1 Exhibit R-2, RDT&E Budget Item Justification: PB 2012 Navy DATE: February 2011 COST ($ in Millions) FY 2010 FY 2013 FY 2014 FY 2015 FY 2016 To Program Element Continuing Continuing Continuing Continuing Note FY11 Military Intelligence Program related funding transitions to PE N beginning in FY11. A. Mission Description and Budget Item Justification The CANES program recapitalizes the Navy's afloat network infrastructure (see note below) by consolidation of diverse physical networks and implementation of Afloat Core Services (ACS) and Cross Domain Solutions (CDS). CANES will provide all security domains from Unclassified through Top Secret/Sensitive Compartmented Information (SCI) Common Computing Environment (CCE) for a wide variety of Navy surface combatants, submarines, Maritime Operations Centers, and Aircraft. CANES will enable more efficient data visibility and flow between operational nodes on the Global Information Grid using an open architecture. Additionally, virtualization on the CCE enhances the department's ability to reduce the multitude of standalone command and control systems and applications eliminating the need to field additional or unique hardware (servers and workstations). Through CCE, CDS and virtualization, CANES will improve the Navy's Command, Control, Communications, Computers, Intelligence, Surveillance, and Reconnaissance (C4ISR) security and agility while reducing total ownership costs. Note existing afloat networks include: Integrated Shipboard Network Systems (ISNS), Combined Enterprise Regional Information Exchange System - Maritime (CENTRIXS-M), SCI Networks, and Submarine Local Area Network (SubLAN). In addition, CANES will provide functionality currently provided in the Video Information Exchange System (VIXS) and portions of afloat Computer Network Defense (CND). CANES will field on a rolling four year hardware baseline and a two year software baseline. The CANES vision is based on the overarching concept of reducing the number of afloat networks and providing enhanced efficiency through a single engineering focus on integrated technical solutions. This will allow for streamlined acquisition, contracting, and test events, and significant lifecycle efficiencies through consolidation of multiple current configuration management baselines, logistics and training efforts into a unified support structure. The primary goals of the CANES program are to: 1) reduce the number of networks through the use of mature, certified, cross domain technologies; 2) reduce the infrastructure footprint and associated costs for hardware afloat; and 3) provide increased capability to meet current and projected warfighter requirements. CANES will enable application developers to begin decoupling applications and services software away from independent, unique hardware stacks and host them on a common interoperable environment. In FY12, the CANES RDT&E investment ramps down with the close out of the Engineering and Manufacturing Development (EMD) phase, transitioning to the Limited Deployment (LD) phase to continue development on additional platform set baselines and ramp up of testing events. Engineering Development Model (EDM) units are installed on Unit level platforms to support Initial Operational Test & Evaluation (IOT&E). Legacy afloat networks and hosted applications fully transition for integration Navy Page 1 of 11 R-1 Line Item #201

2 Exhibit R-2, RDT&E Budget Item Justification: PB 2012 Navy DATE: February 2011 testing as they migrate to CANES baseline. Begin to prepare Enterprise Engineering and Certification (E2C) lab for Submarine Hosted System Integration. Develop Request For Proposal (RFP) for Full Deployment contract and associated source selection activities. B. Program Change Summary ($ in Millions) FY 2010 Previous President's Budget Current President's Budget Adjustments Congressional General Reductions - Congressional Directed Reductions - Congressional Rescissions - - Congressional Adds - Congressional Directed Transfers - Reprogrammings SBIR/STTR Transfer - - Program Adjustments Rate/Misc Adjustments Congressional General Reductions Adjustments Change Summary Explanation Technical: On 29 March 2010, CANES was designated an ACAT IAM pre-major Automated Information System (MAIS) program. Per FY10 National Defense Authorization Act (NDAA), Low Rate Initial Produciton (LRIP) is replaced with Limited Deployment (LD) and Full Rate Production (FRP) is replaced with Full Deployment (FD) for MAIS programs. Schedule: MS B shifted from Q3FY10 to Q2FY11 due to closeout coordination of Preliminary Design Review (PDR) Requests for Action (RFA) for both Engineering and Manufacturing Development (EMD) developers combined with acquisition documentation staffing timelines and alignment with new OSD mandated requirements for milestone events. Execution of the EMD contract was not impacted or affected by the scheduling of MS B. MS B O-IPT was held 1QFY11, and Acquisition Decision Memorandum (ADM) was signed 2QFY11. MS C planned completion date has shifted from late Q4FY11 to Q2FY12 due to the EMD contract award which re-baselined the program schedule including the lab based Operational Assessment (OA) which is the main entrance criteria for MS C. Initial Operational Capability (IOC): IOC shifted to Q4FY12 aligning with the Joint Staff definition of IOC completion. IOC is achieved when first CANES unit is installed, and maintenance and training support programs are in place. Full Deployment (FD) : Shift related to Milestone Decision Authority (MDA) decision to wait until MS C to release FD contract Request for Proposal (RFP). Funding: A $2,636K increase in FY12 occurred since PB11. As a result, the program is fully funded to develop required platform sets. Navy Page 2 of 11 R-1 Line Item #201

3 Exhibit R-2A, RDT&E Project Justification: PB 2012 Navy DATE: February 2011 COST ($ in Millions) FY 2010 FY 2013 FY 2014 FY 2015 FY 2016 To Continuing Continuing Quantity of RDT&E Articles Note FY11 Military Intelligence Program related funding transitions to PE N beginning in FY11. A. Mission Description and Budget Item Justification The CANES program recapitalizes the Navy's afloat network infrastructure (see note below) by consolidation of diverse physical networks and implementation of Afloat Core Services (ACS) and Cross Domain Solutions (CDS). CANES will provide all security domains from Unclassified through Top Secret/Sensitive Compartmented Information (SCI) Common Computing Environment (CCE) for a wide variety of Navy surface combatants, submarines, Maritime Operations Centers, and Aircraft. CANES will enable more efficient data visibility and flow between operational nodes on the Global Information Grid using an open architecture. Additionally, virtualization on the CCE enhances the department's ability to reduce the multitude of standalone command and control systems and applications eliminating the need to field additional or unique hardware (servers and workstations). Through CCE, CDS and virtualization, CANES will improve the Navy's Command, Control, Communications, Computers, Intelligence, Surveillance, and Reconnaissance (C4ISR) security and agility while reducing total ownership costs. Note existing afloat networks include: Integrated Shipboard Network Systems (ISNS), Combined Enterprise Regional Information Exchange System - Maritime (CENTRIXS-M), SCI Networks, and Submarine Local Area Network (SubLAN). In addition, CANES will provide functionality currently provided in the Video Information Exchange System (VIXS) and portions of afloat Computer Network Defense (CND) CANES will enable application developers to begin decoupling applications and services software away from independent, unique hardware stacks and host them on a common interoperable environment. This approach will incrementally deploy and will provide a basis for overall Navy Return on Investment (ROI) over the existing strategies. B. Accomplishments/Planned Programs ($ in Millions, Article Quantities in Each) FY 2010 Title: CANES Integration FY 2010 Accomplishments: Program/budget transitioned from ISNS Inc 2/CANES to CANES which consolidates afloat networks and enterprise services aboard ships and shore sites. These capabilities include increased availability to mission critical level ships, multiple security enclaves, application hosting, Afloat Core Services (ACS), and collaboration services. Began required statutory and regulatory programmatic activities to support Milestone B (MS B) and Milestone C (MS C) including acquisition documentation and Engineering Manufacturing Development (EMD) efforts. Conducted Developmental Testing (DT) on CANES. Conducted Articles: Navy Page 3 of 11 R-1 Line Item #201

