1 INFRASTRUCTURE PROJECT FINANCING DWRF AND SRF FUNDING OVERVIEW FOR WATER / WASTEWATER IMPROVEMENTS By: Dima El-Gamal, Ph.D., PE, LEED AP February 8, 2011
2 State Revolving Loan Funds Low-interest Loans Distributed By MDNRE Water Systems Sanitary Sewer Systems Drinking Water Revolving Fund (DWRF) State Revolving Fund (SRF)
3 Why Revolving Loan? Planning/Design/Construction Cost $2,000,000 $5,000,000 $10,000,000 Annual Capital ( 20 years) 2.5% $128,000 $321,000 $641,000 Annual Capital ( 20 years) Bond 5% $160,000 $401,000 $802,000 Annual Savings $32,000 $80,000 $161,000 Total Savings ( 20 years) $640,000 $1,600,000 $3,220,000
4 Drinking Water Revolving Fund Funds Planning, Design and Construction of Water Supply Projects Current Interest Rate is 2.5% Over 20 To 30 Years Projects Funded Based On: Priority Listing Availability of Funds
5 Examples of Eligible Projects Projects That Can Justify/Demonstrate Existing Need Water Source and Treatment Upgrades Security Upgrades Correction of Pressure Deficiencies: Water System Looping To Improve Pressure Upgrades of Water Mains (< 8-inch Diameter) Booster Stations / Pressure Reducing Valves Replacement of Frequently Breaking Water Mains System Replacement / Repairs (Exceeded Its Service Life) Meter Replacements and Meter Reading System
6 Examples of Ineligible Projects Projects That Are Aimed At Only: Promoting Growth Or Improving Fire Flow
7 DWRF PROJECT PRIORITY LIST Water Quality Issues Components Addressed Water Source / Treatment Water Distribution Booster Stations / Storage Tanks Minimum Capacity Reliability System Upgrades Enforcement Action Population Disadvantaged Communities
8 DWRF PROJECT SUBMITTALS PROJECT PLAN Justify Project s Needs Address Project s 20 Year Needs For Project Components Obtain Environmental Clearances Identify Potential Alternatives (Feasibility Analysis And Environmental Impacts) Select Alternative And Estimate Impact On User Charge Public Hearing, Finalize Project Plan, And Submit To Mdnre
9 DWRF Project Plan Timeline ASAP Start Project Planning No Later than March 20 th Public Review Of Draft Project Plan No Later Than April 20 th Public Hearing No Later Than April 20 th Project Plan Adoption No Later Than May 1 st Project Plan Submittal
10 ADDITIONAL DWRF PROJECT SUBMITTALS Three Part Application User Charge System (Draft / Final) Plans and Specifications For Construction Permits Bond Sale Resolution
11 DWRF Design / Construction Timeline August to September Priority Point List
12 Project Phasing Multiple Project Phases Are Allowed For Up To Five Years Project Maintains Priority Ranking For Three Years Project Re-ranked In The Fourth Year
13 STATE REVOLVING FUND Funds Planning, Design and Construction of Wastewater System Improvements Current Interest Rate is 2.5% Over 20 Years Projects Funded Based On: Priority Listing Availability Of Funds
14 Examples of Eligible Projects Projects That Can Justify / Demonstrate Existing Need Enforcement Actions ( ACOs) Wastewater Treatment Plant Upgrades Pump Station Rehabilitation Emergency Backup Power Correction of Infiltration and Inflow Construction of CSO Basins Rehabilitation of Sewers (Imminent )
15 Examples of Ineligible Projects Projects That Are Aimed At: Promoting Growth Storm Water Conveyance
16 SRF PROJECT PRIORITY LIST Water Quality Issues Enforcement Points ( Administrative Consent Orders) Population Discharge Stream Dilution Factors
17 SRF PROJECT SUBMITTALS PROJECT PLAN Justify Existing Needs and Address 20 Year Needs Address Infiltration and Inflow Conduct Pipe / Manhole Assessments per the NASSCO (National Association of Sewer Service Companies) Certification Programs Obtain Environmental Clearances Identify and Evaluate Potential Alternatives Select Alternatives and Estimate The Impact On User Charges Public Hearing, Finalize Project Plan, and Submit to MDNRE
18 SRF Project Plan Timeline ASAP Start Project Planning No Later than May Public Review of Draft Project Plan No Later Than June 20 th Public Hearing No Later Than June 20 th Project Plan Adoption No Later Than July 1 Project Plan Submittal
19 ADDITIONAL SRF PROJECT SUBMITTALS Three Part Application User Charge System (Draft / Final) Plans and Specifications For Construction Permits Bond Sale Resolution
20 SRF Design/Construction Timeline September to October Priority Point List
