1 Memorandum CITY OF DALLAS February 1, 2013 Honorable Mayor and Members of the City Council S.M Wright Project and Job Opportunity Regional Pilot Program On Wednesday, February 6, 2013, the City Council will be briefed on the S.M. Wright Project and the associated Job Opportunity Regional Pilot Program by the Texas Department of Transportation and the North Central Texas Council of Governments, respectively. The briefing materials are attached for your review. Please let me know if you have questions or need additional information. Jill A. Jordan, P.E. Assistant City Manager Attachments c: Mary K. Suhm, City Manager Rosa Rios, City Secretary Thomas P. Perkins, Jr., City Attorney Craig D. Kinton, City Auditor Honorable Daniel F. Solis, Administrative Judge A.C. Gonzalez, First Assistant City Manager Ryan S. Evans, Assistant City Manager Forest E. Assistant City Manager Joey Assistant Jeanne :rhl"lrlayt,,'it1 Frank and Council Office The City That Works: Diverse, Vibrant and Progressive."

2 Proposed SM Wright Project on I-45 / US 175 / SH 310 Dallas City Council Briefing Bill Hale, P.E. Dallas District Engineer February 6,

3 Focus on Increased Safety through Removing the CF Hawn to SM Wright Bend Improved Mobility and Efficiency Enhancing Community Connectivity and Aesthetics Proposed Trinity Parkway (by others) Project Study Area SM Wright Project Scope 2

4 Current 6-Lane freeway & frontage roads serve over 82,000 vehicles per day (vpd). 45 S.M. Wright Freeway Colonial Ave Diversion to I-45 and Trinity Parkway reduces SM Wright traffic to about 50,000 vpd. Traffic reduction no longer needs freeway or bridges on SM Wright. Remaining local & through traffic volume requires only 6-lane signalized arterial. No added (new) right-of-way is anticipated for SM Wright. ROW is anticipated for US 175 connection to I-45. SM Wright Fundamentals 3

5 30 Phase I Adds direct connecting ramps between US 175 CF Hawn Freeway & I Phase I: US 175 to I-45 Connection Project Segments & Phasing 4

6 30 Phase I Phase I: I-45 Improvements Provides lane balance on I-45 to facilitate new direct connecting CF Hawn ramps Project Segments & Phasing 5

7 30 Phase II Phase II: SM Wright Redevelopment Converts SM Wright to a low speed, signalized, pedestrian-friendly, landscaped arterial Project Segments & Phasing 6

8 30 Proposed Trinity Project Under study by NTTA Proposed Trinity Parkway 175 Space for proposed Trinity Parkway provided within the direct connecting ramps from CF Hawn to I Project Segments & Phasing 7

9 30 SM Wright Costs Construction: $119.7M ROW/Enviro/ Utilities/Engineering: $31.9M 175 Total Project Cost: $151.6M 45 Fully Funded Project Segments & Phasing 8

10 N Today s Commuter Flow 45 Today s Traffic Flow 9

11 N Today s Commuter Flow Proposed Commuter Flow 45 This Project s Traffic Flow 10

12 N Today s Access Added Access Combined Access 45 This Project s Access 11

13 45 Approximately $1 million spent by City of Dallas for early acquisitions. Dallas Right of Way Purchases 12

14 Water Feature Intersection Enhancement SM Wright Redevelopment Aesthetics Master Plan SM Wright Aesthetics 13

15 Conceptual rendering, subject to further refinement CITY OF DAllAS SM Wright Redevelopment Aesthetics Master Plan Video SM Wright Aesthetics 14

16 4 Years of Cooperative Public Involvement 2 Dallas Council Trinity River Committee Briefings 5 Stakeholder Work Group Meetings City of Dallas Public Meeting 3 SM Wright Project TxDOT Public Meetings Trinity Pkwy NTTA Public Hearing 9 SM Wright Project Elected Officials Briefings Community Involvement 15

17 S.M. Wright Public Hearing Held January 31, 2013 at Park South YMCA Approximately 119 public attendees Public comments due by February 11, 2013 Received 16 verbal and 9 written comments so far Most common comments: o Concerned with Penn./MLK Blvd access on I-45 o Considered a catalyst for economic development o Improves safety by removing CF Hawn curve o Maintain existing and future landscape/roadways Public Hearing 16

18 Public Hearing January 31, 2013 FHWA Approval (Anticipated) March 2013 City Council Resolution (Anticipated) Spring 2013 ROW Acquisition Summer/Fall 2013 Transfer SM Wright from TxDOT to City of Dallas after construction Planning Schedule 17

19 ROW Acquired Phase I I-45, US 175 Let 2014 Open 2016 Phase II SM Wright Let 2017 Open 2019 Construction Schedule 18

20 Stephen Endres, P.E. TxDOT Project Manager Texas Department of Transportation 4777 E. Highway 80 Mesquite, Texas Phone: Fax: Or visit the project web site at: For More Information 19

21 THE S.M. Wright Job Opportunity Regional Pilot Program Dallas City Council Briefing on February 6, 2013 Michael Morris, P.E. Christopher Anderson North Central Texas Council 0/ Governments 1

22 Regional Program Overview Program has two Primary Components: Residents ~ trained to be employed on highway construction ~ Certified and Placed on highway construction projects Minority Contractors ~ Increase the number of TxDOT certified contractors: Increase competition ~ Improve chances for winning highway construction contracts 2

23 Program Needs Shortage of Certified Transportation Construction Workers Enhanced Minority, Women and Small Business Enterprises {{Competitive Effectiveness" Communication Plan on Transportation Projects in Southern Dallas 3

24 Contractor Elements Comprehensive Minority Contractor and Laborer Opportunities Program Laborer Elements Land Use Change around SM Wright 7. Sustain / Enhance Community's Economic Development 1. Identify Potential Projects? ~ SM Wright Trinity Pkwy Others Sidewalk / Landscape 2. Identify Minority Contractors and their Opportunities to Successfully Bid TxDOTLead TxDOT Outreach Program ( \ Public Sector and Private Sector Opportunities - Internship program(s) Work Force Board Lead 6. Establish Graduate Pool of Qualified Laborers MLK Cedar Valley and other Community Colleges South Dallas Training Center \ 5. Secure Funding for Training Classes for Contractors and Laborers ~ 4. Increase DBE Participation A - Overall Goal B - Contract Specific Goal 3. "Size" Construction Contracts to Enable Minority Participation,j Present Overall Program to Establish TxDOT minority progra m size TxDOT Contract Size Minority Contractor Growth Minority Labor Pool Growth 4

