1 Agenda Date: 8/20/2013 Agenda Placement: 9D Set Time: 9:30 AM Estimated Report Time: 30 Minutes NAPA COUNTY BOARD OF SUPERVISORS Board Agenda Letter TO: FROM: Board of Supervisors Lederer, Steven - Director of Public Works Public Works REPORT BY: MALLIKA RAMACHANDRAN, SUPERVISING CIVIL ENGINEER SUBJECT: Highway Bridge Program RECOMMENDATION Director of Public Works requests discussion and possible action regarding the County s Highway Bridge Program. EXECUTIVE SUMMARY On January 25, 2013, Public Works submitted Highway Bridge Rehabilitation & Replacement Program (HBRRP) applications to request funding for eight bridges in the Federal Transportation Improvement Program (FTIP). Seven of the eight bridges submitted have been approved. The bridges are programmed to be completed over the next ten to fifteen years. The total funding requested is approximately $10,000,000. Today's briefing is intended to update the Board on the bridges in question and the approximate schedule of bridge projects, and will also provide an update on the Oakville Crossroad bridge over the Napa River, which is in the final stages of design and permitting. PROCEDURAL REQUIREMENTS 1. Staff reports. 2. Public comments. 3. Motion, second, discussion and vote should the Board chose to provide specific direction. FISCAL IMPACT Is there a Fiscal Impact? No

2 Page 2 ENVIRONMENTAL IMPACT ENVIRONMENTAL DETERMINATION: The proposed action is not a project as defined by 14 California Code of Regulations (State CEQA Guidelines) and therefore CEQA is not applicable. BACKGROUND AND DISCUSSION On August 20, 2012, Caltrans issued a letter to Cities and Counties requesting local agencies to review their public highway bridges for potential replacement, rehabilitation, or preventive maintenance and to take necessary actions to address any public safety issues and to extend the life of their bridge inventories. Caltrans also requested agencies to develop a Bridge Preventive Maintenance Program, to prevent deterioration of bridges that are in good condition. Caltrans routinely inspects public highway bridges and the information is posted on its Structures Maintenance and Investigation web site. Additionally, a Bridge Inspection Report is sent to the County. The report identifies required maintenance activity. The report also provides the sufficiency ratings of the bridges. Bridges with a Sufficiency Rating (SR) less than or equal to 50, which are also flagged Structurally Deficient (SD) or Functionally Obsolete (FO) are eligible for replacement. Bridges with a Sufficiency Rating (SR) less than or equal to 80, which are also flagged Structurally Deficient (SD) or Functionally Obsolete (FO) are eligible for major reconstruction or rehabilitation. In order for the bridges to be included into the Local Assistance Bridge Program and the Federal Transportation Improvement Program (FTIP), the funding application had to be submitted by January 31, In October and November of 2012, staff met with several consultants to discuss potential funding sources to program County bridges. The county selected Mark Thomas & Company, Inc to assist with performing structural investigations, and to prioritize and develop scopes and cost estimates for the applications. Under the Federal program that is administered by Caltrans, there is federal aid available to local agencies. For On-System Bridges (those located on arterials and major collectors), the program will fund 88.53%, with a required 11.47% local match. For Off-System Bridges (those located on local roads or minor collectors), the program will fund 100%, utilizing toll credits for the 11.47% local match. The prioritization of bridges was based on the following criteria: Off system bridges, because currently there is 100% funding available utilizing the toll credits (which may be depleted in the future) Location of the bridge, number of residents served and evaluation of the Average Daily Traffic (ADT) Sufficiency ratings and status identified as Structurally Deficient (SD) or Functionally Obsolete (FO) Site visits and visual inspection Feasibility of programming On January 25, 2013, staff submitted Highway Bridge Rehabilitation & Replacement Program (HBRRP) applications to program the following eight bridges in the FTIP at 100% Federal funding reimbursement, utilizing toll credits for the 11.47% local match:

3 Page 3 ITEM BRIDGE NUMBER 1 21C C C C C C C C0074 LOCATION SUFFICIENCY RATING STRUCTURALLY DEFICIENT (SD) FUNCTIONALLY OBSOLETE (FO) REPLACE OR REHABILITATE Dry Creek Dry Creek 18 SD Replace Chiles- Pope Valley Rd over Chiles Creek 73.4 SD Rehabilitate Canyon Creek 47.5 FO Replace Loma Vista Drive over Creek 57.2 FO Rehabilitate Hardin Maxwell Creek 34.8 SD Replace Conn Valley Rd over Conn Creek 42.5 FO Replace Larkmead Lane over Dutch Henry Creek 56.8 FO Rehabilitate Berryessa- Knoxville over Eticuera Creek 25.4 SD Replace Subsequently, Caltrans reviewed the applications and provided feedback for the following bridges: Bridge No. 21C0075 Chiles-Pope Valley Rd over Chiles Creek (#2 above) - The bridge was reclassified as On System and it was programmed for HBRRP 88.53% Federal funding with 11.47% local match. Bridge No. 21C0108 Larkmead Lane over Dutch Henry Creek (#7 above) - The two span stone masonry arch structure was constructed in 1910 (approximately103 years old). Currently the bridge

