersburg hhsouth Tampa to Downtown Tampa Critical Regional Connections (light blue) Commuter Services (orange) The downtown St. Petersburg to the Gulf Beaches connection is also included in the Regional Transit Vision. This important project is already on its way to being built! the Top Performers and Critical Regional Connections Would Serve The following Within 1/2 Mile of Each Connection by 2040 Serves approx. 2,100 jobs per mile (2040) Serves approx. 3,000 residents per mile (2040) Serves approx. 5 in 10 residents (2040) Serves approx. 6 in 10 jobs (2040) Serves approx. 6 in 10 residents WITHOUT cars (2040) Technical Bulletin #3 October 2017 Page 2

3 Gearing Up for Step Two Prior to the start of the Step Two Evaluation, modeling software was used to estimate several characteristics about the top performing connections. Understanding who would likely use the service, the types of trips they would make, and the average length of those trips helped the team to understand the transit modes that would best serve the needs. Assigning Transit Modes To identify the projects to evaluate during Step Two, the team considered several transit modes based on the characteristics of each connection and the type of service that could be successful in serving the connection. Connection + Mode = Project The transit modes evaluated during Step Two are pictured to the right. Rubber-tire modes included vehicles operating in toll lanes (similar to Express Bus) and in dedicated lanes (similar to bus rapid transit, or BRT), as well as autonomous solutions. Steel wheel or rail modes including light rail or modern streetcar, commuter rail, or elevated. Water ferry and aerial cable transit were also considered but will be further analyzed where they may be appropriate, such as crossing the Bay. For more information about the transit modes considered, check out the transit mode brochure on the documents page of the website: RUBBER TIRE: IN TOLL LANE RUBBER TIRE: IN DEDICATED LANE RUBBER TIRE: AUTONOMOUS SOLUTIONS MODERN STREETCAR/ LIGHT RAIL COMMUTER RAIL ELEVATED RAIL Photo Credit: Creative Solutions Technical Bulletin #3 October 2017 Page 3

4 Step Two: WHAT are the best projects? Each connection was paired with the appropriate transit modes for a total of 15 projects going into the Step Two evaluation. Five criteria were used to evaluate each of the projects in Step Two. Each category accounted for 20 percent of the total score. Projects were then compared to one another to identify which performed best. The range of performance totals were divided into five statistical quintiles, with 5 being the highest score possible. The evaluation criteria and how they meet the purpose of the plan are shown below: Preliminary FTA Rating Return on Investment Feasibility Community Benefits Public Opinion Compete for state and federal grants Best serves our region today while supporting tomorrow s growth The following pages present the results of the sensitivity analysis and the results of the Step Two Evaluation, organized by connection. The top half of each page presents the information used to assign transit modes - demographics along the connection, who would likely use the service, and the number and type of work trips they would make. The bottom half of each page shows the transit modes evaluated for each connection, the conceptual level cost ranges, and performance in the evaluation criteria, as discussed above. The Preliminary Ranking shows how the projects were ranked when all criteria scores were calculated. The following describes the evaluation criteria. Preliminary FTA Rating. This category evaluated each project s ability to meet the FTA Capital Investment Grant (CIG) program funding requirements (Mobility Improvements, Environmental Benefits, Congestion Relief, Cost Effectiveness, and Land Use). Return on Investment. This category evaluated each project s ability to reduce crashes and miles traveled by personal vehicles, yield farebox recovery (fares paid by riders), save energy, reduce pollutants/improve air quality, and increase revenues over existing annual capital and operating costs. Feasibility. This category evaluated projects for their potential to be built considering possible engineering challenges and impacts, such as utilities, natural resource impacts, and cultural resource impacts. Community Benefits. This category evaluated each project s ability to serve the community, specifically in regards to jobs and population in 2017 and 2040, and elderly, low income, and minority populations. Public Opinion. Public opinion was gathered through the public workshops and online survey. The results were combined with the technical results to refine the rankings. Projects were compared and statistical quintiles were assigned based on the highest and lowest raw scores in each category. The dots signify the project s performance for that category: represents the highest (best) score possible. Technical Bulletin #3 October 2017 Page 4

5 Step Two Results WESTSHORE TO BRANDON Total Jobs: 149,400 9,600 jobs served per mile Work Trips: 83,000+ daily trips to activity centers 59% Professional 21% Industrial 20% Service Population: 4,800 per square mile Age: 24% under 20 years old 65% years old 11% 65 years old or over Income: 60% $0-50k 28% $50-100k 12% over $100k Note: 2017 data within 1/2 mile of connection Mode Options Conceptual Costs fta rating return on investment feasibility community benefits Public Opinion ranking RUBBER TIRE: IN DEDICATED LANE $80-675M $3-4M/yr 7 MODERN STREETCAR/ LIGHT RAIL $360-1,850M $4-5M/yr 7 COMMUTER RAIL $ M $19-23M/yr 13 Detailed results and quintile scores are available on the project website. Technical Bulletin #3 October 2017 Page 5

6 Step Two Results DOWNTOWN TAMPA TO USF Total Jobs: 83,800 8,700 jobs served per mile Work Trips: 9,000+ daily trips to activity centers 72% Professional 14% Industrial 14% Service Population: 5,300 per square mile Age: 30% under 20 years old 60% years old 10% 65 years old or over Income: 73% $0-50k 20% $50-100k 7% over $100k Note: 2017 data within 1/2 mile of connection Mode Options Conceptual Costs fta rating return on investment feasibility community benefits Public Opinion ranking RUBBER TIRE: IN DEDICATED LANE $ M* $2-3M/yr 4 MODERN STREETCAR/ LIGHT RAIL $290-1,205M* $4-5M/yr 3 COMMUTER RAIL $ M* $7-9M/yr 5 * May require purchase of 96-mile CSX line at a cost of approximately $ million Detailed results and quintile scores are available on the project website. Technical Bulletin #3 October 2017 Page 6

