1 Puget Sound Gateway Program SR 509 Completion Project PSRC FAST Committee October 11, 2017 MIKE RIGSBY, PE ANDREY CHEPEL, PE DEPUTY PROGRAM ADMINISTRATOR SR 509 PROJECT ENGINEER 1
2 Puget Sound Gateway Program - SR 509 & SR 167 Completing the Gateway Program provides more direct links from the state s largest ports to the distribution centers in the region and to Eastern Washington Provides direct access to Seattle-Tacoma International Airport from the south for both passenger and air cargo Supports community and economic development 2
3 SR 509 History Begin Corridor EIS 1991 Gas tax increase Gas tax increase Major Investment Study 1995 Ref 49 funding Initiative SR 509 Record of Decision (ROD issued; IJR completed Nickel funding Nickel funding 2003 Begin ROW acquisition TPA funding 2005 TPA funding SR 509 Toll Feasibility Study Fee bill funding Puget Sound Gateway Report Fee bill funding CWA funding CWA funding NEPA Re-evaluation Gateway Program Established NEPA Re-evaluation Begin Corridor EIS Major Investment Study Tier I EIS Record of Decision (ROD), Begin Right of Way acquisition Tier II EIS ROD SR 167 Toll Feasibility and Comprehensive Studies Puget Sound Gateway Report SR 167 History 3
4 Puget Sound Gateway Funding as enacted by the 2015 Legislature 4
5 Puget Sound Gateway Funding as enacted by the 2017 Legislature $20m 5
6 Puget Sound Gateway Funding Sources 6
7 Program Funding STATE (CWA) 78.7% TOLLS 9.0% LOCAL 6.5% FEDERAL 5.7% Total Funding with INFRA Grant $1.989B 7
8 Puget Sound Gateway Stakeholder Engagement Legislature/Governor WSDOT Public Outreach SR 167 Steering Committee SR 167 Executive Committee SR 509 Executive Committee SR 509 Steering Committee 8
9 Scenario Refinement Process SR 509 Process $712M 1 CLOSE THE GAP SR 167 Process $973M 1 CLOSE THE GAP 2 3 2A 3A $923M $1,059M 3A 3A 2E 2C $978M $1,080M 3B 2E 2A 2B A 4A 4 $1,897M 5 EIS $1,933M 5 EIS+ 9
10 Scenario 3A 10
11 SR 509 Right of Way Overview 11
12 SR 167 Scenario 2E: Full Connectivity at I-5 and Meridian Avenue, with Half Diamond Interchange at Valley Avenue 12
13 SR 167 Right of Way Overview 13
14 Traffic Analysis Results 2045 PM Peak projected travel times for select routes Using Dynamic Traffic Assignment (DTA) /Mesoscopic Forecast Model 14
15 Gateway Phasing Preliminary Preferred Scenario PHASE 1 (to 2031) SR 509: 3A $923m PHASE 2 (future) Local Access Meridian Interchange (west half) 188 th Interchange (south half) 200 th Interchange Valley Interchange (east half) I-5 SR 167 SR 18 NB auxiliary lane 272 nd SR 516 NB auxiliary lane SR 516 SR 509 NB collector/distributor lanes SR 167: 2C $1,059m HOV SR 509 HOV (fifth and sixth lanes) SR 509 HOV Direct Access Ramps SR 167 HOV (fifth and sixth lanes) SR 167 HOV Direct Access Ramps Connect WA $1,565m Toll $180m Local $130m Forward Compatibility (features that could be constructed in Phase 1 that are needed in Phase 2) SR 509 Sea-Tac Airport South Access Expressway I-5 SR 167 INFRA $114m 15
16 Public Outreach and Inclusion Since 2015, the Program team executed multiple outreach and engagement activities, including: 6 open houses Approximately 30 briefings to councils, chambers and other interested groups 20 environmental justice interviews 1 innovative EJ and ROW meeting 5 fairs and festivals 10 Steering Committee meetings 4 Executive Committee meetings 1 Funding and Phasing Subcommittee 16
17 Puget Sound Gateway Program Timeline 17
18 Next Steps Collect letters of support for the INFRA grant Identify specific grant projects for the local funding MOU Continue right of way acquisition process Continue design to reach 15% Complete the NEPA re-evaluations for SR 509 and SR
19 More information: Mike Rigsby, PE Deputy Program Manager (206) Andrey Chepel, PE SR 509 Project Engineer (206)
20 Legislative Direction 2017 Update The secretary of transportation must develop a memorandum of understanding with local project stakeholders that identifies a schedule for stakeholders to provide local matching funds for the Puget Sound Gateway project. Criteria for eligibility of local match includes matching funds and equivalent in-kind contributions including, but not limited to, land donations. The memorandum of understanding must be finalized by July 1, The department must submit a copy of the memorandum of understanding to the transportation committees of the legislature and report regularly on the status. 20