4 Exhibit R-2A, RDT&E Project Justification: PB 2012 Navy DATE: February 2011 B. Accomplishments/Planned Programs ($ in Millions, Article Quantities in Each) FY 2010 Preliminary Design Review (PDR). CANES ACS version 1.1 was delivered to the two system developers for integration with the proposed development baselines. Developed Analysis Requirements Description (CARD) and Life Cycle Estimate (LCCE) for CANES. ed system development contract on two system developer baselines. Developed design installation studies and participated in source selection activities. Assessed alternatives for a command and control (C2) path. Plans: Continue CANES statutory and regulatory acquisition documentation to achieve Milestone C (MS C). revised Analysis Requirements Document (CARD) and Life Cycle Estimate (LCCE). Procure two (2) Engineering and Development Model (EDM) units for Initial Operational Test and Evaluation (IOT&E) integration, and regression testing. The EDM units function as pre-production units and require funding for necessary installation design and installation costs. Continue Developmental Testing (DT) and begin Operational Assessment (OA) for Operational Testing (OT) event. Close out EMD contract and complete down-select of the prime system developer to continue into Limited Deployment (LD) phase to develop additional platform set baselines. Develop Request for Proposal for Full Deployment contract and associated source selection activities. Achieve Milestone B (MS B). It is important to note, quantities represent the sites receiving the CANES enclave as also referenced in PE N. Plans: statutory and regulatory acquisition documentation to achieve CANES MS C. Revise CARD and LCCE in support of Navy's Service Position (SCP) for MS C. Following Operational Testing (OT), preparation begins for IOT&E to include installation of EDM units on Unit level platforms to complete operational assessments for readiness. Also, continue developmental Legacy afloat networks and hosted applications fully transition for integration testing as they migrate to CANES baseline. Begin to prepare Enterprise Engineering and Certification (E2C) lab for Submarine Hosted System Integration. Completion of Source Selection activities to award Full Deployment contract. Continue development of platform set baselines. Accomplishments/Planned Programs Subtotals C. Other Program Funding Summary ($ in Millions) Line Item FY 2010 FY 2013 FY 2014 FY 2015 FY 2016 To OPN/2915: CANES Continuing Continuing OPN/2925: CANES Intell Continuing Continuing Navy Page 4 of 11 R-1 Line Item #201

5 Exhibit R-2A, RDT&E Project Justification: PB 2012 Navy DATE: February 2011 C. Other Program Funding Summary ($ in Millions) Line Item FY 2010 FY 2013 FY 2014 FY 2015 FY 2016 To RDTE/ N: CANES MIP D. Acquisition Strategy CANES was identified as a ACAT IAM pre-mais. Formal program initiation at MS B (2QFY11). The program office is employing a multiple-phase, multiple-award downselect contract strategy to reduce program risks and maintain competition in both design development and production during contract performance. Two competitive contracts have been awarded to design, develop, and deliver all hardware and the associated operating system, virtualization and other commercial software needed to deliver a functional network. As the program accomplishes system development, a down-select will be conducted to choose the best design for Limited Deployment (LD). At the completion of LD, a separate competitive contract will be awarded for Full Deployment (FD) efforts. E. Performance Metrics Early RDT&E investment and sustainment of dual design contractors through the development phase will save 10-30% of Ownership (TOC) over the life cycle of the program. avoidance throughout the life of the program is based on performance gains that are measured (not quantified) by 1) reducing the number of networks through the use of mature, certified, cross domain technologies; 2) reducing the infrastructure footprint and associated costs for hardware afloat; and 3) providing increased capability to meet current and projected warfighter requirements. Navy Page 5 of 11 R-1 Line Item #201

6 Exhibit R-3, RDT&E Project Analysis: PB 2012 Navy DATE: February 2011 Product Development ($ in Millions) Category Item Primary Hardware Development Primary Hardware Development Primary Hardware Development Primary Hardware Development Systems Engineering Systems Engineering Systems Engineering Systems Engineering Lockheed Martin:San Diego, CA Northrop Grumman:Reston, VA SPAWAR Systems Center:San Diego, CA Prior To Nov Nov Nov Continuing Continuing Continuing C/FFP UNKNOWN:UNKNOWN Aug Nov MIPR SPAWAR Systems Center:San Diego, CA and Charleston, SC US ARMY CECOM (MITRE):San Diego, CA Lockheed Martin:San Diego, CA Northrop Grumman:Reston, VA Dec Dec Continuing Continuing Continuing Dec Dec Continuing Continuing Continuing Mar Mar Subtotal Support ($ in Millions) Category Item Studies & Design MIPR Washington HQ Services:Washington DC Prior To System Installation Design Puget Sound Naval ShipYard:Bremerton, Washington May Dec System Installation SPAWAR Systems Center Atlantic Jul Jan Navy Page 6 of 11 R-1 Line Item #201

7 Exhibit R-3, RDT&E Project Analysis: PB 2012 Navy DATE: February 2011 Support ($ in Millions) Category Item IMO:North Charelston, SC Prior To Subtotal Test and Evaluation ($ in Millions) Category Item Development Test & Evaluation Operational Test & Evaluation Development Test & Evaluation Studies & Design Prior Navy Page 7 of 11 R-1 Line Item #201 To MIPR JITC:Fairfax, VA Nov Dec Continuing Continuing Continuing MIPR COMOPTEVFOR:Norfolk, VA and Washington, DC Spawar System Center:San Diego, CA USAF:Research Laboratory: UNKNOWN Nov Dec Continuing Continuing Continuing Dec Dec Continuing Continuing Continuing Subtotal Remarks FY10 Studies & Design effort at USAF: Research Laboratory received 1QFY11 in support of FLTCYBERCOM lifeline study. UNKNOWN will be defined after OMNIBUS contract is awarded. Management Services ($ in Millions) Category Item Program Management Support Program Management & Acquisition Support SPAWAR Systems Center:San Diego, CA and Charleston, SC Prior To Nov Dec Continuing Continuing Continuing Nov Dec Continuing Continuing Continuing

