1 An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Guidance Notes for Applying for a Licence to Generate Electricity Information Paper Reference: Date Published: January

2 Table of Contents Introduction... 2 Application Validity CRU Acceptance/Rejection Criteria... 4 CRU Assessment and Applicant Updates... 4 Additional Information Requests... 5 CRU Decision Making process... 6 Terms and Conditions of a Generation Licence... 6 When should I apply?... 6 How long will it take to consider my application?... 6 Format of Submission and application Fee... 7 Confidentiality of information submitted... 8 Further information on the Irish electricity market... 9

3 Introduction These guidance notes are to assist applicants in applying for a Licence to Generate Electricity. They should be read in conjunction with the Commission for Regulation of Utilities (CRU) application form that is applicable to the project. 1.1 Legislative Background Grant/Refuse Authorisations and Licences The Electricity Regulation Act, 1999 as amended (the Act) gives CRU the necessary powers to licence and regulate the generation, distribution, transmission and supply of electricity in Ireland. One of the functions of CRU under the Act is to grant or refuse Licences to Generate Electricity (a Licence) following assessment of an associated application. All electricity generators must hold a Licence under the Act. It is an offence to generate electricity prior to obtaining a Licence from CRU. On conviction, a person may be liable to a fine up to 1,904, imprisonment for a term not exceeding 12 months, or both. Authorisations to construct or reconstruct generating stations (Authorisations) are also issued by CRU and separate Authorisation Guidance Notes are available at Joint application forms are used for both Authorisations and Licences Environmental Assessment The European Union (EU) (Birds and Natural Habitats) Regulations 2011 (S.I. 477 of 2011) (as amended) implement the EU Habitats Directive (92/43/EEC) and EU Birds Directive (2009/147/EC). Under the European Union (EU) (Birds and Natural Habitats) Regulations 2011 (as amended) the CRU is defined as a public authority. Regulation 42 of the EU (Birds and Natural Habitats) Regulations 2011 (as amended) outlines the obligations on public authorities in relation to Appropriate Assessment (AA). All projects seeking an Authorisation to Construct or Reconstruct and/or a Licence to Generate in order to generate electricity are required to undergo AA screening and/or AA. 2

4 1.2 Exemption for <1MW Generating Stations If a proposed generating station has an installed capacity of less than or equal to 1MW then applicants are exempted from the need to apply to CRU for a Licence. Such generating stations stand licensed pursuant to S.I 384 of S.I. No. 384/2008 Electricity Regulation Act 1999 (Section 14 (1A)) Order

5 Application Validity CRU Acceptance/Rejection Criteria CRU has developed application forms and guidance documents to assist applicants in developing a valid application. The relevant application forms and guidance documents are available at On receipt of an application, the CRU assessment team will carry out a Completeness Check to confirm that the application is valid. Should CRU receive an invalid application i.e. missing documentation or an incomplete application form, it will inform the applicant in writing that their application is incomplete and will not be processed. A written list of the incomplete sections will be provided to support the applicant s development of a new and valid application. To avoid the potential for submission of an invalid application, new applicants are encouraged to contact CRU via licensing@cru.ie to request a pre submission meeting. At this pre submission meeting, CRU will set out the application and assessment process and answer any questions the applicant may have. Additionally, the CRU completeness check template is provided in Appendix 1 to assist applicants in developing valid applications.applicants should note that updating their application mid assessment will delay the CRU assessment process and may necessitate a full reassessment. It may also invalidate the original application and result in the requirement for a full new application. The decision to require a new application or recommence an assessment will be made on a case by case basis and is fully at the discretion of CRU. CRU Assessment and Applicant Updates Once the application has passed the Completeness Check, the applicant will be notified that the assessment has formally commenced. A CRU application reference number will be assigned for assessment and this should be used in all correspondence with CRU. The assessment will cover the following disciplines: (a) Administrative; (b) Technical; (c) Environmental; and (d) Financial. 4

6 To keep applicants aware of assessment progress, fortnightly Assessment Progress Reports will be issued by CRU for the duration of the assessment. An Assessment Progress Report template is provided in Appendix 2. Should an applicant require information that is not contained in the Assessment Progress Report, they may submit a request for information to CRU by via licensing@cru.ie. During the assessment, CRU may require Additional Information from the applicant to support their application, or to clarify information already submitted. These requests will be issued within the Assessment Progress Report. Where matters arise that have the potential to result in a refusal of an application, the applicant will be informed at the earliest opportunity to afford them the time to address the matter through the submission of Additional Information. Additional Information Requests As outlined above, CRU may require Additional Information from the applicant to progress the application, or to clarify information already submitted. Examples of Additional Information that may be requested include: Environmental - Specific chapters of the Environmental Impact Assessment Report (EIAR), Environmental Impact Statement (EIS) or Environmental Report (ER) that are relevant too and may help to inform the Appropriate Assessment; - Post-approval documentation that has been supplied to the planning authority that might include but is not limited to habitat restoration plans/management plans, species protection plans or other planning compliance documentation relating to ecology; and - Copies of correspondence/consultation with relevant authorities such as NPWS, IFI or local authority Biodiversity Officer. 5

7 CRU Decision Making process If CRU determines a Licence should be granted, the applicant will be issued with a soft and hard copy of the signed Licence. If CRU decides to refuse a Licence application, the applicant will be notified in writing of the reasons for the refusal and will be informed of the appeals process as per Part IV, Sections 29 to 32 of the 1999 Act. Please note that the appeals process is external to CRU procedure. In granting a Licence, the CRU is not endorsing the plans of a generating station and it cannot be relied upon as an indication of the likely commercial success or otherwise of its holder. Terms and Conditions of a Generation Licence A Licence is valid for a minimum of 30 years, subject to the Licence holder complying with the terms and conditions of the Licence. This 30 year period includes a 15 year initial term and the potential for CRU to issue a 15 year notice of termination of the Licence. CRU may revoke a Licence if the holder fails to comply with the terms and conditions. The revocation terms of the Licence are detailed in Schedule 2 of the Licence. Details of other terms and conditions of a generation Licence can be found in the Licence. When should I apply? Applicants can apply as soon as they have all the CRU required information. Where a joint application for and Authorisation and a Licence is not submitted, applicants must hold an Authorisation from CRU prior to submitting their Licence application. How long will it take to consider my application? CRU aims to meet the following application assessment timelines: Assessment steps Acknowledge receipt of application Timeline Within 1 week of receiving application 6