21 Legislative Direction 2017 Update During the course of developing the memorandum of understanding, the department must evaluate the project schedules to determine if there are any benefits to be gained by moving the project schedule forward. Additionally, the department must consider completing a full single-point urban interchange at the junction of state route number 161 (Meridian avenue) and state route number 167 and a full single-point urban interchange at the junction of state route number 509 and 188th Street. If the department receives additional funds from an outside source for this project, the funds must be applied toward the completion of these two full single-point urban interchanges. 21
22 Legislative Direction Local Contribution $130 million for Puget Sound Gateway Program $60 million for SR 509 Project $70 million for SR 167 Project 81 highway improvement and bridge replacement projects across the state have local contributions for a total of $523 million 60 additional paving, safety and fish passage projects across the state have local contributions of $51 million 22
23 Legislative Direction In making budget allocations to the Puget Sound Gateway project, the department shall implement the project's construction as a single corridor investment. The department shall develop a coordinated corridor Construction and Implementation Plan for SR 167 and SR 509 in collaboration with affected stakeholders. Specific funding allocations must be based on where and when specific project segments are ready for construction to move forward and investments can be best optimized for timely project completion. Emphasis must be placed on avoiding gaps in fund expenditures for either project. 23
24 Program Schedule to Construction and Implementation Plan 24
25 Context for the Program Forecasted travel patterns 2025 & 2045 Practical design process 25
26 Port Access Travel Times 2045 Peak projected travel times (minutes) for select routes Using Dynamic Traffic Assignment (DTA) /Mesoscopic Forecast Model AM PM 26
27 Burien Travel Times AM Peak Hour PM Peak Hour Trip Pair No Build 2E/3A Tolled No Build 2E/3A Tolled Burien to Duwamish Northbound Southbound Burien to SeaTac Eastbound Westbound Burien to Tukwila Eastbound Westbound Burien to Kent Northbound Southbound Burien to Renton Eastbound Westbound Burien to Auburn Northbound Southbound Burien to Puyallup Northbound Southbound Burien to Port of Tacoma Northbound Southbound (in minutes)
28 2045 Traffic Volume Changes AM PM
29 Legislative Direction In making budget allocations to the Puget Sound Gateway project, the department shall implement the project's construction as a single corridor investment. The department shall develop a coordinated corridor Construction and Implementation Plan for SR 167 and SR 509 in collaboration with affected stakeholders. Specific funding allocations must be based on where and when specific project segments are ready for construction to move forward and investments can be best optimized for timely project completion. Emphasis must be placed on avoiding gaps in fund expenditures for either project. 29
30 Sound Transit Coordination Federal Way Link Extension 30
Puget Sound Gateway Program
Puget Sound Gateway Program SR 167 Completion Project Tacoma Transportation Commission April 18, 2018 THOMAS SLIMAK, PE SR 167 ASSISTANT PROJECT MANAGER Agenda Puget Sound Gateway Program Overview Program
More informationFunding Application. Project Information. Contact Information. Project Description. 1 of 6. September 20th, :55 AM
1 of 6 Funding Application Competition Application Type Status Submitted: Regional TAP Bicycle and Pedestrian submitted September 20th, 2017 9:55 AM Project Information 1. Project Title Interurban Trail/Trailhead
More informationFY16 Annual Report WHAT IS GTIB? WHO ADMINSTERS GTIB? Summary of GTIB Funding Through FY16
FY16 Annual Report PROVIDING FUNDS TO IMPROVE MOBILITY, SUSTAIN DEVELOPMENT AND ENHANCE COMMUNITIES THROUGHOUT GEORGIA WHAT IS GTIB? The Georgia Transportation Infrastructure Bank (GTIB) provides financial
More informationUrban Partnership Communications Plan
Urban Partnership Communications Plan CONTENTS URBAN PARTNERSHIP OVERVIEW 01 COMMUNICATIONS PLAN 02 TOLLING 04 TRANSIT 05 TECHNOLOGY 06 TRANSPORTATION DEMAND MANAGEMENT 07 APPENDICES A: SR 520 Bridge Tolling
More informationStaff Approve Resolution R to amend the FY TIP.