21 Project Segmenting Multiple Project Segments Are Allowed For Up To Five Years Project Maintains Priority Ranking For Three Years Project Re-ranked On The Fourth Year
22 2011 S2 GRANT Signed Into Law December 14, 2010 Covers 90% of Planning and Design $40 Million Available. Up To $1 Million Per Applicant Covers Expenses Incurred On or After December 14, 2010 Grants Awarded In October, January, April, and July MDNRE Is Working On Application Project Must Be Built Within 3 Years of Receiving the Grant
23 2011 S2 GRANT S2 Grant Eligible Activities: Flow Monitoring Infiltration / Inflow Analysis Sewer System Evaluation Surveys Soil Surveys Wetlands Surveys, SRF Project Plan Activities S2 Grant Ineligible Activities: Bidding Services Construction Costs Construction Engineering Applicant s Administrative Costs Engineering Design Basis of Design Report Value Engineering Report User Charge System Report Pilot Studies
24 Thank You Questions
Water Infrastructure Funding Opportunities through The NYS Environmental Facilities Corporation
Water Infrastructure Funding Opportunities through The NYS Environmental Facilities Corporation Genesee/Finger Lakes Regional Council Fall Local Government Workshop November 16, 2016 EFC Overview 2 Public
More informationDWSRF Intended Use Plan
State of Alabama Alabama Department of Environmental Management Drinking Water State Revolving Fund (DWSRF) Loan Program SRF Section (334) 271-7796 Permits and Services Division (334) 271-7950 FAX Alabama
More information4/14/2017. Green Infrastructure Funding Opportunities
Green Infrastructure Funding Opportunities CDRPC Grant Funding Workshop Hudson Valley Community College, Troy, NY April 12, 2017 EFC Overview Public benefit corporation that provides low-cost capital and
More informationALABAMA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT PERMITS AND SERVICES DIVISION STATE REVOLVING FUND PROGRAMS DIVISION
ALABAMA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT PERMITS AND SERVICES DIVISION STATE REVOLVING FUND PROGRAMS DIVISION 335 11 1400 Coliseum Boulevard Montgomery, Alabama 36110 CITE AS ADEM Admin. Code r.
More informationCWSRF Intended Use Plan
State of Alabama Alabama Department of Environmental Management Clean Water State Revolving Fund (CWSRF) Program SRF Section (334) 271-7796 Permits and Services Division (334) 271-7950 FAX Alabama Department
More informationFederal and State Funding Roundtable - EFC Minnowbrook Local Leaders Conference. April 26, 2016
Federal and State Funding Roundtable - EFC Minnowbrook Local Leaders Conference April 26, 2016 EFC Overview 2 Public benefit corporation that provides low-cost capital and grants for water quality improvement
More informationState and Federal Funding, Financing and Resources for Municipal Infrastructure March 15, 2018
EFC FUNDING OPPORTUNITIES State and Federal Funding, Financing and Resources for Municipal Infrastructure March 15, 2018 1 EFC Overview Public benefit corporation that provides low-cost capital and grants
More informationState Revolving Fund Program
State Revolving Fund Program James Dailey, Chief SRF Section Alabama Department of Environmental Management What is the SRF? The Clean Water State Revolving Fund (CWSRF) and the Drinking Water State Revolving
More informationMASSACHUSETTS WATER RESOURCES AUTHORITY
MASSACHUSETTS WATER RESOURCES AUTHORITY REGIONAL INFILTRATION/INFLOW SEPTEMBER 2002 Table of Contents 1. Introduction 1.1. Background...1 1.2. Description of the Regional I/I Problem...1 1.3. MWRA Initial
More informationArizona s Drinking Water Revolving Fund
Water Infrastructure Finance Authority of Arizona Arizona s Drinking Water Revolving Fund Intended Use Plan Funding Cycle 2005 Governor Janet Napolitano WIFA Chairman Stephen A. Owens WIFA Executive Director
More informationEnvironmental Management Chapter
Environmental Management Chapter 335-11-1 ALABAMA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT PERMITS AND SERVICES DIVISION STATE REVOLVING FUND PROGRAMS ADMINISTRATIVE CODE CHAPTER 335-11-1 CLEAN WATER STATE
More information1 Milwaukee Metropolitan Sewerage District Green Solutions Guidelines
1 Milwaukee Metropolitan Sewerage District Green Solutions Guidelines District s Project Overview To assist the municipalities served by the Milwaukee Metropolitan Sewerage District (District) with Total
