1 TREASURE COAST REGIONAL PLANNING COUNCIL DRAFT Subject to modifications M E M O R A N D U M To: Council Members AGENDA ITEM 9A From: Date: Subject: Staff January 19, 2007 Council Meeting Florida Research Park Amended Development Order Introduction The Florida Research Park Development of Regional Impact (DRI) filed a Notice of Proposed Change (NOPC) to a previously approved Development Order (DO) on April 5, The NOPC was updated on November 2, Based on the NOPC, Palm Beach County issued an amended DO for the Florida Research Park DRI on November 27, The DO has been rendered to Council and the Department of Community Affairs (DCA). At this point, the Council is to advise DCA on: 1) whether the County s DO addresses all regional issues; and 2) whether DCA should appeal the DO. DCA must make the determination whether or not to appeal the DO by February 2, Background The Florida Research Park DRI was originally approved as the Palm Beach Park of Commerce, a 1,243-acre industrial development that was reviewed by Council in December, 1981, and approved by Palm Beach County on February 2, The project is located in unincorporated Palm Beach County on the north side of SR 710 (Beeline Highway) and east side of SR 711 (Pratt and Whitney Road) (Exhibit 1). The Master Development Plan provides for 6,250,000 square feet of industrial and commercial development (Exhibit 2). The Florida Research Park DRI owners are proposing to reconfigure the master plan by adding approximately 80 acres in the northwest portion of the project site, adding an additional access point from a new 80 foot right-of-way, and redesignating acres from utility to general industrial. The property owner is also requesting to extend the build out for 7 years from 2014 to December 31, In 1993, the County granted a buildout extension from 2006 to July 31, Overview Palm Beach County has amended the development order (Exhibit 4) to extend the buildout date, include additional property into the project, and provide a new access driveway. Revised traffic

2 2 DRAFT Subject to modifications conditions have been incorporated into the amended development order. These conditions are based on a Traffic Impact Analysis prepared by Kimley-Horn and Associates dated November The traffic study was prepared to identify traffic impact due to a) the proposed buildout extension to the year 2021; and b) a new proposed access driveway onto Seminole Pratt-Whitney Road. The traffic study was performed in conformance with the requirements of Palm Beach County Traffic Performance Standards, Article 12 of the Unified Land Development Code. The 2021 traffic projections include traffic from projects currently approved in Palm Beach County. While most of these projects are expected to be built, the Palm Beach County Biotechnology Research Park (usually referred to as Mecca Site) Development of Regional Impact is not likely to be built as approved. However, as part of approved developments, this project was included when estimating traffic projections. If the density and intensity of development at the Mecca Site were reduced as expected, traffic projections included in the Florida Research Park Traffic Impact Analysis would be overestimated. Two resolutions regarding the development order for the Florida Research Park have been adopted. These are: Resolution Numbers R and R Most of the transportation related conditions are included in Resolution R , while the other resolution only includes three conditions related to transportation. Both resolutions include three sections which are summarized as follows: Section I Includes conditions of development with a buildout date of 2014 (no extension). Section II Includes conditions of development with a buildout date of 2021 (proposed extension). Section III Indicates Section II shall become effective upon the effective date of the Constrained Roadways at a Lower Level of Service (CRALLS) Comprehensive Plan Amendment and the applicant obtaining the LOS modifications necessary from the Florida Department of Transportation to address transportation related conditions of approval. However, it also includes a clause indicating Section II will expire within two years from the date of approval of the development order if the applicant does not obtain the LOS modifications or CRALLS designations. Analysis The Traffic Impact Analysis shows that at buildout of the project (year 2021) several roadways significantly impacted by project traffic are projected to exceed the adopted service volume at some time during development of the Florida Research Park (Exhibit 3): Indiantown Road from Jupiter Farms Road to Florida s Turnpike Seminole Pratt-Whitney Road from Orange Boulevard to Northlake Boulevard PGA Boulevard from Florida s Turnpike to Central Boulevard Indiantown Road from Florida s Turnpike to I-95 PGA Boulevard from Jog Road/Ryder Cup Boulevard to Florida s Turnpike PGA Boulevard from Central Boulevard to Military Trail PGA Boulevard from Beeline Highway to Jog Road/Ryder Cup Boulevard Indiantown Road from I-95 to Central Boulevard

3 DRAFT Subject to modifications Seminole Pratt-Whitney Road from PGA Boulevard to Beeline Highway Seminole Pratt-Whitney Road from Beeline Highway to Indiantown Road Coconut Boulevard from Orange Boulevard to Northlake Boulevard Indiantown Road from Alexander Run Road to Jupiter Farms Road Indiantown Road from Pratt-Whitney Road to Alexander Run Road Orange Boulevard from Coconut Boulevard to Royal Palm Beach Boulevard The CRALLS designations for the roadway segments identified above as well as several intersections have been transmitted to the DCA by Palm Beach County as part of a Comprehensive Plan Amendment. Once CRALLS designations have been adopted, no improvements will be required on these roads. Beeline Highway (SR 710) is part of the Florida Intrastate Highway System as well as the Strategic Intermodal System. As such, the Florida Department of Transportation has established minimum level of service standards. The following roadway segments within Beeline Highway are projected to exceed the adopted service volume at some time during development of the Florida Research Park: Jog Road to Blue Heron Boulevard Northlake Boulevard to Jog Road North County Airport to PGA Boulevard Martin County Line to west of Pratt Whitney Entrance The developer has requested a variance to the adopted level of service from the Department of Transportation. If approved, no improvements will be required on these roadway segments. Regional Issues The following issues have been identified: 1. Impacts into Martin County As the Traffic Impact Analysis has been prepared based on the requirements of Palm Beach County Traffic Performance Standards, impacts into Martin County have not been identified or mitigated. Florida Research Park Traffic has significant impact on both Beeline Highway and Pratt-Whitney Road into Martin County. Conditions to widen these two roads within Palm Beach County up to the Martin County line are included in the development order. These conditions also include the alternative of getting variances or CRALLS designations. Therefore, impacts into Martin County, which have not been evaluated, will create unreviewed and unmitigated traffic impacts on the regional roadway network. Palm Beach County can address this regional concern by adding a condition which requires an analysis of traffic impact of the Florida Research Park DRI into Martin County. The methodology should be approved by Martin County, the Florida Department of Transportation and the Treasure Coast Regional Planning Council. The 3