25 Program Funding (No City Funds Needed) Amount Up to $500,000 Source Anticipated Work Force Development Grant Purpose Work Force Training, Education $1,000,000 Regional Transportation Council (RTC) Federal / TxDOTfunds Communication Plan, Training Outreach, Contractor Outreach $1,000,000 RTC Federal funds Sidewalks, Landscaping, Small Scale Construction Projects 5

26 Program Support Federal & Statewide FHWA Office of Civil Rights "excited by program's possibilities" MAP21 - (most recent transportation authorization bill) approves use of federal funds for Workforce Development, Training and Education TxDOT to explore Statewide Application of Pilot Program 6

Memorandum. CAPRA: Commission for Accreditation of Park and Recreation Agencies

Memorandum. CAPRA: Commission for Accreditation of Park and Recreation Agencies Memorandum DATE August 22,2014 CITY OF DALLAS TO Honorable Members of the Quality of Life & Environment Committee: Dwaine R. Caraway (Chair) Sandy Greyson (Vice Chair), Adam Medrano, Rick Callahan, Carolyn

More information

PUBLIC MEETING. For I-10 East, I-410 to Loop 1604

PUBLIC MEETING. For I-10 East, I-410 to Loop 1604 PUBLIC MEETING For I-10 East, I-410 to Loop 1604 November 3, 2016 Welcome Thank you for participating in the Public Meeting for the proposed I-10 East, I-410 to Loop 1604 Project. The meeting is in an

More information

Memorandum CITY OF DALLAS

Memorandum CITY OF DALLAS Memorandum CITY OF DALLAS DATE November11, 2016 TO: Honorable Members of the Public Safety Committee: Adam Medrano (Chair), B. Adam McGough (Vice Chair), Sandy Greyson, Tiffinni A, Young, Jennifer S. Gates,

More information

Council. Jill A. Jordan, RE., Assistant Joey Zapata, Assistant M.

Council. Jill A. Jordan, RE., Assistant Joey Zapata, Assistant M. Memorandum CITY OF DALLAS DATE TO SUBJECT December 2, 2016 Members of the Economic Development Committee: Rickey D. Callahan (Chair), Casey Thomas, II, (Vice Chair), Adam Medrano, Lee M. Kleinman, Carolyn

More information

DESIGN BID BUILD IS ALIVE & WELL 2007 Texas Transportation Forum. Doug Pitcock, P.E. President and CEO Williams Brothers Construction Co., Inc.

DESIGN BID BUILD IS ALIVE & WELL 2007 Texas Transportation Forum. Doug Pitcock, P.E. President and CEO Williams Brothers Construction Co., Inc. DESIGN BID BUILD IS ALIVE & WELL 2007 Texas Transportation Forum Doug Pitcock, P.E. President and CEO Williams Brothers Construction Co., Inc. I. WHAT IS THE KATY FREEWAY PROJECT? Regional Map Bush Intercontinental

More information

Memorandum CITY OF DALLAS. Hazardous Property Receivership and Operation Goodwill Program

Memorandum CITY OF DALLAS. Hazardous Property Receivership and Operation Goodwill Program Memorandum CITY OF DALLAS DATE December 3, 2010 TO Housing Committee Members: Steve Salazar, Chair, Carolyn R. Davis, Vice Chair, Tennell Atkins, Dwaine Caraway, Angela Hunt, Ann Margolin, Pauline Med

More information

Memorandum. Trinity River Corridor Project Committee Members: David A. Neumann (Chairman) Vonciel Jones Hill Steve Salazar (Vice-Chair) Delia Jasso

Memorandum. Trinity River Corridor Project Committee Members: David A. Neumann (Chairman) Vonciel Jones Hill Steve Salazar (Vice-Chair) Delia Jasso Memorandum DATE October 7, 2010 TO Trinity River Corridor Project Committee Members: David A. Neumann (Chairman) Vonciel Jones Hill Steve Salazar (Vice-Chair) Delia Jasso Mayor Pro Tern Dwaine Caraway

More information

Please contact me or Director of Transportation Michael Rogers at (214) if you have any questions or concerns.

Please contact me or Director of Transportation Michael Rogers at (214) if you have any questions or concerns. Memorandum DATE January 12, 2018 CITY OF DALLAS TO Honorable Mayor and Members of the City Council SUBJECT Riverfront Boulevard Project Return of Unused Funds The Riverfront Boulevard project is a joint

More information

STATE HIGHWAY (SH) 34 FEASIBILITY STUDY PUBLIC MEETING

STATE HIGHWAY (SH) 34 FEASIBILITY STUDY PUBLIC MEETING STATE HIGHWAY (SH) 34 FEASIBILITY STUDY PUBLIC MEETING From FM 2578 in Terrell to SH 243 in Kaufman CSJ: 0173-04-056 June 28, 2018 WHAT IS A FEASIBILITY STUDY WHAT IS A FEASIBILITY STUDY? A feasibility

More information

Memorandum CITY OF DALLAS

Memorandum CITY OF DALLAS Memorandum CITY OF DALLAS DATE. August 19, 2016 o. Honorable Members of the Public Safety Committee: Adam Medrano (Chair), B. Adam McGough (Vice Chair), Sandy Greyson, Tiffinni A. Young, Jennifer S. Gates,

More information

Rickey D. Callahan (Chair), Casey Thomas, II (Vice Chair), Adam Medrano, Lee M. Kleinman, Carolyn King Arnold, B. Adam McGough

Rickey D. Callahan (Chair), Casey Thomas, II (Vice Chair), Adam Medrano, Lee M. Kleinman, Carolyn King Arnold, B. Adam McGough oare Memorandum May 8, 2017 a CITY OF DALLAS To Members of the Economic Development Committee: Rickey D. Callahan (Chair), Casey Thomas, II (Vice Chair), Adam Medrano, Lee M. Kleinman, Carolyn King Arnold,