8 Exhibit R-3, RDT&E Project Analysis: PB 2012 Navy DATE: February 2011 Management Services ($ in Millions) Category Item Financial Management Support Estimation and Analyses Systems Research & Application:San Diego, CA INDUS Technology:San Diego, CA Booz Allen Hamilton:San Diego, CA Prior To Nov Continuing Continuing Continuing Nov Dec Continuing Continuing Continuing Logistics Support TCI:San Diego, CA Nov Dec Continuing Continuing Continuing Subtotal Prior Project s To Remarks 4QFY11 UNKNOWN will be defined after down select to one contractor at the completion of the Engineering and Manufacturer Development (EMD) competitive contract. This winning prime contractor will be selected for the Limited Deployment (LD) option and to continue development of additional platform set baselines. 4QFY11 funds are paramount to procurement of (2) Engineering Design Model (EDM) units to be installed in 1QFY12 in support of Initial Operational Test & Evaluation (IOT&E), Full Deployment Decision (FDD) and program's ability to meet 5 year requirement from Funds First Obligated to FDD. Navy Page 8 of 11 R-1 Line Item #201

9 Exhibit R-4, RDT&E Schedule Profile: PB 2012 Navy DATE: February 2011 Navy Page 9 of 11 R-1 Line Item #201

10 Exhibit R-4A, RDT&E Schedule Details: PB 2012 Navy DATE: February 2011 Schedule Details Start End Events by Sub Project Quarter Year Quarter Year Proj 9C87 Acquisition Milestone - CANES Transition Acquisition Milestone - CANES Milestone (MS) B Acquisition Milestone - CANES MS C Acquisition Milestone - Initial Operational Capability (IOC) Acquisition Milestone - Full Deployment Decision Review System Development - Surface (2 developers) System Development - Preliminary Design Review (PDR) System Development - Critical Design Review (CDR) System Development - Submarines System Development - Technical Insertion (TI) Software (SW) System Development - Technical Insertion 2 Hardware (HW)/SW Development Software Development - ACS Development Test OperationalTest - Limited Deployment (LD) OperationalTest - Initial Operatinal Test & Evaluation (IOT&E) Development Test - Submarines Operational Test - Submarines Development Test - TI Operational Test - TI Production Milestone - Limited Deployment (LD) Production Milestone - Full Deployment (FD) Navy Page 10 of 11 R-1 Line Item #201

11 Exhibit R-4A, RDT&E Schedule Details: PB 2012 Navy DATE: February 2011 Start End Events by Sub Project Quarter Year Quarter Year Deliveries - ACS Deliveries - CANES Engineering Design Model (EDM) Unit Deliveries - CANES EDM Unit Environmental Qualification Test (EQT) Deliveries - Limited Deployment (LD) Deliveries - Full Deployment (FD) System Development - Surface (1 developer) Navy Page 11 of 11 R-1 Line Item #201

UNCLASSIFIED. FY 2016 Base FY 2016 OCO

UNCLASSIFIED. FY 2016 Base FY 2016 OCO Exhibit R2, RDT&E Budget Item Justification: PB 2016 Navy : February 2015 1319: Research,, Test & Evaluation, Navy / BA 5: System & Demonstration (SDD) COST ($ in Millions) Years R1 Program Element (Number/Name)

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE Exhibit R-2, RDT&E Budget Item Justification: PB 2013 Navy DATE: February 2012 COST ($ in Millions) FY 2011 FY 2012 FY 2014 FY 2015 FY 2016 FY 2017 Navy Page 1 of 8 R-1 Line #83 To Program Element - -

More information

UNCLASSIFIED. FY 2016 Base FY 2016 OCO

UNCLASSIFIED. FY 2016 Base FY 2016 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2016 Army : February 2015 2040: Research, Development, Test & Evaluation, Army / BA 5: System Development & Demonstration (SDD) COST ($ in Millions) Years

More information

UNCLASSIFIED. FY 2016 Base FY 2016 OCO

UNCLASSIFIED. FY 2016 Base FY 2016 OCO Exhibit R2, RDT&E Budget Item Justification: PB 2016 Navy : February 2015 1319: Research, Development, Test & Evaluation, Navy / BA 4: Advanced Component Development & Prototypes (ACD&P) COST ($ in Millions)

More information

UNCLASSIFIED. FY 2016 Base

UNCLASSIFIED. FY 2016 Base Exhibit R-2, RDT&E Budget Item Justification: PB 2016 Defense Security Cooperation Agency : February 2015 0400: Research, Development, Test & Evaluation, Defense-Wide / BA 7: Operational Systems Development

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 213 Army DATE: February 212 COST ($ in Millions) FY 211 FY 212 FY 214 FY 215 FY 216 FY 217 To Complete Program Element 125.44 31.649 4.876-4.876 25.655

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE Exhibit R-2, RDT&E Budget Item Justification: PB 214 Navy DATE: April 213 COST ($ in Millions) Years FY 212 FY 213 # ## FY 215 FY 216 FY 217 FY 218 To Program Element 217.794 3.418 3.773 3.262-3.262 3.433

More information

UNCLASSIFIED. FY 2016 Base FY 2016 OCO

UNCLASSIFIED. FY 2016 Base FY 2016 OCO Exhibit R2, RDT&E Budget Item Justification: PB 2016 Navy : February 2015 1319: Research, Development, Test & Evaluation, Navy / BA 5: System Development & Demonstration (SDD) COST ($ in Millions) Years

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE. FY 2014 FY 2014 OCO ## Total FY 2015 FY 2016 FY 2017 FY 2018

UNCLASSIFIED R-1 ITEM NOMENCLATURE. FY 2014 FY 2014 OCO ## Total FY 2015 FY 2016 FY 2017 FY 2018 Exhibit R-2, RDT&E Budget Item Justification: PB 2014 Navy DATE: April 2013 COST ($ in Millions) # ## FY 2015 FY 2016 FY 2017 FY 2018 To Program Element 578.093 95.097 137.369 205.615-205.615 196.665 257.393