4 Page 4 is not on National Registry, according to Caltrans database. However, in order to preserve the stone masonry arch structure, staff and the consultant proposed only to correct scouring problems and did not propose widening of the bridge. The existing width of the bridge is 24 feet and the minimum required width per current standards is 32 feet. The proposed rehabilitation (which would maintain the current 24 foot width) would not remove the Functionally Obsolete (FO) classification; therefore, it will not be eligible for bridge replacement funding. This bridge will be resubmitted under the Bridge Maintenance Program (BMP). In summary, seven of the eight bridges submitted are programmed. County staff is awaiting FHWA obligation of funds in September/October 2013 before proceeding with a Request for Authorization for Preliminary Engineering. The bridges are programmed to be completed over the next ten to fifteen years. The total funding requested is approximately $10,000,000. Because of the incredibly long lead time for these projects, staff thought it important to brief the Board and obtain feedback at this early stage. Project decisions made early in this process are expensive and time consuming to change later on. There is one other bridge that was programmed in the FTIP circa 1996, the Oakville Crossroad Bridge over the Napa River. This project is currently in the final design (95%) and environmental permitting phase. Construction is tentatively planned for FY 2014/2015. Pictures of the current bridge (a nonhistoric, concrete structure) and what the replacement bridge will look like, are attached. CEQA (including public notice) and design decisions associated with the bridge were made in the late 1990s. As the project is finally nearing construction, on June 12, 2013 Public Works staff conducted a neighborhood meeting to discuss potential traffic impacts associated with the bridge replacement. Neighbors commented about how important it was to not have a complete road closure, a request we had already planned to accommodate by building the bridge in two sections, thus always maintaining one lane of traffic open. A recent newsletter sent to the neighbors summarizing the meeting is also attached. During the meeting, and in communications later with at least one Supervisor, neighbors also requested that the bridge be redesigned to have more a rural character. While the County is proud of its many existing lovely bridges, staff has significant concerns in being able to accommodate this request. These concerns include: Safety: This bridge is in the Caltrans inspection system. Caltrans looks at the bridge annually and based on the age and structural integrity, the bridge has been identifed for replacement. Based on this inspection system, we have taken interim actions including signage and other traffic control measures, to minimize the traffic across the existing bridge to maximize its life span. Cost & Schedule: Over $800,000 has been spent on design and permitting to get the project to its current stage. The project to date has been 80% funded by federal funds (the remaining costs are county). Going forward the Feds are committed to 100% of the costs of the current design. Several Resource Agencies (Army Corps, NOAA, Fish and Wildlife (State and Federal), Regional Board, etc.) are involved, as well as FEMA for flood protection and mapping. Each element of the design, including height, width, location of footings, even the railing design, is interconnected with these sometimes conflicting agency requirements. Changing even seemly minor elements of the design affects the permitting requirements of all. Taking a step back at this late hour would cause tens, maybe hundreds of thousands of dollars in additional costs for design, additional environmental studies, and permitting. It is also likely that these additional costs would fall solely on the county as the Federal Government is unlikely to want to (or be able to) fund rework. It is also expected that the County would become responsible for the full cost of bridge construction,

5 Page 5 approximately $2,000,000. The County might also be obligated to return existing funds already spent. The County is also under schedule pressure from the Federal Government to move the project forward in 2014, or construction money will be deobligated, once again moving construction costs from the Federal Government to the County. It is expected that redesigning and re-permitting the project would cause a delay of at least one, maybe several, construction seasons. Traffic: Should the project be delayed, as discussed above, and should the existing bridge deteriorate further in the meantime such that it needs to be closed, we run the risk of having a complete closure of Oakville Crossroad for a significant period, perhaps years. This is in direct contradiction of the stated desires of many residents and businesses in the area to maintain the road open at all times, and would significantly impact traffic patterns throughout the central part of the valley. Staff welcomes any comments or guidance the Board wishes to provide, though no specific action is needed. SUPPORTING DOCUMENTS A. Existing bridge B. Example of replacement bridge style C. Community newsletter CEO Recommendation: Approve Reviewed By: Molly Rattigan

6. HIGHWAY FUNDING Introduction Local Funding Sources Property Tax Revenues valuation County Transportation Excise Tax

6. HIGHWAY FUNDING Introduction Local Funding Sources Property Tax Revenues valuation County Transportation Excise Tax 6. HIGHWAY FUNDING Introduction This chapter discusses local, state and federal highway funding sources. Local Funding Sources Property Tax Revenues Once the Board of Supervisors has established a roadway,

More information

SPECIAL MEETING OF THE METROPOLITAN PARKS AND OPEN SPACE COMMISSION Tuesday, February 9, 2016

SPECIAL MEETING OF THE METROPOLITAN PARKS AND OPEN SPACE COMMISSION Tuesday, February 9, 2016 Minutes of the SPECIAL MEETING OF THE METROPOLITAN PARKS AND OPEN SPACE COMMISSION Tuesday, February 9, 2016 Committee Members Present: Rick Theisen, Bill Weber, Anthony Taylor, Todd Kemery, Sarah Hietpas,

More information

SMALL CITY PROGRAM. ocuments/forms/allitems.