More information

Katy Trail Extension from McCommas Boulevard to White Rock Station

Katy Trail Extension from McCommas Boulevard to White Rock Station Katy Trail Extension from McCommas Boulevard to White Rock Station Presented to the Quality of Life Committee By Public Works and Transportation October 26, 2009 Purpose of Briefing Provide updates on

More information

R rtf~ t:" \1 F [L. ~. ;:-" t V'\ S'tV 2012 JAN 13 PH 5: 53. CI ry SE.CRETAif { DALLAS. TEXAS

R rtf~ t: \1 F [L. ~. ;:- t V'\ S'tV 2012 JAN 13 PH 5: 53. CI ry SE.CRETAif { DALLAS. TEXAS Memorandum R rtf~ t:" \1 F [L ~. ;:-" t V'\ S'tV 2012 JAN 13 PH 5: 53 CI ry SE.CRETAif { DALLAS. TEXAS OATE January 12, 2012 CITY OF DALLAS TO Honorable Members of the Arts, Culture & Libraries Committee:

More information

CITY OF DALLAS Bid Review # S15-001

CITY OF DALLAS Bid Review # S15-001 Memorandum CITY OF DALLAS Bid Review # S15-001 DATE: November 26, 2014 TO: SUBJECT: A.C. Gonzalez, City Manager Michael Frosch, Director Department of Business Development and Procurement Services William

More information

Appendix A: Public Involvement Plan

Appendix A: Public Involvement Plan Appendix A: Public Involvement Plan RM 620 Corridor Improvement Study Appendix A Draft Public Involvement Plan RM 620 Feasibility Study US 183 to SH 71 Williamson and Travis Counties CSJs: 0683-02-062,

More information

Better Cultural, Arts and Recreational Amenities. Trinity Watershed Management

Better Cultural, Arts and Recreational Amenities. Trinity Watershed Management Total KEY FOCUS AREA: Better Cultural, Arts and Recreational Amenities AGENDA DATE: May 26, 2010 COUNCIL DISTRICT(S): 2, 7 DEPARTMENT: Trinity Watershed Management CMO: Jill A. Jordan, P.E., 6705299 MAPSCO:

More information

Memorandum. Please contact me if you have any questions or need additional information. Eric D. Campbell CITY OF DALLAS

Memorandum. Please contact me if you have any questions or need additional information. Eric D. Campbell CITY OF DALLAS Memorandum CITY OF DALLAS DATE April 3, 2017 TO SUBJECT Honorable Members of the Committee: Adam Medrano (Chair), B. Adam McGough (Vice Chair), Sandy Greyson, Tiffinni A. Young, Jennifer S. Gates, Philip

More information

August 2007 Thomas Bohuslav Texas Department of Transportation

August 2007 Thomas Bohuslav Texas Department of Transportation Public Private Partnerships Activities in Texas AASHTO SOC 2007 Summer Meeting Biloxi Mississippi August 2007 Thomas Bohuslav Texas Department of Transportation Topics The Problem (Needs) Comprehensive

More information

SCOTT COUNTY COMMUNITY SERVICES DIVISION

SCOTT COUNTY COMMUNITY SERVICES DIVISION SCOTT COUNTY COMMUNITY SERVICES DIVISION PHYSICAL DEVELOPMENT 600 COUNTRY TRAIL EAST JORDAN, MN 55352-9339 (952) 496-8346 Fax: (952) 496-8365 www.co.scott.mn.us MITCHELL J. RASMUSSEN, P.E. COUNTY ENGINEER

More information

Apologies Michael, but lets work off of the attached update version. James Bass came back with a few additional minor tweaks to the language.

Apologies Michael, but lets work off of the attached update version. James Bass came back with a few additional minor tweaks to the language. REFERENCE ITEM 3.16 RTC Handout March 8, 2018 From: To: Cc: Subject: Date: Attachments: Marc Williams Michael Morris Bill Hale; Kelly Selman; Mo Bur; Brian Barth RE: Recommended RTC Action for LBJ/IH 635

More information

REQUEST FOR INFORMATION

REQUEST FOR INFORMATION REQUEST FOR INFORMATION REGARDING THE DEVELOPMENT OF AND PROCUREMENT PROCESS FOR THE GRAND PARKWAY PROJECT TEXAS DEPARTMENT OF TRANSPORTATION RFI Issuance Date: June 10, 2011 RFI Closing Date: July 6,

More information

SH 121: FM 423 To SH 121 At US 75 Interchange. APPENDIX B: Coordination and Policy

SH 121: FM 423 To SH 121 At US 75 Interchange. APPENDIX B: Coordination and Policy Re-evaluation SH 121: FM 423 To SH 121 At US 75 Interchange APPENDIX B: Coordination and Policy Revised 10/4/2007 RESOLUTION NO. 2431-8-05(R) A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF ALLEN, COLLIN

More information

Strategic Projects Division

Strategic Projects Division Strategic Projects Division DESIGN BUILD: The Texas Story 2012 AASHTO Conference May 2, 2012 Portland, Oregon Don Toner, Jr., SRWA Director Strategic Projects Right of Way Strategic Projects Division Texas

More information

I-15/Tropicana Interchange Feasibility Study in Clark County, NV. Comments are due October 16, 2015, 5 p.m.

I-15/Tropicana Interchange Feasibility Study in Clark County, NV. Comments are due October 16, 2015, 5 p.m. Welcome Nevada Department of Transportation Public Meeting I-15/Tropicana Interchange Feasibility Study in Clark County, NV Ways to Comment Tonight Comment during public meeting Court reporter Comment

More information

RESOLUTION FOR APPROVAL OF AMENDMENTS TO THE TRANSPORTATION IMPROVEMENT PROGRAM (TIP) AND 2040 REGIONAL TRANSPORTATION PLAN (RTP)

RESOLUTION FOR APPROVAL OF AMENDMENTS TO THE TRANSPORTATION IMPROVEMENT PROGRAM (TIP) AND 2040 REGIONAL TRANSPORTATION PLAN (RTP) TPC Agenda Item 6A Mailout 10/20/16 RESOLUTION FOR APPROVAL OF AMENDMENTS TO THE 2017-2020 TRANSPORTATION IMPROVEMENT PROGRAM (TIP) AND 2040 REGIONAL TRANSPORTATION PLAN (RTP) Amendment Summary Amendment