ITEM 11 Action April 19, 2017 Approval to Amend the FY 2017-2022 (TIP) to add nine New Projects to the FY 2017-2022 TIP, As Requested By the Virginia Department of Transportation (VDOT) Staff Recommendation:
More informationCITY OF SPOKANE VALLEY Request for Council Action
CITY OF SPOKANE VALLEY Request for Council Action Meeting Date: Department Director Approval: Check all that apply: consent old business new business public hearing information admin. report pending legislation
More information2013 Louisiana Transportation Conference
February 20, 2013 Baton Rouge River Center 2013 Louisiana Transportation Conference Partnerships for Progress in Transportation Mega Projects Session (I-12 to Bush) I-12 to Bush Agenda Inclusion into TIMED
More information1.0 EXECUTIVE SUMMARY
1.0 EXECUTIVE SUMMARY FEASIBILITY REPORT In November 2008, Measure R was approved by a significant two-thirds majority, committing a projected $40 billion to traffic relief and transportation upgrades
More informationSubject: Request for Proposal Route 99 Interchanges at Hammett Road and Kiernan Avenue
DEPARTMENT OF PUBLIC WORKS Matt Machado Director 1010 10 th Street, Suite 3500, Modesto, CA 95354-0847 Phone: 209.525.6550 Date «FirstName» «LastName» «Company» «Address1» «City», «State» «PostalCode»
More information2018 STP & CMAQ Project Selection Process
2018 STP & CMAQ Project Selection Process Available Funding: (In Millions) CMAQ STP Preservation TOTAL 2021 2022 2021 2022 2021 2022 Regional $14.27 (project cap)$7.13 Countywide $2.41 (project cap)$1.2
More informationNCDOT Planning Summary for NCTA Projects
NCDOT Planning Summary for NCTA Projects Page 1 Triangle Expressway Southeast Extension Wake and Johnston Counties (STIP Projects R-2721, R-2828, and R-2829) The Triangle Expressway Southeast Extension
More informationCompiled by the Office of Rep. Pramila Jayapal MAY 2018
Compiled by the Office of Rep. Pramila Jayapal MAY 2018 1904 3rd Avenue, Suite 510 Seattle, WA 98101 206-674-0040 319 Cannon House Office Building Washington, DC 202-225-3106 Table of Contents Introductory
More informationAGENDA SHORELINE CITY COUNCIL SPECIAL MEETING
AGENDA SHORELINE CITY COUNCIL SPECIAL MEETING Monday, July 11, 2016 Conference Room 303 Shoreline City Hall 5:45 p.m. 17500 Midvale Avenue North PUGET SOUND REGIONAL COUNCIL EXECUTIVE DIRECTOR 1. CALL
More informationCity of Seattle Partnering Agreement. December 2017
City of Seattle Partnering Agreement December 2017 Agenda System Expansion Plan West Seattle and Ballard Link Extensions Partnering Agreement System expansion Sound Transit s system expansion means every
More informationPARTNERSHIPS ACCELERATE ECONOMIC DEVELOPMENT & JOB CREATION. J. Douglas Koelemay, Director
PARTNERSHIPS ACCELERATE ECONOMIC DEVELOPMENT & JOB CREATION J. Douglas Koelemay, Director VIRGINIA LEADERSHIP IN PUBLIC-PRIVATE PARTNERSHIPS PPTA enabling legislation 1995 2001, 2005, 2008 Revisions to
More informationI-15/Tropicana Interchange Feasibility Study in Clark County, NV. Comments are due October 16, 2015, 5 p.m.
Welcome Nevada Department of Transportation Public Meeting I-15/Tropicana Interchange Feasibility Study in Clark County, NV Ways to Comment Tonight Comment during public meeting Court reporter Comment
More informationSTATE HIGHWAY (SH) 34 FEASIBILITY STUDY PUBLIC MEETING
STATE HIGHWAY (SH) 34 FEASIBILITY STUDY PUBLIC MEETING From FM 2578 in Terrell to SH 243 in Kaufman CSJ: 0173-04-056 June 28, 2018 WHAT IS A FEASIBILITY STUDY WHAT IS A FEASIBILITY STUDY? A feasibility
More informationPublic-Private Private Partnership Projects (P3P) Seminar
Public-Private Private Partnership Projects (P3P) Seminar Speaker Information: Allen W. Estes, III Partner Gordon & Rees, LLP Practice Areas: Construction, Green Technology & Climate Change and Commercial
More information2018 POLICY FRAMEWORK FOR PSRC S FEDERAL FUNDS
2018 POLICY FRAMEWORK FOR PSRC S FEDERAL FUNDS TABLE OF CONTENTS Section 1: Background... 3 A. Policy Framework... 3 B. Development of the 2019-2022 Regional Transportation Improvement Program (TIP)..
More informationCommunity Development Agency Capital Improvement Program TIM Fee Program Cash Proforma (by Revenue Grouping)
Community Development Agency Prior* 16/17 17/18 18/19 19/2 2/21 21/22-25/26 26/27-35/36 El Dorado Hills TIM Zone 8 Cash 14,38,412 5,952,818 19,991,23 Revenue 3,511,925 2,196,826 2,151,276 2,445,139 2,445,139
More informationCity Council Study Session HHS SFA May 29, :30 PM Council Chambers - City Hall AGENDA Watch the meeting LIVE!
