1 Response to Devastating Floods and Landslides in Northern Afghanistan (Jawzjan and Badakhshan Provinces) 2014 Annual Project Progress Report UNITED NATIONS DEVELOPMENT PROGRAMME
2 DONOR PROJECT INFORMATION Project ID: Duration: 12 months (1st August July 2015) Strategic Plan Component: Outcome 6 ANDS Component: Environment Total Project Budget: 200,000 US$ Annual Budget 2014: 55,400 US$ Implementing Partner: UNDP Responsible Agency: UNDP Sustainable Development Unit and FOCUS International Project Manager: Mohammad Salim Chief Technical Advisor: Not Applicable Responsible Assistant Country Director: Mamunul Haq Khan Cover Page Photo: Early Recovery consultation workshop on November 26, 2014 Kabul Afghanistan
3 ACRONYMS ANDMA CDCs DRF DRR DRR WG ERNA ERP FGD FOCUS GIS IOM KII M&E MRRD NA NFI NGO PDNA RC RCO ToR UN UNAMA UNDP UNFPA UNHCR UNOCHA Afghanistan National Disaster Management Authority Community Development Councils Disaster Recovery Framework Disaster Risk Reduction Disaster Risk Reduction Working Group Early Recovery Needs Assessment Early Recovery Plan Focus Group Discussion FOCUS Humanitarian Assistance Geographical Information System International Organization for Migration Key Informant Interview Monitoring and Evaluation Ministry of Rural Rehabilitation and Development Not Available Non-Food Item Non-Government Organization Post-Disaster Needs Assessment Resident Coordinator Resident Coordinator s Office Terms of Reference United Nations United Nations Assistance Mission in Afghanistan United Nations Development Program United Nations Population Fund United Nations High Commissioner for Refugees United Nations Office for Coordination of the Humanitarian Assistance
4 TABLE OF CONTENTS I. RESULTS:... 2 II. GENDER SPECIFIC RESULTS... 5 III. PARTNERSHIPS... 5 IV. ISSUES... 5 V. RISKS... 6 VI. LESSONS LEARNED... 7 VII. FUTURE PLANS... 7 VIII. ANNEXES... 8 A. Annex 1: FINANCIAL TABLE... 8 B. ANNEX 2: EXPENSES BY OUTPUT... 9 C. ANNEX 4: RISK LOG D. ANNEX 5: ISSUE LOG... 11
5 I. EXECUTIVE SUMMARY Flash floods of April and a subsequent devastating landslide occurred on 2 May 2014 impacted 35 districts across 10 provinces of northern Afghanistan caused human casualty and severe damage of assets and infrastructure affecting thousands of people. While humanitarian agencies are actively collaborating with the government in providing support to the affected people to meet the urgent and immediate needs, recurring flooding events in Northern Afghanistan are aggravating the vulnerability of the people. This project would carry out a comprehensive needs assessment to identify early recovery and rehabilitation needs as well as identify appropriate options for enhancing long term resilience of the affected population in Badakhshan and Jawzjan provinces. On the basis of the needs assessment, a comprehensive plan would be prepared for recovery, rehabilitation and resilience building. The Sustainable Development Unit (SDU) of UNDP has started the Early Recover Project in response to devastating floods and landslides in northern Afghanistan (Jawzjan and Badakhshan provinces) from 1 st August 2014 with the recruitment of two qualified and experienced national staff as National Officers for Early Recovery and Rehabilitation. One ERR officer for SDU Unit and another for Resident Coordinator s Office (RCO) to ensure the successful and proper implementation of the project activities. Meanwhile, SDU has assigned an International Organization (FOCUS International) based on competitive procurement procedure to conduct the Early Recovery Need Assessment (ERNA), prepare a detailed report of ERNA and develop a comprehensive Development Action Plan for Jawzjan and Badakhshan provinces. The project activities were coordinated with government ministries (ANDMA and MRRD), UN agencies such as UNOCHA, WFP, UNICEIF, FAO, UNEF, IOM, DRR working group and with other DRR stakeholders. The project information was also shared with all 14 humanitarian clusters in the country. FOCUS International, the implementing partner has developed and submitted the comprehensive Inception Report indicating the planning and implementing methodology for conducting ERNA in targeted provinces. A one day consultation workshop was conducted on 26 th November 2014 at Inter-Continental Hotel, all Humanitarian Cluster members, UN Agencies, 13 line ministry representatives and other stakeholders participated in the workshop. Project and ERNA information was shared with the participants to receive their inputs, feedback and support in effective implementation of the project. The Report of the workshop was prepared by FOCUS and shared with UNDP. The ERNA questionnaire and survey tools were development by FOCUS International and translated into local languages as well as the field level data collectors were trained on the questionnaire and data collection methodology by UNDP, RCO and FOCUS International. FOCUS International started field level activities in Badakhshan and Jawzjan provinces in Early December 2014 and identified key areas of improvement as well as requested for the no cost extension for extending the period of data collection and report submission due to security and accessibility reasons in targeted areas; The no cost extension request has not been submitted to UNDP procurement yet. 1 P a g e
6 II. RESULTS Output: Appropriate plan is developed for early recovery, rehabilitation and resilience building for the community in the disaster affected areas of Northern Afghanistan. A.1 Indicator 1: Number of RC Office staff trained on early recovery principles: Five staff members of RC Office were trained in early recovery principles. One Early Recovery and Rehabilitation Officer was recruited and placed in Resident Coordinator s Office to ensure Early Recovery activities are reflected in development response to disasters and to ensure coordination of ERNA with Government, UN agencies and all Clusters. A.2 Indicator 2: Number of Early Recovery meetings held: Twenty Early Recovery meetings were held and Project team shared information and delivered presentations on early recovery in 14 different humanitarian clusters and DRR working groups such as Disaster Risk Reduction, Nutrition, Health, Food Security and Agriculture, Water Sanitation and Hygiene, GBV Sub Cluster, Emergency Shelter and Non Food Items, Emergency Preparedness Sub working group, Afghanistan Humanitarian Forum, Inter Cluster coordination, Protection, Child Protection in Emergencies Sub Cluster, Program Management Team and National IDP task force. The Early Recovery Project team also conducted monthly meetings with ANDMA and Ministry of Rural Rehabilitation and Development (MRRD) as well as with Implementing partner FOCUS International to share and provide sufficient information about Early Recovery Data collection, assessment and information. A.3 Indicator 3: NGO to conduct Early Recovery Needs Assessments (ERNA) mobilized: UNDP recruited qualified and experienced Implementing Partner (FOCUS Humanitarian International) through open biding competition for conducting Early Recovery Needs Assessment (ERNA) in Badakhshan and Jawzjan provinces and developing Early Recovery Action Plan. FOCUS International collected secondary data for cross checking and verification from ANDMA, MRRD, IOM, UNOCHA and other stakeholders for targeted districts of Badakhshan and Jawzjan provinces through their coordination meeting. The team in the field level were mobilized and the format for the collecting data were drafted to start the need assessment process. In Badakhshan the need assessment in a few villages were mobilized but in Jowzjan Province it was not started due to security and community conflict. Data collection in Badakhshan province 2 P a g e