7 Step Two Results WESLEY CHAPEL, USF, TAMPA, ST. PETERSBURG Total Jobs: 193,800 4,800 jobs served per mile Work Trips: 48,900+ daily trips to activity centers 68% Professional 16% Industrial 15% Service Population: 5,000 per square mile Age: 24% under 20 years old 64% years old 12% 65 years old or over Income: 60% $0-50k 25% $50-100k 15% over $100k Note: 2017 data within 1/2 mile of connection Mode Options Conceptual Costs fta rating return on investment feasibility community benefits Public Opinion ranking RUBBER TIRE: IN TOLL LANE RUBBER TIRE: IN DEDICATED LANE MODERN STREETCAR/ LIGHT RAIL COMMUTER RAIL * May require additional cost for bridge crossing $75-150M* $5-6M/yr $215-1,760M* $6-8M/yr $940-4,820M* $12-14M/yr $475-1,560M* $19-23M/yr Detailed results and quintile scores are available on the project website. Technical Bulletin #3 October 2017 Page 7

8 Step Two Results CLEARWATER TO ST. PETERSBURG Total Jobs: 156,200 6,500 jobs served per mile Work Trips: 25,500+ daily trips to activity centers 68% Professional 21% Industrial 12% Service Population: 4,500 per square mile Age: 18% under 20 years old 64% years old 18% 65 years old or over Income: 64% $0-50k 25% $50-100k 11% over $100k Note: 2017 data within 1/2 mile of connection Mode Options Conceptual Costs fta rating return on investment feasibility community benefits Public Opinion ranking RUBBER TIRE: IN DEDICATED LANE $125-1,035M $3-4M/yr 12 MODERN STREETCAR/ LIGHT RAIL $555-2,840M $8-10M/yr 11 Detailed results and quintile scores are available on the project website. Technical Bulletin #3 October 2017 Page 8

9 Step Two Results SOUTH TAMPA TO DOWNTOWN TAMPA Total Jobs: 92,800 10,200 jobs served per mile Work Trips: 43,500+ daily trips to activity centers 75% Professional 13% Industrial 12% Service Population: 6,100 per square mile Age: 22% under 20 years old 66% years old 12% 65 years old or over Income: 46% $0-50k 26% $50-100k 28% over $100k Note: 2017 data within 1/2 mile of connection Mode Options Conceptual Costs fta rating return on investment feasibility community benefits Public Opinion ranking RUBBER TIRE: IN DEDICATED LANE $ M* $3-4M/yr 13 MODERN STREETCAR/ LIGHT RAIL $275-1,145M* $8-10M/yr 9 ELEVATED RAIL $1,260-5,165M* $44-52M/yr 13 * May require purchase of 9.1-miile CSX line at a cost of approximately $ million Detailed results and quintile scores are available on the project website. Technical Bulletin #3 October 2017 Page 9

10 Public Workshops In August, three community workshops, one each in Hillsborough, Pasco, and Pinellas Counties were held. Meetings were open house format, allowing participants to take their time to review the materials and ask questions. The room was set up in stations based on the steps of the technical work that has been completed. The final station showed the technical results of Step Two, including how each project performed and allowed attendees to vote on their preferred projects. A total of 137 attendees were present at the three meetings. Many provided valuable comments and stayed to talk with the team. We received more than 350 comments on the different exercises (some of the more common comments are shown to the right). Rail has left the station, focus on rubber tire Stop talking, start building St. Pete to Tampa is where we live and work What about a Gandy connection? Use CSX Autonomous vehicles is a no brainer Need frequent rail transit Focus on land use and economic growth Need a connection to the airport Have to connect urban centers For more information about what we heard from the workshops and to view the display boards that were provided at the meeting, visit the Documents page of the website, Station 1: Plan Overview Station 2: Step One Exercise Station 4: Step Two Voting Station 4: Step Two Results and Voting Technical Bulletin #3 October 2017 Page 10

11 Step Two Preliminary Rankings As shown in the previous pages, the evaluation criteria were used to rank the projects based on both technical merit and public preference. Following the ranking, the top projects rogressing to Step Three include: Rank Connection Mode Wesley Chapel, USF, Tampa, Gateway, St. Petersburg Wesley Chapel, USF, Tampa, Gateway, St. Petersburg Light Rail Rubber Tire in Exclusive Lane & mixed traffic Downtown Tampa to USF Light Rail 4 Downtown Tampa to USF Rubber Tire in Exclusive Lane Next Steps Step Three will take the top projects from Step Two and identify the most competitive catalyst project or projects for federal and state funding. The projects will be refined to make them as competitive and efficient as possible. This will include revisiting the performance of each project and where appropriate, looking into suitable ways of phasing the project over time. Estimated costs to construct the projects will be calculated as well. As part of Step Three, the team will also develop a Draft Implementation Plan that outlines the steps needed to take each project from a line on the map to a route on the ground. The Implementation Plan will not only address the catalyst project or projects, but each connection in the Regional Transit Vision with varying degrees of detail. 5 6 Wesley Chapel, USF, Tampa, Gateway, St. Petersburg Commuter Rail Downtown Tampa to USF Commuter Rail The Draft Implementation Plan will be presented to the Tampa Bay Transportation Management Area Leadership Group in January At that time, the project team will kick-off an eight-month community vetting period that will include a variety of outreach events and public comment opportunities. Timeline The timeline below shows where we are in regards to the Regional Transit Feasibility Plan. The Draft Implementation Plan will be presented in January 2018, followed by an eight-month community vetting WORK PLAN SUMMARY period. The Final Implementation Plan will be unveiled in September We are here Oct - Dec Jan - Apr May Jun July Aug Sep Oct - Dec Jan Feb Mar Apr May Jun July Aug Sep Study Management, Coordination, and Outreach Step 1: WHERE Step 2: WHAT Step 3: HOW Draft Implementation Plan Community Vetting Period Implementation Plan Technical Bulletin #3 October 2017 Page 11

12 Be Part of the Plan If you have any questions or comments about the plan or ideas for public engagement related to the plan, please let us know! You can send them to or tell us via or and use #TBRegionalTransit. check out our project videos! You can also watch the narrated presentations step one results step two update step two results Primary Points of Contact: This plan is funded by the Florida Department of Transportation (FDOT). The Hillsborough Area Regional Transit Authority (HART) is administering the work effort with Jacobs. For more information, contact HART s Director of Service Development and Project Manager Steve Feigenbaum, or TBRegionalTransit@gohart.org. Advisory Support: Members of our region s business community, the Tampa Bay Transportation Management Area (TMA) Leadership Group, and a coalition of Hillsborough, Pasco, and Pinellas transit agencies are contributing to the plan. GET INVOLVED: Visit the project website to provide your input and sign up to receive updates. Technical Bulletin #3 October 2017 Page 12