4 4 DRAFT Subject to modifications traffic analysis should evaluate traffic impact at buildout of the DRI and identify improvements, if any, necessary to maintain roadways and intersections at the adopted levels of service. The development order should then be amended to include additional conditions of approval necessary to mitigate traffic impact of the proposed development in Martin County. 2. Seminole Pratt-Whitney Road One of the development order conditions includes construction of Seminole Pratt- Whitney Road between its terminus near Northlake Boulevard and Beeline Highway. However, this condition also indicates the project can proceed after September 30, 2007 without construction of the road as the improvement was part of the County s Five-Year Road Program at the time the project got concurrency approval. In the interim time, Palm Beach County has deleted this improvement from its Five-Year Road Program. As a result, the project will create unreviewed and unmitigated traffic impacts on the regional roadway network. The County can address this regional concern by putting the improvement back into its Five-Year Road Program, or by adding a condition in the development order that requires an analysis which does not include this road. The analysis will result in additional impact to nearby roadways. Therefore, the development order should be amended to include additional conditions of approval necessary to mitigate traffic impact. It is expected that both the CRALLS designation and variance would require revisions to include this additional traffic. 3. Impacts along SR 710 As mentioned earlier, Beeline Highway (SR 710) is part of the Florida Intrastate Highway System as well as the Strategic Intermodal System. Since the Florida Department of Transportation establishes minimum level of service standards, CRALLS designations are not permitted. A variance to mitigate traffic impact of the Florida Research Park by lowering the level of service on some roadway segments along Beeline Highway has been requested from the Department of Transportation. Two other Developments of Regional Impact (Quillen and Indiantown) are projected to have significant impact on SR 710. These developments have obtained an impact assessment report from the Treasure Coast Regional Planning Council and are awaiting approval from Martin County. Some segments along SR 710 will be significantly impacted by all three developments of regional impact: Quillen, Indiantown and Florida Research Park. The Florida Department of Transportation is currently undertaking a preliminary design and engineering (PD&E) study for all segments of SR 710 under consideration. The study is expected to be finished within the next two to three years. Once the study is finished, identified improvements need to be included for construction in the Department s Five-Year Road Program. Therefore, as of now, no improvements have been scheduled for any segments of SR 710.

5 DRAFT Subject to modifications Comments Since there are three developments of regional impact which are projected to have significant impact on segments of SR 710, it is recommended the variance for SR 710 include all three projects. This approach would be comprehensive in nature as it includes two counties. In addition, the variance should present mitigation measures to minimize traffic impact on SR 710 and should evaluate funding options to schedule construction of improvements as soon as possible. The development order is difficult to follow since the last section is the one indicating which of the preceding sections is applicable. The following two conditions appear to be in conflict and they should be revised, if appropriate: Engineering Condition 5 of Section I: No building permits for the site may be issued after July, 31, Engineering Condition 5 of Section II: No building permits for the site may be issued after December, 31, The traffic impact analysis shows significant impact on the segment of Florida s Turnpike between Beeline Highway and Okeechobee Boulevard. This segment is not projected to maintain the adopted level of service. While the applicant has obtained a letter from the Florida s Turnpike Enterprise indicating no objections to the extended buildout date, the development order does not include improvements to mitigate traffic impact. This issue should be addressed either in the traffic impact analysis or the development order. Conclusions Council believes the concerns expressed above can be adequately addressed by amending the development order as recommended in this report. The DCA should appeal the development order for the Florida Research Park DRI unless the County agrees to amend the DO as recommended by Council. Recommendation Council should adopt and transmit its report and recommendations on the Florida Research Park DRI Amended Development Order to the Florida Department of Community Affairs. Attachments 5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

32

33

34

35

36

37

38

39

40

41

42

43

44

45

46

47

48

49

50

51

52

53

54

55

56

57

58

59

60

61

62

63

64

65

66

67

68

DRAFT Subject to Modifications

DRAFT Subject to Modifications TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M DRAFT Subject to Modifications To: Council Members AGENDA ITEM 5I From: Date: Subject: Staff June 15, 2012 Council Meeting Local Government

More information

CITY GATE COMMERCE PARK DRI NOTICE OF PROPOSED CHANGE IN COLLIER COUNTY

CITY GATE COMMERCE PARK DRI NOTICE OF PROPOSED CHANGE IN COLLIER COUNTY CITY GATE COMMERCE PARK DRI NOTICE OF PROPOSED CHANGE IN COLLIER COUNTY BACKGROUND The City Gate Commerce Park Development of Regional Impact (DRI) is located on 291.55 acres at the northeast corner of

More information

ADMINISTRATIVE CODE BOARD OF COUNTY COMMISSIONERS

ADMINISTRATIVE CODE BOARD OF COUNTY COMMISSIONERS ADMINISTRATIVE CODE BOARD OF COUNTY COMMISSIONERS CATEGORY: DEVELOPMENT/PLANNING/ZONING TITLE: TRANSPORTATION PROPORTIONATE SHARE CALCULATIONS FOR NEW DEVELOPMENT PROJECTS CODE NUMBER: AC-13-16 ADOPTED:

More information

BABCOCK RANCH MASTER DEVELOPMENT ORDER DRI # NOTICE OF PROPOSED CHANGE

BABCOCK RANCH MASTER DEVELOPMENT ORDER DRI # NOTICE OF PROPOSED CHANGE BABCOCK RANCH MASTER DEVELOPMENT ORDER DRI # 03-0607-177 NOTICE OF PROPOSED CHANGE Background: The Charlotte County Board of County Commissioners (the Board) originally approved the Babcock Ranch Master

More information

PUBLIC SCHOOL FACILITIES ELEMENT:

PUBLIC SCHOOL FACILITIES ELEMENT: PUBLIC SCHOOL FACILITIES ELEMENT: Goals, Objectives and Policies Goal 1: Public School Concurrency. It is a GOAL of the Town of Jupiter to provide for future availability of public school facilities consistent

More information

INTERGOVERNMENTAL COORDINATION ELEMENT:

INTERGOVERNMENTAL COORDINATION ELEMENT: INTERGOVERNMENTAL COORDINATION ELEMENT: Goals, Objectives and Policies Goal 1: To give the Town the maximum amount of input, control, and advisory power with other public agencies for the protection of

More information

REQUEST FOR CITY COUNCIL ACTION

REQUEST FOR CITY COUNCIL ACTION REQUEST FOR CITY COUNCIL ACTION MEETING DATE: MARCH 14, 2017 TITLE: SCOPING SESSION FOR A GENERAL PLAN AMENDMENT REQUEST REPRESENTING AN EXCHANGE OF NON RESIDENTIAL BUILDING SQUARE FOOTAGE FOR NEW RESIDENTIAL

More information

ORDINANCE NO WHEREAS, the Town Council of the Town of Jupiter, Florida (Town), has adopted a

ORDINANCE NO WHEREAS, the Town Council of the Town of Jupiter, Florida (Town), has adopted a 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 ORDINANCE NO. 7-18 AN ORDINANCE OF THE TOWN COUNCIL OF THE TOWN OF JUPITER, FLORIDA, AMENDING ORDINANCE