7 A.4 Indicator 4: Processes of ERNA properly monitored: The Implementing Partner, FOCUS International conducted field visits to Badakhshan and Jawzjan provinces for collecting primary data and receiving confirmation on the damages and losses occurred due to landslides and flush floods. Monitoring visits took place by the FOCUS International to ensure the quality of primary data collection but UNDP did not conduct any field monitoring visits due to worse security condition in Jawazjan and Badakhshan provinces. A.5 Indicator 5: UNDP capacity strengthening in Early Recover: UNDP recruited one National Officer for Early Recovery and Rehabilitation trained the GIRoA official s staff in early recovery and rehabilitation and provided the information regarding the assessment take place in Badakhsan and Jawzjan provinces. UNDP and FOCUS International in close coordination with ANDMA and MRRD conducted one day consultation workshop on 26 th November 2014 at Inter-Continental Hotel to share information regarding early recovery project on larger scale that support the implementation and coordination methodology in the field. All relevant stakeholders (UN agencies, Line ministries, donor organizations, National and International NGOs and provincial Early Recovery Workshop conducted in November 2014 representatives of ANDMA and MRRD) participated in the workshop that supported to strengthening Early Recovery process. FOCUS international developed field implementation plan based on the findings and recommendations of the mentioned workshop. A.6 Indicator 6: One NGO recruited to develop Early Recovery Plan: Focus international was emplaced to carry out the development of Early Recovery plan for the two provinces of the northern region of Afghanistan. On the basis of the result of ERNA, Focus International will draft two Early Recovery Plans specific to the two affected areas will be developed. Special focus has to be on building consensus among all the actors that the plan would be the basis for all to act and it would be implemented in a coherent, concerted and coordinated manner. EXPENSES FOR THE YEAR: USD 40, P a g e
8 Table 1 (Results) 2014 BASELINE 2014 ANNUAL TARGETS Inadequate RC office coordination 5 RCO staff oriented on on early recovery issues early recovery Q3 Q ACTUAL COMMENTS x Five staff members of RCO was oriented on early recovery. This it is on-target Existence of DRR working group and DRR task force 10 Early recovery monthly meeting held x x Twenty meetings of Early Recovery were held. This is on-target No comprehensive early recovery assessment done One NGO recruited to undertake ER assessment x FOCUS Humanitarian International was recruited to undertake early recovery assessment This it is on-target No monitoring mechanism in place 3 monitoring visits to oversee the process of ERA undertaken x x FOCUS international consultants had to monitor the process UNDP staff could not have any monitoring visits due to the security both in Badakhshan and Jowjzan No dedicated staff for early recovery at UNDP No early recovery plan exist One UNDP national staff recruited and trained on early recovery One NGO recruited to develop comprehensive ER plan x x 2 early recovery officers were recruited (one for UNDP and another for RC office) FOCUS humanitarian was recruited to developed early recovery action plan This it is on-target This is on-target Some important things to keep in mind: Adjust graph to specific needs of projects. When targets are not split into quarters, remove the Q1-Q4 columns or put N/A The comments section should note progress and provide a brief explanation if behind planned target 4 P a g e
9 III. GENDER SPECIFIC RESULTS The project activities and methodology is shared with the department of Women Affairs at provincial level by FOCUS International. Based on field visits of the implementing partner all humanitarian organizations distributed NFIs packages to women and children to consider gender equality in responses to emergencies and natural disasters in Badakhshan and Jawzjan provinces. The questionnaire and survey forms consists special analytical methods to understand the gender dimension in a comprehensive manner which will be reflected in both the Early Recovery Need Assessment report and Development Action Plan. A mixed-gender assessment team will address vulnerabilities related to gender, and the capacity of women and girls to engage in implementation of early recovery action plan. IV. PARTNERSHIPS The project is implemented in close coordination and partnership among UNDP, UNOCHA and Resident Coordinator s Office where UNOCHA is taking lead on coordinating Early Recovery activities in all relevant clusters and the RC office providing effective coordination on the project while UNDP is responsible for the quality assurance and effective implementation of the project activities in targeted provinces. On the other hand ANDMA and MRRD are the Government counterparts ensuring that the secondary and primary data is collected and verified at both national and sub national levels. Both ANDMA and MRRD are providing necessary support at the field level for the data collection in Badakhshan and Jawzjan provinces. V. ISSUES FOCUS International has started the Early Recovery Need Assessment in both provinces. Field data collection process is going very smoothly in coordination with local government and relevant agencies. Consultation sessions took place with community leaders, district governors and police heads of the Jawzjan and Badakhshan provinces. The overall progress of the project activities are on right track. However, due to security and political challenges in the targeted provinces, the project may be delayed till end of 2015 due to the following reasons. The recruitment of NGO and staff took more than three months due to lengthy HR and procurement processes of UNDP. NGO was not able to deploy field team for data collection on time due to security concerns in Jawzjan province and a few flood affected areas of Badakhshan province. 5 P a g e
10 Due to discrepancy in primary and secondary data received from the government line ministries and clusters, FOCUS International requested for additional time through no cost extension to collect, verify and compile all the data. Considering the above mentioned facts the project activities delayed to a certain extent and FOCUS International has not submitted the No-cost extension memo to UNDP procurement unit to extend the implementation period in order to complete all deliverables till to the end of December, The RCO will be required to continue its support the project through vital coordination with clusters, UN agencies and other stakeholders. VI. RISKS Security and Instability: The instability in Jawzjan and Badakhshan provinces created challenges in terms of access and primary data collection from reliable ground sources regarding the damages and losses caused by flash floods and landslides. The Implementing partner hired local staff members who have good local knowledge and are familiar with local sensitivities to remain low profile and collect accurate primary data required for analysis and reporting purposes. Data collection: The secondary data from relevant authorities was not filtered in an appropriate manner in order to ensure receiving accurate data, FOCUS International conducted field level need assessment to collect accurate primary data on the losses and damages due to landslides and flash floods in targeted areas. FOCUS International suggested conducting more consultation and discussion sessions with influential and key leaders of communities in both provinces to ensure the accuracy of the collected data. Ownership and Coordination: Going forward, there is medium risk that the project will have ownership and coordination issues from the government side. There is no short-term solution to this risk. However, increased support from the Project Board can mitigate some of the risk. Given the current security situation, further delays are also expected where interaction is required with provincial Government offices for the preparation of the Action Plan. 6 P a g e