More information11/9/2017 EFC FUNDING OPPORTUNITIES. EFC Overview. National Leader in Water Infrastructure Investment
EFC FUNDING OPPORTUNITIES Genesee/Finger Lakes Regional Planning Council Fall 2017 Local Government Workshop November 17, 2017 EFC Overview Public benefit corporation that provides low-cost capital and
More informationWater & Wastewater Funding. County Commissioners Association Webinar March 12, 2014
Water & Wastewater Funding County Commissioners Association Webinar March 12, 2014 Ohio Water Development Authority Ohio Water Development Authority was created by the Ohio Legislature in 1968 To preserve,
More informationFY 2018 Watershed-Based Funding Pilot Program Policy
FY 2018 Watershed-Based Funding Pilot Program Policy From the Board of Water and Soil Resources, State of Minnesota Version: FY2018 Effective Date: 12/20/2017 Approval: Board Resolution #17-94 Policy Statement
More informationTunnel Contractor Pre-SOQ & Networking Meeting February 17, 2015
Ohio Canal Interceptor Tunnel Tunnel Contractor Pre-SOQ & Networking Meeting February 17, 2015 February 17, 2015 Welcome and Program Overview OCIT Tunnel Contractor Pre-SOQ Meeting Page 2 Service Area
More informationALTERNATIVE SOURCES OF FUNDING FOR
January 2017 ALTERNATIVE SOURCES OF FUNDING FOR Flood-Related General Water Management Water Supply Projects The following inventory contains information about a variety of funding programs offered by
More informationState Assistance to Disadvantaged Communities During California s Historic Drought
STATE WATER RESOURCES CONTROL BOARD DIVISION OF FINANCIAL ASSISTANCE State Assistance to Disadvantaged Communities During California s Historic Drought November 6, 2017 Presented By: Joe Karkoski P.E.
More informationClean Water and Wastewater Fund. Program Guidelines
Clean Water and Wastewater Fund Program Guidelines September 2016 1 Table of Contents 1. Introduction... 4 2. Objectives... 4 3. Recipient Eligibility... 4 4. Project Criteria and Requirements... 5 4.1
More informationDWSRF Intended Use Plan
State of Alabama Alabama Department of Environmental Management Drinking Water State Revolving Fund (DWSRF) Loan Program SRF Section (334) 271-7796 Permits and Services Division (334) 271-7950 FAX Alabama
More informationTypes of Eligible Projects
U.S. Department of Agriculture Rural Development, Rural Utilities Service Water and Environmental Programs UNC School of Government Environmental Finance Center 2018 Water & Wastewater Finance Workshop
More informationREPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE DEVELOPMENT AND ENGINEERING SERVICES DEPARTMENT
October 19, 2016 REPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE DEVELOPMENT AND ENGINEERING SERVICES DEPARTMENT ON APPLICATIONS TO THE CLEAN WATER AND WASTEWATER FUND PURPOSE To seek Council's authorization
More information1. The purpose of this Program is to provide a framework for asset management of separate sanitary sewer systems to meet the following goals:
ARTICLE 8. INFILTRATION / INFLOW CONTROL PROGRAM 800. Introduction The separate sanitary sewers within the District s service area are designed and intended to receive and convey only domestic and industrial
More informationIndiana Finance Authority State Revolving Fund Loan Program
State Revolving Fund Loan Program ACEC Environmental Business Meeting September 17, 2015 Camille Meiners, PE State Revolving Fund Section Chief Indiana Finance Authority State Revolving Fund 100 N. Senate
More informationREQUEST FOR QUALIFICATIONS PROFESSIONAL ENGINEERING SERVICES for CITY OF SHELBY, NORTH CAROLINA. Shelby Water Treatment Plant Plant Upgrades
REQUEST FOR QUALIFICATIONS PROFESSIONAL ENGINEERING SERVICES for CITY OF SHELBY, NORTH CAROLINA Shelby Water Treatment Plant Plant Upgrades Issued: June 20, 2017 By: David Hux; Water Resources Director
More informationLexington s Stormwater Quality Projects Incentive Grant Program
Lexington s Stormwater Quality Projects Incentive Grant Program PRESENTED BY: Gregory S. Lubeck, P.E., CFM, ENGINEERING SECTION MANAGER LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT Discussion Topics EPA Consent
More informationCITY OF BUENA PARK SEWER SYSTEM MANAGEMENT PLAN
CITY OF BUENA PARK SEWER SYSTEM MANAGEMENT PLAN Updated Originally Submitted August 2, 2009 LIST OF ABBREVIATIONS/ACRONYMS... 4 EXECUTIVE SUMMARY... 5 CHAPTER 1 PROHIBITIONS AND PROVISIONS... 6 1.1 Prohibitions...
