1 REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR THE SIERRA NEVADA STREET SANITARY SEWER LINE REHABILITATION, PROJECT NO. M18029 Issued by: City of Stockton Public Works Department 22 E. Weber Avenue, Room 301 Stockton, CA Date Issued: Monday, October 1, 2018 Date Proposals Due: Thursday, November 8, 2018 by 3:00 PM LATE SUBMITTALS WILL NOT BE ACCEPTED

2 1.0 INTRODUCTION The City of Stockton (City) is soliciting proposals from qualified firms to provide professional engineering services to prepare plans, specifications and estimate (PS&E) leading to the rehabilitation of the 36 reinforced concrete pipe on Sierra Nevada Street between Hazelton Avenue and Worth Street. The City proposes to engage the services of a Consultant to determine the rehabilitation measures and alternatives leading to the preparation of PS&E. 2.0 BACKGROUND The sanitary system deficiency improvements program is designed to address capacity deficiencies and corrosion problems of existing sewer trunk lines that are deteriorating with the crown of pipe cracking and/or have the potential for structural failure. 3.0 PROJECT DESCRIPTION The project includes the rehabilitation of approximately 1,089 feet of existing 36-inch diameter sewer line along Sierra Nevada Street between Hazelton Avenue and Worth Street, see Attachment A Vicinity Map. 4.0 SCOPE OF WORK Each consultant shall prepare a detailed scope of services based, in part and at a minimum, on information presented in the Request of Proposal, and other available information. Consultants are encouraged to include items that are felt necessary for this project. 4.1 Background Research The Consultant shall research and review existing topographic mapping, right-of-way maps, as-built plans, record maps, surveys, assessor maps, improvement plans, and other characteristics for the project. The Consultant shall conduct field reconnaissance of the project limits. The Consultant shall also conduct field surveys that include collecting topographic information, and locating and referencing any survey monumentation to be compromised by the project. The Consultant shall identify required permits, prepare all permit applications, including railroad permits and assist the City with negotiations relative to permit conditions, if required. Permit fees will be paid by the City. The Consultant will need to prepare utility letters and project location exhibits. Utility requests need to be on a City letterhead to avoid paying fees for utility information.

3 Consultants shall also coordinate and identify existing utilities that will be impacted by the proposed project, and will need to coordinate with the City to the maximum extent possible to route this information to utility companies. The Consultant shall review City maintenance records, available upon request. Identify required permits, prepare all permit applications, and assist the City with negotiations relative to permit conditions, if required. Permit fees will be paid by the City. The Consultant shall review existing CCTV inspection reports and videos to consider what method of pipe rehabilitation will be recommended by Consultant. CCTV inspection reports and videos will be made available to the selected Consultant. The Consultant will need to prepare all public notices required to access private property during field reconnaissance and also provide a right of entry letter to access those private properties. All access and coordination to residential neighborhoods will be acquired by Consultant. The Consultant will need to identify impacts to all residences and businesses and present mitigation measures on the design improvement plans. This includes but is not limited to: service interruptions, property encroachments, access restrictions, potential damage to properties, etc. The Consultant will provide copies of all utility correspondence, public notices, and right of entry letter s for City files. 4.2 Plans, Specifications, and Estimate Design Report The Consultant shall provide a preliminary design report (report) to determine the structural integrity and useful life of sanitary sewer line; and recommend multiple rehabilitation measures and most cost effective alternatives to extend the useful life of the pipe. The Consultant shall review the existing CCTV inspection reports and videos to confirm deficiencies, assess the suitability for trenchless rehabilitation or replacement, locate manholes, and determine the locations of laterals. There are no manhole inspection reports. The Consultant must coordinate with City to access each manhole once selected. Existing CCTV inspection reports and videos of the sewer main line will be made available to the selected Consultant. The Consultant shall recommend a number of rehabilitation measures to extend the useful life of the pipe. The recommendation of the rehabilitation measures shall be as specific as possible and include product names, etc. Any rehabilitation measures recommended shall include references and examples of where the proposed technology was utilized. Consultant shall conclude with a preferred, final recommendation. Costs for all recommended rehabilitation measures/alternatives shall be included in the Report. Costs shall include all engineering, design, construction, permit acquisition, environmental mitigation measures (if necessary), etc. to completely carry-out the recommended measure/alternative rehabilitation of the pipe. In addition to costs, the following are required to be considered in the decision matrix of the final recommendation: Impacts to residential neighbors; and

4 Sewage flow bypassing The Consultant shall provide two (2) hard-copies and one (1) electronic version (pdf) of the Draft Report and incorporate comments upon review by the City. The review comments generated by the City shall be itemized and a written response to each comment shall be prepared in a comment matrix. The comment matrix shall be attached as an appendix of the Final Report. The Consultant shall provide two (2) hard-copies and one (1) electronic version (pdf) of Final Report PS&E The Consultant shall prepare complete PS&E documents, which include design improvement plans, traffic control plans, bypassing plans, specifications, and engineer s estimate. The traffic control plans and bypassing plans will be incorporated into the design improvement plans as actual design sheets (technical specifications will be included to specifications). PS&E documents shall be prepared according to City s standards and current CA MUTCD, as appropriate. Prepare a base map showing existing information to facilitate the design of all the necessary improvements using the City s latest Benchmark information. The base map limits shall be sufficient to cover all necessary improvements. The Consultant shall provide one electronic (pdf format) copy to the City Project Manager and four (4) 24 x36 sets of plans, one set of specifications, and one engineer s estimate at the 50% and 90% design phases to the Engineer for review and comment. With each stage, the review comments from previous stages shall be itemized and a written response to each shall be prepared in a comment matrix. The original red-line comments from the reviewing agency shall be returned with the succeeding submittal. The Consultant shall provide one electronic (pdf format) copy at 100% design stage for final review prior to plotting mylars, and providing final specifications and engineer s estimate. The Consultant is responsible for the final submittal which incorporates all previous review comments, survey information, technical requirements, right-of-way information, utility verification/protection, minimum contractor qualifications, regulatory agency permits and mitigation monitoring requirements, and any applicable encroachment permit requirements, and City requirements. The Consultant will provide the necessary final PS&E documents in a bid-ready form. The final submittal shall include: One complete plan set of reproducible 24 x36 on Mylars Printed, stamped and signed final specifications (also in Word and PDF format) Printed, final cost estimate (stamped and signed, in excel and pdf format), Drawing files in AutoCAD and PDF format, specifications in Word format and cost estimate in Excel format on a CD. Resident Engineer (RE) file on a CD The Consultant will provide all correspondence for City files.

5 4.3 Public Outreach The Consultant will need to prepare all public notices along with right-of-entry letters in order to access private properties during field reconnaissance. The Consultant will need to identify impacts to all residences and businesses and present mitigation measures on the design improvement plans. This includes but is not limited to: service interruptions, property encroachments, access restrictions, potential damage to property, etc. 4.4 Coordination/Meetings At a minimum, the consultant shall attend a project kickoff, design, and a pre-construction meeting. The Consultant shall establish a clear and consistent communication with the City to discuss progress of design. The Consultant shall attend meetings (or conference call) with City as needed to discuss and finalize the design. The Consultant shall provide meeting minutes for all meetings. This does not include investigative and/or field meetings that Consultant will need to conduct to execute the intent of the project. 4.5 Design Support During Construction Consultant shall be available and respond to questions concerning the plans, specifications and estimates prior to bid opening and prepare contract addenda and letters of clarification. The Consultant shall provide supplemental project drawings as needed. The Consultant will provide Engineering Services as required during construction. The following are the minimum required services that will need to be included in the Scope of Services: 1. Attending the pre-construction meeting; 2. Reviewing shop drawing submittals; 3. Responding to requests for information (RFIs); 4. Preparing clarification sketches; 5. Performing field observations during construction period; and 6. Preparing Record Drawings on mylars based upon Contractor field as-builts. 4.6 As-built Drawings The consultant should prepare as built drawings upon receipt of red-lines from the contractor. Consultant should produce one complete set of as built drawings in AutoCad. Changes should be reflected on the mylars either by hand or a new printed sheet. 5.0 PROJECT GENERAL INFORMATION 5.1 Proposal Submissions Proposals shall be submitted no later than 3:00 PM on Thursday, November 8, 2018 to:

6 RAY DEYTO CITY OF STOCKTON 22 E. WEBER AVENUE, ROOM 301 STOCKTON, CA The proposal should be firmly sealed in an envelope which will clearly be marked on the outside with SIERRA NEVADA STREET SANITARY SEWER LINE REHABILITATION for the City of Stockton (Project No. M18029). The suggested fee for the service shall be submitted in a separate sealed envelope. Late Proposals will not be accepted. 5.2 Acceptance or Rejection of Proposal The City reserves the right to negotiate an agreement with the firm submitting the highest ranking proposal. Also, the City reserves the right to reject any and all proposals or to waive any irregularity in a proposal if it is deemed to be in the best interest of the City. Failure to submit all requested information could be grounds to reject the proposal. 5.3 Proposal Questions and Requests for Clarification Any question or request for clarification shall be submitted in writing to: Ray.Deyto@stocktonca.gov Requests for clarification shall be submitted at least eight (8) business days prior to the proposal due date. If a response warrants an addendum to the RFP, such addendum will be posted on bidflash at least two days prior to the proposal due date. It is the proposer s responsibility to check the website for any addendums or responses to questions. The website address is as follows: Causes for Disqualification Any of the following may be considered cause to disqualify a proposal: A. Evidence of collusion among proposers B. Any attempt to improperly influence any member of the evaluation panel C. A proposer s default or breach of contract in previous work that resulted in termination of that agreement and/or D. Existence of any lawsuit, unresolved contractual claim, or dispute between proponent and the City. E. Any attempt to communicate in any manner with the City of Stockton elected official during the RFP/bid process will, and shall be, just cause for disqualification/rejection of proponent s proposal/proponent s bid submittal and considered non-responsive. F. No person, firm, or corporation shall be allowed to make a file or be interested in more than one bid for the same supplies, services, or both; provided, however, that subcontract bids to the principal bidders are excluded from the requirements of this section; Section of the Municipal Code.

7 5.5 Licensing Requirements Any professional certifications or licenses that may be required are the sole cost and responsibility of the proposer. A City of Stockton business license is required. Please contact the City of Stockton Business License Customer Service at (209) Insurance Requirements The proposer must obtain and maintain the required insurance. Proposer should review Attachment B, Instructions to Proposers for information regarding insurance, indemnification, Disadvantaged Business Enterprises, prevailing wages, etc. Failure to comply with the Instructions to Proposers may be grounds for rejection. 5.7 Department of Industrial Relations Please refer to Attachment B, Instructions to Proposers, for registration requirements with the Department of Industrial Relations. 5.8 Product Ownership Any documents resulting from the performance of work in the contract will become property of the City. This includes all work performed by subconsultants. 6.0 REQUIRED PROPOSAL CONTENT The proposal shall contain the following, at a minimum: Cover Letter Table of Contents Executive Summary Project Team Project Understanding Detailed Work Plan Examples of experience with similar types of work References (Three for the firm, two of which are familiar with the proposed team) Schedule (Microsoft Project schedule, with key dates, milestones, critical path) Cost Proposal (separate sealed envelope) Local Preference (Statement and Supporting Information) The body of the technical proposal shall not exceed 20 pages with a minimum font size of 10. Proposer shall submit three (3) bound sets of the proposal. The maximum allowable length is exclusive of any folder, cover, or section dividers. Proposals shall be no more than 30 pages (double sided), including resumes and the cover letter.

8 6.1 Cover Letter The letter shall be signed by an official with the authority to negotiate and contractually bind the firm with the City of Stockton. Provide name, title, address, , and telephone number for this officer. Describe any subcontract arrangements or licensing agreements. Include any potential conflict of interest. 6.2 Table of Contents The proposal should include a table of contents. 6.3 Executive Summary The Executive Summary shall include a summary of the proposal, emphasizing the approach to be taken and including a work plan, schedule, and description of the capabilities of the Consultant and sub consultants. The summary should convey an understanding of the purpose of the project and the services required for performance. 6.4 Project Team Describe your team organization including the qualifications of the prime consultant and any sub consultants. Provide an organizational chart of the proposed team structure. The following should be addressed: Demonstrate the firm s experience in each of the areas of expertise needed to successfully complete the project. This should include a description of prior experience in working with public agencies, including working with City staff. Ability for project team to perform the proposed work within the time limits of the project, considering their current and projected workload and assignments. Ability to provide quality control of all deliverables and be responsive to all issues in a timely manner. Provide project team resumes 6.5 Project Understanding Describe your understanding of the needs of the Sierra Nevada Street Sanitary Sewer Line Rehabilitation, Project No. M Detailed Work Plan Provide a proposed work plan for development and implementation of the program as described in the Scope of Work. Describe the proposed approach and the activities to be accomplished. Describe how the team will complete each task. Alternative approaches to the project can be submitted if a rationale is given for

9 the suggested changes. Information on software which will be used to prepare all working documents and final documents shall be provided to the City. 6.7 Examples of Experience with Similar Types of Work Provide examples of projects similar in scope and size to this project. 6.8 References Provide three client references for the firm, two of which are familiar with the project manager and key personnel. This shall include the name, company, contact information, and description of related work that was provided to the client. 6.9 Schedule Provide a Microsoft Project Schedule with key dates, milestones, and critical path. The selected consultant shall be expected to begin work within two weeks of contract signing Cost Proposal Proposer shall submit a cost proposal in a separate sealed envelope. Identify all key members, including sub consultants, in a work chart, including their name, title, hours per task, hourly rate, total hours, direct labor, overhead, and percentage of work by task. Include total fee for all costs to complete all the tasks. 7.0 PROPOSAL EVALUATION The Consultant Selection process will follow the approximate timeline shown below: Event Date Post Request for Proposals October 1, 2018 Written Questions submitted by October 22, 2018 Response to Written Questions October 31,2018 Proposals due November 8, 2018 Negotiations November 21, 2018 Anticipated City Council Approval February 2019 Dates are tentative.

10 7.1 Proposal Evaluation The selection committee will evaluate all proposals. This is a qualifications and cost based selection, so ranking will be in accordance with the attached Evaluation Scoring Worksheet (See Attachment C). Cost will be a factor in evaluation, but selection is predominately qualifications based. Local Preference will also be a factor, so Stockton firms are encouraged to propose. Also, non-stockton firms should make an effort to use Stockton consultants whenever possible. Points will be weighted based on the amount of work being performed by the local consultants and/or businesses. Please allow for three weeks to evaluate proposals. 7.2 Negotiations City staff will begin negotiations with the highest ranked firm. If an agreement cannot be reached after a reasonable period of time, as determined by the City, Then the City will terminate negotiations with the number one ranked firm and negotiations will be opened with the second ranked firm. The compensation discussed with one prospective Consultant will not be disclosed or discussed with another Consultant. The selected consultant will be expected to enter into a Professional Services Contract with the City. Proposers should direct their attention to Attachment B, Instructions to Proposers for the most current insurance and indemnification language. It is expected that the successful proposer will accept these terms without modification. The contract shall not be in force until the Council approves the contract and the City manager signs it. Work performed before the issuance of a Notice to Proceed cannot be paid by the City. ATTACHMENTS: Attachment A Vicinity Map Attachment B Instructions to Proposers Attachment C Evaluation Scoring Sheet Attachment D - Location Map

REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR INSTALLATION & UPGRADE OF BICYCLE FACILITIES (CLASS II & CLASS III) Issued by:

REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR INSTALLATION & UPGRADE OF BICYCLE FACILITIES (CLASS II & CLASS III) Issued by: REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR INSTALLATION & UPGRADE OF BICYCLE FACILITIES (CLASS II & CLASS III) City Project No. PW1517 Federal Project No. CML-5008(150) Issued by: City of Stockton

More information

REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR RAISED MEDIAN AT EL DORADO STREET. Issued by:

REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR RAISED MEDIAN AT EL DORADO STREET. Issued by: REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR RAISED MEDIAN AT EL DORADO STREET (BETWEEN ESSEX STREET AND THE CALAVERAS RIVER BRIDGE) Federal Project No. HRRRL-5008(163) Issued by: City of Stockton Public

More information

REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR THE MARCH LANE/EAST BAY MUD BICYCLE AND PEDESTRIAN PATH CONNECTIVITY IMPROVEMENTS.

REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR THE MARCH LANE/EAST BAY MUD BICYCLE AND PEDESTRIAN PATH CONNECTIVITY IMPROVEMENTS. REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR THE MARCH LANE/EAST BAY MUD BICYCLE AND PEDESTRIAN PATH CONNECTIVITY IMPROVEMENTS Federal Project No. CML-5008(179) City Project No. PW1722 Issued by: City

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS FOR PROFESSIONAL DESIGN SERVICES INSTALL PEDESTRIAN CROSSINGS AT NINE INTERSECTIONS CITY PROJECT NO. PW1715 FEDERAL PROJECT NO. HSIPL-5008(161) CITY OF STOCKTON PUBLIC WORKS DEPARTMENT

More information

REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR THE BRIDGE REHABILITATION PROJECT. Issued by:

REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR THE BRIDGE REHABILITATION PROJECT. Issued by: REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR THE BRIDGE REHABILITATION PROJECT FEDERAL PROJECT NO. BPMP-5008 (157) CITY PROJECT NO. PW1603 Issued by: City of Stockton Public Works Department 22 E. Weber

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS FOR PROFESSIONAL DESIGN SERVICES RAISED MEDIAN ALONG DR. MARTIN LUTHER KING JR. BOULEVARD CITY PROJECT NO. PW1716 FEDERAL PROJECT NO. HSIPL-5008(167) CITY OF STOCKTON PUBLIC WORKS

More information

GRANT WRITING ASSISTANCE FOR THE HIGHWAY SAFETY IMPROVEMENT PROGRAM CYCLE 9

GRANT WRITING ASSISTANCE FOR THE HIGHWAY SAFETY IMPROVEMENT PROGRAM CYCLE 9 REQUEST FOR PROPOSALS PROFESSIONAL SERVICES GRANT WRITING ASSISTANCE FOR THE HIGHWAY SAFETY IMPROVEMENT PROGRAM CYCLE 9 PROJECT NO. SEB-18-005 Issued by: City of Stockton Public Works Department 22 E.

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS FOR TO PREPARE PROFESSIONAL DESIGN SERVICES PLANS, SPECIFICATIONS, AND ESTIMATE (PS&E) FOR THE RAISED MEDIAN ALONG DR. MARTIN LUTHER KING JR. BOULEVARD CITY PROJECT NO. PW1716/ FEDERAL

More information

REQUEST FOR PROPOSALS PROFESSIONAL SERVICES GRANT WRITING ASSISTANCE FOR THE ACTIVE TRANSPORTATION PROGRAM

REQUEST FOR PROPOSALS PROFESSIONAL SERVICES GRANT WRITING ASSISTANCE FOR THE ACTIVE TRANSPORTATION PROGRAM REQUEST FOR PROPOSALS PROFESSIONAL SERVICES GRANT WRITING ASSISTANCE FOR THE ACTIVE TRANSPORTATION PROGRAM PROJECT NO. SEB-18-004 Issued by: City of Stockton Public Works Department 22 E. Weber Avenue,

More information

PUBLIC WORKS DEPARTMENT 22 E. Weber Avenue, Room 301 Stockton, CA (209) REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR THE

PUBLIC WORKS DEPARTMENT 22 E. Weber Avenue, Room 301 Stockton, CA (209) REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR THE PUBLIC WORKS DEPARTMENT 22 E. Weber Avenue, Room 301 Stockton, CA 95202-3717 (209) 937-8411 REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR THE TRAFFIC SIGNAL, ROUNDABOUT, AND PROTECTED LEFT-TURN PHASING

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS ENGINEERING/ARCHITECTURAL DESIGN SERVICES FOR THE NORTHEAST STOCKTON LIBRARY AND RECREATION CENTER CITY PROJECT NO. PW1724 City of Stockton Public Works Department 22 E. Weber Avenue,

More information

REQUEST FOR PROPOSALS PROFESSIONAL SERVICES

REQUEST FOR PROPOSALS PROFESSIONAL SERVICES REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR THE TAM O SHANTER DRIVE AND KNICKERBOCKER DRIVE ROUNDABOUT City Project No. PW1727 Federal Project No. CML-5008(173) Issued by: City of Stockton Public Works

More information

PUBLIC WORKS DEPARTMENT 22 E. Weber Avenue, Room 301 Stockton, CA (209) REQUEST FOR PROPOSALS PROFESSIONAL DESIGN SERVICES FOR THE

PUBLIC WORKS DEPARTMENT 22 E. Weber Avenue, Room 301 Stockton, CA (209) REQUEST FOR PROPOSALS PROFESSIONAL DESIGN SERVICES FOR THE PUBLIC WORKS DEPARTMENT 22 E. Weber Avenue, Room 301 Stockton, CA 95202-3717 (209) 937-8411 REQUEST FOR PROPOSALS PROFESSIONAL DESIGN SERVICES FOR THE TRAFFIC SIGNAL AND SAFETY LIGHTING MODIFICATIONS AT

More information

MINER AVENUE COMPLETE STREET IMPROVEMENTS

MINER AVENUE COMPLETE STREET IMPROVEMENTS REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR THE MINER AVENUE COMPLETE STREET IMPROVEMENTS Federal Project No. ATP 5008(158), City Project No. PW1607, Federal Project No. ATP 5008(170), City Project

More information

REQUEST FOR PROPOSALS PROFESSIONAL DESIGN SERVICES

REQUEST FOR PROPOSALS PROFESSIONAL DESIGN SERVICES PUBLIC WORKS DEPARTMENT 22 E. Weber Avenue, Room 301 Stockton, CA 95202-3717 REQUEST FOR PROPOSALS PROFESSIONAL DESIGN SERVICES FOR THE CONVERT SIGNALS FROM PEDESTAL-MOUNTED TO MAST ARMS (AT THE INTERSECTIONS

More information

Facilities Condition Assessment

Facilities Condition Assessment Facilities Condition Assessment (O&M 16 018) Date Issued: January 29, 2016 Date Due: Contact: March 3, 2016 at 4:00:00 pm Paul Acosta, Program Manager III paul.acosta@stocktonca.gov City of Stockton Public

More information

REQUEST FOR PROPOSALS For Design Services for New Fire Station

REQUEST FOR PROPOSALS For Design Services for New Fire Station REQUEST FOR PROPOSALS For Design Services for PROPOSAL SUBMISSION DEADLINE: March 18, 2015 Page 1 Table of Contents A. Introduction B. Project Description C. Scope of Services D. Qualifications E. Selection

More information

REQUEST FOR QUALIFICATIONS G ELLUCIAN (Datatel) COLLEAGUE CONVERSION TO MS SQL AND RELATED UPGRADES PROJECT

REQUEST FOR QUALIFICATIONS G ELLUCIAN (Datatel) COLLEAGUE CONVERSION TO MS SQL AND RELATED UPGRADES PROJECT SAN JOSE/EVERGREEN COMMUNITY COLLEGE DISTRICT 4750 San Felipe Road, San Jose, CA 95135 REQUEST FOR QUALIFICATIONS G2010.0069 ELLUCIAN (Datatel) COLLEAGUE CONVERSION TO MS SQL AND RELATED UPGRADES PROJECT