SMALL CITY PROGRAM.  ocuments/forms/allitems. SMALL CITY PROGRAM The Small City Program provides Federal funds to small cities with populations from 5,000 to 24,999 that are NOT located within Metropolitan Planning Organizations' boundaries. Currently

More information

Western Slope CIP and TIM Fee Update Workshop

Western Slope CIP and TIM Fee Update Workshop Western Slope CIP and TIM Fee Update Workshop Board of Supervisors Study Session May 5, 2015 14-0245 8K 1 of 39 Agenda 1. Brief Background 2. Receive and file: Traffic Analysis Methodology 3. BOS Direction:

More information

Delaware Smart Transportation: Save Money and Grow the Economy

Delaware Smart Transportation: Save Money and Grow the Economy Delaware Smart Transportation: Save Money and Grow the Economy Keep Delaware Moving in the Right Direction Save Money by Taking Better Care of What You Have 1. Dedicate more to maintain and repair existing

More information

Florida Smart Transportation: Save Money and Grow the Economy

Florida Smart Transportation: Save Money and Grow the Economy Florida Smart Transportation: Save Money and Grow the Economy Keep Florida Moving in the Right Direction Save Money by Taking Better Care of What You Have 1. Dedicate more to maintain and repair existing

More information

Appendix B Review Matrix Text & Table Footnotes

Appendix B Review Matrix Text & Table Footnotes Review Submissions The PDP includes a series of review submissions designed to ensure that all projects are developed in accordance with ODOT policies. The PDP Products Review Matrix found in this Appendix

More information

Expedited Bridge Replacement Program

Expedited Bridge Replacement Program Expedited Bridge Replacement Program Proposed program for select BRX BRO & BRZ KYTC & FHWA Kevin F. Damron, P.E. Executive Director for Office of Project Development Kentucky Transportation Cabinet kevin.damron@ky.gov

More information

Nevada Smart Transportation: Save Money and Grow the Economy

Nevada Smart Transportation: Save Money and Grow the Economy Nevada Smart Transportation: Save Money and Grow the Economy Keep Nevada Moving in the Right Direction Save Money by Taking Better Care of What You Have 1. Dedicate more to maintain and repair existing

More information

DOT FUNDING OPPORTUNITIES FOR TRANSPORTATION ASSETS

DOT FUNDING OPPORTUNITIES FOR TRANSPORTATION ASSETS DOT FUNDING OPPORTUNITIES FOR TRANSPORTATION ASSETS 1 237 237 237 217 217 217 200 200 200 80 119 27 252 174.59 255 255 255 0 0 0 163 163 163 131 132 122 239 65 53 Meredith Bridgers: Outdoor Recreation

More information

Order of Business. D. Approval of the Statement of Proceedings/Minutes for the meeting of November 15, 2017.

Order of Business. D. Approval of the Statement of Proceedings/Minutes for the meeting of November 15, 2017. COUNTY OF SAN DIEGO BOARD OF SUPERVISORS REGULAR MEETING MEETING AGENDA WEDNESDAY, DECEMBER 6, 2017, 9:00 AM BOARD OF SUPERVISORS NORTH CHAMBER 1600 PACIFIC HIGHWAY, SAN DIEGO, CALIFORNIA Order of Business

More information

Community Development Agency Capital Improvement Program TIM Fee Program Cash Proforma (by Revenue Grouping)

Community Development Agency Capital Improvement Program TIM Fee Program Cash Proforma (by Revenue Grouping) Community Development Agency Prior* 16/17 17/18 18/19 19/2 2/21 21/22-25/26 26/27-35/36 El Dorado Hills TIM Zone 8 Cash 14,38,412 5,952,818 19,991,23 Revenue 3,511,925 2,196,826 2,151,276 2,445,139 2,445,139

More information

Tentative Project Schedule. Non-Discrimination i i Laws. Para Preguntas en español

Tentative Project Schedule. Non-Discrimination i i Laws. Para Preguntas en español Florida Department of Transportation, District Seven Project Newsletter Number 1 October 2012 The Florida Department of Transportation (FDOT) is conducting a Project Development & Environment (PD&E) study

More information

Department of Transportation (MCDoT) Director s Report August 4, Annual County Capital Improvement Project Development Activities:

Department of Transportation (MCDoT) Director s Report August 4, Annual County Capital Improvement Project Development Activities: Agenda Item 5(j) Department of Transportation (MCDoT) Director s Report August 4, 2015 Annual County Capital Improvement Project Development Activities: 2011 Storm Damage: The projects completed under

More information

L e t t e r o f I n t e r e s t : S t r u c t u r e s D e s i g n ( B r i d g e ) - S t a t e w i d e

L e t t e r o f I n t e r e s t : S t r u c t u r e s D e s i g n ( B r i d g e ) - S t a t e w i d e November 15, 2013 LPA Advisory Committee Re: Letter of Interest Structures Design (Bridge) Services LPA On-Call Services: Statewide Dear Committee Members: The Team we have assembled is very excited to

More information

Caltrans Sustainable Transportation Planning Grant Program

Caltrans Sustainable Transportation Planning Grant Program Caltrans Sustainable Transportation Planning Grant Program FY 2017-18 Strategic Partnerships & Sustainable Communities Presented by California Department of Transportation (Caltrans) FY 2017-18 Update