More information

Memorandum. RIGHT Care Pilot Program

Memorandum. RIGHT Care Pilot Program Memorandum CITY OF DALLAS OATE April 3, 2017 TO SUBJECT Honorable Members of the Committee: Adam Medrano (Chair), B. Adam McGough (Vice Chair), Sandy Greyson, Tiffinni A. Young, Jennifer S. Gates, Philip

More information

~ - /). (''''''--- R~a7s. Evans. Memorandum

~ - /). (''''''--- R~a7s. Evans. Memorandum Memorandum CITY OF DALLAS DATE: June 20, 2014 TO: Honorable Members of the Public Safety Committee: Sheffie Kadane (Chair), Adam Medrano (Vice Chair), Dwaine Caraway, Jennifer S. Gates, Sandy Greyson,

More information

Memorandum. Please feel free to contact me if you have any questions or concerns. Joey Zapata Assistant City Manager

Memorandum. Please feel free to contact me if you have any questions or concerns. Joey Zapata Assistant City Manager Memorandum DATE March 22, 2018 CITY OF DALLAS TO Honorable Members of the Quality of Life, Arts & Culture Committee: Sandy Greyson (chair), Mark Clayton (Vice Chair), Rickey D. Callahan, Jennifer S. Gates,

More information

TIGER DISCRETIONARY PROGRAM Project Application

TIGER DISCRETIONARY PROGRAM Project Application TIGER DISCRETIONARY PROGRAM Project Application Name of Project: US 175/Interstate Highway (IH) 45 Connector Agency Submitting Project: North Central Texas Council of Governments (NCTCOG) and the Texas

More information

REVISED AGENDA. 1. Approval of December 6, 2010 Minutes of the Economic Development Committee

REVISED AGENDA. 1. Approval of December 6, 2010 Minutes of the Economic Development Committee Memorandum REVISED DATE February 4, 2011 TO SUBJECT Members of the Economic Development Committee: Tennell Atkins (Vice-Chair), Dwaine Caraway, Jerry R. Allen, Sheffie Kadane, Ann Margolin, Linda Koop,

More information

REGIONAL 10-YEAR PLAN AND NEXT DECADE OF PROJECTS. Regional Transportation Council December 8, 2016

REGIONAL 10-YEAR PLAN AND NEXT DECADE OF PROJECTS. Regional Transportation Council December 8, 2016 REGIONAL 10-YEAR PLAN AND NEXT DECADE OF PROJECTS Regional Transportation Council December 8, 2016 POLICY SUMMARY Thank the Texas Transportation Commission for formula funds. Thank the Legislature and

More information

Memorandum June 1, 2017

Memorandum June 1, 2017 DRAF DRA Memandum June 1, 2017 To: From: Subject: Our Partners in Transptation Planning Isidro (Sid) Martinez, Direct Notification of the FY 2019-2022 Transptation Improvement Program Surface Transptation

More information

Transportation Alternatives Program Application For projects in the Tulsa Urbanized Area

Transportation Alternatives Program Application For projects in the Tulsa Urbanized Area FFY 2015-2016 Transportation Alternatives Program Application For projects in the Tulsa Urbanized Area A Grant Program of Moving Ahead for Progress in the 21st Century (MAP-21) U.S. Department of Transportation

More information

IH 30 HOV/Managed Lanes and President George Bush Turnpike (PGBT) EE Revenue Projections (FY 2011-FY 2035)

IH 30 HOV/Managed Lanes and President George Bush Turnpike (PGBT) EE Revenue Projections (FY 2011-FY 2035) IH 30 HOV/Managed Lanes and President George Bush Turnpike (PGBT) EE Revenue Projections (FY 2011-FY 2035) FISCAL YEAR IH 30 THROUGH FINANCE REPAYMENT IH 30 HOV/Managed Lanes Pass Through Finance & Excess

More information

On December 13, 2017, City Council approved Resolution No , to take the following action, as modified by floor amendment:

On December 13, 2017, City Council approved Resolution No , to take the following action, as modified by floor amendment: Memorandum DATE January 26, 2018 CITY OF DALLAS TO Honorable Mayor and Members of the City Council SUBJECT Update on Bridge Steps FY2017-18 Amended and Restated Management Services Contract, Phase II Background

More information

SIXTH STREET VIADUCT REPLACEMENT PROJECT MONTHLY EXECUTIVE MEETING REPORT NOVEMBER 2012

SIXTH STREET VIADUCT REPLACEMENT PROJECT MONTHLY EXECUTIVE MEETING REPORT NOVEMBER 2012 SIXTH STREET VIADUCT REPLACEMENT PROJECT MONTHLY EXECUTIVE MEETING REPORT NOVEMBER 2012 Sixth Street Viaduct Replacement Project Monthly Executive Meeting Report November 2012 TABLE OF CONTENTS Project

More information

WESTERN SLOPE CIP AND TIM FEE UPDATE

WESTERN SLOPE CIP AND TIM FEE UPDATE WESTERN SLOPE CIP AND TIM FEE UPDATE 12/6/16 BOARD OF SUPERVISORS STUDY SESSION B O A R D S T U D Y S E S S I O N # 8 2015 14-0245 Revised 22M 1 of 53 AGENDA 1. Background 2. Programmatic EIR 3. General

More information

SUBJECT: SEE BELOW DATE: May 26, 2016

SUBJECT: SEE BELOW DATE: May 26, 2016 COUNCIL AGENDA: 06-07-16 ITEM: A. CI CITY OF C: 3- SAN JOSE CAPITAL OF SILICON VALLEY TO: HONORABLE MAYOR AND CITY COUNCIL Memorandum FROM: Barry Ng SUBJECT: SEE BELOW DATE: Approved IL2_PS^ Date 5 ^ lip

More information

TxDOT Funding and Accelerated Construction Program

TxDOT Funding and Accelerated Construction Program TxDOT Funding and Accelerated Construction Program RANDY C. HOPMANN, P.E. DIRECTOR OF DISTRICT OPERATIONS TXAPA s 42nd Annual Meeting September 22, 2016 Highway Transportation in Texas: Today and Our Future