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE Exhibit R-2, RDT&E Budget Item Justification: PB 213 Navy DATE: February 212 COST ($ in Millions) FY 211 FY 212 Total FY 214 FY 215 FY 216 FY 217 To Complete Total Total Program Element - 75.7 122.481-122.481

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE Exhibit R-2, RDT&E Budget Item Justification: PB 2013 Navy DATE: February 2012 COST ($ in Millions) FY 2011 FY 2012 Total FY 2014 FY 2015 FY 2016 FY 2017 Navy Page 1 of 8 R-1 Line #142 To Complete Total

More information

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE A: Biometrics Enabled Intelligence FY 2012 OCO

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE A: Biometrics Enabled Intelligence FY 2012 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2012 Army DATE: February 2011 COST ($ in Millions) FY 2010 FY 2011 FY 2013 FY 2014 FY 2015 FY 2016 To Program Element - 14.114 15.018-15.018 15.357 15.125

More information

UNCLASSIFIED. FY 2016 Base FY 2016 OCO

UNCLASSIFIED. FY 2016 Base FY 2016 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2016 Army : February 2015 2040: Research, Development, Test & Evaluation, Army / BA 5: System Development & Demonstration (SDD) COST ($ in Millions) Years

More information

UNCLASSIFIED FY 2016 OCO. FY 2016 Base

UNCLASSIFIED FY 2016 OCO. FY 2016 Base Exhibit R2, RDT&E Budget Item Justification: PB 2016 Navy : February 2015 1319: Research, elopment, Test & Evaluation, Navy / BA 7: Operational Systems elopment COST ($ in Millions) Prior Years FY 2014

More information

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE F: Air Force Integrated Personnel and Pay System (AF-IPPS) FY 2012 OCO

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE F: Air Force Integrated Personnel and Pay System (AF-IPPS) FY 2012 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2012 Air Force DATE: February 2011 COST ($ in Millions) FY 2013 FY 2014 FY 2015 FY 2016 To Complete Program Element 20.405 43.300 91.866-91.866 90.598 129.201

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2013 Navy DATE: February 2012 COST ($ in Millions) FY 2011 FY 2012 Total FY 2014 FY 2015 FY 2016 FY 2017 To Complete Total Total Program Element 49.625

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 213 Navy DATE: February 212 COST ($ in Millions) FY 211 FY 212 FY 214 FY 215 FY 216 FY 217 To Program Element 147.268 6.751 61.163-61.163 94.537 369.826

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE Exhibit R-2, RDT&E Budget Item Justification: PB 213 Navy DATE: February 212 COST ($ in Millions) FY 211 FY 212 FY 214 FY 215 FY 216 FY 217 To Program Element 3.997 3.72 3.773-3.773 3.327 3.424 3.539 3.69

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 213 Navy DATE: February 212 COST ($ in Millions) FY 211 FY 212 Total FY 214 FY 215 FY 216 FY 217 To Complete Total Total Program Element.96 8.765 21.17-21.17

More information

UNCLASSIFIED. FY 2016 Base FY 2016 OCO

UNCLASSIFIED. FY 2016 Base FY 2016 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2016 Air Force : February 2015 3600: Research, Development, Test & Evaluation, Air Force / BA 5: System Development & Demonstration (SDD) COST ($ in Millions)

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE. FY 2014 FY 2014 OCO ## Total FY 2015 FY 2016 FY 2017 FY 2018

UNCLASSIFIED R-1 ITEM NOMENCLATURE. FY 2014 FY 2014 OCO ## Total FY 2015 FY 2016 FY 2017 FY 2018 Exhibit R-2, RDT&E Budget Item Justification: PB 2014 Air Force DATE: April 2013 COST ($ in Millions) # ## FY 2015 FY 2016 FY 2017 FY 2018 To Program Element - 0.000 24.500 23.016-23.016 25.350 26.026

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE Exhibit R-2, RDT&E Budget Item Justification: PB 213 Navy DATE: February 212 COST ($ in Millions) FY 211 FY 212 FY 214 FY 215 FY 216 FY 217 To Program Element 214.597 37. 95.182-95.182 149.871 276.217

More information

UNCLASSIFIED. FY 2017 Base FY 2017 OCO

UNCLASSIFIED. FY 2017 Base FY 2017 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2017 Air Force : February 2016 3600: Research, Development, Test & Evaluation, Air Force / BA 5: System Development & Demonstration (SDD) COST ($ in Millions)

More information

KC-46A Tanker DoD Budget FY2013-FY2017. RDT&E U.S. Air Force

KC-46A Tanker DoD Budget FY2013-FY2017. RDT&E U.S. Air Force KC-46A Tanker DoD Budget FY2013-FY2017 RDT&E U.S. Air Force Exhibit R-2, RDT&E Budget Item Justification: PB 2013 Air Force DATE: February 2012 FY 2013 FY 2013 FY 2013 Cost To COST ($ in Millions) FY 2011

More information

UNCLASSIFIED. R-1 Program Element (Number/Name) PE F / Advanced Medium Range Air-to-Air Missile (AMRAAM) Prior Years FY 2013 FY 2014 FY 2015

UNCLASSIFIED. R-1 Program Element (Number/Name) PE F / Advanced Medium Range Air-to-Air Missile (AMRAAM) Prior Years FY 2013 FY 2014 FY 2015 Exhibit R-2, RDT&E Budget Item Justification: PB 2015 Air Force : March 2014 COST ($ in Millions) Years FY 2013 FY 2014 # FY 2016 FY 2017 FY 2018 FY 2019 To Program Element 242.669 68.656 70.614 82.195-82.195

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2013 Air Force DATE: February 2012 COST ($ in Millions) FY 2011 FY 2014 FY 2015 FY 2016 FY 2017 Air Force Page 1 of 14 R-1 Line #216 To Program Element

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 213 Navy DATE: February 212 COST ($ in Millions) FY 211 FY 212 Total FY 214 FY 215 FY 216 FY 217 To Complete Total Total Program Element 1.613 1.418 1.56-1.56

More information

UNCLASSIFIED. Cost To Complete Total Program Element ED8: Paladin Integrated Management (PIM)

UNCLASSIFIED. Cost To Complete Total Program Element ED8: Paladin Integrated Management (PIM) Exhibit R-2, RDT&E Budget Item Justification: PB 2016 Army : February 2015 2040: Research, Development, Test & Evaluation, Army / BA 5: System Development & Demonstration (SDD) COST ($ in Millions) Years

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE Exhibit R-2, RDT&E Budget Item Justification: PB 2013 Navy DATE: February 2012 COST ($ in Millions) FY 2011 FY 2012 Total FY 2014 FY 2015 FY 2016 FY 2017 To Complete Total Total Program Element - 3.377