11 VII. LESSONS LEARNED One of the lessons learnt from the project is to conduct preliminary assessment of community conflict and security situation prior to deploying data collection team to make sure the data can be collected on timely basis and without any security threats directed to the project staff in both targeted provinces. The Implementing Partner FOCUS International should have reflected the security situations and analysis in the inception report for proper planning and implementing purposes. The field level coordination and cooperation among ANDMA, MRRD and FOCUS International should have been established in the earlier stages of the project for avoiding time extending of project deliverables. A strong coordination among all stakeholders such as RC Office, UNOCHA, ANDMA, MRRD, UNDP and FOCUS international is required to ensure all project activities are implemented according the designed scheduled and to mainstream Early Recovery in all development plans and activities in Afghanistan. Post Disaster Needs Assessment (PDNA) is a new concept in Afghanistan. Internationally, mainly the governments leads the process. However, security situation in Afghanistan keeps the Government on its toes in terms of provision of relief, which takes away attention and resources from longer term development initiatives at all levels. This situation is beyond the control of the project. This situation implies higher costs for the implementation of the current project and greater risks of failure. Success of the project requires persistence and willingness to educate others on part of sponsoring UN agencies and FOCUS. VIII. FUTURE PLANS UNDP will approve the No Cost Extension for FOCUS International to allow all deliverables to be completed and submitted according to the Annual Work Plan (AWP). FOCUS International will complete the Early Recovery Needs Assessment (ERNA) in targeted provinces and will prepare a comprehensive report of the ERNA to be submitted to UNDP and other stakeholders such as ANDMA, MRRD, UNOCHA and RC Office. UNDP and FOCUS will convene a one day workshop in Badakhshan province to bring all relevant stakeholders, share with them the achievements so far and get their ideas and advise in the process. Security situation in Afghanistan has resulted in serious delays affecting the timeline of the project. Draft Needs Assessment report, which was expected to be ready by the end of December 2014, is now expected to be completed by the mid to end of February P a g e
12 IX. ANNEXES A. Annex 1: FINANCIAL TABLE 8 P a g e
13 B. ANNEX 2: EXPENSES BY OUTPUT 9 P a g e
14 C. ANNEX 4: RISK LOG # Description 1 The instability in Jawzjan and Badakhshan provinces created challenges in terms of access and primary data collection from reliable ground sources regarding the damages and losses caused by flush floods and landslides. Date Identified 10 December 2014 Type Security Impact & Probability The risk has prevented access to the targeted districts and villages to conduct field visits and data collect Countermeasures / Management response The Implementing partner hired local staff members who have good local knowledge and are familiar with local sensitivities to remain low profile and collect as much as accurate primary data required for analysis and reporting purposes. FOCUS International suggested conducting more consultation and discussion sessions with influential and key leaders of communities in both provinces to ensure the accuracy of the data collected. Owner FOCUS International Submitted by FOCUS International Status Resolved 10 P a g e
15 D. ANNEX 5: ISSUE LOG ID Type Date Identified 001 HR/Procurement 31 October Security 10 December Procurement 15 December 2015 Description The recruitment of NGO and staff took more than three months due to lengthy HR and procurement processes of UNDP. NGO was not able to deploy field team for data collection on time due to security concerns in Jawzjan province and a few flood affected areas of Badakhshan province. Due to discrepancy in primary and secondary data received from the government line ministries and clusters, FOCUS International requested for additional time through no cost extension to collect, verify and compile all the data. Status/Priority Resolved/Low Ongoing/High Ongoing/High Status Change Date 10 December January January 2015 Author Eng. Saleem FOCUS International FOCUS International 11 P a g e
TERMS OF REFERENCE RWANDA LESSONS LEARNED ON DISASTER RECOVERY
TERMS OF REFERENCE RWANDA LESSONS LEARNED ON DISASTER RECOVERY Job Title: Category: Duty Station: Type of contract: Expected starting date: Duration of assignment: Individual Consultancy Communications
More informationTERMS OF REFERENCE Individual Contractor. National Consultant Post Disaster Needs Assessment in Cambodia
TERMS OF REFERENCE Individual Contractor 1. Project Information Assignment Title Organization Post Level Cluster/Project Duty Station Duration National Consultant Post Disaster Needs Assessment in Cambodia
More informationWater, Sanitation and Hygiene Cluster. Afghanistan
Water, Sanitation and Hygiene Cluster Afghanistan Strategy Paper 2011 Kabul - December 2010 Afghanistan WASH Cluster 1 OVERARCHING STRATEGY The WASH cluster agencies in Afghanistan recognize the chronic
More informationDisaster Management Structures in the Caribbean Mônica Zaccarelli Davoli 3
Disaster Management Structures in the Caribbean Mônica Zaccarelli Davoli 3 Introduction This chapter provides a brief overview of the structures and mechanisms in place for disaster management, risk reduction
More informationIASC Subsidiary Bodies. Reference Group on Meeting Humanitarian Challenges in Urban Areas Work Plan for 2012
INTER-AGENCY STANDING COMMITTEE WORKING GROUP IASC Subsidiary Bodies Reference Group on Meeting Humanitarian Challenges in Urban Areas Work Plan for 2012 Date circulated: 31/10/2011 I Narrative Summary
More informationEmergency Education Cluster Terms of Reference FINAL 2010
Emergency Education Cluster Terms of Reference FINAL 2010 Introduction The Government of Pakistan (GoP), in partnership with the Humanitarian Coordinator in Pakistan, is responsible for leading and ensuring
More informationTERMS OF REFERENCE. East Jerusalem with travel to Gaza and West Bank. June 2012 (flexible depending on consultant availability between June-July 2012)
TERMS OF REFERENCE THE DEVELOPMENT OF TRAINING FOR WASH CLUSTER PARTNERS IN THE DEVELOPMENT & DESIGN OF KNOWLEDGE, ATTITUDE, PRACTICE SURVEYS IN THE OCCUPIED PALESTINIAN TERRITORY. Summary Title Purpose
More informationEvaluation of the Global Humanitarian Partnership between Save the Children, C&A and C&A Foundation
Evaluation of the Global Humanitarian Partnership between Save the Children, C&A and C&A Foundation Terms of Reference Contents: I. INTRODUCTION 2 II. GLOBAL HUMANITARIAN PARTNERSHIP 3 III. SCOPE 4 IV.