More information

BOARD OF RECREATION AND PARK COMMISSIONERS OF THE CITY OF LOS ANGELES

BOARD OF RECREATION AND PARK COMMISSIONERS OF THE CITY OF LOS ANGELES S P E C I A L A G E N D A BOARD OF RECREATION AND PARK COMMISSIONERS OF THE CITY OF LOS ANGELES Wednesday, October 5, 2011 at 9:35 a.m. or as soon thereafter as the Commission recesses its Regular Meeting

More information

STRUCTURE AND BRIDGE DIVISION

STRUCTURE AND BRIDGE DIVISION VIRGINIA DEPARTMENT OF TRANSPORTATION STRUCTURE AND BRIDGE DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDUM GENERAL SUBJECT: Bridge Safety Inspection QC/ Program SPECIFIC SUBJECT: Establishing Quality

More information

CITY OF ROHNERT PARK CITY COUNCIL AGENDA REPORT

CITY OF ROHNERT PARK CITY COUNCIL AGENDA REPORT ITEM NO. 6.C.3 Mission Statement We Care for Our Residents by Working Together to Build a Better Community for Today and Tomorrow. CITY OF ROHNERT PARK CITY COUNCIL AGENDA REPORT Meeting Date: November

More information

Safety Projects and the Local Agency Program (LAP)

Safety Projects and the Local Agency Program (LAP) Safety Projects and the Local Agency Program (LAP) Wednesday, January 8, 2014 Lawrence Taylor Consultant D7 Safety/LAP Project Manager Workshop Series Wed. Oct. 30 Wed. Nov. 6 Wed. Nov. 13 Wed. Nov. 20

More information

CHAPTER ONE PURPOSE AND NEED. 1.1 Context

CHAPTER ONE PURPOSE AND NEED. 1.1 Context CHAPTER ONE PURPOSE AND NEED This Final Environmental Impact Statement/Report (FEIS/R) incorporates the entire South Access to the Golden Gate Bridge - Doyle Drive Project Draft Environmental Impact Statement/Report

More information

Douglas P. Stanley County Administrator

Douglas P. Stanley County Administrator COUNTY OF WARREN County Administrator s Office Warren County Government Center 220 North Commerce Avenue, Suite 100 Front Royal, Virginia 22630 Phone: (540) 636-4600 FAX: (540) 636-6066 Email: dstanley@warrencountyva.net

More information

Board of Supervisors' Agenda Items

Board of Supervisors' Agenda Items A. Roll Call COUNTY OF SAN DIEGO BOARD OF SUPERVISORS REGULAR MEETING MEETING AGENDA WEDNESDAY, APRIL 13, 2016, 9:00 A.M. BOARD OF SUPERVISORS NORTH CHAMBER 1600 PACIFIC HIGHWAY, ROOM 310, SAN DIEGO, CALIFORNIA

More information

APPENDIX 5. Funding Plan

APPENDIX 5. Funding Plan STUDY: FINAL REPORT APPENDIX 5 Funding Plan May 2015 V:\2073\active\2073009060\report\DRAFT Final Report\rpt_MalPCH_DRAFTFinalReport-20150515.docx Pacific Coast Highway Safety Study: Funding Plan City

More information

MEMORANDUM. July 7, 2016

MEMORANDUM. July 7, 2016 MEMORANDUM July 7, 2016 TO: FROM: MEMBERS, PORT COMMISSION Hon. Willie Adams, President Hon. Kimberly Brandon, Vice President Hon. Leslie Katz Hon. Eleni Kounalakis Hon. Doreen Woo Ho Elaine Forbes Interim

More information

Addendum. Final Environmental Impact Report for North Campus Project. California State University Los Angeles SCH# March 2018.

Addendum. Final Environmental Impact Report for North Campus Project. California State University Los Angeles SCH# March 2018. Addendum Final Environmental Impact Report for North Campus Project to SCH#2016111038 California State University Los Angeles March 2018 Lead Agency The Board of Trustees of the California State University

More information

DEPARTMENT OF TRANSPORTATION POLICY FOR INDUSTRIAL PARK, AGRI-BUSINESS ACCESS, AND COMMUNITY ACCESS GRANT PROGRAMS

DEPARTMENT OF TRANSPORTATION POLICY FOR INDUSTRIAL PARK, AGRI-BUSINESS ACCESS, AND COMMUNITY ACCESS GRANT PROGRAMS DOT-168 Revised 12/22/06 DEPARTMENT OF TRANSPORTATION POLICY FOR INDUSTRIAL PARK, AGRI-BUSINESS ACCESS, AND COMMUNITY ACCESS GRANT PROGRAMS SOUTH DAKOTA DEPARTMENT OF TRANSPORTATION 700 EAST BROADWAY PIERRE,

More information

Innovative Project Finance

Innovative Project Finance Innovative Project Finance National Governor s Association Utah State Planning Retreat on Public-Private Partnerships Ivan Marrero, P.E. Division Administrator, FHWA Utah October 7, 2016 The Status Quo:

More information

WACOG FY Transportation Improvement Program STP PROJECTS AT A GLANCE

WACOG FY Transportation Improvement Program STP PROJECTS AT A GLANCE FY - Transportation Improvement Program PROJECTS AT A GLANCE TIP TIP ID # PROJECT PROJECT PROJECT LENGTH TYPE OF Functional LANES LANES FED AID FEDERAL FEDERAL ADOT LOCAL OTHER OTHER HURF TOTAL YEAR TRAC's

More information

Transportation Management Plan Overview

Transportation Management Plan Overview Transportation Management Plan Overview Module 3 Module Outline TMPs and the WZ Rule What is a TMP? Why TMPs? When to Develop TMPs State-of-the-Practice Tools Tips TMP Overview 2 TMP Beginnings Idea for

More information

INDIAN RIVER COUNTY METROPOLITAN PLANNING ORGANIZATION

INDIAN RIVER COUNTY METROPOLITAN PLANNING ORGANIZATION 2016 PRIORITY PROJECTS REPORT INDIAN RIVER COUNTY METROPOLITAN PLANNING ORGANIZATION This document was produced in cooperation with the Florida Department of Transportation and the Federal Highway Administration

More information

Arkansas State Highway and Transportation Department. Jonesboro Exchange Club

Arkansas State Highway and Transportation Department. Jonesboro Exchange Club Arkansas State Highway and Transportation Department Jonesboro Exchange Club Arkansas Highway & Transportation AHTD Quick Facts 3rd Largest State Agency (3,634 employees) Maintain 16,416 miles of highway

More information

S E N A T E F I S C A L O F F I C E I S S U E B R I E F 2016-S RhodeWorks FEBRUARY 2, 2016

S E N A T E F I S C A L O F F I C E I S S U E B R I E F 2016-S RhodeWorks FEBRUARY 2, 2016 2016-S-2246 - RhodeWorks FEBRUARY 2, 2016 SUMMARY 2016-S-2246 - The Rhode Island Bridge Replacement, Reconstruction and Maintenance Fund Act of 2016, also known as RhodeWorks, does the following: Allows

More information

COALINGA REDEVELOPMENT AGENCY PARKING LOT IMPROVEMENT PROGRAM GUIDELINES INTRODUCTION

COALINGA REDEVELOPMENT AGENCY PARKING LOT IMPROVEMENT PROGRAM GUIDELINES INTRODUCTION COALINGA REDEVELOPMENT AGENCY PARKING LOT IMPROVEMENT PROGRAM GUIDELINES INTRODUCTION The Parking Lot Improvement Program (PIP) is designed to stimulate building improvements and upgrade the appearance

More information

Funding the plan. STBG - This program is designed to address specific issues

Funding the plan. STBG - This program is designed to address specific issues Iowa DNR Solid Waste Alternatives Program USDA Rural Development Solid Waste Grants Hazard Mitigation Grant Program (HMGP) Pre-Disaster Mitigation (PDM) Flood Mitigation Assistance (FMA) Water Quality

More information

CITY OF SAN JOSE CHARCOT AVENUE EXTENSION PROJECT COMMUNITY STAKEHOLDER MEETING

CITY OF SAN JOSE CHARCOT AVENUE EXTENSION PROJECT COMMUNITY STAKEHOLDER MEETING CITY OF SAN JOSE CHARCOT AVENUE EXTENSION PROJECT COMMUNITY STAKEHOLDER MEETING Summary of Community Outreach Meeting Wednesday March 22, 2017 The City of San Jose hosted a community stakeholder outreach

More information

ENVIRONMENTAL ASSESSMENTS. Classification & Documentation

ENVIRONMENTAL ASSESSMENTS. Classification & Documentation ENVIRONMENTAL ASSESSMENTS Classification & Documentation CLASSIFICATION What s an Environmental Assessment? Not a Categorical Exclusion (CE) Not an Environmental Impact Statement (EIS) 3 Classification

More information

IRR Program, Inventory and Funding Formula Update

IRR Program, Inventory and Funding Formula Update IRR Program, Inventory and Funding Formula Update TRIBAL TRANSPORTATION AT A CROSSROAD: TRIBAL LEADERS FORUM ON THE CURRENT STATE OF TRIBAL TRANSPORTATION National Congress of American Indians Palm Springs,

More information

Kent Leben Rural Programs NDDOT-Local Government

Kent Leben Rural Programs NDDOT-Local Government Kent Leben Rural Programs NDDOT-Local Government Topics Federal and State Funding Programs Funding Programs Federal SC Roads BR Bridges ER Emergency Relief HSIP Highway Safety Improvement Program TA Transportation

More information

NAPA COUNTY GRAND JURY

NAPA COUNTY GRAND JURY NAPA COUNTY GRAND JURY 2016-2017 June 22, 2017 FINAL REPORT NAPA VALLEY TRANSPORTATION AGENCY VISION 2040 PLAN County Traffic Problems Need a Comprehensive Plan with Measurable Results 2 NAPA VALLEY TRANSPORTATION

More information

NACUBO APC and FASB Meeting April 11, 2017 Grant Scenarios for Discussion Grants and Contract Project

NACUBO APC and FASB Meeting April 11, 2017 Grant Scenarios for Discussion Grants and Contract Project Background: The Grant and Contract Revenue project was added to FASB s agenda because significant portions of revenue recognition guidance for not-or-profit entities was eliminated when FASB issued Accounting