More information

REQUEST FOR PROPOSALS PROFESSIONAL ENGINEERING SERVICES WATER SYSTEM RELIABILITY STUDY CITY OF MT. PLEASANT WATER DEPARTMENT

REQUEST FOR PROPOSALS PROFESSIONAL ENGINEERING SERVICES WATER SYSTEM RELIABILITY STUDY CITY OF MT. PLEASANT WATER DEPARTMENT REQUEST FOR PROPOSALS PROFESSIONAL ENGINEERING SERVICES WATER SYSTEM RELIABILITY STUDY CITY OF MT. PLEASANT WATER DEPARTMENT The City of Mt. Pleasant, Michigan, is seeking a consultant to prepare a Reliability

More information

REQUEST FOR PROPOSALS. For: As needed Plan Check and Building Inspection Services

REQUEST FOR PROPOSALS. For: As needed Plan Check and Building Inspection Services Date: June 15, 2017 REQUEST FOR PROPOSALS For: As needed Plan Check and Building Inspection Services Submit Responses to: Building and Planning Department 1600 Floribunda Avenue Hillsborough, California

More information

Request for Proposals To Provide Engineering Services for the Wastewater Treatment Facility Improvements Project

Request for Proposals To Provide Engineering Services for the Wastewater Treatment Facility Improvements Project Request for Proposals To Provide Engineering Services for the Wastewater Treatment Facility Improvements Project City of Dixon City Engineer/ Public Works Department December 2013 The City of Dixon (CITY)

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS Community Development Department Planning & Zoning Division REQUEST FOR PROPOSALS COMBINED ACTIVE TRANSPORTATION/ SAFE ROUTES TO SCHOOL PLAN State Project No. ATPL-5169 (048) RELEASE DATE: SEPTEMBER 23,

More information

REQUEST FOR PROPOSALDevelopment of a Local

REQUEST FOR PROPOSALDevelopment of a Local 2012 REQUEST FOR PROPOSALDevelopment of a Local Limits Study Terry Hagen, Director of Public Works City of El Centro 307 West Brighton Avenue El Centro, CA 92243 (760) 337-4505 Request for Proposals Development

More information

REQUEST FOR QUALIFICATIONS TO PROVIDE ON-CALL ENGINEERING SERVICES FOR CONSTRUCTION MANAGEMENT AND INSPECTION

REQUEST FOR QUALIFICATIONS TO PROVIDE ON-CALL ENGINEERING SERVICES FOR CONSTRUCTION MANAGEMENT AND INSPECTION REQUEST FOR QUALIFICATIONS TO PROVIDE ON-CALL ENGINEERING SERVICES FOR CONSTRUCTION MANAGEMENT AND INSPECTION FOR THE COUNTY OF RIVERSIDE TRANSPORTATION DEPARTMENT Table of Contents ADDENDUM NO. 2 March

More information

SACRAMENTO REGIONAL SOLID WASTE AUTHORITY REQUEST FOR PROPOSALS FOR CONSULTING SERVICES FOR A REGIONAL GREEN WASTE PROCESSING FACILITY

SACRAMENTO REGIONAL SOLID WASTE AUTHORITY REQUEST FOR PROPOSALS FOR CONSULTING SERVICES FOR A REGIONAL GREEN WASTE PROCESSING FACILITY SACRAMENTO REGIONAL SOLID WASTE AUTHORITY SACRAMENTO REGIONAL SOLID WASTE AUTHORITY REQUEST FOR PROPOSALS FOR CONSULTING SERVICES FOR A REGIONAL GREEN WASTE PROCESSING FACILITY January 28, 2003 TABLE OF

More information

REQUEST FOR PROPOSAL FOR POLICE OPERATIONS STUDY. Police Department CITY OF LA PALMA

REQUEST FOR PROPOSAL FOR POLICE OPERATIONS STUDY. Police Department CITY OF LA PALMA REQUEST FOR PROPOSAL FOR POLICE OPERATIONS STUDY Police Department CITY OF LA PALMA Released on November 27, 2013 Police Operations Study REQUEST FOR PROPOSAL ( RFP ) 1. BACKGROUND The City of La Palma

More information

BASIN CITY WATER AND SEWER DISTRICT Request for Qualifications

BASIN CITY WATER AND SEWER DISTRICT Request for Qualifications BASIN CITY WATER AND SEWER DISTRICT for: LEON DRIVE AND ESTELLA DRIVE WATERLINE REPLACEMENT PROJECT Basin City Water and Sewer District (hereinafter called District ) is requesting Statements of Qualifications

More information

PIEDMONT TRIAD AIRPORT AUTHORITY

PIEDMONT TRIAD AIRPORT AUTHORITY PIEDMONT TRIAD AIRPORT AUTHORITY REQUEST FOR QUALIFICATIONS (RFQ) for FAR PART 150 NOISE COMPATIBILITY STUDY for PIEDMONT TRIAD INTERNATIONAL AIRPORT The Piedmont Triad Airport Authority (PTAA) will receive

More information

REQUEST FOR PROPOSALS FOR AS-NEEDED TRAFFIC ENGINEERING AND PROFESSIONAL SERVICES FISCAL YEARS 2017 THRU 2019

REQUEST FOR PROPOSALS FOR AS-NEEDED TRAFFIC ENGINEERING AND PROFESSIONAL SERVICES FISCAL YEARS 2017 THRU 2019 Board of Commissioners of the Port of New Orleans REQUEST FOR PROPOSALS FOR AS-NEEDED TRAFFIC ENGINEERING AND PROFESSIONAL SERVICES FISCAL YEARS 2017 THRU 2019 June 17, 2016 Deadline for proposals is no

More information

SUSQUEHANNA AREA REGIONAL AIRPORT AUTHORITY

SUSQUEHANNA AREA REGIONAL AIRPORT AUTHORITY SUSQUEHANNA AREA REGIONAL AIRPORT AUTHORITY REQUEST FOR QUALIFICATIONS/PROPOSALS Professional Construction Management Services Gettysburg Regional Airport Rehabilitate Runway 6-24, Phase IV Susquehanna

More information

City of Waterloo, Wisconsin. Request for Proposals. Municipal Engineering Services

City of Waterloo, Wisconsin. Request for Proposals. Municipal Engineering Services City of Waterloo, Wisconsin Request for Proposals Municipal Engineering Services Submission Date: December 1, 2011 @ 4:00 p.m. Issued by: Mo Hansen, Clerk/Treasurer City of Waterloo 136 N. Monroe Street

More information

TABLE OF CONTENTS. Notice Inviting Qualifications Background Scope of Work Request for Qualifications (RFQ) Selection Process...

TABLE OF CONTENTS. Notice Inviting Qualifications Background Scope of Work Request for Qualifications (RFQ) Selection Process... TABLE OF CONTENTS Notice Inviting Qualifications... 3 Background... 4 Scope of Work... 4 Request for Qualifications (RFQ) Selection Process... 9 RFQ & Request for Proposal (RFP) Schedule... 10 Other Terms

More information

2018 Pipelines Engineering Services Boerne Stage Road, West Avenue, and Highway 90 & General McMullen

2018 Pipelines Engineering Services Boerne Stage Road, West Avenue, and Highway 90 & General McMullen 2018 Pipelines Engineering Services Boerne Stage Road, West Avenue, and Highway 90 & General McMullen M. Antonio Leyva, P.E. Manager Engineering Angelica Mata Manager Contract Administration Marisol V.