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 213 Navy DATE: February 212 COST ($ in Millions) FY 211 FY 212 FY 214 FY 215 FY 216 FY 217 To Complete Program Element 22.63 3.676 32.789-32.789 35.932

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE Exhibit R-2, RDT&E Budget Item Justification: PB 2013 Army DATE: February 2012 COST ($ in Millions) FY 2011 FY 2012 FY 2014 FY 2015 FY 2016 FY 2017 To Program Element 58.348 68.628 158.646-158.646 144.625

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE PE F: NUCLEAR WEAPON MODERNIZATION FY 2012 OCO

UNCLASSIFIED R-1 ITEM NOMENCLATURE PE F: NUCLEAR WEAPON MODERNIZATION FY 2012 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2012 Air Force DATE: February 2011 COST ($ in Millions) FY 2010 FY 2013 FY 2014 FY 2015 FY 2016 To Program Element - - 93.867-93.867 158.218 315.238 397.880

More information

UNCLASSIFIED UNCLASSIFIED

UNCLASSIFIED UNCLASSIFIED EXHIBIT R-2, RDT&E Budget Item Justification APPROPRIATION/BUDGET ACTIVITY R-1 ITEM NOMENCLATURE RESEARCH DEVELOPMENT TEST & EVALUATION, NAVY / BA-7 0305208N Distributed Common Ground Systems (DCGS) COST

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 213 Army DATE: February 212 COST ($ in Millions) FY 211 FY 212 FY 214 FY 215 FY 216 FY 217 To Program Element 24.648 42.347 68.325-68.325 66.869 4.46 -

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE. FY 2014 FY 2014 OCO ## Total FY 2015 FY 2016 FY 2017 FY 2018

UNCLASSIFIED R-1 ITEM NOMENCLATURE. FY 2014 FY 2014 OCO ## Total FY 2015 FY 2016 FY 2017 FY 2018 Exhibit R-2, RDT&E Budget Item Justification: PB 214 Navy DATE: April 213 COST ($ in Millions) Years FY 212 FY 213 # ## FY 215 FY 216 FY 217 FY 218 To Program Element 378.884 24.75 19.28 21.729-21.729

More information

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 7 R-1 Line #91

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 7 R-1 Line #91 Exhibit R-2, RDT&E Budget Item Justification: PB 2016 Air Force : February 2015 3600: Research, Development, Test & Evaluation, Air Force / BA 5: System Development & Demonstration (SDD) COST ($ in Millions)

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE Exhibit R-2, RDT&E Budget Item Justification: PB 2013 Air Force DATE: February 2012 COST ($ in Millions) FY 2011 FY 2012 Base OCO Total FY 2014 FY 2015 FY 2016 FY 2017 Cost To Complete Total Cost Total

More information

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE A: Combat Identification FY 2012 OCO

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE A: Combat Identification FY 2012 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 212 Army DATE: February 211 COST ($ in Millions) FY 21 FY 211 FY 213 FY 214 FY 215 FY 216 To Program Element 7.74 29.884 - - - - - - - Continuing Continuing

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2013 Navy DATE: February 2012 COST ($ in Millions) FY 2011 FY 2012 FY 2014 FY 2015 FY 2016 FY 2017 To Program Element 14.965 55.017 - - - - - - - 0.000

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 213 Navy DATE: February 212 COST ($ in Millions) FY 211 FY 212 PE 65866N: Navy Space & Electr Warfare FY 214 FY 215 FY 216 FY 217 Cost To Complete Cost

More information

UNCLASSIFIED. FY 2016 Base FY 2016 OCO

UNCLASSIFIED. FY 2016 Base FY 2016 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2016 Air Force : February 2015 3600: Research, Development, Test & Evaluation, Air Force / BA 5: System Development & Demonstration (SDD) COST ($ in Millions)

More information

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 9 R-1 Line #94

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 9 R-1 Line #94 Exhibit R-2, RDT&E Budget Item Justification: PB 2015 Air Force Date: March 2014 3600: Research, Development, Test & Evaluation, Air Force / BA 5: System Development & Demonstration (SDD) COST ($ in Millions)

More information

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 8 R-1 Line #211

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 8 R-1 Line #211 Exhibit R-2, RDT&E Budget Item Justification: PB 2015 Air Force Date: March 2014 3600: Research, Development, Test & Evaluation, Air Force / BA 7: Operational Systems Development COST ($ in Millions) Prior

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE. FY 2014 FY 2014 OCO ## Total FY 2015 FY 2016 FY 2017 FY 2018

UNCLASSIFIED R-1 ITEM NOMENCLATURE. FY 2014 FY 2014 OCO ## Total FY 2015 FY 2016 FY 2017 FY 2018 Exhibit R-2, RDT&E Budget Item Justification: PB 2014 Navy DATE: April 2013 COST ($ in Millions) Years FY 2012 FY 2013 # ## FY 2015 FY 2016 FY 2017 FY 2018 To Program Element 127.403 27.495 14.676 19.718-19.718

More information

UNCLASSIFIED FY 2016 OCO. FY 2016 Base

UNCLASSIFIED FY 2016 OCO. FY 2016 Base Exhibit R-2, RDT&E Budget Item Justification: PB 2016 Army : February 2015 2040: Research, Development, Test & Evaluation, Army / BA 7: Operational Systems Development COST ($ in Millions) Years FY 2014

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE COST ($ in Millions) FY 2011 FY 2012 Base OCO Total FY 2014 FY 2015 FY 2016 FY 2017 Cost To Complete Total Cost Total Program Element 4.846 3.825 4.316-4.316 3.813 3.582 3.336 3.379 Continuing Continuing

More information

UNCLASSIFIED. R-1 Program Element (Number/Name) PE F / NAVSTAR Global Positioning System (User Equipment) (SPACE) Prior Years FY 2013 FY 2014

UNCLASSIFIED. R-1 Program Element (Number/Name) PE F / NAVSTAR Global Positioning System (User Equipment) (SPACE) Prior Years FY 2013 FY 2014 Exhibit R-2, RDT&E Budget Item Justification: PB 2015 Air Force : March 2014 COST ($ in Millions) Years FY 2013 FY 2014 # FY 2016 FY 2017 FY 2018 FY 2019 To Program Element 0.000 63.687 127.172 156.659-156.659

More information

UNCLASSIFIED. R-1 Program Element (Number/Name) PE F / Common Data Link Executive Agent (CDL EA) FY 2016 OCO. FY 2016 Base