I. CALL TO ORDER II. III. A. Roll Call ANNOUNCEMENTS REPORTS AND PRESENTATIONS AGENDA ITEMS FOR COUNCIL DISCUSSION A. SR167 and SR509 Gateway Project (Gaub) (20 Minutes) City Council Study Session HHS
More informationBUSINESS OF THE CITY COUNCIL CITY OF MERCER ISLAND, WA
BUSINESS OF THE CITY COUNCIL CITY OF MERCER ISLAND, WA AB 4604 February 7, 2011 Regular Business TOWN CENTER TRANSIT ORIENTED DEVELOPMENT FEASIBILITY STUDY SCOPE OF WORK Proposed Council Action: Appropriate
More informationMassachusetts Department of Transportation (MassDOT) Route 3 South Managed Lanes Project DRAFT FOR DISCUSSION PURPOSES ONLY
Massachusetts Department of Transportation (MassDOT) Project High Level P3 Project Suitability Assessment Report September 11, 2013 Contents Proposed Project Description Project Background and Status Commonwealth
More informationPROJECT DELIVERY MODELS ARKANSAS PLANNING RETREAT ON P3S. J. Douglas Koelemay, Director October 7, 2015
PROJECT DELIVERY MODELS ARKANSAS PLANNING RETREAT ON P3S J. Douglas Koelemay, Director October 7, 2015 VIRGINIA LEADERSHIP IN PUBLIC-PRIVATE PARTNERSHIPS Virginia and California first P3 legislation in
More informationI-69 Corridor Segment Committee 1 and 2 Kick-off Meeting April 15 Nacogdoches, Texas
I-69 Corridor Segment Committee 1 and 2 Kick-off Meeting April 15 Nacogdoches, Texas 10:00 a.m. Welcome/ Introductions Mark Tomlinson Division Dir., Texas Turnpike Authority Div, TxDOT 10:15 a.m. Presentations
More informationDIRECTOR S REPORT TRANSPORTATION BOARD SEPTEMBER 10, 2018
DIRECTOR S REPORT TRANSPORTATION BOARD SEPTEMBER 10, 2018 1 EMERGENCY OPERATIONS MAINTENANCE FORCES IN DISTRICTS 2 AND 3 CLOSED ROADS DUE TO WILDFIRES FLOODING IN SOUTHERN NEVADA DUE TO MONSOON SEASON
More informationTexas Department of Transportation Corpus Christi District
Texas Department of Transportation Corpus Christi District U.S. 181 Harbor Bridge Project Environmental Documentation and Schematic Development Public Scoping Meeting August 9, 2011 Welcome John A. Casey,
More informationGeorgia s Operational Improvement Program. Paul DeNard, P.E., PTOE State Traffic Operations Manager
Georgia s Operational Improvement Program Paul DeNard, P.E., PTOE State Traffic Operations Manager How do you address Capacity? We can t build our way out of the congestion problem Widening projects cost
More informationPresentation to Roseville City Council April 15, 2015
Regional Transportation Projects in South Placer County Presentation to Roseville City Council April 15, 2015 Completed Regional Transportation Projects Lincoln Bypass 2014 SR 65/Ferrari Ranch Rd 2012
More informationSteering Committee Meeting #1 March 31, 2016
North Shore Transit Service Coordination Plan Steering Committee Meeting #1 March 31, 2016 Today s Meeting Welcome Introductions Project Overview Project Schedule Outreach Highlights Research Plan Highlights
More informationRoadway Closures / Limited Access Marine Corps Marathon Sunday, October 26th, 2014
Roadway Closures / Limited Access arine Corps arathon Sunday, October 26th, 2014 ultiple Road Closures in Crystal City Please be aware that numerous road closures will be in place on Sunday, October 26th
More informationProject Budget and Schedule Status
Program Management Project Budget and Schedule Status Highway Program Planning & Programming Committee June 19, 2013 Highway Program Project Schedules EIR/EIS Construction Various project stages Engineering
More informationIn-Step, In Line, On Time. Robert F. Tally Jr. FHWA Indiana Division Administrator Monday, November 16, 2009
In-Step, In Line, On Time Robert F. Tally Jr. FHWA Indiana Division Administrator Monday, November 16, 2009 I-69 Corridor 1 I-69 Corridor I-69 is expected to create more than 27,000 new jobs by 2025, resulting
More informationWORK SESSION ITEM City Council
DATE: STAFF: October 25, 2016 Mark Jackson, PDT Deputy Director WORK SESSION ITEM City Council SUBJECT FOR DISCUSSION I-25 Northern Colorado Improvements. EXECUTIVE SUMMARY The purpose of this item is
More informationState Route 91 Corridor Improvement Project Update. State Route 91 Advisory Committee June 4, 2010
State Route 91 Corridor Improvement Project Update State Route 91 Advisory Committee June 4, 2010 Presentation Agenda Recent Project Milestones Project Development Schedule Environmental Permitting Design-Build
More informationNorth Carolina Turnpike Authority Joint Appropriations Committee on Transportation Beau Memory & Rodger Rochelle
North Carolina Turnpike Authority Joint Appropriations Committee on Transportation Beau Memory & Rodger Rochelle March 17, 2015 Agenda Legislation Review / Turnpike Vision Beau Memory Turnpike Authority
More informationLocal Taxes and Highway Tolls: The New Normal
Local Taxes and Highway Tolls: The New Normal Los Angeles County Metropolitan Transportation Authority Public-Private Partnership Program August 16, 2012 Transportation and Infrastructure Summit Michael
More informationDESIGN BID BUILD IS ALIVE & WELL 2007 Texas Transportation Forum. Doug Pitcock, P.E. President and CEO Williams Brothers Construction Co., Inc.