More information

TEXT AMENDMENT STAFF REPORT AMENDMENT ROUND 05-1

TEXT AMENDMENT STAFF REPORT AMENDMENT ROUND 05-1 TEXT AMENDMENT STAFF REPORT AMENDMENT ROUND 05-1 Item Name: Element: Item Before the Board: Westgate CRA TCEA Modification Transportation Element (TE) To hold a public hearing on a proposed amendment to

More information

DECISION OF THE CAPE COD COMMISSION

DECISION OF THE CAPE COD COMMISSION Date: To: From: Re: Applicant: Michael D. Ford, Esq. P.O. Box 665 Harwich, MA 02671 Cape Cod Commission Development of Regional Impact Hardship Exemption Cape Cod Commission Act, Section 23 Couto Management

More information

City of Lynwood MODIFIED REQUEST FOR PROPOSALS FOR

City of Lynwood MODIFIED REQUEST FOR PROPOSALS FOR City of Lynwood MODIFIED REQUEST FOR PROPOSALS FOR AN URBAN PLANNING FIRM TO PREPARE A SPECIFIC PLAN AMENDMENT TO THE LYNWOOD TRANSIT AREA SPECIFIC PLAN AND REQUIRED CEQA SUPPORTING DOCUMENTS (SUPPLEMENTAL

More information

NOW THEREFORE, the parties enter into the following Agreement:

NOW THEREFORE, the parties enter into the following Agreement: Interlocal Agreement Between the Board of County Commissioners of St. Johns County, Florida, City of St. Augustine, City of St. Augustine Beach, Town of Hastings and the School Board of St. Johns County,

More information

-Recitals- - Signatures on following pages - Revised Exhibit 1 Rev MOU June 5, TEU Page 1 of 44

-Recitals- - Signatures on following pages - Revised Exhibit 1 Rev MOU June 5, TEU Page 1 of 44 This Memorandum of Understanding between the City of Jacksonville and the Florida Department of Transportation is regarding the Mayo Foundation for Medical Education and Research s fulfillment of Phase

More information

TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M

TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M To: Council Members AGENDA ITEM 5D From: Date: Subject: Staff March 18, 2011 Council Meeting Local Government Comprehensive Plan Review Draft

More information

Florida Job Growth Grant Fund. Public Infrastructure Grant Proposal. Table of Contents

Florida Job Growth Grant Fund. Public Infrastructure Grant Proposal. Table of Contents Florida Job Growth Grant Fund Public Infrastructure Grant Proposal Table of Contents Florida Job Growth Grant Fund Public Infrastructure Grant Proposal Application 1 Florida Job Growth Grant Fund Public

More information

CYPRESS GROVE COMMUNITY DEVELOPMENT DISTRICT BOARD OF SUPERVISORS MINUTES. Date: April 16, :00 A.M.

CYPRESS GROVE COMMUNITY DEVELOPMENT DISTRICT BOARD OF SUPERVISORS MINUTES. Date: April 16, :00 A.M. CYPRESS GROVE COMMUNITY DEVELOPMENT DISTRICT BOARD OF SUPERVISORS MINUTES Date: April 16, 2018 8:00 A.M. Held at 8756 Boynton Beach Boulevard, Suite 2100 Boynton Beach, Florida 33472 1. Roll Call The meeting

More information

SOUTHWEST LRT (METRO GREEN LINE EXTENSION)

SOUTHWEST LRT (METRO GREEN LINE EXTENSION) 10 Joint Development This chapter describes potential long-term direct and indirect and short-term (construction) direct and indirect effects that would result from the Southwest Light Rail Transit (LRT)

More information

PINELLAS COUNTY DEO#12-1ESR

PINELLAS COUNTY DEO#12-1ESR Agenda Item #3.H.11 02/13/12 LOCAL GOVERNMENT COMPREHENSIVE PLAN PROPOSED AMENDMENT REPORT PINELLAS COUNTY DEO#12-1ESR 1 THIS PAGE INTENTIONALLY LEFT BLANK 2 PINELLAS COUNTY LPA 22-10-11 Expedited State

More information

2018 AMERICAN COUNCIL OF ENGINEERING COMPANIES OF FLORIDA (ACEC-FL) OUTSTANDING PROJECT AWARDS (OPA) PROGRAM

2018 AMERICAN COUNCIL OF ENGINEERING COMPANIES OF FLORIDA (ACEC-FL) OUTSTANDING PROJECT AWARDS (OPA) PROGRAM 2018 AMERICAN COUNCIL OF ENGINEERING COMPANIES OF FLORIDA (ACEC-FL) OUTSTANDING PROJECT AWARDS (OPA) PROGRAM I. GENERAL The American Council of Engineering Companies of Florida (ACEC-FL), formerly Florida

More information

FLAGLER COUNTY BOARD OF COUNTY COMMISSIONERS

FLAGLER COUNTY BOARD OF COUNTY COMMISSIONERS FLAGLER COUNTY BOARD OF COUNTY COMMISSIONERS Government Services Building, Board Chambers 1769 E. Moody Blvd., Building #2 Bunnell, FL 32110 July 7, 2008 @ 9:00 a.m. AGENDA PLEDGE TO THE FLAG Announcements

More information

ELEMENT 12 - INTERGOVERNMENTAL COORDINATION ELEMENT

ELEMENT 12 - INTERGOVERNMENTAL COORDINATION ELEMENT ELEMENT 12 - INTERGOVERNMENTAL COORDINATION ELEMENT The context area for the John D. MacArthur Campus of FAU is defined to be that area bounded by Highway 441 on the west, the Atlantic Ocean on the east,

More information

FAMRC FLORIDA ADVANCED MANUFACTURING RESEARCH CENTER. Osceola County Commissioner Cheryl Grieb Greater Osceola Partnership Director Bill Martin

FAMRC FLORIDA ADVANCED MANUFACTURING RESEARCH CENTER. Osceola County Commissioner Cheryl Grieb Greater Osceola Partnership Director Bill Martin FAMRC FLORIDA ADVANCED MANUFACTURING RESEARCH CENTER Osceola County Commissioner Cheryl Grieb Greater Osceola Partnership Director Bill Martin FAMRC Florida Advanced Manufacturing Research Center The Center

More information

REPORT. To the Honorable Mayor and City Council From the City Manager. May 9, 2016

REPORT. To the Honorable Mayor and City Council From the City Manager. May 9, 2016 REPORT To the Honorable Mayor and City Council From the City Manager May 9, 2016 SUBJECT Study Session for Consideration of the Draft Inner Harbor Specific Plan, Draft Inner Harbor Specific Plan Environmental