More information

NASHVILLE AREA MPO FY TIP - ADOPTED DECEMBER

NASHVILLE AREA MPO FY TIP - ADOPTED DECEMBER WILSON NASHVILLE AREA MPO FY -2017 TIP - ADOPTED DECEMBER 11, 2013 Beckwith Road/Eastern Connector TIP # 2008-71-038 New Road Mt. Juliet Wilson Length 5.00 Regional Plan ID 1072-132 Air Quality Status

More information

Guidance. Historical Studies Review Procedures

Guidance. Historical Studies Review Procedures Guidance Historical Studies Review Procedures This guidance document provides instructional material regarding how to review and process project activities in accordance with TxDOT s Section 106 of the

More information

UNFUNDED TRANSPORTATION PROJECTS OVERVIEW

UNFUNDED TRANSPORTATION PROJECTS OVERVIEW UNFUNDED TRANSPORTATION PROJECTS OVERVIEW THE LIST 40 unique unfunded projects are on the list All projects are important to the future of Arvada s transportation needs. The list has developed over many

More information

SAN JOSE CAPITAL OF SILICON VALLEY

SAN JOSE CAPITAL OF SILICON VALLEY CITY OF "3 SAN JOSE CAPITAL OF SILICON VALLEY COUNCIL AGENDA: 11/29/16 ITEM: Memorandum TO: HONORABLE MAYOR AND CITY COUNCIL FROM: Barry Ng Jim Ortbal SUBJECT: 7652 - ST. JOHN STREET MULTI MODAL IMPROVEMENTS

More information

Expected Roadway Project Crash Reductions for SMART SCALE Safety Factor Evaluation. September 2016

Expected Roadway Project Crash Reductions for SMART SCALE Safety Factor Evaluation. September 2016 Expected Roadway Project Crash Reductions for SMART SCALE Safety Factor Evaluation September 2016 SMART SCALE Safety Factors Evaluation 1. Using Crash Modification Factors for SMART SCALE Safety Evaluation

More information

Sixth Street Viaduct Replacement Project

Sixth Street Viaduct Replacement Project Sixth Street Viaduct Replacement Project Skanska Stacy & Witbeck DBE & Local Business Networking Event Wednesday, November 5, 2014 PUENTE Learning Center 501 S. Boyle Ave., Los Angeles, CA 20023 2013 Fluor.

More information

Appendix F Public Meeting Summaries. F1: May 2013 Public Meeting Summary F2: September 2013 Public Meeting Summary

Appendix F Public Meeting Summaries. F1: May 2013 Public Meeting Summary F2: September 2013 Public Meeting Summary Loop 9 Southeast Corridor/Feasibility Study Appendix F Public Meeting Summaries F1: May 2013 Public Meeting Summary F2: September 2013 Public Meeting Summary Loop 9 Southeast Corridor/Feasibility Study

More information

ROUTE 52 CAUSEWAY REPLACEMENT PROJECT STEERING COMMITTEE MEETING NO. 5 REPORT

ROUTE 52 CAUSEWAY REPLACEMENT PROJECT STEERING COMMITTEE MEETING NO. 5 REPORT STEERING COMMITTEE MEETING NO. 5 REPORT DATE: November 11, 2004 TIME: 10:00 a.m. 2:00 p.m. LOCATION: Office of Michael Baker, Jr., Princeton, NJ - Conference Room ATTENDEES: REPRESENTING: PHONE: Carol

More information

US 59 Diboll Relief Route (Future I-69) Angelina County Open House Summary and Comment Response Report March 3, 2015

US 59 Diboll Relief Route (Future I-69) Angelina County Open House Summary and Comment Response Report March 3, 2015 US 59 Diboll Relief Route (Future I-69) Angelina County Open House Summary and Comment Response Report March 3, 2015 Texas Department of Transportation, Lufkin District The environmental review, consultation,

More information

ENVIRONMENTAL STATUS OF THE US 59/LOOP 20/I-69W PROJECT

ENVIRONMENTAL STATUS OF THE US 59/LOOP 20/I-69W PROJECT ENVIRONMENTAL STATUS OF THE US 59/LOOP 20/I-69W PROJECT A Brief Overview As Of June 15, 2015 Mike Graham Laredo District Environmental Coordinator June 15, 2015 Projects Locations & Design: Additional

More information

STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM FY Amarillo District May FY 2010 Quarterly Revisions

STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM FY Amarillo District May FY 2010 Quarterly Revisions STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM FY 2008-2011 Amarillo District May FY 2010 Quarterly Revisions 5-2010 MONDAY, APRIL 26, 2010 STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM PAGE: 1 OF 1 11:21:55

More information

Texas Department of Transportation Corpus Christi District

Texas Department of Transportation Corpus Christi District Texas Department of Transportation Corpus Christi District U.S. 181 Harbor Bridge Project Environmental Documentation and Schematic Development Public Scoping Meeting August 9, 2011 Welcome John A. Casey,

More information

FHWA Initiatives. Mary Stringfellow Program Delivery Team Leader FHWA Louisiana Division PH

FHWA Initiatives. Mary Stringfellow Program Delivery Team Leader FHWA Louisiana Division PH FHWA Initiatives Mary Stringfellow Program Delivery Team Leader FHWA Louisiana Division PH 225-757-7610 mary.stringfellow@dot.gov Federal Requirements Federal Transportation Law (USC) programs & $$ Written

More information

George Douglas John Bowker Mayor Jon Costas Jan Dick David Smith Stu Summers Dave Pilz Jim Jorgensen Craig Phillips Patrick Lyp

George Douglas John Bowker Mayor Jon Costas Jan Dick David Smith Stu Summers Dave Pilz Jim Jorgensen Craig Phillips Patrick Lyp July 10, 2008 VALPARAISO REDEVELOPMENT COMMISSION MEETING: Valparaiso Redevelopment Commission LOCATION: North Fire Station 2605 Cumberland Dr. SUBJECT: Minutes of the July 10, 2008 Meeting IN ATTENDANCE:

More information

SUBCONTRACTING ON CDOT CONSTRUCTION PROJECTS Ramp Up Ridgway!