TAMPA BAY PUBLIC TRANSIT INITIATIVES: A Response to Questions of the MPO citizens advisory committee

TAMPA BAY PUBLIC TRANSIT INITIATIVES: A Response to Questions of the MPO citizens advisory committee TAMPA BAY PUBLIC TRANSIT INITIATIVES: A Response to Questions of the MPO citizens advisory committee How can we address our future needs with transit? Projected Growth of the Network 2010-2040 200% 180%

More information

MULTIMODAL TRANSPORTATION DISTRICT ALTERNATIVES ANALYSIS. Executive Summary

MULTIMODAL TRANSPORTATION DISTRICT ALTERNATIVES ANALYSIS. Executive Summary MULTIMODAL TRANSPORTATION DISTRICT ALTERNATIVES ANALYSIS Executive Summary February 2015 Executive Summary 1. Define the Problem This Alternatives Analysis report is submitted as a deliverable for the

More information

Central City Line Kick-off and Tour

Central City Line Kick-off and Tour Central City Line Kick-off and Tour Phase C Preliminary Engineering, Environmental Documentation and Small Starts Submittal Kickoff Meeting Agenda Time Item 1:00 PM Welcome, Introductions and Agenda Review

More information

Creation of a New Limited Express Route 275LX. Board of Directors Meeting February 5, 2018

Creation of a New Limited Express Route 275LX. Board of Directors Meeting February 5, 2018 Creation of a New Limited Express Route 275LX Board of Directors Meeting February 5, 2018 Background COA/TPD process recommended and vetted new route through public outreach connecting University Area/Downtown/Airport

More information

Regional Transit System Plan. Regional Task Force Meeting No. 1

Regional Transit System Plan. Regional Task Force Meeting No. 1 Regional Transit System Plan Regional Task Force Meeting No. 1 Thursday, December 2, 2010 James Wagner Welcome! Introductions Venue Packet Displays Opening Session 1 Agenda (5 mins) (20 mins) What is a

More information

2040 Transportation Policy Plan Update. Council Committee of the Whole December 6, 2017

2040 Transportation Policy Plan Update. Council Committee of the Whole December 6, 2017 2040 Transportation Policy Plan Update Council Committee of the Whole December 6, 2017 What is the Transportation Policy Plan (TPP)? Long-range transportation plan for the region Required under state and

More information

Transportation Planning & Investment in Urban North Carolina

Transportation Planning & Investment in Urban North Carolina Transportation Planning & Investment in Urban North Carolina Using the Voice of Mayors to Advance North Carolina Almost all future NC growth projected to occur in urban areas Projected share of 2010-2035

More information

METHODOLOGY - Scope of Work

METHODOLOGY - Scope of Work The scope of work for the Truckee West River Site Redevelopment Feasibility Study will be undertaken through a series of sequential steps or tasks and will comprise four major tasks as follows. TASK 1:

More information

To: From: Subject: Program continues to. Overview. the City of. Background. began the. As part of with both

To: From: Subject: Program continues to. Overview. the City of. Background. began the. As part of with both September 8, 2010 To: From: Subject: Transportation 2020 Committee Will Kempton, Chief Executive Officer Go Local Fixed-Guideway Program Update Overview The Go Local Fixed-Guideway Program continues to

More information

FEDERAL TRANSIT ADMINISTRATION

FEDERAL TRANSIT ADMINISTRATION FEDERAL TRANSIT ADMINISTRATION JOB ACCESS & REVERSE COMMUTE PROGRAM AND NEW FREEDOM PROGRAM Competitive Grant Application for the Tampa Bay Metropolitan Area, including the urbanized areas of Pasco, Pinellas,

More information

FEDERAL TRANSIT ADMINISTRATION

FEDERAL TRANSIT ADMINISTRATION FEDERAL TRANSIT ADMINISTRATION JOB ACCESS & REVERSE COMMUTE PROGRAM AND NEW FREEDOM PROGRAM Competitive Grant Application for the Tampa Bay Metropolitan Area, including the urbanized areas of Pasco, Pinellas,

More information

METRO Orange Line Extension Planning and Implementation

METRO Orange Line Extension Planning and Implementation METRO Orange Line Extension Planning and Implementation December 9, 2015 Planning has begun for an extension of METRO Orange Line south from Burnsville to the Kenrick Avenue park and ride in Lakeville.

More information

May 17, To: From: Subject: Program continues to. Overview. Step Two. fixed-guideway. Program. for. Background

May 17, To: From: Subject: Program continues to. Overview. Step Two. fixed-guideway. Program. for. Background May 17, 2010 To: From: Subject: Transportation 2020 Committee Will Kempton, Chief Executive Officer Go Local Fixed-Guideway Program Update Overview The Go Local Fixed-Guidewaof the program, the City of

More information

Puget Sound Gateway Program

Puget Sound Gateway Program Puget Sound Gateway Program SR 167 Completion Project Tacoma Transportation Commission April 18, 2018 THOMAS SLIMAK, PE SR 167 ASSISTANT PROJECT MANAGER Agenda Puget Sound Gateway Program Overview Program

More information

SFRTA/TRI-RAIL PAST, PRESENT & FUTURE

SFRTA/TRI-RAIL PAST, PRESENT & FUTURE SFRTA/TRI-RAIL PAST, PRESENT & FUTURE Presented by: Joseph Giulietti, Executive Director South Florida Regional Transportation Authority July 25, 2007 Tri-Rail History OVERVIEW South Florida Regional Transportation

More information

STATE HIGHWAY (SH) 34 FEASIBILITY STUDY PUBLIC MEETING

STATE HIGHWAY (SH) 34 FEASIBILITY STUDY PUBLIC MEETING STATE HIGHWAY (SH) 34 FEASIBILITY STUDY PUBLIC MEETING From FM 2578 in Terrell to SH 243 in Kaufman CSJ: 0173-04-056 June 28, 2018 WHAT IS A FEASIBILITY STUDY WHAT IS A FEASIBILITY STUDY? A feasibility