More information

BUS ROUTES. Stop #3: PGA Boulevard and Military Trail, north west corner, Publix Plaza, behind PNC Banks by Paddy Mac s

BUS ROUTES. Stop #3: PGA Boulevard and Military Trail, north west corner, Publix Plaza, behind PNC Banks by Paddy Mac s 2018-19 BUS ROUTES NOTE: contracts with Jupiter School Bus Service for our yellow school bus service. The buses will have JUPITER SCHOOL BUS SERVICE written in large letters on the side. This document

More information

Synopsis of Revised Changes to DCA s Rules for Developments of Regional Impact

Synopsis of Revised Changes to DCA s Rules for Developments of Regional Impact The Georgia Planning Act, passed by the General Assembly in 1989, charged the Georgia Department of Community Affairs with administering the State s comprehensive planning program. 1 That legislation assigned

More information

LAKE~SUMTER MPO 2035 TRANSPORTATION PLAN & LAND USE WORKSHOP

LAKE~SUMTER MPO 2035 TRANSPORTATION PLAN & LAND USE WORKSHOP LAKE~SUMTER MPO 2035 TRANSPORTATION PLAN & LAND USE WORKSHOP Wednesday, January 14, 2009 9:00 a.m. to Noon Lake County Agricultural Center 1951 Woodlea Road Tavares, Florida 32778 PROMOTING REGIONAL TRANSPORTATION

More information

Invitation letters were ed to 44 members of the PAG on June 23, Reminder invites were ed to PAG members on July 18, 2017.

Invitation letters were  ed to 44 members of the PAG on June 23, Reminder invites were  ed to PAG members on July 18, 2017. POINCIANA PARKWAY EXTENSION / I-4 CONNECTOR PROJECT ADVISORY GROUP (PAG) MEETING SUMMARY Date/Time: Wednesday, July 19, 2017, 2:00 p.m. to 3:30 p.m. Location: Poinciana Library, 101 N. Dover Plum Road,

More information

Client Authorization

Client Authorization Carnahan, Proctor and Cross, Inc. 814 S. Military Trail Amendment No. NA Project No: Deerfield Beach, Florida 33442 11/11/15 Phone: 954.972.3959 Rev. 04/01/16 Fax: 954.972.4178 www.carnahan proctor.com

More information

Tentative Project Schedule. Non-Discrimination i i Laws. Para Preguntas en español

Tentative Project Schedule. Non-Discrimination i i Laws. Para Preguntas en español Florida Department of Transportation, District Seven Project Newsletter Number 1 October 2012 The Florida Department of Transportation (FDOT) is conducting a Project Development & Environment (PD&E) study

More information

VALUE ENGINEERING PROGRAM

VALUE ENGINEERING PROGRAM Approved: Effective: May 17, 2017 Review: March 30, 2017 Office: Production Support Office Topic No.: 625-030-002-i Department of Transportation PURPOSE: VALUE ENGINEERING PROGRAM To provide a consistent

More information

STAFF REPORT Toyota of Hollywood 044-MP-15

STAFF REPORT Toyota of Hollywood 044-MP-15 Page 1 of 12 STAFF REPORT Toyota of Hollywood 044-MP-15 A request to modify conditions of plat approval has been filed with the Planning and Development Management Division. This plat was approved by the

More information

4.b. 6/22/2017. Local Agency Formation Commission. George J. Spiliotis, Executive Officer

4.b. 6/22/2017. Local Agency Formation Commission. George J. Spiliotis, Executive Officer 4.b. 6/22/2017 TO: FROM: SUBJECT: Local Agency Formation Commission George J. Spiliotis, Executive Officer LAFCO 2014-09-5 SPHERE OF INFLUENCE AMENDMENT TO THE CITY OF BEAUMONT (ADDITION) AND AMENDMENT

More information

Variance and Cisco Systems Attachments:

Variance and Cisco Systems Attachments: Variance 15-03 and 15-04 Cisco Systems Attachments: 1. Locator 2. Staff Report 3. Applicant s Statement 4. Variance Exhibit 5. VAR 00-07 exhibit Pres G eo r ge B us h Hw y Infocom Dr VAR 15-03 and 04 Cisco

More information

INDIAN RIVER COUNTY METROPOLITAN PLANNING ORGANIZATION

INDIAN RIVER COUNTY METROPOLITAN PLANNING ORGANIZATION 2016 PRIORITY PROJECTS REPORT INDIAN RIVER COUNTY METROPOLITAN PLANNING ORGANIZATION This document was produced in cooperation with the Florida Department of Transportation and the Federal Highway Administration

More information

A. 3. Identify whether the proposed development is located in a designated special hurricane preparedness district.

A. 3. Identify whether the proposed development is located in a designated special hurricane preparedness district. 23. HURRICANE PREPAREDNESS A. 1. Identify any residential development proposed within the hurricane vulnerability zone delineated in the applicable regional hurricane evacuation study, regional public

More information

Corridor Advisory Committee Meeting #52. February 16, :00 PM - 8:00 PM Progress Park Downey Ave, Paramount, CA MEETING SUMMARY

Corridor Advisory Committee Meeting #52. February 16, :00 PM - 8:00 PM Progress Park Downey Ave, Paramount, CA MEETING SUMMARY Corridor Advisory Committee Meeting #52 February 16, 2017 6:00 PM - 8:00 PM Progress Park 15500 Downey Ave, Paramount, CA 90723 INTRODUCTION On Thursday, February 16, 2017, the Corridor Advisory Committee

More information

Coolidge - Florence Regional Transportation Plan

Coolidge - Florence Regional Transportation Plan Coolidge - Florence Regional Transportation Plan A Partnership Among the City of Coolidge, Town of Florence, and ADOT FINAL REPORT Kimley-Horn Kimley Kimley-Horn and and Associates, Associates, Inc. Inc.

More information

500 EL CAMINO REAL PROJECT. City Council Tuesday, April 16, 2013

500 EL CAMINO REAL PROJECT. City Council Tuesday, April 16, 2013 500 EL CAMINO REAL PROJECT City Council Tuesday, April 16, 2013 Background Proposal Project Review Process Summary Background Vision Plan (2007-2008) 12 overarching goals Established foundation for the

More information

INTERGOVERNMENTAL COORDINATION ELEMENT

INTERGOVERNMENTAL COORDINATION ELEMENT INTERGOVERNMENTAL COORDINATION ELEMENT I. PURPOSE The purpose of this Element is to identify and resolve incompatible goals, objectives, policies and development proposed by other governmental entities,

More information

South Florida Transit Oriented Development (SFTOD) Grant Program Request for Applications

South Florida Transit Oriented Development (SFTOD) Grant Program Request for Applications South Florida Transit Oriented Development (SFTOD) Grant Program Request for Applications BACKGROUND AND PURPOSE The South Florida Regional Transportation Authority (SFRTA), South Florida Regional Planning

More information

Highway Safety Improvement Program Procedures Manual

Highway Safety Improvement Program Procedures Manual Highway Safety Improvement Program Procedures Manual February 2017 Division of Planning Office of Systems Planning and Program Management Contents Section Page Preface... iii HSIP Program Procedure...