DESIGN BID BUILD IS ALIVE & WELL 2007 Texas Transportation Forum Doug Pitcock, P.E. President and CEO Williams Brothers Construction Co., Inc. I. WHAT IS THE KATY FREEWAY PROJECT? Regional Map Bush Intercontinental
More informationAssociation of Metropolitan Planning Organizations Fixing America s Surface Transportation (FAST) Act
Association of Metropolitan Planning Organizations Fixing America s Surface Transportation (FAST) Act General Overview Total authorizations (Highway Trust Fund, HTF, Contract Authority plus General Funds
More informationWestern Slope CIP and TIM Fee Update Workshop
Western Slope CIP and TIM Fee Update Workshop Board of Supervisors Study Session May 5, 2015 14-0245 8K 1 of 39 Agenda 1. Brief Background 2. Receive and file: Traffic Analysis Methodology 3. BOS Direction:
More informationTransit Operations Funding Sources
Chapter 7. Funding Operations Funding Funding has increased about 56% in absolute terms between 1999 and 2008. There have been major variations in individual funding sources over this time, including the
More informationDEPARTMENT OF TRANSPORTATION. Notice of Intent to Prepare Environmental Impact Statement, I-495 & I-270 Managed
This document is scheduled to be published in the Federal Register on 03/16/2018 and available online at https://federalregister.gov/d/2018-05354, and on FDsys.gov DEPARTMENT OF TRANSPORTATION [4910-22-P]
More informationI-95 Southbound Collector-Distributor (CD) Lanes - Rappahannock River Crossing From Exit 130 (Route 3) To Exit 133 (Route 17)
I-95 Southbound Collector-Distributor (CD) Lanes - Rappahannock River Crossing From Exit 130 (Route 3) To Exit 133 (Route 17) Initial Financial Plan January 31, 2017 State Project Number(s): 0095-111-259,
More informationPSRC Funding Application
PSRC Funding Application Competition Application Status Submitted: Prepopulated with screening form? Regional FTA Main Competition submitted March 17th, 2017 6:07 PM Yes Project Information 1. Project
More informationAppendix 5 Freight Funding Programs
5. Chapter Heading Appendix 5 Freight Programs Table of Contents 4.1 Surface Transportation Block Grant (STBG);... 5-1 4.2 Transportation Investment Generating Economic Recovery Discretionary Grant Program
More informationMark A. Doctor, PE CAREER PATH
Mark A. Doctor, PE Professional Profile A career of over 27 years with the Federal Highway Administration in various transportation engineering positions with diverse experiences and accomplishments in
More informationSMART SCALE Application Guide
SMART SCALE Application Guide prepared for Commonwealth Transportation Board Date, revised September 9, 2016 Table of Contents 1.0 Introduction... 3 1.1 Purpose of this Document... 3 1.2 Application Process...
More informationI-25 GAP COALITION MEETING #3 August 24, 2017 Douglas County Fairgrounds Main Event Center 500 Fairgrounds Blvd., Castle Rock MEETING SUMMARY
I-25 GAP COALITION MEETING #3 August 24, 2017 Douglas County Fairgrounds Main Event Center 500 Fairgrounds Blvd., Castle Rock MEETING SUMMARY Attendees Dale Anderson Rachel Beck Linda Black Representative
More informationNASHVILLE AREA MPO FY TIP - ADOPTED DECEMBER
WILSON NASHVILLE AREA MPO FY -2017 TIP - ADOPTED DECEMBER 11, 2013 Beckwith Road/Eastern Connector TIP # 2008-71-038 New Road Mt. Juliet Wilson Length 5.00 Regional Plan ID 1072-132 Air Quality Status
More informationPublic Meeting #5 Summary
Public Meeting #5 Summary Pulaski County, Arkansas February 4, 2016 TABLE OF CONTENTS 1.0 Introduction... 1 2.0 Public Meeting #5... 1 2.1 Public Meeting Advertising and Outreach... 2 2.2 Public Meeting
More informationVTA s Capital Projects Program & BART Phase II Procurement Opportunities. VTA s Procurement Fair and Workshop. November 1, 2016
VTA s Capital Projects Program & BART Phase II Procurement Opportunities VTA s Procurement Fair and Workshop November 1, 2016 Capital Projects Program Capital Projects Program Major Projects in Construction
More information1. Which of the following most closely represents the number of people in your local organization/household?