More information

Transit-Oriented Development and Land Use Subarea Plan for Central Lake Forest Park

Transit-Oriented Development and Land Use Subarea Plan for Central Lake Forest Park CITY OF LAKE FOREST PARK REQUEST FOR PROPOSALS Transit-Oriented Development and Land Use Subarea Plan for Central Lake Forest Park PROJECT DESCRIPTION The City of Lake Forest Park is seeking qualified

More information

Beth Day Director, FTA Office of Project Planning RailVolution October 2011

Beth Day Director, FTA Office of Project Planning RailVolution October 2011 Beth Day Director, FTA Office of Project Planning RailVolution October 2011 What is a New or Small Start? New fixed guideways and extensions to existing systems Includes light rail, heavy rail, commuter

More information

Tampa Bay TMA Leadership Group Workshop

Tampa Bay TMA Leadership Group Workshop Tampa Bay TMA Leadership Group Workshop Representing the MPOs in Pasco, Pinellas, & Hillsborough Counties Friday, September 5, 2014 Atkins Conference Room 4030 West Boy Scout Blvd, 6th Floor Tampa, Florida

More information

Board Meeting. Wednesday, June 20, :00 a.m.

Board Meeting. Wednesday, June 20, :00 a.m. Board Meeting Wednesday, June 20, 2018 9:00 a.m. Invocation Pledge of Allegiance Roll Call of Members Announcements Introduction of FDOT Staff Call to Order Highlands Transit Plan Public Involvement Award

More information

Sustainable Transportation Partnership of the Central Okanagan (STPCO) City of Kelowna Update. November 6, 2017

Sustainable Transportation Partnership of the Central Okanagan (STPCO) City of Kelowna Update. November 6, 2017 Sustainable Transportation Partnership of the Central Okanagan (STPCO) City of Kelowna Update November 6, 2017 Objective - Update council on STPCO activities Part 1 Governance Review Context Fall 2017

More information

APPENDIX B BUS RAPID TRANSIT

APPENDIX B BUS RAPID TRANSIT APPENDIX B BUS RAPID TRANSIT Table of Contents TABLE OF CONTENTS What is Bus Rapid Transit?... 2 BRT Features... 2 BRT Variations... 3 Where is BRT Currently Located?... 4 How Much Does BRT Cost?... 4

More information

Florida Transportation Commission Workshop. Partnerships for the Future 1

Florida Transportation Commission Workshop. Partnerships for the Future 1 Florida Transportation Commission Workshop Regional Governance Florida Department of Transportation Tallahassee, FL September 19, 2012 Scott R. Koons, AICP, Executive Director, North Central Florida Regional

More information

Smart Region Smart Transportation

Smart Region Smart Transportation Smart Region Smart Transportation Joe Milazzo II, PE, RTA Executive Director Wednesday, Oct. 19, 2016 The Regional Transportation Alliance business coalition: MISSION To leverage the strength of the regional

More information

Regional Core Circulator Study Final Report

Regional Core Circulator Study Final Report Regional Core Circulator Study Final Report TOLEDO METROPOLITAN AREA COUNCIL OF GOVERNMENTS Prepared By: Wilbur Smith Associates In association with: Parsons Brinckerhoff Finkbeiner, Pettis, & Strout Funk

More information

Fiscal Year October September 2018 Statistics

Fiscal Year October September 2018 Statistics Fiscal Year October 2017 - September 2018 Statistics Month Live Chat per Month E-mails per Month Texts per Month Combined Sessions Per Month Oct 4460 1685 425 6570 Nov 3659 1474 398 5531 Dec 1875 1392

More information

Lessons Learned for a Transit Public-Private Partnership. Phillip A. Washington, General Manager Regional Transportation District

Lessons Learned for a Transit Public-Private Partnership. Phillip A. Washington, General Manager Regional Transportation District Lessons Learned for a Transit Public-Private Partnership Phillip A. Washington, General Manager Regional Transportation District Feb. 7, 2011 The RTD FasTracks Plan 122 miles of new light rail and commuter

More information

Florida s Future: Funding Growth Through Public Private Partnerships. Ed Turanchik. March 10, 2014

Florida s Future: Funding Growth Through Public Private Partnerships. Ed Turanchik. March 10, 2014 Florida s Future: Funding Growth Through Public Private Partnerships Ed Turanchik March 10, 2014 Fla. Statute 287.05712 Effective July 1, 2013, Florida s new public-private partnership statute introduces

More information

Public Information Plan

Public Information Plan Metcalf Shawnee Mission Parkway Bus Corridors Transit Improvements Public Information Plan Prepared by 1 Plan Purpose The public information plan for the Metcalf Avenue/Shawnee Mission Parkway Bus Corridor

More information

Financing Transit Projects with Traditional and Innovative Sources And Mechanisms

Financing Transit Projects with Traditional and Innovative Sources And Mechanisms Financing Transit Projects with Traditional and Innovative Sources And Mechanisms Exploring the Potential for Bus Rapid Transit and Transit- Oriented Development in the I- 287/Tappan Zee Bridge Corridor

More information

Safety Projects and the Local Agency Program (LAP)

Safety Projects and the Local Agency Program (LAP) Safety Projects and the Local Agency Program (LAP) Wednesday, January 8, 2014 Lawrence Taylor Consultant D7 Safety/LAP Project Manager Workshop Series Wed. Oct. 30 Wed. Nov. 6 Wed. Nov. 13 Wed. Nov. 20

More information

Federal Public Transportation Program: In Brief

Federal Public Transportation Program: In Brief Federal Public Transportation Program: In Brief William J. Mallett Specialist in Transportation Policy December 2, 2013 Congressional Research Service 7-5700 www.crs.gov R42706 Contents Introduction...