UNCLASSIFIED. R-1 Program Element (Number/Name) PE F / Common Data Link Executive Agent (CDL EA) FY 2016 OCO. FY 2016 Base Exhibit R-2, RDT&E Budget Item Justification: PB 2016 Air Force : February 2015 COST ($ in Millions) Years FY 2017 FY 2018 FY 2019 FY 2020 To Program Element - 33.896 32.015 43.986-43.986 42.760 41.790

More information

UNCLASSIFIED. FY 2016 Base FY 2016 OCO. Quantity of RDT&E Articles

UNCLASSIFIED. FY 2016 Base FY 2016 OCO. Quantity of RDT&E Articles Exhibit R-2, RDT&E Budget Item Justification: PB 2016 Air Force : February 2015 3600: Research, Development, Test & Evaluation, Air Force / BA 7: Operational Systems Development COST ($ in Millions) PE

More information

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE N: Distributed Common Ground Sys FY 2012 OCO

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE N: Distributed Common Ground Sys FY 2012 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2012 Navy DATE: February 2011 COST ($ in Millions) FY 2010 FY 2011 Total FY 2013 FY 2014 FY 2015 FY 2016 To Complete Total Total Program Element 11.979

More information

UNCLASSIFIED. FY 2016 Base FY 2016 OCO

UNCLASSIFIED. FY 2016 Base FY 2016 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2016 Air Force : February 2015 3600: Research, Development, Test & Evaluation, Air Force / BA 7: Operational Systems Development COST ($ in Millions) FY

More information

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE F: Evolved Expendable Launch Vehicle Program (SPACE) - EMD

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE F: Evolved Expendable Launch Vehicle Program (SPACE) - EMD Exhibit R-2, RDT&E Budget Item Justification: PB 2014 Air Force DATE: April 2013 COST ($ in Millions) # PE 0604853F: Evolved Expendable Launch Vehicle Program (SPACE) - EMD ## FY 2015 FY 2016 FY 2017 FY

More information

UNCLASSIFIED FY 2016 OCO. FY 2016 Base

UNCLASSIFIED FY 2016 OCO. FY 2016 Base Exhibit R-2, RDT&E Budget Item Justification: PB 2016 Army : February 2015 2040: Research, Development, Test & Evaluation, Army / BA 5: Development & Demonstration (SDD) COST ($ in Millions) Years FY 2014

More information

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 7 R-1 Line #91

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 7 R-1 Line #91 Exhibit R-2, RDT&E Budget Item Justification: PB 2015 Air Force : March 2014 3600: Research, Development, Test & Evaluation, Air Force / BA 5: Development & Demonstration (SDD) COST ($ in Millions) # FY

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE. FY 2014 FY 2014 OCO ## Total FY 2015 FY 2016 FY 2017 FY 2018

UNCLASSIFIED R-1 ITEM NOMENCLATURE. FY 2014 FY 2014 OCO ## Total FY 2015 FY 2016 FY 2017 FY 2018 Exhibit R-2, RDT&E Budget Item Justification: PB 2014 Army DATE: April 2013 COST ($ in Millions) Years FY 2012 FY 2013 # ## FY 2015 FY 2016 FY 2017 FY 2018 Army Page 1 of 8 R-1 Line #111 To Program Element

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2013 Air Force DATE: February 2012 COST ($ in Millions) FY 2011 FY 2012 FY 2014 FY 2015 FY 2016 FY 2017 To Program Element 99.992 132.881 143.000-143.000

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE Exhibit R-2, RDT&E Budget Item Justification: PB 213 Navy DATE: February 212 COST ($ in Millions) FY 211 FY 212 FY 214 FY 215 FY 216 FY 217 To Complete Program Element 25.229.872.863 7.6 8.463.874.876.891.96

More information

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 9 R-1 Line #164

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 9 R-1 Line #164 Exhibit R-2, RDT&E Budget Item Justification: PB 2017 Air Force : February 2016 3600: Research, Development, Test & Evaluation, Air Force / BA 7: Operational Systems Development COST ($ in Millions) Years

More information

ARMY RDT&E BUDGET ITEM JUSTIFICATION (R-2 Exhibit)

ARMY RDT&E BUDGET ITEM JUSTIFICATION (R-2 Exhibit) BUDGET ACTIVITY ARMY RDT&E BUDGET ITEM JUSTIFICATION (R-2 Exhibit) PE NUMBER AND TITLE 7 - Operational system development 0303140A - Information Systems Security Program COST (In Thousands) FY 2001 FY

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 213 Navy DATE: February 212 COST ($ in Millions) FY 211 FY 212 Base OCO Total FY 214 FY 215 FY 216 FY 217 To Complete Total Total Program Element 168.157

More information

UNCLASSIFIED FY 2017 OCO. FY 2017 Base

UNCLASSIFIED FY 2017 OCO. FY 2017 Base Exhibit R-2, RDT&E Budget Item Justification: PB 2017 Army : February 2016 2040: Research, Development, Test & Evaluation, Army / BA 7: Operational Systems Development COST ($ in Millions) Years FY 2015

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE Exhibit R-2, RDT&E Budget Item Justification: PB 2013 Air Force DATE: February 2012 COST ($ in Millions) Total FY 2014 FY 2015 FY 2016 FY 2017 Cost To Complete Total Cost Total Program Element 32.797 23.511

More information

UNCLASSIFIED FY 2016 OCO. FY 2016 Base

UNCLASSIFIED FY 2016 OCO. FY 2016 Base Exhibit R-2, RDT&E Budget Item Justification: PB 2016 Air Force Date: February 2015 3600: Research, Development, Test & Evaluation, Air Force / BA 6: RDT&E Management Support COST ($ in Millions) Prior

More information

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE F: Air Traffic Control/Approach/Landing System (ATCALS) FY 2013 OCO

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE F: Air Traffic Control/Approach/Landing System (ATCALS) FY 2013 OCO COST ($ in Millions) FY 2011 FY 2012 Base OCO Total FY 2014 FY 2015 FY 2016 FY 2017 Cost To Complete Total Cost Total Program Element 26.209 20.644 43.187-43.187 28.526 19.802 7.405 5.225 Continuing Continuing

More information

UNCLASSIFIED FY 2016 OCO. FY 2016 Base

UNCLASSIFIED FY 2016 OCO. FY 2016 Base Exhibit R-2, RDT&E Budget Item Justification: PB 2016 Army : February 2015 2040: Research, Development, Test & Evaluation, Army / BA 5: System Development & Demonstration (SDD) COST ($ in Millions) Years