More informationQuarterly Progress Report Mogadishu Clean-up Support Project (Atlas ID: )
Quarterly Progress Report Mogadishu Clean-up Support Project (Atlas ID: 00085376) Reporting Period 01 April to 30 June 2015 Government Counterpart PSG PSG priorities Focus Locations: AWP Budget 594,150
More informationCCCM Cluster Somalia Terms of Reference
I. Background Due to significantly below average rains, severe drought conditions and the underlying security risks and conflicts have forced more than 600,000 people to leave their homes across Somalia
More information1 FSAC Minutes of Meeting- August 6, 2012 TYPE OF MEETING: DATE & LOCATION CHAIR PERSON: NOTE TAKER:
TYPE OF MEETING: DATE & LOCATION CHAIR PERSON: NOTE TAKER: ATTENDEES: FSAC Regional Monthly Meeting Monday,September 3 rd, 2012 at DAIL conference room, Mazar-I-Sharif Balkh Province FAO regional leads
More informationPROJECT COMPLETION REPORT
PROJECT COMPLETION REPORT This report must be completed and signed by the Contact person. The information provided below must correspond to the financial information that appears in the financial report.
More informationTerms of Reference. Consultancy for Third Party Monitor for the Aga Khan Development Network Health Action Plan for Afghanistan (HAPA)
Terms of Reference Consultancy for Third Party Monitor for the Aga Khan Development Network Health Action Plan for Afghanistan (HAPA) I. Purpose and Objectives of the Assignment Aga Khan Foundation Canada
More informationThe IASC Humanitarian Cluster Approach. Developing Surge Capacity for Early Recovery June 2006
The IASC Humanitarian Cluster Approach Developing Surge Capacity for Early Recovery June 2006 Aims of the cluster approach The cluster leadership approach is part of a wider process of humanitarian reform
More informationOverall Goal: Contributing to the Humanitarian Response Plan by reducing the numbers of IDPs
Title of Position: Evaluation Team of GFFO Project, Ukraine Location: Kramatorsk, Ukraine (Government Controlled Area) Contract term: 19 September to 26 October 2018 (including preparation, evaluation
More informationDelay in response may result in increased loss of lives and livelihoods.
Islamic Republic of Afghanistan National Disaster Management Authority (ANDMA) 26-29 August 2013 1 Delay in response may result in increased loss of lives and livelihoods. 2 Introduction Afghanistan has
More informationTERMS OF REFERENCE (TOR)
TERMS OF REFERENCE (TOR) Assignment Title: External Evaluation of the School Development Fund project in Mandera County. The project is titled Improving enrolment and retention in primary schools in Mandera
More informationGENERAL INFORMATION Services/Work Description: Project/Program Title: Home-based with travel to Addis Ababa I. BACKGROUND
TOR for reframe project proposal for Resilience and Livelihood support GENERAL INFORMATION Services/Work Description: Project/Program Title: Type of the contract: Duty Station: Duration: Expected Start
More informationWHO s response, and role as the health cluster lead, in meeting the growing demands of health in humanitarian emergencies
SIXTY-FIFTH WORLD HEALTH ASSEMBLY A65/25 Provisional agenda item 13.15 16 March 2012 WHO s response, and role as the health cluster lead, in meeting the growing demands of health in humanitarian emergencies
More informationAFRICAN DEVELOPMENT BANK
Public Disclosure Authorized Public Disclosure Authorized AFRICAN DEVELOPMENT BANK TANZANIA PROPOSAL FOR A GRANT OF US$ 1 MILLION FOR HUMANITARIAN EMERGENCY ASSISTANCE TO MITIGATE THE EFFECTS OF EARTHQUAKE
More informationEuropean Commission - Directorate General - Humanitarian Aid and Civil Protection - ECHO Project Title:
Terms of Reference FINAL PROJECT EVALUATION Strengthening humanitarian action in urban areas by promoting settlement approaches and effective engagement with local stakeholders Executive Summary Donor:
More informationThe Syria Co-ordinated Accountability and Lesson Learning (CALL) Initiative. Terms of Reference for the Thematic Synthesis of Evaluative Reports
The Syria Co-ordinated Accountability and Lesson Learning (CALL) Initiative Terms of Reference for the Thematic Synthesis of Evaluative Reports Background The Syria crisis has entered its fifth year with
More informationIMPACT REPORTING AND ASSESSMENT OFFICER IN SOUTH SUDAN
Terms of Reference IMPACT REPORTING AND ASSESSMENT OFFICER IN SOUTH SUDAN BACKGROUND ON IMPACT AND REACH REACH was born in 2010 as a joint initiative of two International NGOs (IMPACT Initiatives and ACTED)
More informationThe Vanuatu Humanitarian Team
The Vanuatu Humanitarian Team Paolo Malatu VHT Coordinator Oxfam in Vanuatu pacifichumanitarian.info #phtpacific Presentation outline: What and why of the VHT Overview of activities Achievements Challenges
More informationSupporting Nepal to Build Back Better
OCTOBER 2015 Empowered lives. Resilient nations. Supporting Nepal to Build Back Better Key Achievements in UNDP s Earthquake Response UNDP Nepal 1 2 Supporting Nepal to Build Back Better Context Two devastating