More information

CASE # N OLYMPIC METAL - STREET NAME CHANGE BILL SKINNER, SENIOR PLANNER NOVEMBER 28, 2017

CASE # N OLYMPIC METAL - STREET NAME CHANGE BILL SKINNER, SENIOR PLANNER NOVEMBER 28, 2017 ARAPAHOE COUNTY PLANNING COMMISSION PUBLIC HEARING DECEMBER 5, 2017 6:30 P.M. CASE # N17-001 OLYMPIC METAL - STREET NAME CHANGE BILL SKINNER, SENIOR PLANNER NOVEMBER 28, 2017 VICINITY MAP The roadway proposed

More information

A G E N D A LEWISVILLE CITY COUNCIL MEETING JULY 2, 2018 LEWISVILLE CITY HALL 151 WEST CHURCH STREET LEWISVILLE, TEXAS 75057

A G E N D A LEWISVILLE CITY COUNCIL MEETING JULY 2, 2018 LEWISVILLE CITY HALL 151 WEST CHURCH STREET LEWISVILLE, TEXAS 75057 A G E N D A MEETING LEWISVILLE CITY HALL 151 WEST CHURCH STREET LEWISVILLE, TEXAS 75057 WORKSHOP SESSION - 6:30 P.M. REGULAR SESSION 7:00 P.M. Call to Order and Announce a Quorum is Present. WORKSHOP SESSION

More information

TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M. To: Council Members AGENDA ITEM 5H

TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M. To: Council Members AGENDA ITEM 5H TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M To: Council Members AGENDA ITEM 5H From: Date: Subject: Staff December 10, 2010 Council Meeting Intergovernmental Coordination and Review Log

More information

Western Slope CIP and TIM Fee Update Workshop

Western Slope CIP and TIM Fee Update Workshop Western Slope CIP and TIM Fee Update Workshop Board of Supervisors Study Session May 5, 2015 14-0245 8K 1 of 39 Agenda 1. Brief Background 2. Receive and file: Traffic Analysis Methodology 3. BOS Direction:

More information

Capital Circle Southwest (SR 263)

Capital Circle Southwest (SR 263) Capital Circle Southwest (SR 263) from Crawfordville Road (US 319) to Blountstown Highway (SR 20) Tallahassee, Florida FPID 415782-4 Public Hearing December 4, 2014 This Public Hearing is being held in

More information

PUBLIC FACILITIES FINANCING

PUBLIC FACILITIES FINANCING 9. Public Facilities Financing Brisbane Baylands Specific Plan 257 9 PUBLIC FACILITIES FINANCING 9.1 PURPOSE The Baylands is planned to accommodate a variety of uses including retail at a range of types

More information

SCOPE OF SERVICES FOR CONSULTING ENGINEERING SERVICES PROJECT DEVELOPMENT AND ENVIRONMENT STUDY AND DESIGN

SCOPE OF SERVICES FOR CONSULTING ENGINEERING SERVICES PROJECT DEVELOPMENT AND ENVIRONMENT STUDY AND DESIGN I-295 from SR 13 (San Jose) to SR 21 (Blanding Blvd) FIN #: 213345-9-22-01 Federal Project #: TBD Duval County, Florida SCOPE OF SERVICES FOR CONSULTING ENGINEERING SERVICES PROJECT DEVELOPMENT AND ENVIRONMENT

More information

SAFETEA-LU. Overview. Background

SAFETEA-LU. Overview. Background SAFETEA-LU This document provides information related to the Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEA-LU) that was previously posted on the Center for

More information

Florida Job Growth Grant Fund Public Infrastructure Grant Proposal

Florida Job Growth Grant Fund Public Infrastructure Grant Proposal Florida Job Growth Grant Fund Public Infrastructure Grant Proposal Proposal Instructions: The Florida Job Growth Grant Fund Proposal (this document) must be completed by the governmental entity applying

More information

Brevard County Public Schools Growth Management. School Concurrency Review Fees

Brevard County Public Schools Growth Management. School Concurrency Review Fees Brevard County Public Schools Growth Management School Concurrency Review Fees October 2008 PROPOSED FEE SCHEDULE Review / Negotiation Type Cost School Capacity Determination Comp Plan/FLU Amend. $400

More information

NORTH CENTRAL TEXAS COUNCIL OF GOVERNMENTS METROPOLITAN PLANNING ORGANIZATION REQUEST FOR PROPOSALS

NORTH CENTRAL TEXAS COUNCIL OF GOVERNMENTS METROPOLITAN PLANNING ORGANIZATION REQUEST FOR PROPOSALS NORTH CENTRAL TEXAS COUNCIL OF GOVERNMENTS METROPOLITAN PLANNING ORGANIZATION REQUEST FOR PROPOSALS CITY OF CEDAR HILL CITY CENTER TRANSIT-ORIENTED DEVELOPMENT PLAN August 19, 2011 REQUEST FOR PROPOSALS

More information

APPENDIX 1 BROWARD COUNTY PLANNING COUNCIL PLAN AMENDMENT REQUIREMENTS AND PROCEDURES

APPENDIX 1 BROWARD COUNTY PLANNING COUNCIL PLAN AMENDMENT REQUIREMENTS AND PROCEDURES APPENDIX 1 BROWARD COUNTY PLANNING COUNCIL PLAN AMENDMENT REQUIREMENTS AND PROCEDURES Broward County Land Use Plan Amendment Requirements Amendments which are not within the rules of flexibility or more

More information

MEMORANDUM AGENDA ITEM #7c

MEMORANDUM AGENDA ITEM #7c South Florida Regional Planning Council MEMORANDUM AGENDA ITEM #7c DATE: SEPTEMBER 8, 2008 TO: FROM: SUBJECT: COUNCIL MEMBERS STAFF MIAMI-DADE COUNTY ADOPTED COMPREHENSIVE PLAN AMENDMENT Introduction On

More information

3 MAJOR MACKENZIE DRIVE TRANSPORTATION IMPROVEMENTS HIGHWAY 50 TO WESTON ROAD, CITY OF VAUGHAN STATUS UPDATE, PROJECT 8066