More information

UNCLASSIFIED. FY 2016 Base FY 2016 OCO

UNCLASSIFIED. FY 2016 Base FY 2016 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2016 Air Force : February 2015 3600: Research, Development, Test & Evaluation, Air Force / BA 5: System Development & Demonstration (SDD) COST ($ in Millions)

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE Exhibit R-2, RDT&E Budget Item Justification: PB 213 Army DATE: February 212 COST ($ in Millions) FY 211 FY 212 FY 214 FY 215 FY 216 FY 217 To Program Element 1.547 1.935 4.39-4.39 2.917 2.977 3.25 3.77

More information

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE BB: SOF Underwater Systems

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE BB: SOF Underwater Systems Exhibit R-2, RDT&E Budget Item Justification: PB 2012 United States Special Operations Command DATE: February 2011 COST ($ in Millions) FY 2010 FY 2011 Total FY 2013 FY 2014 FY 2015 FY 2016 To Complete

More information

UNCLASSIFIED FY 2016 OCO. FY 2016 Base

UNCLASSIFIED FY 2016 OCO. FY 2016 Base Exhibit R2, RDT&E Budget Item Justification: PB 2016 Navy : February 2015 1319: Research, Development, Test & Evaluation, Navy / BA 7: Operational Systems Development COST ($ in Millions) Years R1 Program

More information

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE F: Control and Reporting Center (CRC) FY 2012 OCO

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE F: Control and Reporting Center (CRC) FY 2012 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2012 Air Force DATE: February 2011 COST ($ in Millions) FY 2010 FY 2013 FY 2014 FY 2015 FY 2016 To Program Element 48.616 58.313 3.954-3.954 7.212 3.129

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE Exhibit R-2, RDT&E Budget Item Justification: PB 2013 Air Force DATE: February 2012 COST ($ in Millions) Total Program Element - 9.967 8.117-8.117 50.084 104.866 132.174 229.912 Continuing Continuing 675346:

More information

UNCLASSIFIED FY 2016 OCO. FY 2016 Base

UNCLASSIFIED FY 2016 OCO. FY 2016 Base Exhibit R-2, RDT&E Budget Item Justification: PB 2016 United States Special Operations Command : February 2015 0400: Research, Development, Test & Evaluation, Defense-Wide / BA 7: Operational Systems Development

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE PE F: WEATHER SERVICE. FY 2011 Total Estimate. FY 2011 OCO Estimate

UNCLASSIFIED R-1 ITEM NOMENCLATURE PE F: WEATHER SERVICE. FY 2011 Total Estimate. FY 2011 OCO Estimate Exhibit R-2, RDT&E Budget Item Justification: PB 2011 Air Force DATE: February 2010 COST ($ in Millions) FY 2009 Actual FY 2010 FY 2012 FY 2013 FY 2014 FY 2015 To Program Element 45.918 33.291 32.373 0.000

More information

EXHIBIT R-2, RDT&E Budget Item Justification RESEARCH DEVELOPMENT TEST & EVALUATION, NAVY / BA4

EXHIBIT R-2, RDT&E Budget Item Justification RESEARCH DEVELOPMENT TEST & EVALUATION, NAVY / BA4 EXHIBIT R-2, RDT&E Budget Item Justification APPROPRIATION/BUDGET ACTIVITY RESEARCH DEVELOPMENT TEST & EVALUATION, NAVY / BA4 R-1 ITEM NOMENCLATURE 0603237N Deployable Joint Command & Control (DJC2) COST

More information

UNCLASSIFIED. Cost To Complete Total Program Element 1, , : Evolved Expendable Launch Vehicle

UNCLASSIFIED. Cost To Complete Total Program Element 1, , : Evolved Expendable Launch Vehicle Exhibit R-2, RDT&E Budget Item Justification: PB 2015 Air Force : March 2014 3600: Research, Development, Test & Evaluation, Air Force / BA 5: System Development & Demonstration (SDD) COST ($ in Millions)

More information

ARMY RDT&E BUDGET ITEM JUSTIFICATION (R-2 Exhibit)

ARMY RDT&E BUDGET ITEM JUSTIFICATION (R-2 Exhibit) BUDGET ACTIVITY ARMY RDT&E BUDGET ITEM JUSTIFICATION (R-2 Exhibit) PE NUMBER AND TITLE 7 - Operational system development 0303140A - Information Systems Security Program COST (In Thousands) FY 2002 FY

More information

ARMY RDT&E BUDGET ITEM JUSTIFICATION (R2 Exhibit)

ARMY RDT&E BUDGET ITEM JUSTIFICATION (R2 Exhibit) Budget Item Justif ication Exhibit R-2 0603460A Joint A ir-to-ground Missile (JAGM) ARMY RDT&E BUDGET ITEM JUSTIFICATION (R2 Exhibit) COST (In Thousands) Actual Estimate Estimate to JOINT AIR-TO-GROUND

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE Exhibit R-2, RDT&E Budget Item Justification: PB 2014 Air Force DATE: April 2013 COST ($ in Millions) # ## FY 2015 FY 2016 FY 2017 FY 2018 To Program Element - 16.397 1.975 1.971-1.971 1.990 1.989 2.023

More information

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE D8Z: Human, Social and Culture Behavior (HSCB) Modeling Advanced Development FY 2011 OCO Estimate

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE D8Z: Human, Social and Culture Behavior (HSCB) Modeling Advanced Development FY 2011 OCO Estimate Exhibit R-2, RDT&E Budget Item Justification: PB 2011 Office of Secretary Of Defense DATE: February 2010 0400: Research,, Test & Evaluation, Defense-Wide BA 4: Advanced Component & Prototypes (ACD&P) COST

More information

2016 Major Automated Information System Annual Report

2016 Major Automated Information System Annual Report 2016 Major Automated Information System Annual Report Global Combat Support System-Marine Corps Logistics Chain Management Increment 1 (GCSS-MC LCM Inc 1) Defense Acquisition Management Information Retrieval

More information

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE F: Specialized Undergraduate Pilot Training. FY 2011 Total Estimate. FY 2011 OCO Estimate

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE F: Specialized Undergraduate Pilot Training. FY 2011 Total Estimate. FY 2011 OCO Estimate Exhibit R-2, RDT&E Budget Item Justification: PB 2011 Air Force DATE: February 2010 COST ($ in Millions) FY 2009 Actual FY 2010 FY 2012 FY 2013 FY 2014 FY 2015 To Complete Program Element 11.801 10.862