More information

NOTICE TO CONSULTANTS REQUEST FOR PROPOSAL FOR PROFESSIONAL SERVICES FOR GROUNDWATER MODELING AND INJECTION TESTING

NOTICE TO CONSULTANTS REQUEST FOR PROPOSAL FOR PROFESSIONAL SERVICES FOR GROUNDWATER MODELING AND INJECTION TESTING NOTICE TO CONSULTANTS REQUEST FOR PROPOSAL FOR PROFESSIONAL SERVICES FOR GROUNDWATER MODELING AND INJECTION TESTING March 30, 2018 Issued by: X Rob Livick, PE/PLS Public Works Director/City Engineer City

More information

RFP # Request for Proposal Grant Writing Services. Date: May 11, Proposals must be submitted by 3:00 PM: June 10, 2016

RFP # Request for Proposal Grant Writing Services. Date: May 11, Proposals must be submitted by 3:00 PM: June 10, 2016 RFP #0516-3 Request for Proposal Grant Writing Services Date: May 11, 2016 Proposals must be submitted by 3:00 PM: June 10, 2016 Purchasing Department Queens Borough Public Library 89-11 Merrick Boulevard

More information

REQUEST FOR PROPOSAL TO PROVIDE AS-NEEDED ENGINEERING SERVICES FOR THE IMPLEMENTATION OF

REQUEST FOR PROPOSAL TO PROVIDE AS-NEEDED ENGINEERING SERVICES FOR THE IMPLEMENTATION OF REQUEST FOR PROPOSAL TO PROVIDE AS-NEEDED ENGINEERING SERVICES FOR THE IMPLEMENTATION OF PURPLE LINE EXTENSION PROJECT BY LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY Project No. 16-34 CITY

More information

CITY OF CAMARILLO AND CAMARILLO SANITARY DISTRICT WATER AND SEWER RATE STUDIES REQUEST FOR PROPOSAL

CITY OF CAMARILLO AND CAMARILLO SANITARY DISTRICT WATER AND SEWER RATE STUDIES REQUEST FOR PROPOSAL CITY OF CAMARILLO AND CAMARILLO SANITARY DISTRICT WATER AND SEWER RATE STUDIES REQUEST FOR PROPOSAL 2011 PREPARED BY THE CITY OF CAMARILLO AND CAMARILLO SANITARY DISTRICT FINANCE DEPARTMENT Ronnie J. Campbell

More information

CITY OF PORTSMOUTH NEW HAMPSHIRE Department of Public Works

CITY OF PORTSMOUTH NEW HAMPSHIRE Department of Public Works CITY OF PORTSMOUTH NEW HAMPSHIRE Department of Public Works RFP #33-11 REQUEST FOR PROPOSALS ENGINEERING SERVICES MECHANIC STREET SEAWALL AT PICKERING DESIGN PROJECT The City of Portsmouth, New Hampshire

More information

Request for Qualifications (RFQ) Environmental and Permitting Services

Request for Qualifications (RFQ) Environmental and Permitting Services Request for Qualifications (RFQ) Environmental and Permitting Services Responses Due: City of Banning Public Works Department 99 E. Ramsey Street Banning, CA 92220 (951) 922-3130 May, 2015 05/19/15 i TABLE

More information

CITY OF PORTSMOUTH, NH DEPARTMENT OF PUBLIC WORKS. RFP Peirce Island Pool House Design Project

CITY OF PORTSMOUTH, NH DEPARTMENT OF PUBLIC WORKS. RFP Peirce Island Pool House Design Project CITY OF PORTSMOUTH, NH DEPARTMENT OF PUBLIC WORKS RFP 78-18 Peirce Island Pool House Design Project Sealed Requests for Proposals, plainly marked RFP# 78-18 Construction Drawings and Bid Documents for

More information

Wastewater Master Plan Request for Proposals May 20, 2014

Wastewater Master Plan Request for Proposals May 20, 2014 Wastewater Master Plan Request for Proposals May 20, 2014 City of Oak Grove 1300 S. Broadway Street Oak Grove, MO 64075 (816) 690-3773 cityofoakgrove.com 1.0 INTRODUCTION The City of Oak Grove, Missouri

More information

REQUEST FOR QUALIFICATIONS CONSULTING SERVICES FOR WALLA WALLA REGIONAL AIRPORT (ALW) WALLA WALLA, WASHINGTON. October 2, 2018

REQUEST FOR QUALIFICATIONS CONSULTING SERVICES FOR WALLA WALLA REGIONAL AIRPORT (ALW) WALLA WALLA, WASHINGTON. October 2, 2018 REQUEST FOR QUALIFICATIONS CONSULTING SERVICES FOR WALLA WALLA REGIONAL AIRPORT (ALW) WALLA WALLA, WASHINGTON October 2, 2018 The Port of Walla Walla, owner and operator of the Walla Walla Regional Airport,

More information

CITY OF HONDO ENGINEERING REQUEST FOR QUALIFICATIONS

CITY OF HONDO ENGINEERING REQUEST FOR QUALIFICATIONS CITY OF HONDO ENGINEERING REQUEST FOR QUALIFICATIONS The City of Hondo requests the submission of qualifications statements, which will lead to the possible award of a contract to provide planning, design

More information

REQUEST FOR QUALIFICATIONS TO PROVIDE ON-CALL ENGINEERING SERVICES FOR CONSTRUCTION MANAGEMENT AND INSPECTION

REQUEST FOR QUALIFICATIONS TO PROVIDE ON-CALL ENGINEERING SERVICES FOR CONSTRUCTION MANAGEMENT AND INSPECTION REQUEST FOR QUALIFICATIONS TO PROVIDE ON-CALL ENGINEERING SERVICES FOR CONSTRUCTION MANAGEMENT AND INSPECTION FOR THE COUNTY OF RIVERSIDE TRANSPORTATION DEPARTMENT Table of Contents I. Events Calendar

More information

REQUEST FOR PROPOSALS FOR AS-NEEDED PROJECT MANAGEMENT AND INSPECTION SERVICES FISCAL YEARS 2017 THRU 2019

REQUEST FOR PROPOSALS FOR AS-NEEDED PROJECT MANAGEMENT AND INSPECTION SERVICES FISCAL YEARS 2017 THRU 2019 Board of Commissioners of the Port of New Orleans REQUEST FOR PROPOSALS FOR AS-NEEDED PROJECT MANAGEMENT AND INSPECTION SERVICES FISCAL YEARS 2017 THRU 2019 June 23, 2016 Deadline for proposals is no later

More information

SECTION 2 INSTRUCTIONS TO BIDDERS (IB)

SECTION 2 INSTRUCTIONS TO BIDDERS (IB) SECTION 2 INSTRUCTIONS TO BIDDERS (IB) RFP 12-18 2012-08-01 Page 1 of 12 Instructions to Bidder (IB) IB 1. Communication / Timelines for submittal of Proposal IB 2. Proposal Submission General Terms IB

More information

Town of Orange Park, Florida. Financial Auditing Services

Town of Orange Park, Florida. Financial Auditing Services , Florida Financial Auditing Services Request for Proposal TOWN OF ORANGE PARK, FLORIDA REQUEST FOR FINANCIAL AUDIT SERVICES The Town of Orange Park, Florida is requesting proposals from qualified firms

More information

City of Portsmouth Portsmouth, New Hampshire Public Works Department RFP #68-14 REQUEST FOR PROPOSAL

City of Portsmouth Portsmouth, New Hampshire Public Works Department RFP #68-14 REQUEST FOR PROPOSAL City of Portsmouth Portsmouth, New Hampshire Public Works Department RFP #68-14 REQUEST FOR PROPOSAL DESIGN ENGINEERING SERVICES NEW CASTLE WATER LINE IMPROVEMENTS INVITATION Sealed Proposals, plainly

More information

Proposals due May 18 th, 2018 at 4:30 PM. Indicate on the Sealed Envelope Do Not Open with Regular Mail.