SUBCONTRACTING ON CDOT CONSTRUCTION PROJECTS Ramp Up Ridgway! SUBCONTRACTING ON CDOT CONSTRUCTION PROJECTS Ramp Up Ridgway! Connect2DOT Colorado Small Business Development Center Network (SBDC) program funded by CDOT Free training, consulting, and resources for small

More information

Welcome to the Public Meeting for the State Highway 68 Project. SH 68 Project Office Information Environmental Constraints & Study Corridors

Welcome to the Public Meeting for the State Highway 68 Project. SH 68 Project Office Information Environmental Constraints & Study Corridors Welcome to the Public Meeting for the State Highway 68 Project ENTRANCE EXIT Registration & Handouts Comment Card Area Welcome Video Next Steps Project History Information Environmental Constraints & Study

More information

Dallas North Tollway Extension Phase 4B/5A Alignment Presented to: Regional Transportation Council

Dallas North Tollway Extension Phase 4B/5A Alignment Presented to: Regional Transportation Council Dallas North Tollway Extension Phase 4B/5A Alignment Presented to: Regional Transportation Council Gerry Carrigan Assistant Executive Director of Project Delivery NTTA July 15, 2010 Agenda Project History

More information

DIRECTOR S REPORT TRANSPORTATION BOARD SEPTEMBER 10, 2018

DIRECTOR S REPORT TRANSPORTATION BOARD SEPTEMBER 10, 2018 DIRECTOR S REPORT TRANSPORTATION BOARD SEPTEMBER 10, 2018 1 EMERGENCY OPERATIONS MAINTENANCE FORCES IN DISTRICTS 2 AND 3 CLOSED ROADS DUE TO WILDFIRES FLOODING IN SOUTHERN NEVADA DUE TO MONSOON SEASON

More information

I-69 Corridor Segment Committee 1 and 2 Kick-off Meeting April 15 Nacogdoches, Texas

I-69 Corridor Segment Committee 1 and 2 Kick-off Meeting April 15 Nacogdoches, Texas I-69 Corridor Segment Committee 1 and 2 Kick-off Meeting April 15 Nacogdoches, Texas 10:00 a.m. Welcome/ Introductions Mark Tomlinson Division Dir., Texas Turnpike Authority Div, TxDOT 10:15 a.m. Presentations

More information

AGC of TEXAS Highway, Heavy, Utilities & Industrial Branch

AGC of TEXAS Highway, Heavy, Utilities & Industrial Branch AGC of TEXAS Highway, Heavy, Utilities & Industrial Branch THOMAS L. JOHNSON, Executive Vice President Texas Transportation Commission Meeting Highlights September 18 and 24, 2014 September 18 Commissioner

More information

DEPARTMENT OF TRANSPORTATION STATE OF GEORGIA

DEPARTMENT OF TRANSPORTATION STATE OF GEORGIA MAY 2, 2014 DEPARTMENT OF TRANSPORTATION STATE OF GEORGIA AWARD ANNOUNCEMENT APRIL 18, 2014 LETTING AWARD IS MADE ON MAY 02, 2014 TO THE ON THE FOLLOWING CONTRACTS UNLESS OTHERWISE INDICATED. DBE PARTICIPANTS

More information

Agenda Item D.2 PRESENTATION Meeting Date: June 17, 2014

Agenda Item D.2 PRESENTATION Meeting Date: June 17, 2014 Agenda Item D.2 PRESENTATION Meeting Date: June 17, 2014 TO: FROM: SUBJECT: Mayor and Councilmembers Rosemarie Gaglione, Interim Public Works Director Capital Improvement Program Update RECOMMENDATION:

More information

AGENDA. Regional Transportation Council Thursday, September 13, 2018 North Central Texas Council of Governments

AGENDA. Regional Transportation Council Thursday, September 13, 2018 North Central Texas Council of Governments AGENDA Regional Transportation Council Thursday, September 13, 2018 North Central Texas Council of Governments 11:30 am Auto Occupancy Detection Technology Rewards Program and Tolled Managed Lanes Policy

More information

Transportation Alternatives (TA) Northeast Minnesota Workshop

Transportation Alternatives (TA) Northeast Minnesota Workshop Transportation Alternatives (TA) Northeast Minnesota Workshop October 4 th, 2016 1 What are TA Projects? Federally funded community based projects o Expand travel choices o Integrate modes o Improve cultural,

More information

Appendix E Major Stakeholder Meeting Summaries. E1: Ash Grove Cement Company E2: Holcim E3: UPRR E3: BNSF E4: IIIPOD E5: Skyline Landfill E6: Oncor

Appendix E Major Stakeholder Meeting Summaries. E1: Ash Grove Cement Company E2: Holcim E3: UPRR E3: BNSF E4: IIIPOD E5: Skyline Landfill E6: Oncor Loop 9 Southeast Corridor/Feasibility Study Appendix E Major Stakeholder Meeting Summaries E1: Ash Grove Cement Company E2: Holcim E3: UPRR E3: BNSF E4: IIIPOD E5: Skyline Landfill E6: Oncor Loop 9 Southeast

More information

AGC of TEXAS Highway, Heavy, Utilities & Industrial Branch

AGC of TEXAS Highway, Heavy, Utilities & Industrial Branch AGC of TEXAS Highway, Heavy, Utilities & Industrial Branch THOMAS L. JOHNSON, Executive Vice President Joint AGC/TxDOT Committee Meeting November 14, 2011 Minutes 1. Words of welcome The Chairs opened

More information

STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM FY AMARILLO DISTRICT. AUGUST FY 2009 Quarterly Revisions

STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM FY AMARILLO DISTRICT. AUGUST FY 2009 Quarterly Revisions STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM FY 2008-2011 AMARILLO DISTRICT AUGUST FY 2009 Quarterly Revisions 8-01-2009 MINUTES AMARILLO METROPOLITAN PLANNING ORGANIZATION POLICY ADVISORY COMMITTEE MEETING

More information

Memorandum CITY OF DALLAS. October 11, 2017 Agenda Item No. 16 Open Records Request

Memorandum CITY OF DALLAS. October 11, 2017 Agenda Item No. 16 Open Records Request Memorandum DATE October 6, 2017 CITY OF DALLAS TO Honorable Mayor and Members of the City Council SUBJECT October 11, 2017 Agenda Item No. 16 Open Records Request As requested by the Committee at its September