More information

PINELLAS COUNTY DEO#12-1ESR

PINELLAS COUNTY DEO#12-1ESR Agenda Item #3.H.11 02/13/12 LOCAL GOVERNMENT COMPREHENSIVE PLAN PROPOSED AMENDMENT REPORT PINELLAS COUNTY DEO#12-1ESR 1 THIS PAGE INTENTIONALLY LEFT BLANK 2 PINELLAS COUNTY LPA 22-10-11 Expedited State

More information

Wolf River Conservancy in partnership with The City of Memphis Division of Park Services. Request for Proposals

Wolf River Conservancy in partnership with The City of Memphis Division of Park Services. Request for Proposals Wolf River Conservancy in partnership with The City of Memphis Division of Park Services Issued by Bob Wenner Wolf River Greenway Coordinator Wolf River Conservancy September 2, 2011 Proposal Deadline:

More information

Preliminary Review and. Reference Guide Sections 4.2 and 4.3

Preliminary Review and. Reference Guide Sections 4.2 and 4.3 Preliminary Review and Early Coordination Reference Guide Sections 4.2 and 4.3 Preliminary Review and Early Coordination (Reference Guide Sections 4.2 and 4.3) Overview Preliminary Review Preliminary Review

More information

THE SAN DIMAS MOUNTAIN RESCUE TEAM

THE SAN DIMAS MOUNTAIN RESCUE TEAM THE SAN DIMAS MOUNTAIN RESCUE TEAM HISTORY To meet the growing need for an organized Special Rescue Unit to assist those victims of accident and circumstances in the San Gabriel Canyon, the San Dimas Mountain

More information

Major in FY2013/2014 (By and ing Source) Municipal Building Acquisition and Operations Balance $1,984, Contributions from Real Estate

Major in FY2013/2014 (By and ing Source) Municipal Building Acquisition and Operations Balance $1,984, Contributions from Real Estate Major in FY2013/2014 (By and ing Source) Environmental Services Solid Waste 4200 4200 06CON 4200 SWM01 Balance $13,753,504.00 Balance $4,631,754.00 Balance $2,738,918.00 ing Source Total: $21,124,176.00

More information

SANTA BARBARA COUNTY PLANNING COMMISSION Staff Report for the Brogin Appeal

SANTA BARBARA COUNTY PLANNING COMMISSION Staff Report for the Brogin Appeal SANTA BARBARA COUNTY PLANNING COMMISSION Staff Report for the Brogin Appeal Deputy Director: Alice McCurdy Staff Report Date: November 20, 2014 Division: Development Review Case Nos.: 14APL-00000-00020

More information

POLICIES RELATING TO FEDERAL HIGHWAY FUNDING

POLICIES RELATING TO FEDERAL HIGHWAY FUNDING Approved: Policy No.: 18-003(P) Effective: April 19, 2002 Responsible Division: Finance and Forecasting Gordon Proctor Director POLICIES RELATING TO FEDERAL HIGHWAY FUNDING I. POLICY STATEMENT: Accrued

More information

Order of Business. D. Approval of the Statement of Proceedings/Minutes for the meeting of January 10, 2018.

Order of Business. D. Approval of the Statement of Proceedings/Minutes for the meeting of January 10, 2018. COUNTY OF SAN DIEGO BOARD OF SUPERVISORS REGULAR MEETING MEETING AGENDA WEDNESDAY, JANUARY 24, 2018, 9:00 AM BOARD OF SUPERVISORS NORTH CHAMBER 1600 PACIFIC HIGHWAY, SAN DIEGO, CALIFORNIA Order of Business

More information

Request for Proposal Design- and Construction- Engineering Services

Request for Proposal Design- and Construction- Engineering Services Request for Proposal For Design- and Construction-Engineering Services for 2019 LUND ROAD improvement project Kalkaska County Road Commission Kalkaska, MI Lund Road improvements from M-66 to Good Road,

More information

County CHSP Project Solicitation 12/08/05

County CHSP Project Solicitation 12/08/05 County CHSP Project Solicitation 12/08/05 Background On October 3, 2005 Mn/DOT State Aid sent a solicitation and to all county engineers for local CHSP projects. Each county could submit up a grant for

More information

WORK SESSION ITEM City Council

WORK SESSION ITEM City Council DATE: STAFF: October 25, 2016 Mark Jackson, PDT Deputy Director WORK SESSION ITEM City Council SUBJECT FOR DISCUSSION I-25 Northern Colorado Improvements. EXECUTIVE SUMMARY The purpose of this item is

More information

Surface Transportation Program (STP) Project Prioritization & Selection Process. For the Tulsa Urbanized Area. Revised July 31, 2013

Surface Transportation Program (STP) Project Prioritization & Selection Process. For the Tulsa Urbanized Area. Revised July 31, 2013 Surface Transportation Program (STP) Project Prioritization & Selection Process For the Tulsa Urbanized Area Revised July 31, 2013 Surface Transportation Program(STP) Project Prioritization and Selection

More information

Nassau County 2030 Comprehensive Plan. Public School Facilities Element (PSF) Goals, Objectives and Policies. Goal