Proposals due May 18 th, 2018 at 4:30 PM. Indicate on the Sealed Envelope Do Not Open with Regular Mail. April 26, 2018 Subject: RFP2M18-06: Request for Proposal Construction Management and Inspection Services for the Sewer Plant #7 Replacement Project. The City of Alhambra is requesting proposals from experienced,

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS Consultant Service to Conduct a Visioning Study and Prepare Recommendations for the Culver City Transit Oriented Development (TOD) District September 2016 RFP Released: September

More information

January 19, To Whom It May Concern:

January 19, To Whom It May Concern: January 19, 2018 To Whom It May Concern: The Airport South Community Improvement District and the Airport West Community Improvement District, collectively known as the Aerotropolis Atlanta Community Improvement

More information

Architectural Services

Architectural Services Architectural Services 2015 Capital Improvement Program Request for Proposal Number: 16-30 Title of the Project: Replacement of Northeast High & Appling Middle School Operations Center - Procurement Office

More information

CITY OF BELL REQUEST FOR PROPOSALS FOR ARCHITECTURAL SERVICES FOR TREDER PARK RESTROOM AND STORAGE FACILITY

CITY OF BELL REQUEST FOR PROPOSALS FOR ARCHITECTURAL SERVICES FOR TREDER PARK RESTROOM AND STORAGE FACILITY CITY OF BELL 6330 PINE AVENUE BELL, CA 90201 PH: (323) 588-6211 fx: (323) 771-9473 I. INTRODUCTION CITY OF BELL REQUEST FOR PROPOSALS FOR ARCHITECTURAL SERVICES FOR TREDER PARK RESTROOM AND STORAGE FACILITY

More information

Request for Proposals City School District of Albany Empire State After-School Program Coordination and Programming June 14, 2017

Request for Proposals City School District of Albany Empire State After-School Program Coordination and Programming June 14, 2017 Request for Proposals City School District of Albany Empire State After-School Program Coordination and Programming June 14, 2017 Attention: Purchasing Agent Address: City School District of Albany 1 Academy

More information

City of Portsmouth Portsmouth, New Hampshire Public Works and Finance Departments RFQ #03-13 REQUEST FOR QUALIFICATIONS

City of Portsmouth Portsmouth, New Hampshire Public Works and Finance Departments RFQ #03-13 REQUEST FOR QUALIFICATIONS RFQ 03-13 1 City of Portsmouth Portsmouth, New Hampshire Public Works and Finance Departments RFQ #03-13 REQUEST FOR QUALIFICATIONS CONSULTING SERVICES WATER AND WASTEWATER SYSTEM RATE STUDY INVITATION:

More information

PROPOSAL INSTRUCTIONS AND REQUIREMENTS

PROPOSAL INSTRUCTIONS AND REQUIREMENTS PROPOSAL INSTRUCTIONS AND REQUIREMENTS A Proposal is requested by the Dallas/Fort Worth International Airport Board (herein called Board). The Board will receive separate sealed Proposals until the deadline

More information

CITY OF PLACERVILLE Development Services Department ENGINEERING DIVISION

CITY OF PLACERVILLE Development Services Department ENGINEERING DIVISION CITY OF PLACERVILLE Development Services Department ENGINEERING DIVISION REQUEST FOR PROPOSALS FOR ENGINEERING DESIGN AND ENVIRONMENTAL CONSULTING SERVICES for PLACERVILLE DRIVE BICYCLE AND PEDESTRIAN

More information

Town of Derry, NH REQUEST FOR PROPOSALS PROFESSIONAL MUNICIPAL AUDITING SERVICES

Town of Derry, NH REQUEST FOR PROPOSALS PROFESSIONAL MUNICIPAL AUDITING SERVICES Town of Derry, NH Office of the Finance Department Susan A. Hickey Chief Financial Officer susanhickey@derrynh.org REQUEST FOR PROPOSALS PROFESSIONAL MUNICIPAL AUDITING SERVICES The Town of Derry, New

More information

ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT. Request for Proposals (RFP) INNOVATIVE FINANCING STUDY FOR THE INTERSTATE 69 CORRIDOR

ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT. Request for Proposals (RFP) INNOVATIVE FINANCING STUDY FOR THE INTERSTATE 69 CORRIDOR ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT Request for Proposals (RFP) INNOVATIVE FINANCING STUDY FOR THE INTERSTATE 69 CORRIDOR Proposals must be submitted No later than 4:00 p.m. CDT July 30,

More information

SOLICITATION FOR PARTICIPATION IN A REQUEST FOR PROPOSALS FOR CHIEF EXECUTIVE OFFICER (CEO) SEARCH SERVICES JACKSONVILLE, FL SOLICITATION NUMBER 94414

SOLICITATION FOR PARTICIPATION IN A REQUEST FOR PROPOSALS FOR CHIEF EXECUTIVE OFFICER (CEO) SEARCH SERVICES JACKSONVILLE, FL SOLICITATION NUMBER 94414 SOLICITATION FOR PARTICIPATION IN A REQUEST FOR PROPOSALS FOR CHIEF EXECUTIVE OFFICER (CEO) SEARCH SERVICES JACKSONVILLE, FL SOLICITATION NUMBER 94414 PROPOSALS ARE DUE ON APRIL 27, 2018 BY 12:00 PM EST

More information

1/8/2013. IMPORTANT Dates

1/8/2013. IMPORTANT Dates Purpose Workforce Connections (WC) seeks a Construction Manager at Risk (CMAR) for preconstruction and potential future construction services for the Workforce Connections One Stop Career Center and Administrative

More information

REQUEST FOR PROPOSAL (RFP) # CONSULTANT SERVICES FOR DEVELOPMENT OF A DISTRICT SUSTAINABILITY PLAN

REQUEST FOR PROPOSAL (RFP) # CONSULTANT SERVICES FOR DEVELOPMENT OF A DISTRICT SUSTAINABILITY PLAN REQUEST FOR PROPOSAL (RFP) #1314-15 CONSULTANT SERVICES FOR DEVELOPMENT OF A DISTRICT SUSTAINABILITY PLAN Request for Proposal must be received no later than January 3, 2014 at 2:00 pm CARRI MATSUMOTO

More information

REQUEST FOR PROPOSALS FOR YOUTH SERVICES COORDINATOR TOWN OF AVON, CONNECTICUT RFP 09/10-26

REQUEST FOR PROPOSALS FOR YOUTH SERVICES COORDINATOR TOWN OF AVON, CONNECTICUT RFP 09/10-26 REQUEST FOR PROPOSALS FOR YOUTH SERVICES COORDINATOR TOWN OF AVON, CONNECTICUT RFP 09/10-26 The Town of Avon is seeking written responses to a Request for Proposal (RFP) for a part-time Youth Services

More information

REQUEST FOR PROPOSAL FOR BACKUP EMERGENCY GENERATORS DESIGN TOWN OF YUCCA VALLEY

REQUEST FOR PROPOSAL FOR BACKUP EMERGENCY GENERATORS DESIGN TOWN OF YUCCA VALLEY REQUEST FOR PROPOSAL FOR BACKUP EMERGENCY GENERATORS DESIGN TOWN OF YUCCA VALLEY RELEASED ON MARCH 21, 2017 PROPOSAL DUE DATE: APRIL 27, 2017 @ 3:00 PM March 21, 2017 NOTICE INVITING SEALED PROPOSALS,

More information

Okeechobee Utility Authority Engineering Services for Water Treatment Plant Improvements

Okeechobee Utility Authority Engineering Services for Water Treatment Plant Improvements Okeechobee Utility Authority Engineering Services for Water Treatment Plant Improvements Request for Qualifications/Proposals PART 1 1.1 PURPOSE The Okeechobee Utility Authority is requesting respondents