8 Completeness Check Assessment CRU final decision making process Within 2 weeks of receiving application Up to 16 weeks* 2 weeks following completion of assessment *The assessment timelines are dependent on a number of factors, including: 1. Applicant response times to Additional Information requests; and 2. The location and ecological sensitivities 2 in the vicinity of the proposed generating station. Format of Submission and application Fee A checklist of all documents applicants should enclose with the completed application form can be found in Appendix 1. The application form also details these required documents. All documentation should be submitted electronically to licensing@cru.ie. Files that are too large to be submitted by should be submitted by CD to: Commission for Regulation of Utilities Generation Licensing Section The Grain House The Exchange Belgard Square North Tallaght Dublin 24 D24 PXW0 2 With reference to the Appropriate Assessment process 7

9 The application fee must be paid at time of submission of the application. Payment will only be accepted by Electronic Funds Transfer (EFT). The CRU bank details are: IBAN: IE91AIBK BIC: AIBKIE2D The application fees involved are banded according to the proposed installed capacity of the proposed generating station. The fees are set out below. Installed Capacity 1MW to < 5MW 35 5MW to <15MW 55 15MW to < 40MW MW to < 50MW MW to < 100MW MW to < 200MW 1, MW to < 500MW 3, MW and greater 3,980 Installed capacity refers to the normal full load MW capacity of the generation unit (or the sum of the normal full load MW capacities of all generation units associated with the application) as stated on the generation unit nameplate(s). For the avoidance of doubt, the installed capacity is to include the MW consumed by generation unit auxiliary plant directly supplied from the generation unit terminals and other site load directly supplied by the generation unit(s) prior to connection with the transmission and/or distribution systems. Confidentiality of information submitted Information provided in an application form and supporting documents will be covered by Section 13 (Prohibition on unauthorised disclosure of information) of the Act. However, CRU and the information we hold is covered by the Freedom of Information Act, 1997 and legislation on the European Communities (Access to Information on the Environment) Regulations 2007 to 2014 (AIE Regulations). Details of the information we will publish can be seen on the CRU website. 8

10 Further information on the Irish electricity market There are a number of websites that can provide applicants with information about developments in the Irish electricity market including: CRU: Regulatory Information: SEMO: Market Information: EirGrid: Connection Matters Gas Networks Ireland: Connection Matters SEAI: Sustainable Energy: DCCAE: REFIT Renewable Subsidies: 9

11 APPENDIX 1: APPLICATION CHECK LISTS GENERATION LICENCE <40MW CRU COMPLETENESS CHECKLIST Date Received: Date of Completeness Check: 1. Application Form Signed and complete application form 2. Application Fee Proof of payment of application fee. The application fee must be paid at the time of submission of the application by EFT. 3. Financial Information Evidence of finance. Where internally funded, proof of available funds from balance sheets is acceptable. For third party finance, a letter of commitment from a financial institution is acceptable, or where shareholders are providing finance the supporting contract documents. Copy of signed and dated letter of offer for REFIT for the proposed generating station. 4. Location of Generating Station Map(s) or marine chart(s) sufficient to identify the location of the proposed generating station. 5. Planning Permission Final grant of planning permission or confirmation of planning exemption from the planning authority. 6. Connection Agreement Proof of connection agreement or proof of application for a connection agreement from the transmission system operator or distribution system operator for the proposed generating station. This must include a reference number and MEC. 7. Technical Information C.V. or equivalent showing the qualifications and experience of the person or company who will operate the proposed generating station. 8. Environmental Information 10

12 APPENDIX 1: APPLICATION CHECK LISTS All Appropriate Assessment (AA) related documentation provided in support of the application. This includes: Up-to-date information in support of AA Screening and/or AA for all elements of the application to CRU that provides a robust scientific assessment of the potential impacts of the proposed project, both alone and in-combination with other plans, projects and land use changes. This might include an AA Screening Report and Natura Impact Statement (NIS) and all associated figures and appendices. Where applicable, all information relevant to the AA process supplied to the planning authority in response to any requests for further information/clarifications at the planning and/or planning appeal stage (including any addendums to AA Screening and NIS). All of the above should be provided as a single pdf, inclusive of all figures and appendices and should be clearly labelled. Where the AA documentation has cross referenced to information outlined in an Environmental Impact Assessment Report (EIAR)/Environmental Impact Statement (EIS) or Environmental Report (ER) prepared for the proposed project, a copy of this information must be provided, including all associated figures and appendices. This usually includes but is not limited to the Flora & Fauna (Biodiversity), Water/Hydrology and Soils chapters of EIARs/EISs/ERs. All of the above should be provided as a single pdf, inclusive of all figures and appendices and should be clearly labelled. The submission of additional information may be requested by CRU at any stage of the assessment process. 11

13 APPENDIX 1: APPLICATION CHECK LISTS GENERATION LICENCE >40MW DOCUMENT CRU CHECKLIST COMPLETENESS CHECK Date Received: Date of Completeness Check: 1. Application Form Signed and complete application form. 2. Application Fee Proof of payment of application fee. The application fee must be paid at the time of submission the application by EFT. 3. Financial Information Statements of the accounts for the last two years kept by the applicant in respect of relevant undertakings carried on by the applicant, showing the financial state of affairs of that undertaking and its profit or loss, together with copies of the latest audited accounts If more than three months have elapsed since the end of the accounting year covered by the accounts submitted, a certificate from the applicant stating no material adverse change has occurred. Where the applicant is a special purpose vehicle, a statement or relevant parent company accounts and guarantees. Copy of signed and dated offer of REFIT for the proposed generating station. An outline statement of the proposals for the business of the applicant to which the application relate, for the next five years, including; Annual forecasts of costs, sales and revenues and project financing, stating the assumptions underlying the figures provided. Details of any expected subsequent substantial capital outflows, including major decommissioning costs Estimates of net annual cash flows for subsequent periods sufficient to demonstrate the financial security and feasibility of the project(s) to which the application relates Information on the intended source of finance and (were relevant) confirmation from the relevant lender(s). 12