3 MAJOR MACKENZIE DRIVE TRANSPORTATION IMPROVEMENTS HIGHWAY 50 TO WESTON ROAD, CITY OF VAUGHAN STATUS UPDATE, PROJECT 8066 3 MAJOR MACKENZIE DRIVE TRANSPORTATION IMPROVEMENTS HIGHWAY 50 TO WESTON ROAD, CITY OF VAUGHAN STATUS UPDATE, PROJECT 8066 The Transportation and Works Committee recommends the adoption of the recommendations

More information

COUNTY OF CHARLOTTE. County Commissioners Murdock Circle Port Charlotte, FL

COUNTY OF CHARLOTTE. County Commissioners Murdock Circle Port Charlotte, FL COUNTY OF CHARLOTTE Board of County Commissioners 18500 Murdock Circle Port Charlotte, FL 33948 www.charlottecountyfl.com County Commissioners Sara Devos, District 5, Chairman Tom Moore, District 3, Vice

More information

CITY OF DANA POINT AGENDA REPORT KYLE BUTTERWICK, DIRECTOR OF COMMUNITY DEVELOPMENT BRAD FOWLER, DIRECTOR OF PUBLIC WORKS DEPARTMENT

CITY OF DANA POINT AGENDA REPORT KYLE BUTTERWICK, DIRECTOR OF COMMUNITY DEVELOPMENT BRAD FOWLER, DIRECTOR OF PUBLIC WORKS DEPARTMENT 01/17/12 Page 1 Item #14 CITY OF DANA POINT AGENDA REPORT Reviewed By: DH _X CM _X CA X DATE: JANUARY 17, 2012 TO: FROM: THE HONORABLE CITY COUNCIL KYLE BUTTERWICK, DIRECTOR OF COMMUNITY DEVELOPMENT BRAD

More information

Florida Job Growth Grant Fund Public Infrastructure Grant Proposal

Florida Job Growth Grant Fund Public Infrastructure Grant Proposal Florida Job Growth Grant Fund Public Infrastructure Grant Proposal Proposal Instructions: The Florida Job Growth Grant Fund Proposal (this document) must be completed by the governmental entity applying

More information

Board of Supervisors' Agenda Items

Board of Supervisors' Agenda Items A. Roll Call COUNTY OF SAN DIEGO BOARD OF SUPERVISORS REGULAR MEETING MEETING AGENDA WEDNESDAY, MARCH 16, 2016, 9:00 A.M. BOARD OF SUPERVISORS NORTH CHAMBER 1600 PACIFIC HIGHWAY, ROOM 310, SAN DIEGO, CALIFORNIA

More information

COUNTY OF LOS ANGELES

COUNTY OF LOS ANGELES COUNTY OF LOS ANGELES DEPARTMENT OF PUBLIC WORKS 900 SOUTH FREMONT AVENUE ALHAMBRA, CALIFORNIA 91803-1331 Telephone: (626) 458-5100 JAMES A. NOYES, Director www.ladpw.org ADDRESS ALL CORRESPONDENCE TO:

More information

TRAFFIC IMPACT ANALYSIS IMPLEMENTATION. Richard L. Caywood, P.E. Robert W. Hofrichter

TRAFFIC IMPACT ANALYSIS IMPLEMENTATION. Richard L. Caywood, P.E. Robert W. Hofrichter TRAFFIC IMPACT ANALYSIS IMPLEMENTATION Richard L. Caywood, P.E. Robert W. Hofrichter Chapter 527: What is it? Passed by General Assembly in 2006 adding Section 15.2-2222.1 to Code of Virginia Directs localities

More information

COUNTY OF CHARLOTTE. County Commissioners Murdock Circle Port Charlotte, FL AGENDA Land Use Meeting

COUNTY OF CHARLOTTE. County Commissioners Murdock Circle Port Charlotte, FL AGENDA Land Use Meeting COUNTY OF CHARLOTTE Board of County Commissioners 18500 Murdock Circle Port Charlotte, FL 33948 www.charlottecountyfl.com County Commissioners Sara Devos, District 5 Tom Moore, District 3, Chairman Matthew

More information

Periodic Review. Quick and easy guidance on the when and how to update your comprehensive plan

Periodic Review. Quick and easy guidance on the when and how to update your comprehensive plan TTHEE COMPLETE PLANNER S GUIDE TTO Periodic Review Quick and easy guidance on the when and how to update your comprehensive plan Idiot-proof steps for getting through all the hoops on the first try Down

More information

Traffic Impact Analysis (TIA) POLICY

Traffic Impact Analysis (TIA) POLICY Ascension Parish Planning Commission Traffic Impact Analysis (TIA) POLICY This policy establishes requirements for studies that provide information on traffic projected to be generated by all proposed

More information

Mission Bay Master Plan File No M September 27, 1990

Mission Bay Master Plan File No M September 27, 1990 SAN FRANCISCO CITY PLANNING COMMISSION RESOLUTION NO. 12040 WHEREAS, Mission Bay is generally bounded by Third Street, Berry Street, Fourth Street, the China Basin Channel, China Basin Street, Mariposa

More information

Florida Job Growth Grant Fund Public Infrastructure Grant Proposal

Florida Job Growth Grant Fund Public Infrastructure Grant Proposal Florida Job Growth Grant Fund Public Infrastructure Grant Proposal Proposal Instructions: The Florida Job Growth Grant Fund Proposal (this document) must be completed by the governmental entity applying

More information

REPORT TO THE 2002 HAWAII STATE LEGISLATURE

REPORT TO THE 2002 HAWAII STATE LEGISLATURE REPORT TO THE 2002 HAWAII STATE LEGISLATURE On the Status of Waianae Coast Transportation Studies and Projects (In response to House Resolution 160 House Draft 1-2000) Oahu Metropolitan Planning Organization

More information

TEX Rail Corridor Memorandum of Agreement 1

TEX Rail Corridor Memorandum of Agreement 1 MEMORANDUM OF AGREEMENT AMONG THE FEDERAL TRANSIT ADMINISTRATION THE TEXAS STATE HISTORIC PRESERVATION OFFICER, AND THE FORT WORTH TRANSPORTATION AUTHORITY OF TARRANT COUNTY, TEXAS REGARDING THE TEX RAIL

More information

Indian River County 2030 Comprehensive Plan

Indian River County 2030 Comprehensive Plan Indian River County 2030 Comprehensive Plan Chapter 11 Intergovernmental Coordination Element Indian River County Community Development Department Adopted: October 12, 2010 Community Development Department

More information

COUNTY OF CHARLOTTE. County Commissioners Murdock Circle Port Charlotte, FL

COUNTY OF CHARLOTTE. County Commissioners Murdock Circle Port Charlotte, FL COUNTY OF CHARLOTTE Board of County Commissioners 18500 Murdock Circle Port Charlotte, FL 33948 www.charlottecountyfl.com County Commissioners Tricia Duffy, District 5, Chairman Richard Loftus, District