More information

Request for Proposals

Request for Proposals Request for Proposals City of Portsmouth, New Hampshire Annual Services Contract - Comprehensive INSTRUMENTATION and SCADA ANNUAL SERVICES CONTRACT RFP No. 04-08 CITY OF PORTSMOUTH, NH DEPARTMENT OF PUBLIC

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS FOR THE Transportation Development Act (TDA) Triennial Performance Audit of the Public Transit Systems and the Council of Governments in Stanislaus County Stanislaus Council of Governments 1111 I Street,

More information

STATE UNIVERSITY CONSTRUCTION FUND P R O G R A M D I R E C T I V E S

STATE UNIVERSITY CONSTRUCTION FUND P R O G R A M D I R E C T I V E S DIRECTIVE 1A-7 Issue date: January 2016 1. General BID PHASE REQUIREMENTS a. The bid period phase includes, but is not limited to, marketing the project to qualified and interested contractors, the reproduction

More information

Request for Proposals. Housing Study Consulting Services. Proposals DUE: January 6, City of Grandview. Economic Development Department

Request for Proposals. Housing Study Consulting Services. Proposals DUE: January 6, City of Grandview. Economic Development Department Request for Proposals Housing Study Consulting Services Proposals DUE: January 6, 2017 City of Grandview Economic Development Department Leonard Jones, Mayor Cory Smith, City Administrator REQUEST FOR

More information

Midpeninsula Regional Open Space District 330 Distel Circle, Los Altos, CA Issued: Friday, January 27, 2017

Midpeninsula Regional Open Space District 330 Distel Circle, Los Altos, CA Issued: Friday, January 27, 2017 Request for Qualifications and Proposals (RFQP) for Design Consulting Services for the Webb Creek Bridge Replacement Project, Bear Creek Redwood Open Space Preserve Midpeninsula Regional Open Space District

More information

REQUEST FOR PROPOSALS FOR ARCHITECTURAL AND ENGINEERING EVALUATION SERVICES FOR THE PUBLIC SAFETY BUILDING CITY OF OWOSSO, MICHIGAN

REQUEST FOR PROPOSALS FOR ARCHITECTURAL AND ENGINEERING EVALUATION SERVICES FOR THE PUBLIC SAFETY BUILDING CITY OF OWOSSO, MICHIGAN REQUEST FOR PROPOSALS FOR ARCHITECTURAL AND ENGINEERING EVALUATION SERVICES FOR THE PUBLIC SAFETY BUILDING CITY OF OWOSSO, MICHIGAN CITY OF OWOSSO 301 W. MAIN STREET OWOSSO, MICHIGAN 48867 February 23,

More information

Knights Ferry Elementary School District

Knights Ferry Elementary School District Knights Ferry Elementary School District REQUEST FOR PROPOSAL FOR THE IMPLEMENTATION OF ENERGY EFFICIENCY MEASURES FUNDED BY THE CLEAN ENERGY JOBS ACT - PROPOSITION 39 REQUEST FOR PROPOSAL SUBMITTAL DEADLINE

More information

FLORIDA DEPARTMENT OF TRANSPORTATION

FLORIDA DEPARTMENT OF TRANSPORTATION FLORIDA DEPARTMENT OF TRANSPORTATION ADDENDUM NO.: 1 Date: May 12, 2015 To: All Proposers From: Procurement Office RE: Questions and Answers RFP-DOT-14/15-9030-GH-ReAd: EMERGENCY MANAGEMENT SERVICES Notice

More information

The District is looking for the architectural firm to provide the following (not listed in order of preference):

The District is looking for the architectural firm to provide the following (not listed in order of preference): Weber Mosquito Abatement District Ryan J. Arkoudas, Director 505 West 12 th Street, Ogden, Utah 84404 Office (801) 392-1630 Fax (801)393-9399 www.webermosquito.com REQUEST FOR PROPOSAL FOR ARCHITECTURAL

More information

Biosolids Forest Fertilization Program

Biosolids Forest Fertilization Program Request for Expressions of Interest (RFEI) Biosolids Forest Fertilization Program Issue Date: June 20, 2017 Closing: 3 complete hard copies plus 1 electronic copy (CD, DVD, or USB flash drive) in.pdf format

More information

CITY OF GREENVILLE, SC REQUEST FOR PROPOSALS RFP NO

CITY OF GREENVILLE, SC REQUEST FOR PROPOSALS RFP NO CITY OF GREENVILLE, SC REQUEST FOR PROPOSALS RFP NO. 18-3602 SEALED PROPOSALS will be received in the Purchasing Division, 7th Floor, City Hall, 206 South Main Street, Greenville, South Carolina until

More information

REQUEST FOR QUALIFICATIONS (RFQ) AIRPORT ARCHITECTURAL AND ENGINEERING SERVICES AGREEMENT MINOT INTERNATIONAL AIRPORT

REQUEST FOR QUALIFICATIONS (RFQ) AIRPORT ARCHITECTURAL AND ENGINEERING SERVICES AGREEMENT MINOT INTERNATIONAL AIRPORT REQUEST FOR QUALIFICATIONS (RFQ) AIRPORT ARCHITECTURAL AND ENGINEERING SERVICES AGREEMENT MINOT INTERNATIONAL AIRPORT 2016-2021 GENERAL The intent and purpose of this Request for Qualifications (RFQ) is

More information

Engineering Consultant Services for FOLLY BEACH FISHING PIER REPLACEMENT. Folly Beach, South Carolina. RFQ # Date: April 26, 2018

Engineering Consultant Services for FOLLY BEACH FISHING PIER REPLACEMENT. Folly Beach, South Carolina. RFQ # Date: April 26, 2018 Engineering Consultant Services for FOLLY BEACH FISHING PIER REPLACEMENT Folly Beach, South Carolina RFQ Date: April 26, 2018 CHARLESTON COUNTY PARKS & RECREATION COMMISSION Table of Contents PRICE PROPOSAL

More information

Request for Proposals

Request for Proposals Request for Proposals COVER PAGE Local Government Management Association of BC FREEDOM OF INFORMATION AND PROTECTION OF PRIVACY ACT TOOL KIT UPDATE RFP Issue Date: July 29, 2011 RFP Closing Date and time:

More information

REQUEST FOR PROPOSALS FOR INFORMATION TECHNOLOGY SUPPORT SERVICES

REQUEST FOR PROPOSALS FOR INFORMATION TECHNOLOGY SUPPORT SERVICES REQUEST FOR PROPOSALS FOR INFORMATION TECHNOLOGY SUPPORT SERVICES ISSUE DATE: Bedford Township 8100 Jackman Rd. PO Box H Temperance, Michigan 48182 1 TABLE OF CONTENTS PAGE 1) Introduction 3 2) Sequence

More information

QUALIFICATIONS BASED SELECTION (QBS)

QUALIFICATIONS BASED SELECTION (QBS) QUALIFICATIONS BASED SELECTION (QBS) Transportation Professional Services Procurement Process LaSalle County Highway Department 1400 N.27 th Road Ottawa, IL 61350 Phone: (815) 434-0743 Fax: (815) 434-0747

More information

REQUEST FOR ARCHITECTURAL SERVICES ACTIVITY CENTER

REQUEST FOR ARCHITECTURAL SERVICES ACTIVITY CENTER REQUEST FOR ARCHITECTURAL SERVICES ACTIVITY CENTER Issued On: February 1, 2018 Date Due: February 23, 2018-2:00 pm CST At: 545 Academy Drive Northbrook, IL 60062 Northbrook Activity Center 180 Anets Drive

More information

REQUEST FOR PROPOSAL (RFP) for Feasibility Study Borough of Kennett Square New Municipal Office and Police Station Joint Facility

REQUEST FOR PROPOSAL (RFP) for Feasibility Study Borough of Kennett Square New Municipal Office and Police Station Joint Facility REQUEST FOR PROPOSAL (RFP) for Feasibility Study Borough of Kennett Square New Municipal Office and Police Station Joint Facility 1 Borough of Kennett Square Request for Proposals (RFP) Feasibility Study

More information

Red River Valley Water Supply Project. Request for Statement of Qualifications and Preliminary Proposal for Value Engineering Services.