14 APPENDIX 1: APPLICATION CHECK LISTS 4. Location of generating station(s) Map(s) or marine chart(s) sufficient to identify the location of all generating stations to which the application relates. 5. Planning Permission Final grant of planning permission or confirmation of planning exemption from planning authority. 6. Connection agreement offer Proof of connection agreement or application for a connection agreement from the transmission system operator or distribution system operator for the proposed generating station. This must include a reference number and MEC. 7. Environmental Information All Appropriate Assessment (AA) related documentation provided in support of the application. This includes: Up-to-date information in support of AA Screening and/or AA for all elements of the application to CRU that provides a robust scientific assessment of the potential impacts of the proposed project, both alone and in-combination with other plans, projects and land use changes. This might include an AA Screening Report and Natura Impact Statement (NIS) and all associated figures and appendices. Where applicable, all information relevant to the AA process supplied to the planning authority in response to any requests for further information/clarifications at the planning and/or planning appeal stage (including any addendums to AA Screening and NIS). All of the above should be provided as a single pdf, inclusive of all figures and appendices and should be clearly labelled. Where the AA documentation has cross referenced to information outlined in an Environmental Impact Assessment Report (EIAR)/Environmental Impact Statement (EIS) or Environmental Report (ER) prepared for the proposed project, a copy of this information must be provided, including all associated figures and appendices. This usually includes but is not limited to the Flora & Fauna (Biodiversity), Water/Hydrology and Soils chapters of EIARs/EISs/ERs. All of the above should be provided as a single pdf, inclusive of all figures and appendices and should be clearly labelled. 13

15 APPENDIX 1: APPLICATION CHECK LISTS 8. Technical Information C.V. or company profile showing the qualifications and experience of the person or company who will operate the proposed generating station 9. Construction Timeline Construction and commissioning programme, identifying the major milestones in the project development, from authorisation to completion. The submission of additional documents may be requested by CRU at any stage of the assessment process. Note All applicants are advised that in order to trade in the market, in addition to holding the necessary Licences from the CRU, accession to the Trading and Settlement Code is required. Applications for market accession are to be made to the Single Electricity Market Operator (SEM-O) once the relevant Licences from the CRU have issued. To facilitate timely accession to the market, applications should be made as early as possible. Please contact the SEM-O Market Registration team at or by telephone at for information on this process. 14

16 APPENDIX 2: ASSESSMENT PROGRESS REPORTS GENERATION LICENCE ASSESSMENT PROGRESS REPORT CRU APPLICATION REFERENCE: GENERATING STATION NAME: DATE RECEIVED: ASSESSMENT AREA PROGRESS REPORTS Assessment Area Progress Report Additional Information request Administrative e.g. in process e.g. Technical e.g. complete Environmental e.g. in process e.g. please provide an updated cumulative impact assessment that assesses the impact of the proposed project other land use types and plans/projects. Financial e.g. in process Response to all Additional Information requests must be made electronically to Please note that a delay in responding to Additional Information requests may result in a delay to the overall assessment timeline. Applicants must insert the CRU application reference number into the subject line on all correspondence. 15

17 16

Ocean Energy Prototype Research and Development. Programme Application Guide

Ocean Energy Prototype Research and Development. Programme Application Guide Ocean Energy Prototype Research and Development Programme Application Guide IMPORTANT NOTICES It is the responsibility of each applicant to ensure that they have read, and fully understand, this Application

More information

Home Energy Saving (HES) scheme - Homeowner Application Form Version 10.0

Home Energy Saving (HES) scheme - Homeowner Application Form Version 10.0 Home Energy Saving (HES) scheme - Homeowner Application Form Version 10.0 Instructions for Completing the Application Form All fields in the form are MANDATORY. Incomplete applications will be returned.

More information

Ocean Energy Prototype Research and Development Programme. Application Guide. Date: 18/2/2015

Ocean Energy Prototype Research and Development Programme. Application Guide. Date: 18/2/2015 Ocean Energy Prototype Research and Development Programme Application Guide Date: 18/2/2015 This programme is supported by the Sustainable Energy Authority of Ireland (SEAI). SEAI is partly financed by

More information

Application Form. Green Infrastructure Fund

Application Form. Green Infrastructure Fund Application Form Green Infrastructure Fund January 2016 Application Form For guidance on completing this form, please refer to the Green Infrastructure Fund Application Form Guidance which explains the

More information

Home Energy Saving (HES) scheme - Homeowner Application Form Version 1.0

Home Energy Saving (HES) scheme - Homeowner Application Form Version 1.0 Home Energy Saving (HES) scheme - Homeowner Application Form Version 1.0 Instruction for Completing the Application Form All fields in the form are MANDATORY. Incomplete applications will be returned.

More information

Application Form Green Infrastructure Fund

Application Form Green Infrastructure Fund Application Form Green Infrastructure Fund Round 2 July 2016 Application Form For guidance on completing this form, please refer to the Green Infrastructure Fund Application Form Guidance which explains

More information

Community Update Brochure

Community Update Brochure North-South 400kV Interconnection Development Community Update Brochure June 2015 Part Funded by the EU-TEN-E Initiative Application for Planning Approval to An Bord Pleanála Project Background The North-South

More information

Enduring Connection Policy Stage 1 (ECP-1)

Enduring Connection Policy Stage 1 (ECP-1) An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Enduring Connection Policy Stage 1 (ECP-1) Proposed Ruleset Annex I to the ECP-1 Proposed Decision Reference: CRU/17/310 Date Published:

More information

Northern Ireland Social Care Council. NISCC (Registration) Rules 2017

Northern Ireland Social Care Council. NISCC (Registration) Rules 2017 Northern Ireland Social Care Council NISCC (Registration) Rules 2017 April 2017 Produced by: Northern Ireland Social Care Council 7 th Floor, Millennium House 19-25 Great Victoria Street Belfast BT2 7AQ

More information

Tender 1/2018 Request for Existing Plant Pre-Qualification for the Power 2022 Procurement Process

Tender 1/2018 Request for Existing Plant Pre-Qualification for the Power 2022 Procurement Process Tender 1/2018 Request for Existing Plant Pre-Qualification for the Power 2022 Procurement Process Oman Power and Water Procurement Company SAOC 3 September 2018 Addendum 1 to the REPPQ NERA Economic Consulting

More information

Application for Recognition or Expansion of Recognition

Application for Recognition or Expansion of Recognition Application for Recognition or Expansion of Recognition Notes for applicants All Applicants Should Read This Section This form is for applicants who are: o applying to become a recognised awarding organisation

More information

Application form for Commissioning Generation Facility Registration by a Market Participant. including explanatory notes

Application form for Commissioning Generation Facility Registration by a Market Participant. including explanatory notes Application form for Commissioning Generation Facility Registration by a Market Participant including explanatory notes IMPORTANT: Please read this carefully before completing this form. Italicised words

More information

Project Assistance Grants for Energy Saving Projects. Application Guide

Project Assistance Grants for Energy Saving Projects. Application Guide Application Guide 6th February 2017 i Contents 1 BACKGROUND & INTRODUCTION... 2 2 GRANT FOR FEASIBILITY STUDY & PROJECT ENERGY AUDIT... 6 3 GRANTS FOR FINAL BUSINESS CASE & PROJECT DELIVERY SUPPORT...