Nassau County 2030 Comprehensive Plan. Public School Facilities Element (PSF) Goals, Objectives and Policies. Goal (PSF) Goal Work closely with the School District of Nassau County to ensure a high quality, fiscally sound public school system which meet the needs of Nassau County s population by providing and maintaining

More information

8/30/ American Public Works Association (APWA) International Congress and Exposition. August 30, 2015

8/30/ American Public Works Association (APWA) International Congress and Exposition. August 30, 2015 The Louisiana Department of Transportation and Development s Submerged Roads and Paths to Progress Programs: A Model for Future Disaster Recovery Efforts 2015 American Public Works Association (APWA) International

More information

PROJECT SELECTION Educational Series

PROJECT SELECTION Educational Series PROJECT SELECTION 2017 Educational Series PROJECT SELECTION THE PROJECT SELECTION PROCESS Understanding how the state s roads, bridges and other transportation infrastructure are selected for funding helps

More information

City of Belvidere Request for Proposals

City of Belvidere Request for Proposals City of Belvidere Request for Proposals Consultant Services to prepare an Architectural/Historical Intensive Survey of Belvidere s Courthouse Square Phase II Area PROPOSALS DUE IN TRIPLICATE Tuesday, September

More information

Planning Commission Motion No HEARING DATE: FEBRUARY 20, 2014

Planning Commission Motion No HEARING DATE: FEBRUARY 20, 2014 Subject to: (Select only if applicable) Affordable Housing (Sec. 415) Jobs Housing Linkage Program (Sec. 413) Downtown Park Fee (Sec. 412) First Source Hiring (Admin. Code) Child Care Requirement (Sec.

More information

MiTIP APPLICATION PACKET

MiTIP APPLICATION PACKET SFY 2022-2023 Illustrative Projects 2018-2021 INDIANAPOLIS REGIONAL TRANSPORTATION IMPROVEMENT PROGRAM (IRTIP) MiTIP APPLICATION PACKET Indianapolis Metropolitan Planning Organization October 2017 This

More information

Midpeninsula Regional Open Space District 330 Distel Circle, Los Altos, CA Issued: Friday, January 27, 2017

Midpeninsula Regional Open Space District 330 Distel Circle, Los Altos, CA Issued: Friday, January 27, 2017 Request for Qualifications and Proposals (RFQP) for Design Consulting Services for the Webb Creek Bridge Replacement Project, Bear Creek Redwood Open Space Preserve Midpeninsula Regional Open Space District

More information

County of Fairfax, Virginia

County of Fairfax, Virginia The presentation summarizes the state and regional components of HB 2313, implementation progress of HB 2313, and briefly presents the history of the Northern Virginia Transportation Authority. We ll also

More information

ORTEGA HIGHWAY: UNNECESSARY DELAYS HAVE COST US MILLIONS

ORTEGA HIGHWAY: UNNECESSARY DELAYS HAVE COST US MILLIONS ORTEGA HIGHWAY: UNNECESSARY DELAYS HAVE COST US MILLIONS 2016-2017 Orange County Grand Jury Page 1 Table of Contents SUMMARY... 3 REASON FOR THE STUDY... 3 METHOD OF STUDY... 4 BACKGROUND AND FACTS...

More information

CIRTPA Small Community Fund Application

CIRTPA Small Community Fund Application CIRTPA Small Community Fund Application November 2017 2 P a g e Schedule and Decision Making Process November 16, 2017 January 18, 2018 Application process approved by CIRTPA Policy Committee and posted

More information

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY THIS PRINT COVERS CALENDAR ITEM NO.: 10.3 SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY DIVISION: Finance and Information Technology BRIEF DESCRIPTION: Approving a fund transfer agreement for $292,149

More information

Internal Audit Report Grantee: University of Texas Southwestern Medical Center

Internal Audit Report Grantee: University of Texas Southwestern Medical Center Internal Audit Report Grantee: University of Texas Southwestern Medical Center Report #2014-101 August 28, 2014 Introduction As part of the Cancer Prevention Research Institute of Texas ( CPRIT ) FY 2014

More information

Bartlesville City Planning Commission SITE DEVELOPMENT PLAN PROCEDURE AND APPLICATION

Bartlesville City Planning Commission SITE DEVELOPMENT PLAN PROCEDURE AND APPLICATION Bartlesville City Planning Commission SITE DEVELOPMENT PLAN PROCEDURE AND APPLICATION Site Development Plans must be submitted prior to the issuance of any building permit for any tract within a district

More information

J o i n t T e c h n i c a l C o o r d i n a t i n g C o m m i t t e e a n d G o v e r n i n g B o a r d

J o i n t T e c h n i c a l C o o r d i n a t i n g C o m m i t t e e a n d G o v e r n i n g B o a r d J o i n t T e c h n i c a l C o o r d i n a t i n g C o m m i t t e e a n d G o v e r n i n g B o a r d November 17, 2016 12: Noon (*MPO Board Members to Join at 12:30), Asheville Area Chamber of Commerce