More informationFigure 1: ALCOSAN ORGANIZATION CHART
Allegheny County Sanitary Authority (ALCOSAN) REQUEST FOR QUALIFICATIONS For Engineering and Architectural Design Services, As Needed Various Small to Mid-Size Capital Projects March 2018 1.0 INTRODUCTION
More informationWater Infrastructure. Kim H. Colson, P.E., Director Division of Water Infrastructure. NC Division of. Water Infrastructure
Water Infrastructure NC Division of Water Infrastructure Kim H. Colson, P.E., Director Division of Water Infrastructure Outline Consolidation of funding programs Funding programs Clean Water and Drinking
More informationWastewater Master Plan Request for Proposals May 20, 2014
Wastewater Master Plan Request for Proposals May 20, 2014 City of Oak Grove 1300 S. Broadway Street Oak Grove, MO 64075 (816) 690-3773 cityofoakgrove.com 1.0 INTRODUCTION The City of Oak Grove, Missouri
More informationRural Development Water and Environmental Programs (WEP) Howard Kunz, Community Programs Specialist
Rural Development Water and Environmental Programs (WEP) Howard Kunz, Community Programs Specialist Rural Utilities Service (RUS) RURAL DEVELOPMENT Water & Environmental Programs (WEP) Broadband Electrical
More informationFY 2017 Proposed Capital Improvement Program
FY 2017 Proposed Capital Improvement Program Metropolitan St. Louis Sewer District FY 2017 Capital Improvement Program Proposed Engineering Services Rich Unverferth, P.E. Director of Engineering January
More informationSTORMWATER UTILITY. CREDIT MANUAL and GRANT PROGRAM DRAFT MAY credit_manual_v7.2.docx
STORMWATER UTILITY CREDIT MANUAL and GRANT PROGRAM DRAFT MAY 2018 credit_manual_v7.2.docx TABLE OF CONTENTS 1. A CITY GOING GREEN 1 1.1 The Green Domino Effect 1 2. LEARN THE ISSUES 2 2.1 Support for the
More informationCWSRF Intended Use Plan
State of Alabama Alabama Department of Environmental Management Clean Water State Revolving Fund (CWSRF) Program SRF Section (334) 271-7796 Permits and Services Division (334) 271-7950 FAX Alabama Department
More informationBeyond Rates: Other Finance Strategies. Glenn Barnes Environmental Finance Center Network
Beyond Rates: Other Finance Strategies Glenn Barnes Environmental Finance Center Network 919-962-2789 glennbarnes@sog.unc.edu Session Objectives Learn about other common sources of water system revenue
More informationEnvironmental Management Chapter ALABAMA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT WATER DIVISION - WATER SUPPLY PROGRAM ADMINISTRATIVE CODE
Environmental Management Chapter 335-7-4 ALABAMA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT WATER DIVISION - WATER SUPPLY PROGRAM ADMINISTRATIVE CODE CHAPTER 335-7-4 PERMIT REQUIREMENTS AND PROCEDURES TABLE
More informationRural Development Water and Environmental Programs (WEP) Brenda L. Smith, Community Programs Director Christina Cerio, Community Programs Specialist
Rural Development Water and Environmental Programs (WEP) Brenda L. Smith, Community Programs Director Christina Cerio, Community Programs Specialist Rural Utilities Service (RUS) RURAL DEVELOPMENT Water
More informationRequest for Proposal Engineering Consultant for City of Ingleside
Request for Proposal Engineering Consultant for Public Works and Building Services Departments Melissa Byrne Vossmer City Manager August 21, 2017 MAYOR AND CITY COUNCIL Luis Lamas, Mayor Oscar Adame, Mayor
More informationREQUEST FOR PROPOSAL
Ithaca Area WWTF 525 Third Street Ithaca, New York 14850 Phone (607) 273-8381 Fax (607) 273-8433 REQUEST FOR PROPOSAL PROFESSIONAL ENGINEERING SERVICES FOR DESIGN AND INSTALLATION OF FLOW MONITORING STATIONS
More informationAGENDA. 1603rd MEETING OF THE BOARD OF TRUSTEES THE METROPOLITAN ST. LOUIS SEWER DISTRICT
AGENDA Pg 1 1603rd MEETING OF THE BOARD OF TRUSTEES THE METROPOLITAN ST. LOUIS SEWER DISTRICT March 8, 2018 4:45 P.M. PENSION MEETING IN MKT 110 5:00 P.M. ROLL CALL & PUBLIC BOARD MEETING MSD OFFICES 2350
More informationSIGNIFICANT NONCOMPLIANCE OF WASTEWATER DISCHARGE LIMITS... 3 NONCOMPLIANCE NOTIFICATION (NCN)... 4 NOTICE OF VIOLATION (NOV)... 4
TABLE OF CONTENTS SIGNIFICANT NONCOMPLIANCE OF WASTEWATER DISCHARGE LIMITS... 3 NONCOMPLIANCE NOTIFICATION (NCN)... 4 NOTICE OF VIOLATION (NOV)... 4 SCHEDULE OF COMPLIANCE... 5 ADMINISTRATIVE PENALTIES...