More information

Report on Economic Development Contracts Pinellas County

Report on Economic Development Contracts Pinellas County Pinellas County Economic Development Annual Report to the Florida Legislative Office of Economic and Demographic Research Pinellas County Fiscal Year 2017 Report on Economic Development Contracts Pinellas

More information

Urban Partnership Communications Plan

Urban Partnership Communications Plan Urban Partnership Communications Plan CONTENTS URBAN PARTNERSHIP OVERVIEW 01 COMMUNICATIONS PLAN 02 TOLLING 04 TRANSIT 05 TECHNOLOGY 06 TRANSPORTATION DEMAND MANAGEMENT 07 APPENDICES A: SR 520 Bridge Tolling

More information

2017 Certification Report. Tampa Bay Transportation Management Area. Hillsborough MPO Forward Pinellas Pasco County MPO.

2017 Certification Report. Tampa Bay Transportation Management Area. Hillsborough MPO Forward Pinellas Pasco County MPO. 2017 Certification Report Tampa Bay Transportation Management Area Hillsborough MPO Forward Pinellas Pasco County MPO Prepared by: Federal Highway Administration Florida Division Federal Transit Administration

More information

Client: Boulder County Transportation Project: SH 119 Bus Rapid Transit & Bikeway Facility Design

Client: Boulder County Transportation Project: SH 119 Bus Rapid Transit & Bikeway Facility Design Client: Boulder County Transportation Project: SH 119 Bus Rapid Transit & Bikeway Facility Design I. Applicant (Client) Information Organization Name and Address Boulder County Transportation, 2525 13th

More information

FUNDING SOURCES. Appendix I. Funding Sources

FUNDING SOURCES. Appendix I. Funding Sources Appendix I. Funding Sources FUNDING SOURCES planning and related efforts can be funded through a variety of local, state, and federal sources. However, these revenues have many guidelines in terms of how

More information

STATUS AND KEY ACTIVITIES

STATUS AND KEY ACTIVITIES Memorandum Date: January 24, 2014 To: Authority Board: Commissioners Avalos (Chair), Wiener (Vice Chair), Breed, Campos, Chiu, Cohen, Farrell, Kim, Mar, Tang and Yee From: Chester Fung Principal Transportation

More information

PINELLAS COUNTY DEO#12-1ESR

PINELLAS COUNTY DEO#12-1ESR Agenda Item #3.H.11 02/13/12 LOCAL GOVERNMENT COMPREHENSIVE PLAN PROPOSED AMENDMENT REPORT PINELLAS COUNTY DEO#12-1ESR 1 THIS PAGE INTENTIONALLY LEFT BLANK 2 PINELLAS COUNTY LPA 22-10-11 Expedited State

More information

Transportation Demand Management Workshop Region of Peel. Stuart M. Anderson David Ungemah Joddie Gray July 11, 2003

Transportation Demand Management Workshop Region of Peel. Stuart M. Anderson David Ungemah Joddie Gray July 11, 2003 Transportation Demand Management Workshop Region of Peel Stuart M. Anderson David Ungemah Joddie Gray July 11, 2003 Why Transportation Demand Management (TDM)? Demand management measures support a sustainable

More information

SAN IPSE CAPITAL OF SILICON VALLEY ?/2W/(T. Memorandum TO: HONORABLE MAYOR AND CITY COUNCIL. FROM: Kim Walesh Jim Ortbal

SAN IPSE CAPITAL OF SILICON VALLEY ?/2W/(T. Memorandum TO: HONORABLE MAYOR AND CITY COUNCIL. FROM: Kim Walesh Jim Ortbal CITY OF 7 S3 SAN IPSE CAPITAL OF SILICON VALLEY TO: HONORABLE MAYOR AND CITY COUNCIL STUDY SESSION: 3/30/2017 Memorandum FROM: Kim Walesh Jim Ortbal SUBJECT: DIRIDON STATION PLAN AND REGIONAL RAIL PROJECTS

More information

BROWARD COUNTY TRANSIT MAJOR SERVICE CHANGE TO 595 EXPRESS SUNRISE - FORT LAUDERDALE. A Title VI Service Equity Analysis

BROWARD COUNTY TRANSIT MAJOR SERVICE CHANGE TO 595 EXPRESS SUNRISE - FORT LAUDERDALE. A Title VI Service Equity Analysis BROWARD COUNTY TRANSIT MAJOR SERVICE CHANGE TO 595 EXPRESS SUNRISE - FORT LAUDERDALE A Title VI Service Equity Analysis Prepared September 2015 Submitted for compliance with Title VI of the Civil Rights

More information

Agenda. 6:00 p.m. - 6:45 p.m. - Registration & Open House. 6:45 p.m. - 6:55 p.m. - Welcome & Opening Remarks

Agenda. 6:00 p.m. - 6:45 p.m. - Registration & Open House. 6:45 p.m. - 6:55 p.m. - Welcome & Opening Remarks Agenda 6:00 p.m. - 6:45 p.m. - Registration & Open House 6:45 p.m. - 6:55 p.m. - Welcome & Opening Remarks 6:55 p.m. - 7:15 p.m. - Formal Presentation 7:15 p.m. - 7:30 p.m. - Questions/Answer Session &

More information

Gold Rush Circulator Study Charlotte, North Carolina REQUEST FOR PROPOSALS

Gold Rush Circulator Study Charlotte, North Carolina REQUEST FOR PROPOSALS Gold Rush Circulator Study Charlotte, North Carolina REQUEST FOR PROPOSALS September 25, 2012 for the Gold Rush Circulator Study A. Purpose Charlotte Center City Partners (CCCP) and the City of Charlotte

More information

Developing the Pulse Corridor

Developing the Pulse Corridor Developing the Pulse Corridor Creating TOD that s effective and equitable Christopher Leinberger Professor George Washington University School of Business Partner, Arcadia Land Company Christopher Zimmerman

More information

Federal Support for Streetcars: Frequently Asked Questions

Federal Support for Streetcars: Frequently Asked Questions Federal Support for Streetcars: Frequently Asked Questions William J. Mallett Specialist in Transportation Policy April 3, 2014 Congressional Research Service 7-5700 www.crs.gov R43464 Summary Streetcars,

More information

Transportation & Parking Advisory Committee

Transportation & Parking Advisory Committee December 6, 2017 Transportation & Parking Advisory Committee Scott Silsdorf, AICP Director of Transportation and Parking Services Agenda Introductions Department Updates Mobile App is live Spring semester

More information

2018 State Legislative Agenda

2018 State Legislative Agenda 2018 State Legislative Agenda WORKFORCE HEALTH CARE The business community must partner with stakeholders and policymakers to advocate for adequate resources to help recruit, develop and retain talent