More information

CITY OF LOS ANGELES INTER-DEPARTMENTAL CORRESPONDENCE

CITY OF LOS ANGELES INTER-DEPARTMENTAL CORRESPONDENCE CITY OF LOS ANGELES INTER-DEPARTMENTAL CORRESPONDENCE Date: May 17, 2016 To: The Honorable City Council c/o City Clerk, Room 395 Attention: Honorable Mike Bonin, Chair, Transportation Committee From: Seleta

More information

Smart Scale Update. May 21, 2018

Smart Scale Update. May 21, 2018 Smart Scale Update May 21, 2018 SMART SCALE - Round 3 Schedule We are here $ Approximately $850M available for Round 3 of SMART SCALE Limited Transportation Funding Available $ Approximately $850M available

More information

In-Step, In Line, On Time. Robert F. Tally Jr. FHWA Indiana Division Administrator Monday, November 16, 2009

In-Step, In Line, On Time. Robert F. Tally Jr. FHWA Indiana Division Administrator Monday, November 16, 2009 In-Step, In Line, On Time Robert F. Tally Jr. FHWA Indiana Division Administrator Monday, November 16, 2009 I-69 Corridor 1 I-69 Corridor I-69 is expected to create more than 27,000 new jobs by 2025, resulting

More information

Module 2 Planning and Programming

Module 2 Planning and Programming Module 2 Planning and Programming Contents: Section 1 Overview... 2-2 Section 2 Coordination with MPO... 2-4 Section 3 Functional Classification... 2-6 Section 4 Minute Order for Designation as Access

More information

AGC of TEXAS Highway, Heavy, Utilities & Industrial Branch

AGC of TEXAS Highway, Heavy, Utilities & Industrial Branch AGC of TEXAS Highway, Heavy, Utilities & Industrial Branch THOMAS L. JOHNSON, Executive Vice President Joint AGC/TxDOT Committee Meeting February 13, 2012 Minutes 1. Words of welcome Attendees AGC Members

More information

Upper Darby Township 100 Garrett Rd. Upper Darby, PA 19082

Upper Darby Township 100 Garrett Rd. Upper Darby, PA 19082 Upper Darby Township 100 Garrett Rd. Upper Darby, PA 19082 REQUEST FOR PROPOSAL BACKGROUND The Aronimink Station area is a mixed use neighborhood commercial area located at the intersection of Ferne Blvd.

More information

Smart Region Smart Transportation

Smart Region Smart Transportation Smart Region Smart Transportation Joe Milazzo II, PE, RTA Executive Director Wednesday, Oct. 19, 2016 The Regional Transportation Alliance business coalition: MISSION To leverage the strength of the regional

More information

Organization Clark County Department of Public Works (DUNS No / CCR 3VNR8) 500 South Grand Central Parkway Las Vegas Nevada,

Organization Clark County Department of Public Works (DUNS No / CCR 3VNR8) 500 South Grand Central Parkway Las Vegas Nevada, TRANSPORTATION INVESTMENT GENERATING ECONOMIC RECOVERY DISCRETIONARY GRANT APPLICATION FOR CACTUS AVENUE / INTERSTATE 15 INTERCHANGE Organization Clark County Department of Public Works (DUNS No. 083782953

More information

Arkansas Transportation Alternatives Program (TAP-2017) & Recreational Trails Program (RTP-2017) Application Seminars

Arkansas Transportation Alternatives Program (TAP-2017) & Recreational Trails Program (RTP-2017) Application Seminars Arkansas Transportation Alternatives Program (TAP-2017) & Recreational Trails Program (RTP-2017) Application Seminars Central Arkansas February 23, 2017 March 15, 2017 Northwest Arkansas March 30, 2017

More information

TRANSPORTATION AD HOC COMMITTEE

TRANSPORTATION AD HOC COMMITTEE TRANSPORTATION AD HOC COMMITTEE 1. Call to Order May 19, 2015 3:00 PM Admin Conference Room 2. Riverbanks Zoo Project: Bridge Construction over Railroad Contractor Quote [Page 2] 3. Bluff Road Widening

More information

TRANSPORTATION ALTERNATIVES PROGRAM (TAP)

TRANSPORTATION ALTERNATIVES PROGRAM (TAP) TRANSPORTATION ALTERNATIVES PROGRAM (TAP) CALL FOR PROJECTS Surface Transportation Technical Committee September 26, 2014 North Central Texas Council of Governments ELECTRONIC ITEM 4.2 FUNDING AVAILABLE

More information

Water Street Corridor Streetscape Improvement Project. Resident Engineer Services Information Session June 1st, 2018, 1:00 PM

Water Street Corridor Streetscape Improvement Project. Resident Engineer Services Information Session June 1st, 2018, 1:00 PM Water Street Corridor Streetscape Improvement Project Resident Engineer Services Information Session June 1st, 2018, 1:00 PM Agenda Welcome Project Location Project Overview DBE Goals Contract Summary

More information

A DEFINITIONS AND ACRONYMS

A DEFINITIONS AND ACRONYMS Exhibit A DEFINITIONS AND ACRONYMS Addenda/Addendum means supplemental additions, deletions, and modifications to the provisions of the RFP after the release date of the RFP. Adjusted Available Public

More information

Mississippi Gulf Coast Metropolitan Planning Organization. Transportation Improvement Program FY

Mississippi Gulf Coast Metropolitan Planning Organization. Transportation Improvement Program FY Mississippi Gulf Coast Metropolitan Planning Organization Transportation Improvement Program FY 2015-2019 November 2015 The Metropolitan Planning Organization (MPO) is a federally mandated planning body

More information

July Five Pages

July Five Pages July 2009 Five Pages Kwame Collins (left) of Minneapolis and Jazlyn Bradley of St. Paul talk with Hue Pham (right), a community outreach coordinator for the Central Corridor LRT Project, on July 18 at

More information

I-69 Angelina and Nacogdoches Counties Committee Charge and Purpose

I-69 Angelina and Nacogdoches Counties Committee Charge and Purpose AGENDA I-69 Angelina and Nacogdoches Counties Committee Tuesday, January 22, 2013 2-5 pm TxDOT Lufkin District 1805 N. Timberland Drive Lufkin, TX 75901 MEETING OBJECTIVE: Review, discuss and understand