More informationImplementation Costs & Sources of Funding. Lucas Gregory, PhD Texas Water Resources Institute
Implementation Costs & Sources of Funding Lucas Gregory, PhD Texas Water Resources Institute Implementation Costs for WPPs in Texas 21 EPA Accepted WPPs in Texas Minimum = $1,167,000 Maximum = $112,696,000
More informationSAN JOSE CAPITAL OF SILICON VALLEY
CITY OF SAN JOSE CAPITAL OF SILICON VALLEY TO: HONORABLE MAYOR AND CITY COUNCIL COUNCIL AGENDA: 1-12-16 ITEM: 7.2 Memorandum FROM: Toni J. Taber, C City Clerk SUBJECT: SEE BELOW DATE: December 18, 2015
More informationCLEAN WATER WASTEWATER FUND (CWWF) APPLICATION GUIDE FOR PROJECTS For the period of 2016/17 to 2017/18*
CLEAN WATER WASTEWATER FUND (CWWF) APPLICATION GUIDE FOR PROJECTS For the period of 2016/17 to 2017/18* 1.0 PURPOSE The Federal Government Budget 2016 announced new infrastructure programs that will be
More informationFY 2016 Clean Water Fund Competitive Grants Policy
FY 2016 Clean Water Fund Competitive Grants Policy Purpose The Clean Water Fund was established to implement part of Article XI, Section 15, of the Minnesota Constitution, and M.S. 114D with the purpose
More informationUSDA, Rural Development.
USDA, Rural Development http://www.rurdev.usda.gov/ny/ WATER & ENVIRONMENTAL PROGRAM (WEP) and COMMUNITY FACILITIES (CF) PROGRAM Water and Environmental Program Facilities include: Water / Wastewater Treatment
More informationAppendix B Review Matrix Text & Table Footnotes
Review Submissions The PDP includes a series of review submissions designed to ensure that all projects are developed in accordance with ODOT policies. The PDP Products Review Matrix found in this Appendix
More informationUSDA Rural Development
USDA Rural Development USDA RD Invested $433 million in rural Kansas in 2011 USDA Rural Development Overview USDA Rural Development Community Programs Community Facilities Water & Environmental Business
More informationNYC S GREEN INFRASTRUCTURE PROGRAM AND USE OF GRANT FUNDING FOR DESIGN & CONSTRUCTION
NYC S GREEN INFRASTRUCTURE PROGRAM AND USE OF GRANT FUNDING FOR DESIGN & CONSTRUCTION June 19, 2013 Nitin Katiyar, P.E. (HDR Engineering) nitin.katiyar@hdrinc.com William Leo, P.E. (HDR Engineering) william.leo@hdrinc.com
More informationHarnett County Public Utilities
Harnett County Public Utilities Funding for Regional Water and Wastewater Projects UNC School of Government Environmental Finance Center Capital Finance Strategies January 24-25, 2007 Departmental History
More informationFinancing Energy Efficiency Projects in Michigan
Wastewater Administrators Conference January 25, 2018 Financing Energy Efficiency Projects in Michigan Andrew Dow, Donohue & Associates 1 Funding Mechanism Overview Qualified Energy Conservation Bonds
More informationCity of Portsmouth Portsmouth, New Hampshire Public Works Department RFP #68-14 REQUEST FOR PROPOSAL
City of Portsmouth Portsmouth, New Hampshire Public Works Department RFP #68-14 REQUEST FOR PROPOSAL DESIGN ENGINEERING SERVICES NEW CASTLE WATER LINE IMPROVEMENTS INVITATION Sealed Proposals, plainly
More informationCommunity Development Part I Application Infrastructure Capacity Enhancement
Community Development Part I Application Infrastructure Capacity Enhancement For eligible activities administered by the Michigan Economic Development Corporation (MEDC) on behalf of the Michigan Strategic
More informationSec moves to amend H.F. No as follows: 1.2 Delete everything after the enacting clause and insert:
1.1... moves to amend H.F. No. 1731 as follows: 1.2 Delete everything after the enacting clause and insert: 1.3 "Section 1. CLEAN WATER FUND APPROPRIATIONS. 1.4 The sums shown in the columns marked "Appropriations"
More informationSouthern Ridge Wastewater Treatment Study Background, Results, Next Steps
Southern Ridge Wastewater Treatment Study Background, Results, Next Steps 2014 HDR, Inc., all rights reserved. Background 2 Other than Springfield, southern Sarpy County is without Sewer Service. 3 Lack
More informationThe New York State Environmental Facilities Corporation