More informationUNICEF s response to the Cholera Outbreak in Yemen. Terms of Reference for a Real-Time Evaluation
UNICEF s response to the Cholera Outbreak in Yemen Terms of Reference for a Real-Time Evaluation Background Two years since the escalation of violence in Yemen, a second wave of fast spreading cholera
More informationLIBYA HUMANITARIAN SITUATION REPORT
Libya Humanitarian Situation Report UNICEF/Libya 2016/Libyan Society SITUATION IN NUMBERS Highlights The United Nations estimates that 79,400 people (including 32,000 children) are in need of immediate
More information10 HAZARD IDENTIFICATION TOOL
10 HAZARD IDENTIFICATION TOOL 10.1 BACKGROUND & OVERVIEW "Disasters and conflicts can impact the environment in ways that threaten human life, health, livelihoods and security. Disaster managers and humanitarian
More informationIndonesia Humanitarian Response Fund Guidelines
Indonesia Humanitarian Response Fund Guidelines July 2011 1. OBJECTIVE The Humanitarian Response Fund for Indonesia (hereafter called HRF ) is a Non Governmental Organizations (NGOs) funding mechanism,
More informationCall for Proposals for small grants
ACCESS TO JUSTICE AND RULE OF LAW PROJECT Call for Proposals for small grants CSOs/NGOs implementation of grants to establish community based entry point to referral pathways through the engagement and
More informationConsultancy to Develop the Model Guidelines for Child-Centred Emergency and Disaster Risk Management in Caribbean Schools and Adaptation Guide
1 The Caribbean Disaster Emergency Management Agency REQUEST FOR PROPOSALS RFP #: UNICEF/9070/17 Consultancy to Develop the Model Guidelines for Child-Centred Emergency and Disaster Risk Management in
More informationNorth Lombok District, Indonesia
North Lombok District, Indonesia Local progress report on the implementation of the 10 Essentials for Making Cities Resilient (2013-2014) Mayor: H. Djohan Sjamsu, SH Name of focal point: Mustakim Mustakim
More informationTerms of Reference (TOR) for end of Project Evaluation TECHNOLOGY FOR MATERNAL HEALTH PROJECT
Terms of Reference (TOR) for end of Project Evaluation TECHNOLOGY FOR MATERNAL HEALTH PROJECT 1.0 Organisational Profile: Savana Signatures is an ICT for Development oriented organization registered in
More informationTerms of Reference (ToR) Developing Advocacy Strategy for NCA Partners
Terms of Reference (ToR) Developing Advocacy Strategy for NCA Partners 1. Introduction Norwegian Church Aid (NCA) with its long presence (since 1979) in Afghanistan. NCA is a partner based organization
More informationDate: November Sudan Common Humanitarian Fund 2014 First Allocation Guidelines on Process
Date: November 2013 Sudan Common Humanitarian Fund 2014 First Allocation Guidelines on Process Page 1 of 11 Purpose: The purpose of this document is to describe the allocation processes of the Sudan Common
More informationCALL FOR GENDER-BASED VIOLENCE PREVENTION & RESPONSE IMPLEMENTING PARTNERS
CALL FOR GENDER-BASED VIOLENCE PREVENTION & RESPONSE IMPLEMENTING PARTNERS I. APPLICATION DETAILS PROGRAM TITLE: INTEGRATED EMERGENCY WATER, SANITATION AND HYGIENE (WASH) AND RESPONSE AND PREVENTION OF
More informationPreliminary job information GRANTS & REPORTING OFFICER AFGHANISTAN, KABUL. General information on the Mission
Preliminary job information JOB DESCRIPTION Job Title Country and Base of posting Reports to Creation / Replacement (incl. name) Handover Duration of Mission GRANTS & REPORTING OFFICER AFGHANISTAN, KABUL
More informationREQUIRED DOCUMENT FROM HIRING UNIT
Terms of reference GENERAL INFORMATION Title: Energy Efficiency Project Development Specialist Project Name : Advancing Indonesia s Lighting Market to High Efficient Technologies (ADLIGHT) Reports to:
More informationTerms of Reference For Cholera Prevention and Control: Lessons Learnt and Roadmap 1. Summary
Terms of Reference For Cholera Prevention and Control: Lessons Learnt 2014 2015 and Roadmap 1. Summary Title Cholera Prevention and Control: lessons learnt and roadmap Purpose To provide country specific
More informationDisaster Risk Reduction Development Case Study WHO - UNDP Collaboration on Improving Hospital Safety in Tajikistan
Disaster Risk Reduction Development Case Study WHO - UNDP Collaboration on Improving Hospital Safety in Tajikistan Disaster Risk Management Program United Nations Development Program (UNDP) Tajikistan
More informationTerms of Reference. 1. Introduction
1. Introduction Terms of Reference Consultancy for and end of project evaluation of the HOPE - A Haus (house) for Protection and Empowerment Project Central Province, Papua New Guinea, 2014-2017 ChildFund
More informationGFDRR Country Evaluation:
GFDRR Country Evaluation: Update and Initial Observations Prepared for: 16 th Consultative Group Meeting May 6, 2015 Presented by: Mark Wagner, ICF International (Lead Evaluator) Jessica Kyle, ICF International
More informationObjectives of the Assignment
Terms of Reference: Preparation of Resilience Strategy for Suaahara II Program and designing of Community Resilience Package for improving nutritional and health status of most vulnerable communities.