LOW LEVEL ROAD PROJECT TRAFFIC MANAGEMENT CONSULTATION FEEDBACK FORM Instructions Thank you for participating in this stakeholder meeting to assist in developing traffic management plans for construction
More informationCONGESTION MANAGEMENT PROGRAM & PLANNING COMMITTEE AGENDA
CONGESTION MANAGEMENT PROGRAM & PLANNING COMMITTEE Thursday, February 18, 2016 10:00 AM VTA Conference Room B-104 3331 North First Street San Jose, CA AGENDA CALL TO ORDER 1. ROLL CALL 2. PUBLIC PRESENTATIONS:
More information2018 Project Selection Process
2018 Project Selection Process Workshop Agenda PSRC Funds Federal Requirements Overall Schedule Overview of Process Project Selection Details Project Evaluation Criteria Project Tracking and Delivery Requirements
More informationDraft for approval by TCC on 8/8; TAQC on 8/14 and ARC on 8/27/14
Draft for approval by TCC on 8/8; TAQC on 8/14 and ARC on 8/27/14 DATE: August 27, 2014 ISSUE SUMMARY: PLAN 2040 RTP/TIP Amendment #1 FROM: Tom Worthan, Transportation & Air Quality Committee IMPORTANCE:
More informationRESOLUTION NO. 18-XX RESOLUTION AUTHORIZING THE EXECUTIVE DIRECTOR TO EXECUTE COOPERATIVE AGREEMENT NO WITH THE CALIFORNIA DEPARTMENT OF
BD041018 RESOLUTION NO. 18-XX RESOLUTION AUTHORIZING THE EXECUTIVE DIRECTOR TO EXECUTE COOPERATIVE AGREEMENT NO. 04-2647 WITH THE CALIFORNIA DEPARTMENT OF TRANSPORTATION FOR THE U.S. 101/I-280 MANAGED
More informationProject Coordination and Public Involvement Plan
Project Coordination and Public Involvement Plan Tampa Interstate Study Supplemental Environmental Impact Statement I-275 from Howard Frankland Bridge to North of Dr. Martin Luther King, Jr. Boulevard
More informationMULTIMODAL TRANSPORTATION DISTRICT ALTERNATIVES ANALYSIS. Executive Summary
MULTIMODAL TRANSPORTATION DISTRICT ALTERNATIVES ANALYSIS Executive Summary February 2015 Executive Summary 1. Define the Problem This Alternatives Analysis report is submitted as a deliverable for the
More informationITEM 11 Information July 20, Strategic Plan for the Development of the TPB Travel Demand Model
ITEM 11 Information July 20, 2016 Strategic Plan for the Development of the TPB Travel Demand Model Staff Recommendation: Issues: Background: Receive briefing None TPB staff and Cambridge Systematics,
More informationINDIAN RIVER COUNTY METROPOLITAN PLANNING ORGANIZATION
2016 PRIORITY PROJECTS REPORT INDIAN RIVER COUNTY METROPOLITAN PLANNING ORGANIZATION This document was produced in cooperation with the Florida Department of Transportation and the Federal Highway Administration
More informationA history of Innovation & Entrepreneurship
Century Agenda A history of Innovation & Entrepreneurship Port of Seattle has generated jobs and economic activity for more than 100 years. As we turned from the past, and looked to the next Century, the
More informationPlanning Phase (Route Study and Pond Siting Analysis & Report) Determines Preferred Alignment Public Workshop and Board Approval Required Completion:
2 Planning Phase (Route Study and Pond Siting Analysis & Report) Determines Preferred Alignment Public Workshop and Board Approval Required Completion: 270 Days Design/Permitting Phase Engineering Plans
More informationVRE Gainesville Haymarket Extension Feasibility Study and Alternatives Analysis
VRE Gainesville Haymarket Extension Feasibility Study and Alternatives Analysis Public Workshop Wednesday, July 30 th, 2008 6:30 9:00 pm Stonewall Jackson High School Presentation Overview Introduction
More informationPUBLIC-PRIVATE PARTNERSHIP PROGRAM, HIGH DESERT CORRIDOR
29 One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 l metro. net PLANNING AND PROGRAMMING COMMITTEE MARCH 20, 2013 SUBJECT: ACTION: PUBLIC-PRIVATE PARTNERSHIP PROGRAM, HIGH DESERT CORRIDOR RECEIVE
More informationMassachusetts Transportation Infrastructure Funding Gap: Revenue Alternatives - The Challenge and Potential Solutions
Massachusetts Transportation Infrastructure Funding Gap: - The Challenge and Potential Solutions Paul T. Godfrey, PE Associate Vice President, HNTB 1 Why are we considering this?? Federal and State Transportation
More informationBy Rmhermen at en.wikipedia (photo by rmhermen) [GFDL (http://www.gnu.org/copyleft/fdl.html) or CC-BY-SA-3.0
Public Participation Plan By Rmhermen at en.wikipedia (photo by rmhermen) [GFDL (http://www.gnu.org/copyleft/fdl.html) or CC-BY-SA-3.0 (http://creativecommons.org/licenses/by-sa/3.0/)], from Wikimedia
More information(This page intentionally left blank)
(This page intentionally left blank) 1 INTERSTATE 564 INTERMODAL CONNECTOR PROJECT R000-122-108 FINANCIAL PLAN NOVEMBER 2014 FEDERAL HIGHWAY ADMINISTRATION EASTERN FEDERAL LANDS HIGHWAY DIVISION VIRGINIA