The New York State Environmental Facilities Corporation Growing Green Infrastructure in New York State: Funding Green Infrastructure The Crowne Plaza Hotel, Syracuse, NY November 17, 2010 David Paterson,
More informationWater and Environmental Programs
U.S. Department of Agriculture Rural Development, Rural Utilities Service Water and Environmental Programs UNC School of Government Environmental Finance Center 2016Water and Wastewater Finance Workshop
More informationSTANDARD DRAWINGS INDEX
STANDARD DRAWINGS INDEX DESCRIPTION GENERAL DRAWING NO. Typical Layout for Improvement Plans... 1 City of Stockton Standard Border and Title Block for 8.5 x 11 Sheet.. 1A City of Stockton Standard Map
More informationGeorgia Water Supply Competitive Grant Program Program Guidelines
Georgia Water Supply Competitive Grant Program Program Guidelines In March 008, the Georgia General Assembly approved and the Governor signed the amended state budget for Fiscal Year 008 (HB 989). The
More informationNew Jersey Energy Resilience Bank
New Jersey Energy Resilience Bank Overview SECTION 1 Introduction to the ERB The State of New Jersey 1 New Jersey Energy Resilience Bank (ERB) Overview The extensive damage and outages caused by Superstorm
More informationPolicy on Development Cost Sharing
Policy on Development Cost Sharing 2016 Contents 1.0 Purpose... 3 2.0 General Principles and Criteria... 4 3.0 Definition of Terms... 6 4.0 Sanitary Sewers, Storm Sewers and Watermains... 9 5.0 Sanitary
More informationREQUEST FOR QUALIFICATIONS FOR OWNER REPRESENTATIVE PROFESSIONAL SERVICES DURING PROCUREMENT AND CONSTRUCTION FOR
REQUEST FOR QUALIFICATIONS FOR OWNER REPRESENTATIVE PROFESSIONAL SERVICES DURING PROCUREMENT AND CONSTRUCTION FOR UPGRADES AND EXPANSION PROJECTOF HAYS WASTEWATER TREATMENT PLANT CITY OF HAYS, KANSAS DECEMBER
More informationBrownsville Treatment Plant after 1 million gallon per day upgrade. 100,000 gallon Storage Tank behind Office Building on KY 259 N.
HISTORY In August 1966, the North Edmonson Water District was created to serve all of the county west of Nolin River and north of Green River with Roger Rich, Gilbert Webb and Haskell Lane as commissioners
More informationCITY OF MOUNT CARROLL CAPITAL IMPROVEMENTS PROGRAM UPDATE
CITY OF MOUNT CARROLL CAPITAL IMPROVEMENTS PROGRAM UPDATE 2017-2021 CITY OF MOUNT CARROLL CAPITAL IMPROVEMENTS PROGRAM UPDATE 2017-2021 December 2016 Prepared By: Council Members City Staff and Local Groups
More informationLOCAL STORMWATER BMP IMPLEMENTATION PROGRAM PROJECT APPLICATION INSTRUCTIONS
COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION BUREAU OF CLEAN WATER LOCAL STORMWATER BMP IMPLEMENTATION PROGRAM PROJECT APPLICATION INSTRUCTIONS The Department of Environmental Protection
More informationELECTRONIC PACKET FEBRUARY 12, 2018 OPERATIONS COMMITTEE MEETING. RELEASED: Monday, February 5, 2018
ELECTRONIC PACKET FEBRUARY 12, 2018 OPERATIONS COMMITTEE MEETING RELEASED: Monday, February 5, 2018 Item 1 COMMISSION FILE NO: 18-020-2 DATE INTRODUCED: February 12, 2018 INTRODUCED BY: REFERRED BY
More informationSTATE ENVIRONMENTAL REVIEW PROCESS FOR PENNSYLVANIA WASTEWATER PROJECTS. Clean Water State Revolving Fund Program
A STATE ENVIRONMENTAL REVIEW PROCESS FOR PENNSYLVANIA WASTEWATER PROJECTS Clean Water State Revolving Fund Program Pennsylvania Infrastructure Investment Authority & Pennsylvania Department of Environmental
More informationFinancing the Future of Water Systems
May 17, 2016 Financing the Future of Water Systems Seth Robertson, PE Overview Background Infrastructure needs Funding availability Summary of funding provided by Division of Water Infrastructure programs
More informationUSDA Rural Development
USDA Rural Development USDA Rural Development USDA RD Mission Committed to helping improve the economy and quality of life in rural America Accomplish the mission by: Providing support for essential public
More information2017 MUNICIAL STATE BOND FUND INFLOW & INFILTRATION (I&I) GRANT PROGRAM
2017 MUNICIAL STATE BOND FUND INFLOW & INFILTRATION (I&I) GRANT PROGRAM Informational Meeting - July 2017 Agenda I. Welcome & Introductions II. III. Inflow & Infiltration Trends Grant Guidelines & Policies:
More informationBEFORE THE STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION
BEFORE THE STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION Style Definition: Header STATE OF FLORIDA, DEPARTMENT ) IN THE OFFICE OF THE OF ENVIRONMENTAL PROTECTION ) SOUTHEAST DISTRICT ) v. ) OGC
More informationREQUEST FOR QUALIFICATIONS HONDO, TEXAS CITY ENGINEERING SERVICES
REQUEST FOR QUALIFICATIONS HONDO, TEXAS CITY ENGINEERING SERVICES 1. REQUEST FOR STATEMENT OF QUALIFICATIONS: The City of Hondo, hereinafter referred to as the City, is soliciting Statement of Qualifications
More informationCapital Improvement Planning. MME Winter Institute January 2017
Capital Improvement Planning MME Winter Institute January 2017 Today s Presenters Jill Bahm, AICP Principal Planner jbahm@giffelswebster.com Mike Kozak, P.E. Partner mkozak@giffelswebster.com 2 About This
More informationCECIL COUNTY MARYLAND REQUEST FOR PROPOSALS. ENGINEERING SERVICES On-call Comprehensive Engineering Contracts Water and Wastewater
PROJECT DESCRIPTION CECIL COUNTY MARYLAND REQUEST FOR PROPOSALS ENGINEERING SERVICES On-call Comprehensive Engineering Contracts Water and Wastewater Cecil County Department of Public Works is seeking
More informationPLEASE READ CAREFULLY THERE ARE SEVERAL REVISIONS EXPANDING ELIGIBILITY
John R. Kasich, Governor Mary Taylor, Lt. Governor Scott J. Nally, Director PLEASE READ CAREFULLY THERE ARE SEVERAL REVISIONS EXPANDING ELIGIBILITY REQUEST FOR PROPOSALS Surface Water Improvement Fund
More informationDOTHAN CLEAN WATERS PROGRAM CITY COMMISSION UPDATE
City of Dothan, Alabama DOTHAN CLEAN WATERS PROGRAM CITY COMMISSION UPDATE PRESENTED : February 19, 2013 Program Overview MOM Programs Capacity Assurance Program Information Management System Omussee WWTP
More informationSafe Drinking Water In Oregon
Oregon Economic and Community Development Department Safe Drinking Water In Oregon Program Guidelines & Applicant s Handbook for the Federally-funded Safe Drinking Water Revolving Loan Fund & Drinking
More informationCity of Defiance Construction Management & Observation Services
City of Defiance Construction Management & Observation Services REQUEST FOR QUALIFICATIONS January 5, PURPOSE The City of Defiance intends to contract for construction management & observation services
More informationService Authority Development Review Process and System Improvement Policy
Purpose The following policy outlines the Development Review Process and System Improvement Policy of the Prince William County Service Authority (the Service Authority ). This policy establishes an applicant
More information5384 Appendices
5384 5385 Appendices 5386 Appendix A Programmatic Review Process Step 1: Is Proposed Action Evaluated in This EA? (Check Section 3 [Proposed Action] to Confirm) Step 2: Is New Action Within Scope of this
More informationREPORT TO THE BOARD OF SUPERVISORS COUNTY OF FRESNO COUNTY SERVICE AREA 30 EL PORVENIR FISCAL YEAR
REPORT TO THE BOARD OF SUPERVISORS COUNTY OF FRESNO COUNTY SERVICE AREA 30 EL PORVENIR FISCAL YEAR 2017-2018 Submitted By: DEPARTMENT OF PUBLIC WORKS AND PLANNING Prepared By: RESOURCES DIVISION June 2017
More informationCAMDEN COUNTY SOIL CONSERVATION DISTRICT 423 COMMERCE LANE, SUITE #1 WEST BERLIN, NJ (FAX) MEETING AGENDA
CAMDEN COUNTY SOIL CONSERVATION DISTRICT 423 COMMERCE LANE, SUITE #1 WEST BERLIN, NJ 08091 856-767-6299 856-767-1676 (FAX) MEETING AGENDA JUNE 18, 2012 CALL TO ORDER MINUTES OF THE PREVIOUS MEETING SOIL
More informationDAILY & WOODS A PROFESSIONAL LfMlTED LIABILITY COMPANY ATTORNEYS AT LAW
JERRY L. CANFIELD, P.A. THOMASA. DAILY, P.A. WYM&.NR. WADE, JR., P.A. DOUGLAS M. CARSON, P.A. C. MICHAEL DATL Y, P.A. t COLBY T. ROE, P.A MICHAEL A. LAFRENIERE t Also Licensed in Oklahoma Also Licensed
More informationMonroe County THE FULL TEXT OF THE PROPOSED RULE IS:
Monroe County THE FULL TEXT OF THE PROPOSED RULE IS: 28-20.130 Work Program Administration. (1) Pursuant to Section 380.0552(4) paragraph (b), the Department of Community Affairs shall submit a written
More informationDepartment of Environmental Quality Water Infrastructure