More informationDREF update Afghanistan: Floods and Landslides
DREF update Afghanistan: Floods and Landslides P a g e 1 DREF Operation n MDRAF002 Glide n FF-2014-000060-AFG DREF update n 3; issued on 15 January 2015 Timeframe covered by this update: 1 October to 31
More informationhumanitarian response to the Syria crisis
evaluation report December 2015 Evaluation of UNICEF s humanitarian response to the Syria crisis Volume 2: Appendices Evaluation of UNICEF s humanitarian response to the Syria crisis Final Report United
More informationMID TERM REVIEW OF EARLY RECOVERY FACILITY (ERF)
Page 1 UNITED NATIONS DEVELOPMENT PROGRAMME BANGLADESH MID TERM REVIEW OF EARLY RECOVERY FACILITY (ERF) February 2014 Preethi De Silva & Hasan Shafie Page 2 ABREVIATIONS& ACRONYMS AusAID BDPC CCED BS CDMP
More informationThe United Nations and International Cooperation
The United Nations and International Cooperation Training and Dispatching Civilian Peacebuilders -Responding to New Challenges to the Ground- Shun-ichi Murata, Director, UNDP Tokyo United Nations Development
More informationHumanitarian and Emergency Affairs Manager, WV Mali/Mauritania
Humanitarian and Emergency Affairs Manager, WV Mali/Mauritania Location: [Africa] [Mali] Town/City: Bamako Category: Humanitarian & Emergency Affairs Job Type: Fixed term, Full-time PURPOSE OF POSITION:
More informationAnalyzing the UN Tsunami Relief Fund Expenditure Tracking Database: Can the UN be more transparent? Vivek Ramkumar
Analyzing the UN Tsunami Relief Fund Expenditure Tracking Database: Can the UN be more transparent? Vivek Ramkumar ramkumar@cbpp.org 820 First St. NE Suite 510 Washington, DC 20002 USA Tel: 1-202 408 1080
More informationDEMOCRATIC PEOPLE S REPUBLIC OF KOREA
DEMOCRATIC PEOPLE S REPUBLIC OF KOREA Assessment of Capacities using SEA Region Benchmarks for Emergency Preparedness and Response SEA-EHA-22-DEMOCRATIC PEOPLE S REPUBLIC OF KOREA Assessment of Capacities
More informationTerms of Reference (TOR) for Independent End of Project Evaluation
Terms of Reference (TOR) for Independent End of Project Evaluation Project Name Increasing the provision of clean energy in Uganda hereafter referred to as Clean Energy Project Project Number(s) ESARPO0218;
More informationFINALIZATION (July 2016) DISASTER RISK REDUCTION ACTION PLAN SUMBAWA DISTRICT Calendar Year: January December 2019
` FINALIZATION (July 2016) DISASTER RISK REDUCTION ACTION PLAN SUMBAWA DISTRICT Calendar Year: January 2016 - December 2019 Name of City/District Province Output Target Focal Point West Nusa Tenggara Disaster
More informationTerms of Reference For Formative research on barriers and enablers of gender equality education in Nepal
Terms of Reference For Formative research on barriers and enablers of gender equality education in Nepal 1 Background Plan International is an independent development and humanitarian organization that
More informationEmergency Plan of Action (EPoA) Tajikistan: Floods in Khuroson District
Emergency Plan of Action (EPoA) Tajikistan: Floods in Khuroson District DREF Operation Operation n MDRTJ018 Glide n MS-2014-000057-TJK Date of issue: 22 April 2014 Date of disaster: 16 April 2014 Operation
More informationUNICEF Cambodia. TERMS OF REFERENCE FOR A CONSULTANT Assist with Emergency Preparedness and Response Plan at sub-national level
UNICEF Cambodia TERMS OF REFERENCE FOR A CONSULTANT Assist with Emergency Preparedness and Response Plan at sub-national level Requesting Section: Local Governance for Child Rights ***************************************************************************
More informationRESIDENT / HUMANITARIAN COORDINATOR REPORT ON THE USE OF CERF FUNDS [COUNTRY] [RR/UFE] [RR EMERGENCY/ROUND I/II YEAR]
Resident / Humanitarian Coordinator Report on the use of CERF funds PLEASE NOTE THAT A PRE-POPULATED TEMPLATE WILL BE PROVIDED TO THE RC/HC OFFICE ONE MONTH PRIOR TO THE EXPIRATION OF THE GRANT. THEREFORE,
More informationNepal : Earthquake Update
Nepal : Earthquake Update Situation Report No. 5 27 September 2011 This report is produced by the OCHA Humanitarian Support Unit, Resident and Humanitarian Coordinator s Office in collaboration with humanitarian
More informationReport of the Administrative Agent of the UN Window of the IMDFF-DR for the period 1 January 31 December 2012
Second Consolidated Annual Progress Report on Activities Implemented under the UN Window of the Indonesia Multi-Donor Fund Facility for Disaster Recovery (IMDFF-DR) Report of the Administrative Agent of
More informationGrantee Operating Manual
Grantee Operating Manual 1 Last updated on: February 10, 2017 Table of Contents I. Purpose of this manual II. Education Cannot Wait Overview III. Receiving funding a. From the Acceleration Facility b.