More information

Asylum Migration and Integration Fund

Asylum Migration and Integration Fund Asylum Migration and Integration Fund Call for Proposals 2016 Information and Guidance for Applicants EUROPEAN UNION Asylum, Migration and Integration Fund Table of Contents Section 1. Overview of Call

More information

COMMERCIALISATION FUND PROGRAMME Reference Document

COMMERCIALISATION FUND PROGRAMME Reference Document COMMERCIALISATION FUND PROGRAMME Reference Document PROGRAMME OVERVIEW The aim of the Commercialisation Fund programme is to improve the competitiveness of the Irish economy through the creation of technology

More information

NIGERIAN ELECTRICITY REGULATORY COMMISSION SCHEDULE 2 APPLICATION FORM FOR A LICENCE. (Pursuant to S.70 Electric Power Sector Reform Act, 2005)

NIGERIAN ELECTRICITY REGULATORY COMMISSION SCHEDULE 2 APPLICATION FORM FOR A LICENCE. (Pursuant to S.70 Electric Power Sector Reform Act, 2005) NIGERIAN ELECTRICITY REGULATORY COMMISSION SCHEDULE 2 APPLICATION FORM FOR A LICENCE (Pursuant to S.70 Electric Power Sector Reform Act, 2005) IMPORTANT NOTE: Your Application is incomplete unless all

More information

STANDARD GRANT APPLICATION FORM 1 REFERENCE NUMBER OF THE CALL FOR PROPOSALS: 2 TREN/SUB

STANDARD GRANT APPLICATION FORM 1 REFERENCE NUMBER OF THE CALL FOR PROPOSALS: 2 TREN/SUB STANDARD GRANT APPLICATION FORM 1 PROGRAMME CONCERNED: 2 ACTIONS IN THE FIELD OF URBAN MOBILITY REFERENCE NUMBER OF THE CALL FOR PROPOSALS: 2 TREN/SUB 02-2008 [Before filling in this form, please read

More information

Radiation Protection Adviser (RPA) Register

Radiation Protection Adviser (RPA) Register Radiation Protection Adviser (RPA) Register Application Guidelines for Approval by the EPA for Inclusion on the RPA Register to an undertaking involved in the practice of medicine, dentistry, chiropractic

More information

MEDICINES FOR HUMAN USE (CLINICAL TRIALS) REGULATIONS Memorandum of understanding between MHRA, COREC and GTAC

MEDICINES FOR HUMAN USE (CLINICAL TRIALS) REGULATIONS Memorandum of understanding between MHRA, COREC and GTAC MEDICINES FOR HUMAN USE (CLINICAL TRIALS) REGULATIONS 2004 Memorandum of understanding between MHRA, COREC and GTAC 1. Purpose and scope 1.1 Regulation 27A of the Medicines for Human Use (Clinical Trials)

More information

The Nursing and Midwifery Order 2001 (SI 2002/253)

The Nursing and Midwifery Order 2001 (SI 2002/253) The Nursing and Midwifery Order 2001 (SI 2002/253) Unofficial consolidated text Effective from 28 July 2017 This consolidated text has been produced for internal use by the Nursing and Midwifery Council.

More information

Guidance Notes Applying for registration online

Guidance Notes Applying for registration online Guidance Notes Applying for registration online An Chomhairle um Ghairmithe Sláinte agus Cúraim Shóisialaigh Health and Social Care Professionals Council December 2017 Important Please read these guidance

More information

Home Energy Saving scheme. Application Guide Version 1.1

Home Energy Saving scheme. Application Guide Version 1.1 Home Energy Saving scheme Application Guide Version 1.1 IMPORTANT NOTICE It is the responsibility of each applicant to the Home Energy Saving scheme to ensure that they have read, and fully understand,

More information

2017 All Source Request for Proposals for Electric Power Supply and Load Management Resources. Pre-Bid Meeting

2017 All Source Request for Proposals for Electric Power Supply and Load Management Resources. Pre-Bid Meeting 2017 All Source Request for Proposals for Electric Power Supply and Load Management Resources Pre-Bid Meeting July 19, 2017 2:00 PM MST 100 N. Stanton Safety and Basics Emergency Escape Routes Facilities

More information

Updated May 2017 University College Dublin Ad Astra Academy Elite Sports Scholarships TERMS AND CONDITIONS

Updated May 2017 University College Dublin Ad Astra Academy Elite Sports Scholarships TERMS AND CONDITIONS Updated May 2017 University College Dublin Ad Astra Academy Elite Sports Scholarships TERMS AND CONDITIONS The UCD Ad Astra Academy Elite Sports Scholarship programme provides support to athletes in pursuit

More information

Registration process for designated centres

Registration process for designated centres Registration process for designated centres Frequently Asked Questions 1. Why has the Authority changed its registration process? Responsible regulators are accountable to the public for the efficiency

More information

Incentive Guidelines Research and Development - Tax Credits INDUSTRIAL RESEARCH PROJECTS; EXPERIMENTAL DEVELOPMENT PROJECTS; INTELLECTUAL PROPERTY

Incentive Guidelines Research and Development - Tax Credits INDUSTRIAL RESEARCH PROJECTS; EXPERIMENTAL DEVELOPMENT PROJECTS; INTELLECTUAL PROPERTY Incentive Guidelines Research and Development - Tax Credits INDUSTRIAL RESEARCH PROJECTS; EXPERIMENTAL DEVELOPMENT PROJECTS; INTELLECTUAL PROPERTY RIGHTS COSTS (FOR SMALL AND MEDIUM-SIZED ENTERPRISES).

More information

25/02/18 THE SOCIAL CARE WALES (REGISTRATION) RULES 2018

25/02/18 THE SOCIAL CARE WALES (REGISTRATION) RULES 2018 25/02/18 THE SOCIAL CARE WALES (REGISTRATION) RULES 2018 April 2018 The regulation of the registration and fitness to practise of the social care workforce by Social Care Wales is governed by three types

More information

Council, 25 September 2014

Council, 25 September 2014 Council, 25 September 2014 Directive 2013/55/EU the revised Recognition of Professional Qualifications (RPQ) Directive challenges and opportunities for the Health and Care Professions Council (HCPC) Executive

More information

REGISTERED NURSES ACT REGISTRATION AND LICENSING OF NURSES REGULATIONS

REGISTERED NURSES ACT REGISTRATION AND LICENSING OF NURSES REGULATIONS c t REGISTERED NURSES ACT REGISTRATION AND LICENSING OF NURSES REGULATIONS PLEASE NOTE This document, prepared by the Legislative Counsel Office, is an office consolidation of this regulation, current