More informationREQUEST FOR INFORMATION
REQUEST FOR INFORMATION REGARDING THE DEVELOPMENT OF AND PROCUREMENT PROCESS FOR THE GRAND PARKWAY PROJECT TEXAS DEPARTMENT OF TRANSPORTATION RFI Issuance Date: June 10, 2011 RFI Closing Date: July 6,
More informationOverview of the Procurement and Project Milestones
Overview of the Procurement and Project Milestones November 3, 2016 Charles A. Kilpatrick, P.E. Commissioner of Highways Virginia Department of Transportation Project Development The Path to Date Summer
More informationRCTC Toll Program and Projects
RCTC Toll Program and Projects for CMAA Southern California Chapter October 13, 2011 Presenta(on Agenda I 15 Corridor Improvement Project SR 91/71 Interchange Improvements Project SR 91 Corridor Improvement
More informationTransportation Planning in the Denver Region
The Prospectus Transportation Planning in the Denver Region TAC Draft (as of June 16, 2011) Approved December 2004 Revised November 2006 Revised August 2007 Revised March 2009 Revised 2011 Key revisions
More information2018 Regional Transportation Improvement Program
2018 Regional Transportation Improvement Program Fiscal Years 2018/19 through 2022/2023 Adopted November 15, 2017 Stanislaus Council of Governments 1111 I Street Suite 308 Modesto, CA 95354 www.stancog.org
More informationCity of La Palma Agenda Item No. 5
City of La Palma Agenda Item No. 5 MEETING DATE: March 7, 2017 TO: FROM: SUBMITTED BY: CITY COUNCIL CITY MANAGER Mike Belknap, Community Services Director AGENDA TITLE: 2017 Street Closures for City Special
More informationLong Range Transportation Plan
Summary of Policy Governor in 2000. The baseline can The purpose of the Long Range also be considered as the scenario in Transportation Plan (LRTP) is to which no new transportation projects provide decision
More informationLakewood Ranch Town Hall 8175 Lakewood Ranch Boulevard Lakewood Ranch, Florida 34202
0 SARASOTA/MANATEE METROPOLITAN PLANNING ORGANIZATION Lakewood Ranch Town Hall Lakewood Ranch Boulevard Lakewood Ranch, Florida MINUTES FOR MARCH, Chair Roff called the meeting to order at : a.m. Nanette
More informationS E N A T E F I S C A L O F F I C E I S S U E B R I E F 2016-S RhodeWorks FEBRUARY 2, 2016
2016-S-2246 - RhodeWorks FEBRUARY 2, 2016 SUMMARY 2016-S-2246 - The Rhode Island Bridge Replacement, Reconstruction and Maintenance Fund Act of 2016, also known as RhodeWorks, does the following: Allows
More informationTurnpike Mitigation Program Application
Ohio Department of Transportation - Ohio Turnpike Infrastructure Commission Turnpike Mitigation Program Application The application has been improved to enable project sponsors to save the application
More informationNATIONAL CAPITAL REGION TRANSPORTATION PLANNING BOARD 777 North Capitol Street, N.E. Washington, D.C
NATIONAL CAPITAL REGION TRANSPORTATION PLANNING BOARD 777 North Capitol Street, N.E. Washington, D.C. 20002 TPB SR22-2017 May 5, 2017 RESOLUTION ON AN AMENDMENT TO THE FY 2017-2022 TRANSPORTATION IMPROVEMENT
More informationTRANSPORTATION AUTHORITY OF MARIN
2018 Marin County Transportation Sales Tax Renewal Expenditure Plan APRIL 2018 TRANSPORTATION AUTHORITY OF MARIN DRAFT FINAL PLAN TRANSPORTATION AUTHORITY OF MARIN Board of Commissioners Damon Connolly,
More informationSTRATEGIC PLAN FOR THE DEVELOPMENT OF THE TPB TRAVEL DEMAND MODEL
STRATEGIC PLAN FOR THE DEVELOPMENT OF THE TPB TRAVEL DEMAND MODEL Ronald Milone, TPB Travel Forecasting & Emissions Analysis Program Director Mark S. Moran, TPB Principal Transportation Engineer National
More informationPublic-Private Partnership Program May 2015 Transit Coalition Update
Public-Private Partnership Program May 2015 Transit Coalition Update Los Angeles County Metropolitan Transportation Authority Mark Linsenmayer Director Presentation Agenda Overview of Metro Public Private
More informationREQUEST FOR INFORMATION
REQUEST FOR INFORMATION OKLAHOMA TURNPIKE AUTHORITY GILCREASE EXPRESSWAY RFI Issue Date: January 2, 2018 RFI Response Due Date: January 31, 2018 The Oklahoma Turnpike Authority ( Authority ) is seeking
More informationImplementation. Implementation through Programs and Services. Capital Improvements within Cambria County
The transportation system serves Cambria County communities because people make decisions and take action toward the stated goals of the long-range transportation plan. Locally, these people include officials
More informationMPO Staff Report MPO Technical Advisory Committee: February 14, 2018 MPO Executive Board: February 21, 2018
MPO Staff Report MPO Technical Advisory Committee: February 14, 2018 MPO Executive Board: February 21, 2018 RECOMMENDED ACTION: Make a Recommendation on the Urban Grant, Regional and Urban Program Candidate