More informationMALAWI Humanitarian Situation Report
MALAWI Humanitarian Situation Report HIGHLIGHTS SITUATION IN NUMBERS The Education cluster administered a situation analysis of the most affected schools over a period of 4 days via the Real Time Monitoring
More informationINDIVIDUAL CONSULTANT PROCUREMENT NOTICE. for individual consultant and consultant assigned by consulting firm/institution
Date: 26 May 2017 INDIVIDUAL CONSULTANT PROCUREMENT NOTICE for individual consultant and consultant assigned by consulting firm/institution Country: Description of the assignment: Project name: Estimated
More informationSomalia Is any part of this project cash based intervention (including vouchers)? Conditionality:
Somalia 2018 Appealing Agency Project Title Project Code Sector/Cluster Refugee project Objectives MERCY CORPS (MERCY CORPS) Provision of live saving and sustainable WASH interventions to conflict and
More informationHandicap International is looking for : Technical Advisor - Libya
Location : TUNISIA (Tunis) Length : 3 months Starting date : 1 st November 2017 Closing date for applications : 29.10.2017 Handicap International is looking for : Technical Advisor - Libya Outraged by
More informationUnited Nations Development Group Iraq Trust Fund Project #66992: C10-08 Date and Quarter Updated: June nd Quarter 2010
United Nations Development Group Iraq Trust Fund Project #66992: C10-08 Date and Quarter Updated: June 2010 2 nd Quarter 2010 Participating UN Organisation: UNESCO (lead) and UNDP Sector: Economic Reform
More informationTerms of Reference. 1. Introduction. 2. Background
Terms of Reference Consultancy Services for the GEF project Strategic Platform to Promote Sustainable Energy Technology Innovation, Industrial Development and Entrepreneurship in Barbados 1. Introduction
More informationPan-American Disaster Response Unit
Pan-American Disaster Response Unit (Appeal 01.25/2001) Click on figures to go to budget In CHF In CHF 1. Disaster Preparedness 1,672,000 Total 1,672,000 Pan-American Disaster Response Unit (PADRU) Background
More informationWORLD HEALTH ORGANIZATION
WORLD HEALTH ORGANIZATION EXECUTIVE BOARD EB115/6 115th Session 25 November 2004 Provisional agenda item 4.3 Responding to health aspects of crises Report by the Secretariat 1. Health aspects of crises
More information3. Where have we come from and what have we done so far?
Long Term Planning Framework 2012-2015 Democratic People s Republic of Korea (DPRK) DPRK Red Cross, with the support of IFRC and its partners, assist vulnerable communities in the country through both
More informationHumanitarian Response Fund Indonesia
Humanitarian Response Fund Indonesia Credit: Islamic Relief Office for the Coordination of Humanitarian Affairs Note from the Humanitarian Coordinator The Humanitarian Response Fund (HRF), previously the
More informationINTERNATIONAL AGRICULTURE AND FORESTRY EXPERT TERMS OF REFERENCE
INTERNATIONAL AGRICULTURE AND FORESTRY EXPERT TERMS OF REFERENCE Country/Location: UNDP Office, Vientiane, Lao PDR Description of assignment: Short Term to develop the Environmental Impact Assessment Agriculture
More informationCluster Primary cluster Sub cluster WATER, SANITATION AND HYGIENE
Project Proposal Organization Project Title Fund Code SC (Save the Children Fund) Strengthening Accessibility to Safe Water and Enhanced Knowledge on Sanitation and Hygiene Practices AFG 15/O580/SA1/WASH/INGO/330
More informationNorth Sudan Disarmament, Demobilization and Reintegration Programme (NSDDRP)
North Sudan Disarmament, Demobilization and Reintegration Programme (NSDDRP) Call for Proposals (CFP/DDR/007/10) Implementation of Cultural Outreach Project DDR Road show Eastern Sudan A. Background BACKGROUND
More informationUnited Nations Children s Fund (UNICEF)
United Nations Children s Fund (UNICEF) Consultant: Design the Child Protection Pagoda Programme, Training Manual and Operational Plan for the Ministry of Cults and Religion Terms of Reference 1. Background
More informationTERMS OF REFERENCE FOR CONSULTANTS
TERMS OF REFERENCE FOR CONSULTANTS A. Consulting Firm The Asian Development Bank (ADB) will engage a consulting firm in accordance with its Guidelines on the Use of Consultants (2013, as amended from time
More informationNUTRITION. UNICEF Meeting Myanmar/2014/Myo the Humanitarian Needs Thame of Children in Myanmar Fundraising Concept Note 5
NUTRITION Improving Equitable Access to Essential Nutrition Interventions for Conflict-Affected Populations in Rakhine, Kachin and Northern Shan States 1 UNICEF Meeting Myanmar/2014/Myo the Humanitarian
More informationTERMS OF REFERENCE: SECURITY FRAMEWORK ADAPTATION -LIBYA MISSION-
TERMS OF REFERENCE: SECURITY FRAMEWORK ADAPTATION -LIBYA MISSION- Zone/Country Libya Start Date March 2017 Duration Proposition of a 3 phases consultancy - First phase : 7 days - Second phase : 2 weeks
More informationFramework on Cluster Coordination Costs and Functions in Humanitarian Emergencies at the Country Level
Framework on Cluster Coordination Costs and Functions in Humanitarian Emergencies at the Country Level Introduction In February 2010, donor partners and cluster representatives agreed that a small group
More informationCOMMISSION DE LA CEDEAO PLAN OF ACTION OF THE ECOWAS HUMANITARIAN POLICY ( )
COMISSÃO DA CEDEAO COMMISSION COMMISSION DE LA CEDEAO PLAN OF ACTION OF THE HUMANITARIAN POLICY (2012 2017) 1 PLAN OF ACTION OF THE HUMANITARIAN POLICY STRATEGIC OBJECTIVE 1 Ensuring Appropriate Legal
More informationMALAWI Humanitarian Situation Report
MALAWI Humanitarian Situation Report UNICEF s Response with partners HIGHLIGHTS Joint Department of Disaster Management Affairs (DoDMA) and UNRCO situation report of 6 February indicates that the number
More informationGuidelines EMERGENCY RESPONSE FUNDS
Emergency Response Fund (ERF) Guidelines EMERGENCY RESPONSE FUNDS Page 1 of 21 Office for the Coordination of Humanitarian Affairs Contents: A. PURPOSE... 4 B. SCOPE... 4 C. RATIONALE... 4 D. GUIDELINES...