More information

Request for Supplementary Tender (mini-competition)

Request for Supplementary Tender (mini-competition) Request for Supplementary Tender (mini-competition) HEA - SYSTEM OF ROLLING REVIEWS Review of Procurement Practices in HEA-funded Higher Education Institutions Terms of Reference Background As part of

More information

25/02/18 THE SOCIAL CARE WALES (REGISTRATION) RULES 2018

25/02/18 THE SOCIAL CARE WALES (REGISTRATION) RULES 2018 25/02/18 THE SOCIAL CARE WALES (REGISTRATION) RULES 2018 April 2018 0 The regulation of the registration and fitness to practise of the social care workforce by Social Care Wales is governed by three types

More information

MARKET PROCEDURE: FACILITY REGISTRATION, DE-REGISTRATION AND TRANSFER

MARKET PROCEDURE: FACILITY REGISTRATION, DE-REGISTRATION AND TRANSFER MARKET PROCEDURE: FACILITY REGISTRATION, DE-REGISTRATION AND TRANSFER PREPARED BY: Market Operations (WA) DOCUMENT REF: VERSION: 5.0 EFFECTIVE DATE: 18 April 2017 STATUS: FINAL Approved for distribution

More information

Indigenous Leadership Scholarship

Indigenous Leadership Scholarship Section A Personal and Contact Details APPLICANT DETAILS The Australian Uranium Association Indigenous Leadership Scholarship APPLICATION FORM Mr / Mrs / Ms / Miss / Other (please specify)... Family Name...

More information

How to register under the Health and Social Care Act 2008

How to register under the Health and Social Care Act 2008 A new system of registration How to register under the Health and Social Care Act 2008 Guidance for new October 2010 Introduction This guidance is for all new who are required to register under the Health

More information

Call for Submission of Proposals

Call for Submission of Proposals SCIENCE FOUNDATION IRELAND SFI FELLOWSHIP PROGRAMME Call for Submission of Proposals KEY DATES Initial Call announcement 9th May 2016 Deadline for submission of proposals 30 th November 2017 Terms of Reference

More information

Guidelines on completing and submitting Banking Licence Applications

Guidelines on completing and submitting Banking Licence Applications 2014 Guidelines on completing and submitting Banking Licence Applications Guidelines on completing and submitting Banking Licence Applications 1 Contents Introduction 2 Exploratory Phase 3 Submission of

More information

Stroke in Young Adults Funding Opportunity for Mid- Career Researchers. Guidelines for Applicants

Stroke in Young Adults Funding Opportunity for Mid- Career Researchers. Guidelines for Applicants Stroke in Young Adults Funding Opportunity for Mid- Career Researchers Guidelines for Applicants 1 Summary This document guides you through the preparation and submission of an application for the Stroke

More information

UPDATE: Regulatory Framework for Medical Devices in South Africa. SAMED Annual Conference. 14 June 2018 Jerry Molokwane

UPDATE: Regulatory Framework for Medical Devices in South Africa. SAMED Annual Conference. 14 June 2018 Jerry Molokwane UPDATE: Regulatory Framework for Medical Devices in South Africa SAMED Annual Conference 14 June 2018 Jerry Molokwane Medicines and Related Substances Act, 1965 (Act 101 of 1965) Act 72 of 2008 and Act

More information

Incentive Guidelines Business START

Incentive Guidelines Business START Incentive Guidelines Business START Issue Date: 1 st June 2015 Update: 1 st July 2016 Version: 3 http://support.maltaenterprise.com Malta Enterprise staff may support interested applicants to understand

More information

SEAI Research Development and Demonstration Funding Programme Budget Policy. Version: February 2018

SEAI Research Development and Demonstration Funding Programme Budget Policy. Version: February 2018 SEAI Research Development and Demonstration Funding Programme Budget Policy Version: February 2018 Contents Introduction... 2 Eligible costs... 2 Budget Categories... 3 Staff... 3 Materials... 3 Equipment...

More information

Government Scheme to provide Temporary Emergency Humanitarian Support to Community, Voluntary & Sporting Bodies

Government Scheme to provide Temporary Emergency Humanitarian Support to Community, Voluntary & Sporting Bodies Application No. Government Scheme to provide Temporary Emergency Humanitarian Support to Community, Voluntary & Sporting Bodies For Community, Voluntary & Sporting Bodies adversely affected by flooding

More information

Practice Review Guide

Practice Review Guide Practice Review Guide October, 2000 Table of Contents Section A - Policy 1.0 PREAMBLE... 5 2.0 INTRODUCTION... 6 3.0 PRACTICE REVIEW COMMITTEE... 8 4.0 FUNDING OF REVIEWS... 8 5.0 CHALLENGING A PRACTICE

More information

Registration under the Care Standards Act 2000

Registration under the Care Standards Act 2000 Registration under the Care Standards Act 2000 Guidance for new providers who are applying to register under the Independent Health Care (Wales) Regulations 2011 September 2017 1 Contents Introduction...

More information

COMMISSION IMPLEMENTING REGULATION (EU)

COMMISSION IMPLEMENTING REGULATION (EU) L 253/8 Official Journal of the European Union 25.9.2013 COMMISSION IMPLEMENTING REGULATION (EU) No 920/2013 of 24 September 2013 on the designation and the supervision of notified bodies under Council

More information

Terms & Conditions of Award

Terms & Conditions of Award PART 1 1. INTRODUCTION 1 Terms & Conditions of Award 1.1. Part 1 of this Terms & Conditions of Award document sets out the standard terms and conditions for all British Academy awards. Additional terms

More information

technical factsheet 182 School academies advice for auditors

technical factsheet 182 School academies advice for auditors technical factsheet 182 School academies advice for auditors INTRODUCTION The number of academies in England has increased drastically over the past few years -from 203 in 2010 to 1,957 by August 2012.