More information

UNCLASSIFIED. FY 2017 Base FY 2017 OCO

UNCLASSIFIED. FY 2017 Base FY 2017 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2017 Air Force : February 2016 3600: Research, Development, Test & Evaluation, Air Force / BA 7: Operational Systems Development COST ($ in Millions) (+)

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE Exhibit R-2, RDT&E Budget Item Justification: PB 213 Navy DATE: February 212 COST ($ in Millions) FY 211 FY 212 FY 214 FY 215 FY 216 FY 217 Navy Page 1 of 26 R-1 Line #87 To Complete Program Element 51.826

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE Exhibit R-2, RDT&E Budget Item Justification: PB 213 Army DATE: February 212 24: Research, Development, Test & Evaluation, Army COST ($ in Millions) FY 211 FY 212 Total FY 214 FY 215 FY 216 FY 217 To Complete

More information

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 9 R-1 Line #188

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 9 R-1 Line #188 Exhibit R-2, RDT&E Budget Item Justification: PB 2017 Air Force : February 2016 3600: Research, Development, Test & Evaluation, Air Force / BA 7: Operational Systems Development COST ($ in Millions) Years

More information

UNCLASSIFIED. FY 2016 Base FY 2016 OCO

UNCLASSIFIED. FY 2016 Base FY 2016 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2016 Army Date: February 2015 2040: Research, Development, Test & Evaluation, Army / BA 4: Advanced Component Development & Prototypes (ACD&P) COST ($ in

More information

UNCLASSIFIED. UNCLASSIFIED Navy Page 1 of 10 R-1 Line #98

UNCLASSIFIED. UNCLASSIFIED Navy Page 1 of 10 R-1 Line #98 Exhibit R2, RDT&E Budget Item Justification: PB 2015 Navy : March 2014 1319: Research, Development, Test & Evaluation, Navy / BA 5: System Development & Demonstration (SDD) COST ($ in Millions) Years FY

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE Exhibit R-2, RDT&E Budget Item Justification: PB 2013 United States Special Operations Command DATE: February 2012 COST ($ in Millions) FY 2011 FY 2012 Preparation (MTPS) Total FY 2014 FY 2015 FY 2016

More information

UNCLASSIFIED. FY 2017 Base FY 2017 OCO

UNCLASSIFIED. FY 2017 Base FY 2017 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2017 Air Force : February 2016 COST ($ in Millions) Years FY 2018 FY 2019 FY 2020 FY 2021 To Program Element 966.537 66.374 29.083 54.838 0.000 54.838 47.369

More information

UNCLASSIFIED FY 2017 OCO. FY 2017 Base

UNCLASSIFIED FY 2017 OCO. FY 2017 Base Exhibit R-2, RDT&E Budget Item Justification: PB 2017 Air Force : February 2016 3600: Research,, Test & Evaluation, Air Force / BA 7: Operational Systems COST ($ in Millions) FY 2018 FY 2019 FY 2020 FY

More information

Exhibit R-2, RDT&E Budget Item Justification February 2008

Exhibit R-2, RDT&E Budget Item Justification February 2008 PE NUMBER: 41318F PE TITLE: CV-22 Exhibit R-2, RDT&E Budget Item Justification February 28 5 System Development and Demonstration (SDD) 41318F CV-22 ($ in Millions) 413 Total Program Element (PE) CV-22

More information

UNCLASSIFIED. FY 2017 Base FY 2017 OCO

UNCLASSIFIED. FY 2017 Base FY 2017 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2017 United States Special Operations Command : February 2016 0400: Research, Development, Test & Evaluation, Defense-Wide / BA 7: Operational Systems Development

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE Exhibit R-2, RDT&E Budget Item Justification: PB 2013 Air Force DATE: February 2012 COST ($ in Millions) FY 2011 FY 2014 FY 2015 FY 2016 FY 2017 To Program Element 138.051 101.348 120.676-120.676 124.805

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2013 Missile Defense Agency DATE: February 2012 COST ($ in Millions) FY 2011 FY 2012 FY 2014 FY 2015 FY 2016 FY 2017 To Program Element 286.142 306.185

More information

UNCLASSIFIED. FY 2016 Base FY 2016 OCO. Quantity of RDT&E Articles Program MDAP/MAIS Code: 121

UNCLASSIFIED. FY 2016 Base FY 2016 OCO. Quantity of RDT&E Articles Program MDAP/MAIS Code: 121 Exhibit R-2, RDT&E Budget Item Justification: PB 2016 Air Force : February 2015 3600: Research, Development, Test & Evaluation, Air Force / BA 5: System Development & Demonstration (SDD) COST ($ in Millions)

More information

Exhibit R-2, RDT&E Budget Item Justification February 2008

Exhibit R-2, RDT&E Budget Item Justification February 2008 PE NUMBER: 65278F PE TITLE: HC/MC-13 Recap Exhibit R-2, RDT&E Budget Item Justification February 28 5 System Development and Demonstration (SDD) 65278F HC/MC-13 Recap ($ in Millions) 5249 Total Program

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE. FY 2014 FY 2014 OCO ## Total FY 2015 FY 2016 FY 2017 FY 2018

UNCLASSIFIED R-1 ITEM NOMENCLATURE. FY 2014 FY 2014 OCO ## Total FY 2015 FY 2016 FY 2017 FY 2018 Exhibit R-2, RDT&E Budget Item Justification: PB 2014 Office of Secretary Of Defense DATE: April 2013 COST ($ in Millions) Years FY 2012 FY 2013 # PE 0607210D8Z: Industrial Analysis and Support ## FY 2015

More information

UNCLASSIFIED. FY 2016 Base

UNCLASSIFIED. FY 2016 Base Exhibit R-2, RDT&E Budget Item Justification: PB 2016 Office of the Secretary Of Defense : February 2015 0400: Research, Development, Test & Evaluation, Defense-Wide / BA 4: Advanced Component Development

More information

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE F: Air Traffic Control/Approach/Landing System (ATCALS) FY 2012 OCO

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE F: Air Traffic Control/Approach/Landing System (ATCALS) FY 2012 OCO Exhibit R-2, RDT&E Budget Item Justification: PB 2012 Air Force DATE: February 2011 COST ($ in Millions) FY 2013 FY 2014 FY 2015 FY 2016 Air Force Page 1 of 10 R-1 Line Item #185 To Program Element 12.939

More information

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED R-1 ITEM NOMENCLATURE COST ($ in Millions) FY 2011 FY 2012 Base OCO Total FY 2014 FY 2015 FY 2016 FY 2017 Cost To Complete Total Cost Total Program Element 11.589 20.727 63.853-63.853 60.995 19.248 19.291 15.230 Continuing

More information