More informationTHIRD NATIONAL FADAMA DEVELOPMENT PROJECT (NFDP 3) THIRD JOINT WORLD BANK/FGN AND CSOs SUPERVISION MISSION (CSOs INDEPENDENT REPORT) EXECUTIVE SUMMARY
THIRD NATIONAL FADAMA DEVELOPMENT PROJECT (NFDP 3) THIRD JOINT WORLD BANK/FGN AND CSOs SUPERVISION MISSION (CSOs INDEPENDENT REPORT) EXECUTIVE SUMMARY The third National Fadama Mission engages CSOs as
More informationGuidelines for Grant Applicants
Guidelines for Grant Applicants The Commonwealth Foundation s mission is to support civic voices to share their stories, learn and act together and influence the institutions that shape people s lives.
More informationWest Africa Regional Office (founded in 2010)
TERMS OF REFERENCE For the External Evaluation of ACF s West Africa Regional Office (founded in 2010) Programme Funded by ACF own funds 29 th November 2012 1. CONTRACTUAL DETAILS OF THE EVALUATION 1.1.
More informationTerms of Reference. International Consultant GEF Project Development Specialist
Antigua and Barbuda Department of Environment GEF/UNDP Medium Sized Project (MSP) Monitoring and assessment of MEA implementation and environmental trends in Antigua and Barbuda Terms of Reference International
More informationCall for Proposals from NGOs INSTRUCTIONS
Call for Proposals from NGOs INSTRUCTIONS I. BACKGROUND UNDP partners with people at all levels of society to help build nations that can withstand crisis, and drive and sustain the kind of growth that
More informationTerms of reference for consultancy Purpose of Project and Background
Vietnam Delegation The International Federation of Red Cross and Red Crescent Societies (IFRC) promotes the humanitarian activities of RC/RC National Societies among vulnerable people. By coordinating
More informationEUROPEAN COMMISSION DIRECTORATE-GENERAL HUMANITARIAN AID AND CIVIL PROTECTION - ECHO
EUROPEAN COMMISSION DIRECTORATE-GENERAL HUMANITARIAN AID AND CIVIL PROTECTION - ECHO SINGLE FORM SINGLE FORM FOR HUMANITARIAN AID ACTIONS 1 1. GENERAL INFORMATION 1.1 Name of Humanitarian Organisation/Country
More informationII. Background Information
II. Background Information Context of the REDD+ initiative: Indonesia is the third largest emitter of CO2 and the world s largest emitter from agriculture, forestry and other land use. Over the past five
More informationChild Care Program (Licensed Daycare)
Chapter 1 Section 1.02 Ministry of Education Child Care Program (Licensed Daycare) Follow-Up on VFM Section 3.02, 2014 Annual Report RECOMMENDATION STATUS OVERVIEW # of Status of Actions Recommended Actions
More informationTerms of Reference. Consultancy to support the Institutional Strengthening of the Frontier Counties Development Council (FCDC)
Terms of Reference Consultancy to support the Institutional Strengthening of the Frontier Counties Development Council (FCDC) 1. Introduction August 2016 to August 2018 1. Supporting Kenya s devolution
More informationGLOBAL REACH OF CERF PARTNERSHIPS
Page 1 The introduction of a new CERF narrative reporting framework in 2013 has improved the overall quality of reporting by Resident and Humanitarian Coordinators on the use of CERF funds (RC/HC reports)
More informationREPORT 2015/187 INTERNAL AUDIT DIVISION. Audit of the operations of the Office for the Coordination of Humanitarian Affairs in Afghanistan
INTERNAL AUDIT DIVISION REPORT 2015/187 Audit of the operations of the Office for the Coordination of Humanitarian Affairs in Afghanistan Overall results relating to effective management of operations
More informationUnited Nations Asia-Pacific Regional Coordination Mechanism Terms of Reference
United Nations Asia-Pacific Regional Coordination Mechanism Terms of Reference Thematic Working Group on Resource Efficient Growth (TWG-REG) August 2016 Objectives The objective of the TWG on Resource
More informationACCESS TO JUSTICE PROJECT. Request for Proposals (RFP)
ACCESS TO JUSTICE PROJECT Request for Proposals (RFP) Request for Civil Society Organizations (CSOs) including NGOs and/or CBOs for application in relation to call for proposals for the establishment of
More informationReport of the joint evaluation of the Indonesian ECB consortium s responses to the West Java and West Sumatra earthquakes
1 Report of the joint evaluation of the Indonesian ECB consortium s responses to the West Java and West Sumatra earthquakes April 2010 Independent Evaluation by Pauline Wilson with the support of Budi
More informationACBAR Twinning Program 2017 Annual Stakeholder Survey Results. For DFID Annual Review from Oct. 1, 2016 Sept. 30, Prepared by Dawn Erickson
ACBAR Twinning Program 2017 Annual Stakeholder Survey Results For DFID Annual Review from Oct. 1, 2016 Sept. 30, 2017 Prepared by Dawn Erickson ACBAR Twinning Program Manager Contents ACBAR Twinning Program...
More informationTERMS OF REFERENCE SETUP AND STRUCTURING OF SHELTER AFRIQUE SOCIAL HOUSING TRUST FUND
TERMS OF REFERENCE SETUP AND STRUCTURING OF SHELTER AFRIQUE SOCIAL HOUSING TRUST FUND 1. BACKGROUND At the 32nd Annual General Meeting held in June 2012 in Kigali Rwanda, Shelter Afrique (SHAF) shareholders
More informationZambezi River Basin Initiative (ZRBI) Progress Update: 12 July 2010
Zambezi River Basin Initiative (ZRBI) Progress Update: 12 July 2010 Introduction The implementation of the ZRBI activities started in the last quarter of 2009, after receiving funding support from the
More informationThe Sphere Project strategy for working with regional partners, country focal points and resource persons
The Sphere Project strategy for working with regional partners, country focal points and resource persons Content 1. Background 2. Aim and objectives 3. Implementation 4. Targets 5. Risks 6. Monitoring
More informationViet Nam. Humanitarian Situation Report No ,000 # of children affected out of 2,000,000 # of people affected
Viet Nam Humanitarian Situation Report No.16 UNICEF s Response with Partners 15 April 2017 Highlights Three lessons learnt workshops with the National Centre for Rural Water Supply and Sanitation (NCERWASS),