More information

CITY OF SPOKANE VALLEY Request for Council Action

CITY OF SPOKANE VALLEY Request for Council Action CITY OF SPOKANE VALLEY Request for Council Action Meeting Date: May 7, 2013 Department Director Approval: Check all that apply: consent old business new business public hearing information admin. report

More information

A FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICTS FOUR AND SIX COMMUTER SERVICES SCOPE OF SERVICES

A FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICTS FOUR AND SIX COMMUTER SERVICES SCOPE OF SERVICES Exhibit A FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICTS FOUR AND SIX COMMUTER SERVICES SCOPE OF SERVICES 1.0 Purpose The South Florida Commuter services vendor (hereinafter referred to as Vendor ) for

More information

Tourism Enhancement Grant Event Application

Tourism Enhancement Grant Event Application Tourism Enhancement Grant Event Application Read the Overview and Instructions before completing the application. Applications may be mailed, e- mailed or dropped-off to the address below. If submitting

More information

City of Seattle Partnering Agreement. December 2017

City of Seattle Partnering Agreement. December 2017 City of Seattle Partnering Agreement December 2017 Agenda System Expansion Plan West Seattle and Ballard Link Extensions Partnering Agreement System expansion Sound Transit s system expansion means every

More information

Central City Line Steering Committee

Central City Line Steering Committee Central City Line Steering Committee Meeting #1 Thursday, Spokane Intermodal Center Great Northern Room, #310 221 W. First Ave. Spokane, WA 1 Agenda Welcome, Introductions and Agenda Review Review of Steering

More information

SOUTH FLORIDA COMMUTER SERVICES CONTRACT SCOPE OF SERVICES

SOUTH FLORIDA COMMUTER SERVICES CONTRACT SCOPE OF SERVICES SOUTH FLORIDA COMMUTER SERVICES CONTRACT SCOPE OF SERVICES 1.1 Purpose The South Florida Commuter Services VENDOR (hereinafter referred to as Vendor) for the Florida Department of Transportation (hereinafter

More information

Citizen Participation in the MPO Transportation Planning Process. Pinellas County Metropolitan Planning Organization Pinellas County, Florida

Citizen Participation in the MPO Transportation Planning Process. Pinellas County Metropolitan Planning Organization Pinellas County, Florida Citizen Participation in the MPO Transportation Planning Process Pinellas County Metropolitan Planning Organization Pinellas County, Florida PUBLIC PARTICIPATION PLAN PINELLAS COUNTY METROPOLITAN PLANNING

More information

George Washington Region Scenario Planning Study Phase II

George Washington Region Scenario Planning Study Phase II George Washington Region Scenario Planning Study Phase II PhaseIIScenarioSummary This final section of the report presents a comparative summary of the regional and corridor level effects of the three

More information

Comprehensive Silver Line Plan & Title VI

Comprehensive Silver Line Plan & Title VI Customer Service and Operations Committee Board Action Item III-A April 11, 2013 Comprehensive Silver Line Plan & Title VI Page 3 of 28 Washington Metropolitan Area Transit Authority Board Action/Information

More information

RideFinders Program Review. RRTPO 2/1/18 Presentation by: Von Tisdale, Executive Director

RideFinders Program Review. RRTPO 2/1/18 Presentation by: Von Tisdale, Executive Director RideFinders Program Review RRTPO 2/1/18 Presentation by: Von Tisdale, Executive Director Brief Introduction Brief Review of Program Highlights Financials & Audit Future Program Plans RideFinders Program

More information

JARC Grant Application

JARC Grant Application JARC Grant Application 2015 JOB Access Reverse Commute (JARC) Program Fund Federal Transit Administration (FTA) Section 5307 Winston-Salem Urban Area Metropolitan Planning Organization City of Winston

More information

Hillsborough County Long Range TDM Plan

Hillsborough County Long Range TDM Plan Hillsborough County Long Range TDM Plan Executive Summary Prepared for Bay Area Commuter Services Prepared by: Philip Winters, Senior Research Associate Christopher Hagelin, Research Associate Center for

More information

Metro. Board Report. File #: , File Type:Informational Report

Metro. Board Report. File #: , File Type:Informational Report Metro Board Report Los Angeles County Metropolitan Transportation Authority One Gateway Plaza 3rd Floor Board Room Los Angeles, CA File #:2015-1743, File Type:Informational Report Agenda Number:56. PLANNING

More information

Capital Investment Program

Capital Investment Program Capital Investment Program FY08-FY13 DRAFT Massachusetts Bay Transportation Authority Draft FY08 FY13 Capital Investment Program Slide 1 Profile of the MBTA Fifth largest transit agency in America 4.5

More information

STAKEHOLDER VISIONING MEETING. November 12, 2015

STAKEHOLDER VISIONING MEETING. November 12, 2015 STAKEHOLDER VISIONING MEETING November 12, 2015 Transportation Responsibilities Maintain approximately 2,450 centerline miles of roadway Maintain more than 180 bridges and bridge culverts Maintain more

More information

METRO Blue Line LRT & METRO Green Line LRT (Light Rail) Table of Contents. Operating Grant Worksheets Pages 6-17

METRO Blue Line LRT & METRO Green Line LRT (Light Rail) Table of Contents. Operating Grant Worksheets Pages 6-17 METRO Blue Line LRT & METRO Green Line LRT (Light Rail) Table of Contents Operating Grant Application Cover Sheet Pages 1-3 Project Benchmarks and Timeline Pages 4-5 Operating Grant Worksheets Pages 6-17

More information

Privacy and Proxy Services Accreditation IRT ICANN57 Working Meeting. 9 November 2016

Privacy and Proxy Services Accreditation IRT ICANN57 Working Meeting. 9 November 2016 Privacy and Proxy Services Accreditation IRT ICANN57 Working Meeting 9 November 2016 Agenda 1 2 3 Project Status Initial Feedback Discussion Topic 1: Regular Meeting Time 4 5 6 Discussion Topic 2: Contract-Based

More information

Executive Director s Report

Executive Director s Report Executive Director s Report Peter V. Lee Executive Director California Health Benefit Exchange Board Meeting December 18, 2012 Covered California Board Calendar 2013 Month / Date January 17 February 21