February 10, 2016 EFC Water & Wastewater Finance Workshop Water Infrastructure Overview Update on Division of Water Infrastructure Programs Working with State Water Infrastructure Authority Coordinating
More informationFive-Year Capital Improvement Plan
Five-Year 2017-2022 Capital Improvement Plan Presentation to Board of Supervisors of Sonoma County and Board of Directors of the Sonoma County Water Agency Presented by County Administrator s Office and
More informationOperating Criteria of the. Wyoming Water Development Program TABLE OF CONTENTS
Operating Criteria of the Wyoming Water Development Program TABLE OF CONTENTS CHAPTER 1 Introduction A. Purpose of the Operating Criteria 1 B. Program Philosophy 2 C. Changes in Program Criteria 2 CHAPTER
More informationWater Trust Board 2019 Application Overview and Frequently Asked Questions
Water Trust Board 2019 Application Overview and Frequently Asked Questions The New Mexico Finance Authority ( NMFA ) administers the application process on behalf of the Water Trust Board ( WTB ). For
More informationACEC Environmental Business & Funding Sources Conference September 15, Camille Meiners, PE
State Revolving Fund Loan Program ACEC Environmental Business & Funding Sources Conference September 15, 2016 Camille Meiners, PE State Revolving Fund Section Chief Indiana Finance Authority State Revolving
More information3-Party Consent Decree Status Report: Quarter No
DISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY Serving the Public Protecting the Environment 3-Party Consent Decree Status Report: Quarter No. 1-2018 Civil Action No. 1:00CV00183TFH Civil Action No. 02-2511
More informationUSDA Rural Development
USDA Rural Development Rural Development INCREASING ECONOMIC OPPORTUNITY AND IMPROVING THE QUALITY OF LIFE FOR PEOPLE IN RURAL AMERICA Rural Development Offices Rural Development Programs Business Programs
More informationTHE ROSE GARDEN LIBRARY CLOSES AT 7:00PM
THE ROSE GARDEN LIBRARY CLOSES AT 7:00PM If you are parked in the library s garage, PLEASE MOVE YOUR CAR TO THE STREET, right away, so your car doesn t get locked in the garage until the library opens
More informationOtter Tail County Limited Area Star Lake Comprehensive Plan PMT Meeting #1
Otter Tail County Limited Area Star Lake Comprehensive Plan PMT Meeting #1 1:00 p.m., Thursday, February 25, 2016 Otter Tail County Government Services Center 520 Fir Ave W, Fergus Falls, MN Attendees:
More informationAPPENDIX 2 TO THE COMPREHENSIVE PLAN. City of West Richland Capital Improvement Plan
APPENDIX 2 TO THE COMPREHENSIVE PLAN City of West Richland 2017-2022 Capital Improvement Plan City of West Richland, WA Adopted by Ordinance No. XXXX APPENDIX 2 6-YEAR CAPITAL IMPROVEMENT PLAN (CIP) Purpose
More informationWEST EARL SEWER AUTHORITY PO BOX 725 BROWNSTOWN, PA
MEETING MINUTES April 11, 2018 WEST EARL SEWER AUTHORITY PO BOX 725 BROWNSTOWN, PA 17508-0725 The regular monthly meeting of the West Earl Sewer Authority was held in room 102 at the West Earl Township
More informationHosted by the SLMBE Office
Hosted by the SLMBE Office Women Presidents Educational Organization - DC Sandra Eberhard, Executive Director Washington Suburban Sanitary Commission - WSSC David Malone, Chief Procurement Officer Carlnetta
More informationCAPITAL IMPROVEMENTS PROGRAM
CAPITAL IMPROVEMENTS PROGRAM OVERVIEW The Capital Improvements Program (CIP) is a long-range capital budget typically covering a three to ten year time frame and including major capital purchases and/or
More informationSEPTIC MAINTENANCE PROGRAM RULES (ARTICLE 10)
SEPTIC MAINTENANCE PROGRAM RULES (ARTICLE 10) Catskill Watershed Corporation PO Box 569 Margaretville, NY 12455 (845) 586-1400 Approved by the Board of Directors October 28, 2003 Revised August 2, 2016
More informationDEFENSE LOGISTICS AGENCY WASTEWATER TREATMENT SYSTEMS. Report No. D March 26, Office of the Inspector General Department of Defense
DEFENSE LOGISTICS AGENCY WASTEWATER TREATMENT SYSTEMS Report No. D-2001-087 March 26, 2001 Office of the Inspector General Department of Defense Form SF298 Citation Data Report Date ("DD MON YYYY") 26Mar2001