Red River Valley Water Supply Project. Request for Statement of Qualifications and Preliminary Proposal for Value Engineering Services. Red River Valley Water Supply Project Request for Statement of Qualifications and Preliminary Proposal for Value Engineering Services June 7, 2018 The Garrison Diversion Conservancy District (Garrison

More information

Amalgamation Study Consultant

Amalgamation Study Consultant REQUEST FOR PROPOSAL RFP 2016 07 December 20, 2016 Amalgamation Study Consultant c/o City of Duncan, Administration Attention: Talitha Soldera, Director of Finance City of Duncan, 200 Craig Street, Duncan,

More information

City of Somersworth, New Hampshire OFFICE OF THE FINANCE DIRECTOR

City of Somersworth, New Hampshire OFFICE OF THE FINANCE DIRECTOR SCOTT A. SMITH Finance Director sasmith@somersworth.com One Government Way Somersworth, New Hampshire 03878 Phone: (603) 692-9504 Fax: (603) 692-9570 www.somersworth.com City of Somersworth, New Hampshire

More information

Request for Proposals (RFP) Consulting and Design Services for Solar Photovoltaic Systems for Iowa City Facilities September 22, 2017

Request for Proposals (RFP) Consulting and Design Services for Solar Photovoltaic Systems for Iowa City Facilities September 22, 2017 (RFP) Consulting and Design Services for Solar Photovoltaic Systems for Iowa City Facilities September 22, 2017 SUMMARY The City of Iowa City, Iowa is soliciting proposals from interested consultants to

More information

The City of Oxnard invites qualified consulting firms or individuals to submit qualifications for On-Call Permit Processing Services.

The City of Oxnard invites qualified consulting firms or individuals to submit qualifications for On-Call Permit Processing Services. Purchasing Division 300 West Third Street Oxnard, CA 93030 (805) 385-7478 www.ci.oxnard.ca.us August 22, 2016 Ladies and Gentlemen: The City of Oxnard invites qualified consulting firms or individuals

More information

REQUEST FOR QUALIFICATIONS CONSULTING SERVICES FOR PULLMAN-MOSCOW REGIONAL AIRPORT PULLMAN, WA

REQUEST FOR QUALIFICATIONS CONSULTING SERVICES FOR PULLMAN-MOSCOW REGIONAL AIRPORT PULLMAN, WA July 12, 2018 REQUEST FOR QUALIFICATIONS CONSULTING SERVICES FOR PULLMAN-MOSCOW REGIONAL AIRPORT PULLMAN, WA The Pullman-Moscow Regional Airport (PMRA) is soliciting Statements of Qualifications (SOQ)

More information

REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES DELTONA MIDDLE 250 ENTERPRISE ROAD DELTONA, FLORIDA MASTER PLAN PROJECT NO.

REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES DELTONA MIDDLE 250 ENTERPRISE ROAD DELTONA, FLORIDA MASTER PLAN PROJECT NO. REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES FOR DELTONA MIDDLE 250 ENTERPRISE ROAD DELTONA, FLORIDA 32725 MASTER PLAN PROJECT NO. 184620 School Board of Volusia County Florida Facilities Services

More information

REQUEST FOR PROPOSAL NEW MARKET TAX CREDIT CONSULTANT SERVICES

REQUEST FOR PROPOSAL NEW MARKET TAX CREDIT CONSULTANT SERVICES REQUEST FOR PROPOSAL NEW MARKET TAX CREDIT CONSULTANT SERVICES INTRODUCTION The City of South San Francisco seeks a consultant to provide professional services to assist with obtaining financing though

More information

Request for Proposals Issued by Northeast Florida Regional Council To Re-Write the City of Atlantic Beach Land Development Regulations

Request for Proposals Issued by Northeast Florida Regional Council To Re-Write the City of Atlantic Beach Land Development Regulations Request for Proposals Issued by Northeast Florida Regional Council To Re-Write the City of Atlantic Beach Land Development Regulations Background The Northeast Florida Regional Council (NEFRC) is the regional

More information

REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES WESTSIDE ELEMENTARY 1210 JIMMY ANN DRIVE DAYTONA BEACH, FLORIDA 32117

REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES WESTSIDE ELEMENTARY 1210 JIMMY ANN DRIVE DAYTONA BEACH, FLORIDA 32117 REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES FOR WESTSIDE ELEMENTARY 1210 JIMMY ANN DRIVE DAYTONA BEACH, FLORIDA 32117 RENOVATIONS & ADDITIONS PROJECT NO. 174582 School Board of Volusia County

More information

REQUEST FOR PROPOSAL

REQUEST FOR PROPOSAL REQUEST FOR PROPOSAL REQUESTOR: 1134 North Fraser Street Georgetown, SC 29440 Contact: Daniella Howard, Purchasing Agent Email: dhoward@cogsc.com Phone: 843.545.4043 PROJECT: Kaminski Street Proj #1511

More information

REQUEST FOR PROPOSALS (RFP #18-001) Vessel Construction Management Services

REQUEST FOR PROPOSALS (RFP #18-001) Vessel Construction Management Services REQUEST FOR PROPOSALS (RFP #18-001) The San Francisco Bay Area Water Emergency Transportation Authority ( WETA ) is seeking proposals from qualified firms in response to this Request for Proposals ( RFP

More information

Dakota County Technical College. Pod 6 AHU Replacement

Dakota County Technical College. Pod 6 AHU Replacement MINNESOTA STATE COLLEGES AND UNIVERSITIES Dakota County Technical College Pod 6 AHU Replacement REQUEST FOR PROPOSAL (RFP) FOR MECHANICAL ENGINEERING SERVICES JULY 16, 2018 SPECIAL NOTE: This Request for

More information

REQUEST FOR PROPOSALS FOR REPLACEMENT OF GENERATOR AT LAKE HILLS 1860 BOOSTER PUMP STATION

REQUEST FOR PROPOSALS FOR REPLACEMENT OF GENERATOR AT LAKE HILLS 1860 BOOSTER PUMP STATION REQUEST FOR PROPOSALS FOR REPLACEMENT OF GENERATOR AT LAKE HILLS 1860 BOOSTER PUMP STATION Issue Date: October 18th, 2016 Submission Deadline: November 8th, 2016, 2:00 PM P a g e 1 Table of Contents Introduction...

More information

City of Imperial On-Call Plan Check and Inspection Services. Released: September 13, Important Dates

City of Imperial On-Call Plan Check and Inspection Services. Released: September 13, Important Dates Request for Proposal On-Call Plan Check and Inspection Services Released: September 13, 2013 Important Dates Proposal Due: September 27, 2013 Award of Contract: October 2, 2013 Planning and Development

More information

CITY OF JOPLIN, MISSOURI

CITY OF JOPLIN, MISSOURI Engineering Department CITY OF JOPLIN 602 South Main Street Joplin, Missouri 64801 Phone (417) 624-0820 Ext. 530 Fax (417) 625-4738 CITY OF JOPLIN, MISSOURI ON-CALL ENGINEERING PROFESSIONAL SERVICES REQUEST

More information

REQUEST FOR PROPOSALS FOR ADMINISTRATION BUILDING REMODELING

REQUEST FOR PROPOSALS FOR ADMINISTRATION BUILDING REMODELING Board of Commissioners of the Port of New Orleans REQUEST FOR PROPOSALS FOR ADMINISTRATION BUILDING REMODELING OCTOBER 3, 2017 Deadline for proposals is no later than Wednesday, October, 18, 2017 by 11

More information