More information

A RESOLUTION ADOPTING THE LADY S ISLAND CORRIDOR STUDY

A RESOLUTION ADOPTING THE LADY S ISLAND CORRIDOR STUDY A RESOLUTION ADOPTING THE LADY S ISLAND CORRIDOR STUDY WHEREAS, Beaufort County, in conjunction with the City of Beaufort, had a corridor study prepared for the Sea Island Parkway corridor on Lady s Island;

More information

Genoa Township Area Road and Bridge Projects

Genoa Township Area Road and Bridge Projects Genoa Township Area Road and Bridge Projects Delaware County Engineer s Office May 18, 2017 Delaware County Engineer s Office 2016 Construction Highlights Biggest construction year in Delaware County Engineer

More information

Appendix E Federal and State Funding Categories

Appendix E Federal and State Funding Categories Appendix E Federal and State Funding Categories This page left blank intentionally. Federal and State Funding Categories Appendix E E 3 Appendix E Federal and State Funding Categories Highway Programs

More information

WELCOME HOW THIS HEARING WORKS:

WELCOME HOW THIS HEARING WORKS: WELCOME Arkansas State Highway and Transportation Department Open Forum Design Public Hearing Job No. 061275 Arkansas River Str. & Apprs. (Broadway) (LR/NLR) (Hwy. 70) Pulaski County March 28, 2013 HOW

More information

Independent Auditor s Report on Applying Agreed-Upon Procedures for the Fiscal Year 2013 # 3 Weapons Destruction

Independent Auditor s Report on Applying Agreed-Upon Procedures for the Fiscal Year 2013 # 3 Weapons Destruction Memorandum CITY OF DALLAS (Report No. W14-001) DATE: January 15, 2014 TO: SUBJECT: A.C. Gonzalez, Interim City Manager David O. Brown, Chief of Police Dallas Police Department Independent Auditor s Report

More information

Transportation Improvement Program

Transportation Improvement Program Transportation Improvement Program Transportation Conformity Check List The Transportation Improvement Program (TIP) and all amendments must include a conformity report. The conformity report must address

More information

Sources of Funding Through MDOT Office of Economic Development

Sources of Funding Through MDOT Office of Economic Development Michael B. Kapp, Administrator Sources of Funding Through MDOT Office of Economic Development 2012 County Engineers Workshop February 15, 2012 OED Programs Safe Routes to School (SRTS) Program Transportation

More information

Using Partnerships to Improve Delivery of Programs in VDOT

Using Partnerships to Improve Delivery of Programs in VDOT Using Partnerships to Improve Delivery of Programs in VDOT 2017 VAA Fall Conference - October 2, 2017 Quintin D. Elliott Chief Deputy Commissioner Topics Workforce Development Civil Rights State of Good

More information

Internal Audit Follow-Up Report

Internal Audit Follow-Up Report Internal Audit Follow-Up Report Civil Rights Division Program Management TxDOT Internal Audit Division Objective To assess the status of corrective actions for high-risk Management Action Plans (MAPs)

More information

BUSINESS OWNERS UPDATE MEETING

BUSINESS OWNERS UPDATE MEETING INTERSTATE-70 / NEW STANTON INTERCHANGE PROJECT BUSINESS OWNERS UPDATE MEETING January 31, 2013 Station 1 Station 2 Station 3 Station 4 Station 5 STATION 1 Welcome Display 1 of 2 INTERSTATE-70 / NEW STANTON

More information

Performance and Production Review of the Florida Department of Transportation FY 2016/17

Performance and Production Review of the Florida Department of Transportation FY 2016/17 Performance and Production Review of the Florida Department of Transportation FY 2016/17 FLORIDA TRANSPORTATION COMMISSION DECEMBER 7, 2017 Introduction How we got here History behind the measures Conclusion

More information

Georgia s Operational Improvement Program. Paul DeNard, P.E., PTOE State Traffic Operations Manager

Georgia s Operational Improvement Program. Paul DeNard, P.E., PTOE State Traffic Operations Manager Georgia s Operational Improvement Program Paul DeNard, P.E., PTOE State Traffic Operations Manager How do you address Capacity? We can t build our way out of the congestion problem Widening projects cost

More information

LG PROJECTS ONLINE TOOLKIT. Statewide Planning Conference June 2016

LG PROJECTS ONLINE TOOLKIT. Statewide Planning Conference June 2016 LG PROJECTS ONLINE TOOLKIT Statewide Planning Conference June 2016 Local Government Projects Definition of a Local Government Project At least one phase of project development* or the program is managed

More information

TEXAS DEPARTMENT OF TRANSPORTATION ON-THE-JOB TRAINING AND SUPPORTIVE SERVICES (OJT/SS) PROGRAM

TEXAS DEPARTMENT OF TRANSPORTATION ON-THE-JOB TRAINING AND SUPPORTIVE SERVICES (OJT/SS) PROGRAM TEXAS DEPARTMENT OF TRANSPORTATION SPECIFICATION NO. ON-THE-JOB TRAINING AND SUPPORTIVE SERVICES (OJT/SS) PROGRAM PUBLICATION This specification is a product of the Texas Department of Transportation (TxDOT).

More information

TxDOT Statewide 2017 TA Set-Aside Questions & Answers

TxDOT Statewide 2017 TA Set-Aside Questions & Answers TxDOT Statewide 2017 TA Set-Aside Questions & Answers Below are some common questions received in TxDOT s 2017 TA Set-Aside Call for Projects. The Code of Federal Regulations (CFR) and Texas Administration

More information

JOINT AGC/TxDOT COMMITTEE MINUTES MAY 19, 2010

JOINT AGC/TxDOT COMMITTEE MINUTES MAY 19, 2010 JOINT AGC/TxDOT COMMITTEE MINUTES MAY 19, 2010 1. Words of welcome Co-Chairs Johnny Weisman and David Casteel opened the meeting. Attendees from TxDOT were David Casteel, Carol Rawson, Michael Lehmann,

More information

TxDOT Internal Audit Local Government Project Oversight Function ( ) Department-wide Report

TxDOT Internal Audit Local Government Project Oversight Function ( ) Department-wide Report Introduction Local Government Project Oversight Function (1201-11) Department-wide Report This report has been prepared for the Transportation Commission, TxDOT Administration and management. The report

More information