More information

Practice Review Guide April 2015

Practice Review Guide April 2015 Practice Review Guide April 2015 Printed: September 28, 2017 Table of Contents Section A Practice Review Policy... 1 1.0 Preamble... 1 2.0 Introduction... 2 3.0 Practice Review Committee... 4 4.0 Funding

More information

Request for Proposal

Request for Proposal Consolidated Edison Company of New York, Inc. Request for Proposal Non-Wires Solutions to Provide Demand Side Management for Subtransmission and Distribution System Load Relief West 42 nd Street Load Transfer

More information

Incentive Guidelines Innovation Clusters

Incentive Guidelines Innovation Clusters Incentive Guidelines Innovation Clusters Issue Date: 1 st June 2009 (updated 04/02/2014) Version: 1.1 http://support.maltaenterprise.com This incentive forms part of a group of R&D&I incentives under the

More information

NEBRASKA ENVIRONMENTAL TRUST BOARD RULES AND REGULATIONS GOVERNING ACTIVITIES OF THE NEBRASKA ENVIRONMENTAL TRUST

NEBRASKA ENVIRONMENTAL TRUST BOARD RULES AND REGULATIONS GOVERNING ACTIVITIES OF THE NEBRASKA ENVIRONMENTAL TRUST NEBRASKA ENVIRONMENTAL TRUST BOARD TITLE 137 RULES AND REGULATIONS GOVERNING ACTIVITIES OF THE NEBRASKA ENVIRONMENTAL TRUST February 2005 1 TITLE 137 RULES AND REGULATIONS GOVERNING ACTIVITIES OF THE NEBRASKA

More information

THIRD COUNTRY Route of Registration

THIRD COUNTRY Route of Registration THIRD COUNTRY Route of Registration Application Booklet for Registration as a Pharmacist under Section 14 and Section (2) (b) of the Pharmacy Act 2007 Third Country Route Pharmaceutical Society of Ireland

More information

HOLSWORTH WILDLIFE RESEARCH FUND

HOLSWORTH WILDLIFE RESEARCH FUND ANZ Charitable Trust Australia (ABN 23 598 387 218) Application Guidelines The Holsworth Wildlife Research Fund invites applications for post-graduate student research support in ecology, wildlife management

More information

Australia s National Guidelines and Procedures for Approving Participation in Joint Implementation Projects

Australia s National Guidelines and Procedures for Approving Participation in Joint Implementation Projects Australia s National Guidelines and Procedures for Approving Participation in Joint Implementation Projects August 2015 Contacting the National Authority for the CDM and JI For information about these

More information

Child Care Services Regulations 2007

Child Care Services Regulations 2007 Western Australia Child Care Services Regulations 2007 As at 27 Feb 2008 Version 00-c0-03 Western Australia Child Care Services Regulations 2007 CONTENTS Part 1 Preliminary 1. Citation 1 Part 2 General

More information

Topical Peer Review 2017 Ageing Management of Nuclear Power Plants

Topical Peer Review 2017 Ageing Management of Nuclear Power Plants HLG_p(2016-33)_348 Topical Peer Review 2017 Ageing Management of Nuclear Power Plants Terms of Reference for Topical Peer Review Process This paper provides the terms of reference for the peer review of

More information

OVERSEAS TERRITORIES AVIATION REQUIREMENTS (OTARs)

OVERSEAS TERRITORIES AVIATION REQUIREMENTS (OTARs) OVERSEAS TERRITORIES AVIATION REQUIREMENTS (OTARs) OTAR Part 145 AIRCRAFT MAINTENANCE ORGANISATION APPROVAL Published by Air Safety Support International Ltd Air Safety Support International Limited 2004

More information

Energy Technology Development and Demonstration Programme (EUDP)

Energy Technology Development and Demonstration Programme (EUDP) Energiteknologisk Udviklingsog Demonstrationsprogram January 16, 2018 Energy Technology Development and Demonstration Programme (EUDP) Call for proposals EUDP 2018-I Dead line March 2, 2018 1500 CET (unofficial

More information

Healthcare Professions Registration and Standards Act 2007

Healthcare Professions Registration and Standards Act 2007 You are here: PacLII >> Databases >> Consolidated Acts of Samoa 2015 >> Healthcare Professions Registration and Standards Act 2007 Database Search Name Search Noteup Download Help Healthcare Professions

More information

Notice of Proposed Rule Making NPRM 15-03

Notice of Proposed Rule Making NPRM 15-03 Notice of Proposed Rule Making NPRM 15-03 16 July 2015 Part 147 Docket 14/CAR/2 Consequential Amendments Part 66 Part 119 Part 145 Published by the Civil Aviation Authority of New Zealand Background to

More information

EUROPEAN MILITARY AIRWORTHINESS REQUIREMENTS EMAR 147 AIRCRAFT MAINTENANCE TRAINING ORGANISATIONS

EUROPEAN MILITARY AIRWORTHINESS REQUIREMENTS EMAR 147 AIRCRAFT MAINTENANCE TRAINING ORGANISATIONS EUROPEAN MILITARY AIRWORTHINESS REQUIREMENTS EMAR 147 AIRCRAFT MAINTENANCE TRAINING ORGANISATIONS E E S MILITARY AIRWORTHINESS AUTHORITIES FORUM DOCUMENT CONTROL DOCUMENT APPROVAL The following table identifies

More information

HERCULE III PROGRAMME CALL FOR PROPOSALS REF. Hercule III 2014 ANTI-FRAUD TRAINING E PROGRA MME ANTI-FRAU

HERCULE III PROGRAMME CALL FOR PROPOSALS REF. Hercule III 2014 ANTI-FRAUD TRAINING E PROGRA MME ANTI-FRAU HERCULE III PROGRAMME 2014-2020 UL CALL FOR PROPOSALS REF. Hercule III 2014 ANTI-FRAUD TRAINING E PROGRA MME 2014-0 Deadline Monday 15 September 2014 Eligibility Period For Activities 13 April 2015 31

More information

Guideline. Assessing qualified persons according to sections 381, 395 and 410 of the Environmental Protection Act 1994

Guideline. Assessing qualified persons according to sections 381, 395 and 410 of the Environmental Protection Act 1994 Guideline Assessing qualified persons according to sections 381, 395 and 410 of the Environmental Protection Act 1994 Prepared by: Statewide Environmental Assessments, Environmental Performance and Coordination,

More information

MINIMUM CRITERIA FOR REACH AND CLP INSPECTIONS 1

MINIMUM CRITERIA FOR REACH AND CLP INSPECTIONS 1 FORUM FOR EXCHANGE OF INFORMATION ON ENFORCEMENT Adopted at the 9 th meeting of the Forum on 1-3 March 2011 MINIMUM CRITERIA FOR REACH AND CLP INSPECTIONS 1 MARCH 2011 1 First edition adopted at the 6

More information

NATIONAL INSTITUTE FOR HEALTH AND CARE EXCELLENCE. Interim Process and Methods of the Highly Specialised Technologies Programme

NATIONAL INSTITUTE FOR HEALTH AND CARE EXCELLENCE. Interim Process and Methods of the Highly Specialised Technologies Programme NATIONAL INSTITUTE FOR HEALTH AND CARE EXCELLENCE Principles Interim Process and Methods of the Highly Specialised Technologies Programme 1. Our guidance production processes are based on key principles,