More information

Agenda Item No. October 14, Honorable Mayor and City Council Attention: David J. Van Kirk, City Manager

Agenda Item No. October 14, Honorable Mayor and City Council Attention: David J. Van Kirk, City Manager Agenda Item No. October 14, 2008 TO: FROM: SUBJECT: Honorable Mayor and City Council Attention: David J. Van Kirk, City Manager Scott D. Sexton, Community Development Director RESOLUTION OF THE CITY COUNCIL

More information

NORTHEAST CONNECTOR EXPRESSWAY PROJECT ADVISORY GROUP (PAG) LOCATION: Narcoossee Community Center, 5354 Rambling Road, St. Cloud

NORTHEAST CONNECTOR EXPRESSWAY PROJECT ADVISORY GROUP (PAG) LOCATION: Narcoossee Community Center, 5354 Rambling Road, St. Cloud NORTHEAST CONNECTOR EXPRESSWAY PROJECT ADVISORY GROUP (PAG) MEETING SUMMARY DATE/TIME: Tuesday, February 6, 2018, 2 p.m. 3 p.m. LOCATION: Narcoossee Community Center, 5354 Rambling Road, St. Cloud ATTENDEES:

More information

PALMER RANCH INCREMENT II (PARCEL F) NOTICE OF PROPOSED CHANGE IN SARASOTA COUNTY

PALMER RANCH INCREMENT II (PARCEL F) NOTICE OF PROPOSED CHANGE IN SARASOTA COUNTY PALMER RANCH INCREMENT II (PARCEL F) NOTICE OF PROPOSED CHANGE IN SARASOTA COUNTY BACKGROUND The Palmer Ranch DRI was originally approved by the Sarasota Board of County Commissioners on December 18, 1984

More information

City of Culver City. Staff Report

City of Culver City. Staff Report City of Culver City City Hall 9770 Culver Blvd. Culver City, CA 90232 (310) 253-5851 Staff Report File #: 18-0499, Version: 1 CC - Approval of Professional Services Agreement with Tetra Tech for the Design

More information

Guidance for Locally Administered Projects. Funded Through the NJDOT/MPO Program Funds Exchange. August 27, Revised September 15, 2014

Guidance for Locally Administered Projects. Funded Through the NJDOT/MPO Program Funds Exchange. August 27, Revised September 15, 2014 1 Guidance for Locally Administered Projects Funded Through the NJDOT/MPO Program Funds Exchange August 27, 2013 Revised September 15, 2014 This document establishes guidelines for administering the program

More information

City of Baker City Public Works Department st Street, Baker City OR /19 Sidewalk Construction Grant Application

City of Baker City Public Works Department st Street, Baker City OR /19 Sidewalk Construction Grant Application City of Baker City Public Works Department 1655 1 st Street, Baker City OR 97814 2018/19 Sidewalk Construction Grant Application Program Background The City of Baker City recognizes that maintenance and

More information

1.0 EXECUTIVE SUMMARY

1.0 EXECUTIVE SUMMARY 1.0 EXECUTIVE SUMMARY FEASIBILITY REPORT In November 2008, Measure R was approved by a significant two-thirds majority, committing a projected $40 billion to traffic relief and transportation upgrades

More information

Bartlesville City Planning Commission SITE DEVELOPMENT PLAN PROCEDURE AND APPLICATION

Bartlesville City Planning Commission SITE DEVELOPMENT PLAN PROCEDURE AND APPLICATION Bartlesville City Planning Commission SITE DEVELOPMENT PLAN PROCEDURE AND APPLICATION Site Development Plans must be submitted prior to the issuance of any building permit for any tract within a district

More information

City of Norwood Young America

City of Norwood Young America To: Mayor and City Council From: Tom Simmons City of Norwood Young America Cc: Diane Frauendienst and Chelsea Alger Date: 10/22/12 Re: 2013 & 2014 Joint Assessment Service Agreement This is the renewal

More information

CITY OF VACAVILLE PLANNING COMMISSION Agenda Item No. G.2 STAFF REPORT May 17, Staff Contact: Ward Stewart (707)

CITY OF VACAVILLE PLANNING COMMISSION Agenda Item No. G.2 STAFF REPORT May 17, Staff Contact: Ward Stewart (707) CITY OF VACAVILLE PLANNING COMMISSION Agenda Item No. G.2 STAFF REPORT May 17, 2011 Staff Contact: Ward Stewart (707) 449-5140 TITLE: REQUEST: I-80/ALAMO POLICY PLAN AMENDMENT (FORMER PALM ISLAND FREEWAY

More information

Revisit & Update Mobility Hubs Program

Revisit & Update Mobility Hubs Program Revisit & Update Mobility Hubs Program Task 1 Market Assessment Prepared for: Broward Metropolitan Planning Organization JULY 2017 Table of Contents Introduction 1 Overview of Key Tasks 2 Summary of Findings

More information

City of Sacramento City Council 915 I Street, Sacramento, CA,

City of Sacramento City Council 915 I Street, Sacramento, CA, City of Sacramento City Council 915 I Street, Sacramento, CA, 95814 www.cityofsacramento.org Meeting Date: 2/22/2011 Report Type: Public Hearing Title: Pell Circle Billboard Relocation (P10-065) Report

More information

KYOVA Interstate Planning Commission

KYOVA Interstate Planning Commission KYOVA Interstate Planning Commission Sub-allocated Funding Process and Application Package This packet includes information and guidance about the process used by KYOVA Interstate Planning Commission to

More information

CITY OF LOMPOC REQUEST FOR PROPOSALS DEVELOPMENT IMPACT FEE UPDATE STUDY

CITY OF LOMPOC REQUEST FOR PROPOSALS DEVELOPMENT IMPACT FEE UPDATE STUDY CITY OF LOMPOC REQUEST FOR PROPOSALS DEVELOPMENT IMPACT FEE UPDATE STUDY NOTICE IS HEREBY GIVEN that the CITY OF LOMPOC (hereinafter "CITY") is seeking proposals for a DEVELOPMENT IMPACT FEE UPDATE STUDY

More information

NCDOT Planning Summary for NCTA Projects

NCDOT Planning Summary for NCTA Projects NCDOT Planning Summary for NCTA Projects Page 1 Triangle Expressway Southeast Extension Wake and Johnston Counties (STIP Projects R-2721, R-2828, and R-2829) The Triangle Expressway Southeast Extension

More information

Hurricane Evacuation Clearance Workshop Meeting 3 April 30, 2012 Minutes 10am 6:00pm