More information

INTRODUCTION. RTPO Model Program Guide February 27, 2007 Page 1

INTRODUCTION. RTPO Model Program Guide February 27, 2007 Page 1 TABLE OF CONTENTS INTRODUCTION... 1 HOW TO USE THIS GUIDE... 2 SECTION I: LAND USE AND TRANSPORTATION CONTEXT... 3 SECTION II: MINIMUM CRITERIA FOR GROWTH AND TRANSPORTATION EFFICIENCY CENTERS... 5 SECTION

More information

Project ENABLE - Alameda County Community Capacity Fund. Project Blueprint. March 2015

Project ENABLE - Alameda County Community Capacity Fund. Project Blueprint. March 2015 Project ENABLE - Alameda County Community Capacity Fund Project Blueprint March 2015 Table of Contents Project Highlights Project Objectives Project Goal Current Challenges of Organizations Serving the

More information

Pasco County Public Information Office. FY 2016 Yearbook Updated

Pasco County Public Information Office. FY 2016 Yearbook Updated Pasco County Public Information Office FY 2016 Yearbook Updated 12.27.16 Public Information Office (PIO) Overview PASCO COUNTY PUBLIC INFORMATION OFFICE FY 2016 YEARBOOK The Public Information Office has

More information

Job Access Reverse Commute Program & New Freedom Program 2013 FUNDING APPLICATION

Job Access Reverse Commute Program & New Freedom Program 2013 FUNDING APPLICATION Job Access Reverse Commute Program & New Freedom Program 2013 FUNDING APPLICATION Important Dates 1. Pre-Application Workshop: 9 a.m. CST, Wednesday, February 13, 2013, Mid-America Regional Council, 600

More information

Last Updated June 20, Goal: Service Development

Last Updated June 20, Goal: Service Development FY Goals, Strategies and Projects Last Updated June 20, MANAGEMENT ACTION PLAN (MAP) Goal: Service Development Strategies (those highlighted in bold indicate highest priority) 1. Provide routes and services

More information

FISCAL YEARS 2017 & 2018 TWO-YEAR UNIFIED PLANNING WORK PROGRAM (UPWP) AND BUDGET

FISCAL YEARS 2017 & 2018 TWO-YEAR UNIFIED PLANNING WORK PROGRAM (UPWP) AND BUDGET FISCAL YEARS 2017 & 2018 TWO-YEAR UNIFIED PLANNING WORK PROGRAM (UPWP) AND BUDGET Adoption Date: May 3, 2016 Effective: July 1, 2016 Modified: December 6, 2016 Amended: May 2, 2017 Prepared by the Hillsborough

More information

Metro Transit Police Department Riders Advisory Council Meeting September 21, 2011

Metro Transit Police Department Riders Advisory Council Meeting September 21, 2011 Metro Transit Police Department Riders Advisory Council Meeting September 21, 2011 Chief Michael Taborn Metro Transit Police Department 1 Metro Transit Police Department MISSION The mission of the Metro

More information

Needs & Opportunities Review

Needs & Opportunities Review Needs & Opportunities Review Preliminary lists created by the Steering Committee Your input will help prioritize items that should be pursued or addressed as part of this plan Place dots besides the highest

More information

Corporate Services Employment Report: January Employment by Staff Group. Jan 2018 (Jan 2017 figure: 1,462) Overall 1,

Corporate Services Employment Report: January Employment by Staff Group. Jan 2018 (Jan 2017 figure: 1,462) Overall 1, Corporate Services Employment Report: January Employment by Staff Group Jan (Jan 20 figure: 1,462) Jan % Overall 1,520 +58 +4.0% 8 Management (VIII+) 403 +52 4.8% Clerical & Supervisory (III to VII) 907

More information

Project ENABLE - Alameda County Community Capacity Fund. Project Blueprint. March 5, 2015

Project ENABLE - Alameda County Community Capacity Fund. Project Blueprint. March 5, 2015 Project ENABLE - Alameda County Community Capacity Fund Project Blueprint March 5, 2015 Table of Contents Executive Summary Project Objectives Current status of Sustainable Organizations Characteristics

More information

Steering Committee Meeting #1 March 31, 2016

Steering Committee Meeting #1 March 31, 2016 North Shore Transit Service Coordination Plan Steering Committee Meeting #1 March 31, 2016 Today s Meeting Welcome Introductions Project Overview Project Schedule Outreach Highlights Research Plan Highlights

More information

Seawall Earthquake Safety + Disaster Prevention Program Community Meeting June 21, 2018

Seawall Earthquake Safety + Disaster Prevention Program Community Meeting June 21, 2018 Seawall Earthquake Safety + Disaster Prevention Program Community Meeting June 21, 2018 WELCOME! This is our first Seawall Community Meeting, so, we ll start at the beginning Tonight, I will present a

More information

Table of Contents. Page 2

Table of Contents. Page 2 Sixth Avenue Transportation Demand Management Construction Mitigation Plan August 2014 Table of Contents Table of Contents... 2 1.0 Introduction... 3 Development of Recommendations... 6 2.0 Recommendations...

More information

San Francisco Transportation Plan (SFTP) and Early Action Plan

San Francisco Transportation Plan (SFTP) and Early Action Plan San Francisco Transportation Plan (SFTP) and Early Action Plan October 2013 SAN FRANCISCO COUNTY TRANSPORTATION AUTHORITY Purpose of the San Francisco Transportation Plan (SFTP) Regional Transportation

More information

Welcome SUPT Students

Welcome SUPT Students Welcome SUPT Students Welcome to Specialized Undergraduate Pilot Training. Please take advantage of this welcome package we have provided for you. If you have any additional questions, feel free to call

More information

Grant Writing for Mobility Management

Grant Writing for Mobility Management Grant Writing for Mobility Management NCMM Mission The mission of the National Center for Mobility Management (NCMM) is to facilitate activities that will help communities to adopt transportation strategies

More information

MID-HUDSON VALLEY TRANSPORTATION MANAGEMENT AREA JOB ACCESS AND REVERSE COMMUTE & NEW FREEDOM PROGRAMS GRANT APPLICATION.