More information

Request for Proposal

Request for Proposal Consolidated Edison Company of New York, Inc. Request for Proposal Non-Wires Solutions to Provide Demand Side Management for Subtransmission and Distribution System Load Relief Newtown Substation Project

More information

DATA PROTECTION POLICY

DATA PROTECTION POLICY DATA PROTECTION POLICY Document Number 2010/35/V1 Document Title Data Protection Policy Author Nic McCullagh Author s Job Title Information Governance Manager Department IM&T Ratifying Committee Capacity

More information

Aboriginal Community Capital Grants Program Guide

Aboriginal Community Capital Grants Program Guide APPLICATION GUIDE FOR THE ABORIGINAL COMMUNITY CAPITAL GRANTS PROGRAM WHAT YOU NEED TO KNOW BEFORE YOU APPLY Before completing your Aboriginal Community Capital Grants Program application, please read

More information

LICENSINGAPPLICATION GUIDELINES, 2016

LICENSINGAPPLICATION GUIDELINES, 2016 LICENSINGAPPLICATION GUIDELINES, 2016 1.0 INTRODUCTION In exercise of the powers conferred by the Communications Act, Cap 68:01 of the Laws of Malawi, Malawi Communications Regulatory Authority (hereinafter

More information

Registration prescribed information handbook

Registration prescribed information handbook Registration prescribed information handbook Guidance for registered providers submitting prescribed information as part of a registration pack or a registration notification form. October 2016 Page 2

More information

Version Number: 004 Controlled Document Sponsor: Controlled Document Lead:

Version Number: 004 Controlled Document Sponsor: Controlled Document Lead: Chief Investigators and Principal Investigators in Research Policy CONTROLLED DOCUMENT CATEGORY: CLASSIFICATION: PURPOSE Controlled Document Number: Policy Governance To set out the responsibilities of

More information

Official Journal of the European Union

Official Journal of the European Union L 19/10 25.1.2017 COMMISSION DELEGATED REGULATION (EU) 2017/118 of 5 September 2016 establishing fisheries conservation measures for the protection of the marine environment in the North Sea THE EUROPEAN

More information

Policy and Guidelines for Conducting Educational Research in the Boston Public Schools

Policy and Guidelines for Conducting Educational Research in the Boston Public Schools Policy and Guidelines for Conducting Educational Research in the Boston Public Schools Updated October 1, 2017 Overview The basic purpose of the Boston Public Schools (BPS) is to educate children. BPS

More information

Casual Worker Agreement Form. This agreement is between: Casual Worker (name): The Royal Liverpool & Broadgreen University Hospitals NHS Trust

Casual Worker Agreement Form. This agreement is between: Casual Worker (name): The Royal Liverpool & Broadgreen University Hospitals NHS Trust Casual Worker Agreement Form This agreement is between: Casual Worker (name): Organisation: The Royal Liverpool & Broadgreen University Hospitals NHS Trust Terms of Agreement START DATE: JOB TITLE: Registered/Unregistered

More information

GRANT APPLICATION FORM 1

GRANT APPLICATION FORM 1 No of proposal: MOVE/C4/SUB/01-2012/.. (for Commission use only) GRANT APPLICATION FORM 1 Road Safety and young road users (a) Project identification Full title Acronym (20 characters max.) (b) Organisation

More information

Overview of Authorisation Process in Ireland

Overview of Authorisation Process in Ireland www.pwc.ie Overview of Authorisation Process in Ireland Overview of Authorisation Process in Ireland for Banking Institutions ECB decision Once review of application has been successfully completed, the

More information

Request for Information and Qualifications RFIQ No Facility Asset Management Consulting Services

Request for Information and Qualifications RFIQ No Facility Asset Management Consulting Services City of Coquitlam Request for Information and Qualifications RFIQ No. 17-11-04 Facility Asset Management Consulting Services Issue Date: November 24, 2017 File #: 03-1220-20/17-11-04/1 Doc #: 2764584.v4

More information

Request for Proposals and Specifications for a Community Solar Project

Request for Proposals and Specifications for a Community Solar Project Request for Proposals and Specifications for a Community Solar Project CPS Energy P.O. Box 1771 San Antonio, TX 78296-1771 October 9, 2014 PR # 10452716 INVITATION TO SUBMIT PROPOSALS 1. Introduction CPS

More information

STANDARD TERMS AND CONDITIONS ON NORWAY GRANTS FROM INNOVATION NORWAY

STANDARD TERMS AND CONDITIONS ON NORWAY GRANTS FROM INNOVATION NORWAY STANDARD TERMS AND CONDITIONS ON NORWAY GRANTS FROM INNOVATION NORWAY 1 Scope of the Project Contract The Grant to the Project Promoter is offered on the terms and conditions laid down in the Grant Offer

More information

Registration Guidelines

Registration Guidelines Registration Guidelines 2 Registration Guidelines Charities Regulator These Guidelines are issued by the Charities Regulator pursuant to section 14(1) of the Charities Act 2009, to encourage and facilitate

More information

Tourism Marketing Strategy

Tourism Marketing Strategy RFP 2015 01 September 15, 2015 City of Duncan, Administration Attention: Peter de Verteuil, CAO City of Duncan, 200 Craig Street, Duncan, BC, V9L 1W3 Submission Deadline: October 15, 2015 TABLE OF CONTENTS

More information

and Commission on the amended Energy Efficiency Directive and Renewable Energies Directives. Page 1

and Commission on the amended Energy Efficiency Directive and Renewable Energies Directives. Page 1 Information on financing of projects under the framework of the European Climate Initiative of the German Federal Ministry for the Environment, Nature Conservation, Building and Nuclear Safety (BMUB) Last

More information

AGENCY RECRUITMENT ONBOARDING PROCEDURE GROUP FIVE RECRUITMENT CENTRE OF EXCELLENCE. Conditions precedent in respect to conducting business with:

AGENCY RECRUITMENT ONBOARDING PROCEDURE GROUP FIVE RECRUITMENT CENTRE OF EXCELLENCE. Conditions precedent in respect to conducting business with: AGENCY RECRUITMENT ONBOARDING PROCEDURE GROUP FIVE RECRUITMENT CENTRE OF EXCELLENCE Conditions precedent in respect to conducting business with: Group Five (Ltd), Group Five Construction (Ltd) and or any

More information

Consultation Document on ComReg's Draft Strategy Statement for Electronic Communications

Consultation Document on ComReg's Draft Strategy Statement for Electronic Communications Consultation Document on ComReg's Draft Strategy Statement for Electronic Communications 2017-2019 Consultation: ComReg 16/116 Date: 21/12/2016 An Coimisiún um Rialáil Cumarsáide Commission for Communications