Hurricane Evacuation Clearance Workshop Meeting 3 April 30, 2012 Minutes 10am 6:00pm Welcome and Opening Remarks Hurricane Evacuation Clearance Workshop Meeting 3 April 30, 2012 Minutes 10am 6:00pm Barbara Powell announced changes to the Agenda and the Work Group approved the previous

More information

COUNTY OF SACRAMENTO CALIFORNIA

COUNTY OF SACRAMENTO CALIFORNIA COUNTY OF SACRAMENTO CALIFORNIA For the Agenda of: January 13, 2010 Agenda Item No. 12 TO: FROM: SUBJECT: BOARD OF SUPERVISORS DEPARTMENT OF PLANNING AND COMMUNITY DEVELOPMENT NATOMAS JOINT VISION PROGRESS

More information

Your Development Project and the Public Works Department Part

Your Development Project and the Public Works Department Part Other useful publications available to help you through the development process: Title 8, Planning and Zoning, County Ordinance Code Title 9, Subdivisions, County Ordinance Code Your Development Project

More information

Planning Commission Public Hearing Exhibits. Powers Ready Mix Plant Oldcastle SW Group, Inc.

Planning Commission Public Hearing Exhibits. Powers Ready Mix Plant Oldcastle SW Group, Inc. Planning Commission Public Hearing Exhibits Powers Ready Mix Plant Oldcastle SW Group, Inc. Substantial Amendment to a Land Use Change Permit, Major Impact Review (File MPAA-02-16-8424) Applicant is CRC,

More information

COASTAL CONSERVANCY. Staff Recommendation June 16, 2005 MALIBU ACCESS: DAN BLOCKER BEACH. File No Project Manager: Marc Beyeler

COASTAL CONSERVANCY. Staff Recommendation June 16, 2005 MALIBU ACCESS: DAN BLOCKER BEACH. File No Project Manager: Marc Beyeler COASTAL CONSERVANCY Staff Recommendation June 16, 2005 MALIBU ACCESS: DAN BLOCKER BEACH File No. 03-163 Project Manager: Marc Beyeler RECOMMENDED ACTION: Authorization to augment the Conservancy s January

More information

Chapter Two STATE FUNCTIONS FOR ENERGY EFFICIENCY PROMOTION Section I Governing Bodies

Chapter Two STATE FUNCTIONS FOR ENERGY EFFICIENCY PROMOTION Section I Governing Bodies Energy Efficiency Act Promulgated, SG No. 98/14.11.2008, effective 14.11.2008, supplemented, SG No. 6/23.01.2009, effective 1.05.2009, amended, SG No. 19/13.03.2009, effective 10.04.2009, supplemented,

More information

Draft CRA Plan Amendment. Community Redevelopment Agency Advisory Board September 23, CRA Plan Amendment

Draft CRA Plan Amendment. Community Redevelopment Agency Advisory Board September 23, CRA Plan Amendment Draft Community Redevelopment Agency Advisory Board September 23, 2013 1 Project Scope Feasibility Study Public Workshops/Stakeholder Interviews Market Study 2 Schedule to Date Feasibility Study Community

More information

This Week in Commission

This Week in Commission This Week in Commission The items in this document have an impact on District 5. If you have any questions or concerns, please contact the office of Chairman Keon Hardemon at 305-250-5390. If you are interested

More information

Request for Qualifications Architectural Analysis Programming and Planning for the Clear Creek County Courts Wing Remodel Project Georgetown, Colorado

Request for Qualifications Architectural Analysis Programming and Planning for the Clear Creek County Courts Wing Remodel Project Georgetown, Colorado Request for Qualifications Architectural Analysis Programming and Planning for the Clear Creek County Courts Wing Remodel Project Georgetown, Colorado PURPOSE The Clear Creek Board of County Commissioners

More information

Florida Job Growth Grant Fund Public Infrastructure Grant Proposal

Florida Job Growth Grant Fund Public Infrastructure Grant Proposal Florida Job Growth Grant Fund Public Infrastructure Grant Proposal Proposal Instructions: The Florida Job Growth Grant Fund Proposal (this document) must be completed by the governmental entity applying

More information

MINUTES OF THE RAPID CITY PLANNING COMMISSION February 9, 2017

MINUTES OF THE RAPID CITY PLANNING COMMISSION February 9, 2017 MINUTES OF THE RAPID CITY PLANNING COMMISSION February 9, 2017 MEMBERS PRESENT: Erik Braun, John Brewer, Karen Bulman, Rachel Caesar, Mike Golliher, John Herr, Galen Hoogestraat, Curt Huus, Mike Quasney

More information

Town of Poughkeepsie

Town of Poughkeepsie Town of Poughkeepsie Planning Department 1 Overocker Road 845-485-3657 Phone Poughkeepsie, NY 12603 845-486-7885 Fax A) PUBLIC HEARINGS NOTICE OF PLANNING BOARD REGULAR MEETING 6:30 PM DECISION AGENDA

More information

PLANNING COMMISSION REGULAR MEETING JULY 5, :00 P.M. Town Board Chambers 301 Walnut Street, Windsor, CO AGENDA

PLANNING COMMISSION REGULAR MEETING JULY 5, :00 P.M. Town Board Chambers 301 Walnut Street, Windsor, CO AGENDA PLANNING COMMISSION REGULAR MEETING JULY 5, 2017-7:00 P.M. Town Board Chambers 301 Walnut Street, Windsor, CO 80550 The Town of Windsor will make reasonable accommodations for access to Town services,

More information

FLORIDA INLAND NAVIGATION DISTRICT INTRACOASTAL WATERWAY MAINTENANCE DREDGING SOUTH OF PORT OF PALM BEACH PALM BEACH COUNTY, FLORIDA

FLORIDA INLAND NAVIGATION DISTRICT INTRACOASTAL WATERWAY MAINTENANCE DREDGING SOUTH OF PORT OF PALM BEACH PALM BEACH COUNTY, FLORIDA GENERAL SCHEDULE: FLORIDA INLAND NAVIGATION DISTRICT INTRACOASTAL WATERWAY MAINTENANCE DREDGING SOUTH OF PORT OF PALM BEACH PALM BEACH COUNTY, FLORIDA MANDATORY PRE-BID MEETING AGENDA TIME ALLOTMENT SCHEDULE

More information

Nassau County 2030 Comprehensive Plan. Public School Facilities Element (PSF) Goals, Objectives and Policies. Goal

Nassau County 2030 Comprehensive Plan. Public School Facilities Element (PSF) Goals, Objectives and Policies. Goal (PSF) Goal Work closely with the School District of Nassau County to ensure a high quality, fiscally sound public school system which meet the needs of Nassau County s population by providing and maintaining

More information