More informationActive Traffic Management Jane Addams Memorial Tollway (I-90) SmartRoad Operational Features and Algorithms
Active Traffic Management Jane Addams Memorial Tollway (I-90) SmartRoad Operational Features and Algorithms Friday, September 23, 2016 Scott Lee, P.E., Senior Project Manager, Parsons Elyse Morgan, TOC
More informationPinellas. (ollnt OFFICE OF THE COUNTY ADMINISTRATOR MEMORANDUM
Pinellas (ollnt WORK SESSION AGENDA J.J~.IO ~ J OFFICE OF THE COUNTY ADMINISTRATOR MEMORANDUM TO: Honorable Chair and Members 0 h Board of County Commissioners FROM: Robert S LaSala, County Adm' I tor
More informationCorridor Advisory Committee Meeting #30. September 20, :00-8:00 p.m. Progress Park Downey Blvd., Paramount MEETING SUMMARY
Corridor Advisory Committee Meeting #30 September 20, 2012 6:00-8:00 p.m. Progress Park 15500 Downey Blvd., Paramount INTRODUCTION On September 20, 2012 the Corridor Advisory Committee met at Progress
More informationThroughout the Open House, the following informational stations will be available:
PECUE LANE/I-10 INTERCHANGE East Baton Rouge Parish CITY/PARISH PROJECT NO. 09-CS-US-0041 STATE PROJECT NO. 700-17-0221 FEDERAL AID PROJECT NO. IM-1709(507) Open House Public Meeting Thursday, February
More information2018 Regional Project Evaluation Criteria For PSRC s FHWA Funds
2018 Regional Project Evaluation Criteria For PSRC s FHWA Funds INTRODUCTION As described in the adopted 2018 Policy Framework for PSRC s Federal Funds, the policy focus for the 2018 project selection
More informationVTP Highway Program. Semi-Annual Report April 2013
VTP Highway Program Semi-Annual Report April 2013 VTP Highway Program Semi-Annual Progress Report April 2013 Table of Contents TABLE OF CONTENTS Section Title Page 1 EXECUTIVE SUMMARY A Background... 1-2
More informationENVIRONMENTAL STATUS OF THE US 59/LOOP 20/I-69W PROJECT
ENVIRONMENTAL STATUS OF THE US 59/LOOP 20/I-69W PROJECT A Brief Overview As Of June 15, 2015 Mike Graham Laredo District Environmental Coordinator June 15, 2015 Projects Locations & Design: Additional
More informationCentral City Line Kick-off and Tour
Central City Line Kick-off and Tour Phase C Preliminary Engineering, Environmental Documentation and Small Starts Submittal Kickoff Meeting Agenda Time Item 1:00 PM Welcome, Introductions and Agenda Review
More information2014 TRAC Funding Application. Cost ODOT greater than $12 million dollars Increase roadway capacity or reduce congestion.
2014 TRAC Funding Application TRAC is responsible for committing development and construction funding towards projects that meet the criteria the of Major New Capacity Program. TRAC Policy defines Major
More informationCommonwealth Transportation Board Briefing
Hampton Roads Crossing Study (HRCS) (SEIS) Commonwealth Transportation Board Briefing September 20, 2016 Angel Deem VDOT, Environmental Division Director HRCS History 1991: Federal funding allocated for
More informationMOTION NO. M Preliminary Engineering Consulting Services Contract for the Downtown Redmond Link Extension
MOTION NO. M2016-116 Preliminary Engineering Consulting Services Contract for the Downtown Redmond Link Extension MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee Board 11/10/2016 11/29/2016
More informationWESTERN SLOPE CIP AND TIM FEE UPDATE
WESTERN SLOPE CIP AND TIM FEE UPDATE 12/6/16 BOARD OF SUPERVISORS STUDY SESSION B O A R D S T U D Y S E S S I O N # 8 2015 14-0245 Revised 22M 1 of 53 AGENDA 1. Background 2. Programmatic EIR 3. General
More informationTransport NI York Street Interchange APPENDIX A PROJECT BRIEF
Transport NI York Street Interchange APPENDIX A PROJECT BRIEF PROPOSED SCHEME REPORT: PART 2 VOLUME 2 January 2015 Roads Service Consultancy Framework Contract BRIEF FOR MAJOR WORKS SCHEMES, EASTERN DIVISION
More informationMajor in FY2013/2014 (By and ing Source) Municipal Building Acquisition and Operations Balance $1,984, Contributions from Real Estate
Major in FY2013/2014 (By and ing Source) Environmental Services Solid Waste 4200 4200 06CON 4200 SWM01 Balance $13,753,504.00 Balance $4,631,754.00 Balance $2,738,918.00 ing Source Total: $21,124,176.00
More informationENVIRONMENTAL JUSTICE IN ACTION
THE NORTHWEST LOUISIANA COUNCIL OF GOVERNMENTS AND PROVIDENCE PRESENT: ENVIRONMENTAL JUSTICE IN ACTION I-49 INNER CITY CONNECTOR (ICC) 2013 Louisiana Transportation Conference WHAT IS ENVIRONMENTAL JUSTICE?
More informationMOBILITY PARTNERSHIP AGENDA
1. CALL TO ORDER/ROLL CALL MOBILITY PARTNERSHIP Wednesday, October 11, 2017 9:00 a.m. to 10:30 a.m. Gilroy City Council Chambers 7351 Rosanna Street, Gilroy, CA AGENDA 2. PUBLIC PRESENTATIONS: This portion
More information