MID-HUDSON VALLEY TRANSPORTATION MANAGEMENT AREA JOB ACCESS AND REVERSE COMMUTE & NEW FREEDOM PROGRAMS GRANT APPLICATION. MID-HUDSON VALLEY TRANSPORTATION MANAGEMENT AREA JOB ACCESS AND REVERSE COMMUTE & NEW FREEDOM PROGRAMS GRANT APPLICATION January 2009 O C T C Introduction The three transportation councils within the Mid-Hudson

More information

SFTP Technical Advisory Committee September 19, 2012

SFTP Technical Advisory Committee September 19, 2012 09.19.12 SFTP Technical Advisory Committee September 19, 2012 SFTP Community Advisory Committee Rachel Hiatt Senior Transportation Planner Draft SFTP Project Performance Evaluation Results The SFTP Project

More information

Implementation Status & Results Nigeria Lagos Urban Transport Project 2 (P112956)

Implementation Status & Results Nigeria Lagos Urban Transport Project 2 (P112956) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Nigeria Lagos Urban Transport Project 2 (P112956) Operation Name: Lagos Urban Transport Project

More information

CONNECTED CITY FREQUENTLY ASKED QUESTIONS

CONNECTED CITY FREQUENTLY ASKED QUESTIONS 1) What is the Connected City project? CONNECTED CITY FREQUENTLY ASKED QUESTIONS The Connected City Corridor is a State-initiated pilot program that is unique to Pasco County, and will be the first planned

More information

Transportation Demand Management (TDM)

Transportation Demand Management (TDM) DEVELOPMENT OF A REGIONAL TRANSPORTATION PLAN FOR THE GREATER TORONTO AND HAMILTON AREA Transportation Demand Management (TDM) Presentation to Metrolinx Board February 8, 2008 TDM Primer TDM is the use

More information

Meeting Minutes. Project: Subject: Date: Wednesday, December 16, 2015 Location: Attendees:

Meeting Minutes. Project: Subject: Date: Wednesday, December 16, 2015 Location: Attendees: Meeting Minutes Project: Subject: DART D2 Stakeholder Work Group for D2 Date: Wednesday, December 16, 2015 Location: Attendees: DART, 1401 Pacific Avenue, Dallas, TX Steve Salin, DART Ernie Martinez, DART

More information

+! % / 0/ 1 2, 2 2, 3 1 ",, 4 +! % # ! 2, $

+! % / 0/ 1 2, 2 2, 3 1 ,, 4 +! % # ! 2, $ Lakeland Vision is an independent, non-profit organization. It was formed in 1998 with the goal of creating and implementing a comprehensive, action-oriented vision for the future of the greater Lakeland

More information

Annual Report on Funding Recommendations

Annual Report on Funding Recommendations Annual Report on Funding Recommendations Fiscal Year 2019 Capital Investment Grants Program Report of the Secretary of Transportation to the United States Congress Pursuant to 49 USC 5309(o)(1) and Section

More information

Summary Report Evaluation of the Measures of Effectiveness in the MPO s Adopted Public Participation Plan (PPP)

Summary Report Evaluation of the Measures of Effectiveness in the MPO s Adopted Public Participation Plan (PPP) Evaluation of the Measures of Effectiveness in the MPO s Adopted Public Participation Plan (PPP) Evaluation Period is March 2010 to August 2013 November 2013 Pasco County Metropolitan Planning Organization

More information

APA/PAW 2013 Joint Awards Program Submittal

APA/PAW 2013 Joint Awards Program Submittal May 30, 2013 APA/PAW Awards Committee Washington APA Office 603 Stewart Street, Suite 610 Seattle, WA 98101 Dear APA/PAW Awards Committee: RE: APA/PAW 2013 Joint Awards Program Submittal Enclosed is a

More information

Cal Poly Pomona Request for Clarification for Lanterman Development Center Land Development Consultant RFC

Cal Poly Pomona Request for Clarification for Lanterman Development Center Land Development Consultant RFC Cal Poly Pomona Request for Clarification for Lanterman Development Center Land Development Consultant RFC 16-006 A. INTRODUCTION California State Polytechnic University, Pomona ( Cal Poly Pomona ), is

More information

Quarterly Progress Report on Strategic Initiatives July to September 2013

Quarterly Progress Report on Strategic Initiatives July to September 2013 Quarterly Progress Report on Strategic Initiatives July to September 2013 July to September 2013 Quarterly Progress Report Page 1 Table of Contents A. Executive Summary... 4 B. Initiatives and at a Glance...

More information

Quality Management Report 2017 Q2

Quality Management Report 2017 Q2 Quality Management Report 2017 Q2 Quality Management Program CMS STAR Ratings Member Satisfaction (CAHPS & HOS) HEDIS Risk Adjustment DHS Member Incident Reporting Member Satisfaction Surveys Pay for Performance

More information

Colorado Medical-Dental Integration Project (CO MDI)

Colorado Medical-Dental Integration Project (CO MDI) Colorado Medical-Dental Integration Project (CO MDI) Allison Cusick, MPA, CHES National Oral Health Conference April 2016 Colorado Medical-Dental Integration CO MDI Five-Year Initiative Launched in 2014

More information

Draft CRA Plan Amendment. Community Redevelopment Agency Advisory Board September 23, CRA Plan Amendment

Draft CRA Plan Amendment. Community Redevelopment Agency Advisory Board September 23, CRA Plan Amendment Draft Community Redevelopment Agency Advisory Board September 23, 2013 1 Project Scope Feasibility Study Public Workshops/Stakeholder Interviews Market Study 2 Schedule to Date Feasibility Study Community

More information

National Transport Development Policy Committee (NTDPC)

National Transport Development Policy Committee (NTDPC) National Transport Development Policy Committee (NTDPC) Presentation on Urban Transport International Lessons: The Lagos Experience By Dr Dayo Mobereola MD/CEO Lagos Metropolitan Area Transport Authority

More information

Tentative Project Schedule. Non-Discrimination i i Laws. Para Preguntas en español

Tentative Project Schedule. Non-Discrimination i i Laws. Para Preguntas en español Florida Department of Transportation, District Seven Project Newsletter Number 1 October 2012 The Florida Department of Transportation (FDOT) is conducting a Project Development & Environment (PD&E) study