More information

EUROPEAN COMMISSION DIRECTORATE-GENERAL FOR HUMANITARIAN AID - ECHO

EUROPEAN COMMISSION DIRECTORATE-GENERAL FOR HUMANITARIAN AID - ECHO EUROPEAN COMMISSION DIRECTORATE-GENERAL FOR HUMANITARIAN AID - ECHO FRAMEWORK PARTNERSHIP AGREEMENT ANNEX III GRANT AGREEMENT WITH HUMANITARIAN ORGANISATIONS Guidelines These guidelines are drafted for

More information

Payments Enterprise Ireland Payments 8 Company Payments 8 Eligible Costs 9

Payments Enterprise Ireland Payments 8 Company Payments 8 Eligible Costs 9 1 CONTENTS Introduction 2 Programme Benefits 2 Contact the Programme Team 2 Eligibility 2 Companies 2 Research Institutes 2 Application Process 3 Process Outline 3 Who Applies? 4 Application Forms 4 Phase

More information

GUIDE FOR APPLICANTS INTERREG VA

GUIDE FOR APPLICANTS INTERREG VA GUIDE FOR APPLICANTS INTERREG VA Cross-border Programme for Territorial Co-operation 2014-2020, Northern Ireland, Border Region of Ireland and Western Scotland & PEACE IV EU Programme for Peace and Reconciliation

More information

LICENCE APPLICATION FORM

LICENCE APPLICATION FORM THE UNITED REPUBLIC OF TANZANIA Energy and Water Utilities Regulatory Authority (EWURA) 6 th Floor, Harbour View Towers, Samora Avenue, P.O. Box 72175, Dar es Salaam TEL: +255-22-2123853; 2123854; 2123856;

More information

Terms and Conditions of studentship funding

Terms and Conditions of studentship funding Terms and Conditions of studentship funding Any offer of PhD funding from Brain Research UK ( the Charity ) is subject to the following Terms and Conditions. By accepting the award, the Host Institute

More information

Questions and Answers SDE+ category offshore wind energy

Questions and Answers SDE+ category offshore wind energy Questions and Answers SDE+ category offshore wind energy QUESTION 1 Will the winning tender bid price be corrected for inflation during the construction and operation phases? No, the winning tender bid

More information

Qualifications Support Pack 03. Making Claims & Results

Qualifications Support Pack 03. Making Claims & Results Qualifications Support Pack 03 Making Claims & Results August 2016 1 CONTENTS Contacting Prince s Trust Qualifications... 3 QUALIFICATION CLAIMS... 4 Centre Approval... 4 Registering Learners... 4 Making

More information

Erasmus+ Application Form. Call: 2014 KA2 Cooperation and Innovation for Good Practices. A. General Information. B. Context

Erasmus+ Application Form. Call: 2014 KA2 Cooperation and Innovation for Good Practices. A. General Information. B. Context A. General Information This application form consists of the following main sections: - Context: this section asks for general information about the type of project proposal you want to submit; - Participating

More information

AUDIT REPORT. Audit of Official Controls carried out by the Health Service Executive (Regulation (EC) No 853/2004)

AUDIT REPORT. Audit of Official Controls carried out by the Health Service Executive (Regulation (EC) No 853/2004) AUDIT REPORT Audit of Official Controls carried out by the Health Service Executive (Regulation (EC) No 853/2004) AUDIT REPORT Audit of Official Controls carried out by the Health Service Executive (Regulation

More information

If any queries arise ESB Networks DAC can be contacted at or

If any queries arise ESB Networks DAC can be contacted at or esbnetworks.ie FORM NC5A EMBEDDED GENERATION FACILITIES Application for a New Connection FOR OFFICIAL USE ONLY B.P. No: MPRN: Introduction This application form outlines the information ESB Networks DAC

More information

The Narragansett Electric Company d/b/a National Grid

The Narragansett Electric Company d/b/a National Grid The Narragansett Electric Company d/b/a National Grid Rhode Island Renewable Energy Growth Program Solicitation and Enrollment Process Rules for Solar (Greater than 25 kw), Wind, Hydro and Anaerobic Digester

More information

Rhode Island Commerce Corporation. Rules and Regulations for the Innovation Voucher Program

Rhode Island Commerce Corporation. Rules and Regulations for the Innovation Voucher Program Rules and Regulations for the Innovation Voucher Program Effective Date: November 25, 2015 Table of Contents Page Rule 1. Purpose.... 2 Rule 2. Authority.... 2 Rule 3. Scope.... 2 Rule 4. Severability....

More information

An Bord Altranais. Download date 19/09/ :12:48. Find this and similar works at -

An Bord Altranais. Download date 19/09/ :12:48.   Find this and similar works at - Information for nurses and midwives educated and trained overseas in non-eu countries and applicants within EU member states who do not qualify under EU directives: regarding eligibility to register with

More information

Open call for proposals VP/2004/021. Initiatives to promote gender equality between women and men, including activities concerning migrant women

Open call for proposals VP/2004/021. Initiatives to promote gender equality between women and men, including activities concerning migrant women EUROPEAN COMMISSION EMPLOYMENT, SOCIAL AFFAIRS AND EQUAL OPPORTUNITIES DG Horizontal and international issues Equality for Women and Men Open call for proposals VP/2004/021 Initiatives to promote gender

More information

R. Fay, Research Governance & GCP Manager K. Mahiouz, Clinical Trials Facilitator E. Clough, R&D Governance Operations Manager

R. Fay, Research Governance & GCP Manager K. Mahiouz, Clinical Trials Facilitator E. Clough, R&D Governance Operations Manager Standard Operating Procedures (SOP) for: BH/QMUL Sponsorship of CTIMPs, ATMPs and Clinical Trials of non- CE marked Medicinal Devices Process for Researchers SOP Number: 11a Version Number: V1.0 Effective

More information

Decommissioning Licensing Process of Nuclear Installations in Spain Cristina CORREA SÁINZ.

Decommissioning Licensing Process of Nuclear Installations in Spain Cristina CORREA SÁINZ. Decommissioning Licensing Process of Nuclear Installations in Spain Cristina CORREA SÁINZ. Enresa, Emilio Vargas 7, 28043 Madrid, Spain Keywords: decommissioning, regulatory framework 1.- Introduction

More information

Registration of Health and Social Care Professions

Registration of Health and Social Care Professions This is an official Northern Trust policy and should not be edited in any way Registration of Health and Social Care Professions Reference Number: NHSCT/12/536 Target audience: Directors, Nursing and Midwifery,

More information