More information

Honorable Mayor Shaw and Members of the City Council

Honorable Mayor Shaw and Members of the City Council DATE: August 31, 2015 TO: FROM: Honorable Mayor Shaw and Members of the City Council Joanne Foust, Consulting Planner AGENDA ITEM: 6 A Outlet Center Feasibility Study Grant Opportunity ******************************************************************************

More information

Formal STIP Amendment

Formal STIP Amendment FHWA/FTA AND MNDOT GUIDANCE FOR FORMAL STIP AMENDMENTS AND ADMINISTRATIVE STIP MODIFICATIONS Effective: April 15, 2015 The STIP may be updated periodically throughout the course of the year for project

More information

CAIS Trustee Head Conference 2014 Developing a Successful Project Entitlements Team & Strategy

CAIS Trustee Head Conference 2014 Developing a Successful Project Entitlements Team & Strategy Todays Topics: Overview of Entitlement Components and Team Case Study: The Urban School Academic and Athletic Building Lessons Learned Questions and Answer Session What are project entitlements and why

More information

2016 Bridge Inspections Border Bridges

2016 Bridge Inspections Border Bridges 2016 Bridge Inspections Border Bridges Request For Proposal Iowa Department of Transportation Introduction The Iowa Department of Transportation s Office of Bridges and Structures is interested in Category

More information

Civil Works Program. non-federal sponsors for specific projects and the total civil program is about $5 billion a year.

Civil Works Program. non-federal sponsors for specific projects and the total civil program is about $5 billion a year. Civil Works Program The Directorate of Civil Works is a major component of the U.S. Army Corps of Engineers. The Civil Works programs include water resource development activities including flood control,

More information

I-605 CORRIDOR HOT SPOT INTERCHANGES

I-605 CORRIDOR HOT SPOT INTERCHANGES I-605 CORRIDOR HOT SPOT INTERCHANGES Project Description Several traffic congestion Hot Spots have been identified in the I-605 Corridor through a Needs Assessment and an Initial Corridor Study. These

More information

RESOLUTION FOR APPROVAL OF AMENDMENTS TO THE TRANSPORTATION IMPROVEMENT PROGRAM (TIP) AND 2040 REGIONAL TRANSPORTATION PLAN (RTP)

RESOLUTION FOR APPROVAL OF AMENDMENTS TO THE TRANSPORTATION IMPROVEMENT PROGRAM (TIP) AND 2040 REGIONAL TRANSPORTATION PLAN (RTP) TPC Agenda Item 6A Mailout 10/20/16 RESOLUTION FOR APPROVAL OF AMENDMENTS TO THE 2017-2020 TRANSPORTATION IMPROVEMENT PROGRAM (TIP) AND 2040 REGIONAL TRANSPORTATION PLAN (RTP) Amendment Summary Amendment

More information

MINUTES MALIBU PUBLIC WORKS COMMISSION REGULAR MEETING SEPTEMBER 28, 2016 MULTIPURPOSE ROOM 3:30 P.M.

MINUTES MALIBU PUBLIC WORKS COMMISSION REGULAR MEETING SEPTEMBER 28, 2016 MULTIPURPOSE ROOM 3:30 P.M. MINUTES MALIBU PUBLIC WORKS COMMISSION REGULAR MEETING SEPTEMBER 28, 2016 MULTIPURPOSE ROOM 3:30 P.M. CALL TO ORDER ROLL CALL Chair Scott called the meeting to order at 3:31 p.m. The following persons

More information

FY16 Annual Report WHAT IS GTIB? WHO ADMINSTERS GTIB? Summary of GTIB Funding Through FY16

FY16 Annual Report WHAT IS GTIB? WHO ADMINSTERS GTIB? Summary of GTIB Funding Through FY16 FY16 Annual Report PROVIDING FUNDS TO IMPROVE MOBILITY, SUSTAIN DEVELOPMENT AND ENHANCE COMMUNITIES THROUGHOUT GEORGIA WHAT IS GTIB? The Georgia Transportation Infrastructure Bank (GTIB) provides financial

More information

NCDOT Planning Summary for NCTA Projects

NCDOT Planning Summary for NCTA Projects NCDOT Planning Summary for NCTA Projects Page 1 Triangle Expressway Southeast Extension Wake and Johnston Counties (STIP Projects R-2721, R-2828, and R-2829) The Triangle Expressway Southeast Extension

More information

OGUNQUIT PLANNING BOARD MINUTES OCTOBER 27, 2014

OGUNQUIT PLANNING BOARD MINUTES OCTOBER 27, 2014 OGUNQUIT PLANNING BOARD MINUTES OCTOBER 27, 2014 A. ROLL CALL The Roll was called with the following results: Members Present: Members Excused: Also Present: Don Simpson, Chair Jackie Bevins Muriel Freedman

More information

CITY OF COCOA BEACH. STRATEGIC PLAN ANNUAL REPORT October 2015 September Acting City Manager City Commission Meeting November 17, 2016

CITY OF COCOA BEACH. STRATEGIC PLAN ANNUAL REPORT October 2015 September Acting City Manager City Commission Meeting November 17, 2016 CITY OF COCOA BEACH STRATEGIC PLAN ANNUAL REPORT October 2015 September 2016 Presented by : Charles H. Holland Jr., CGFO Acting City Manager City Commission Meeting November 17, 2016 1 CONTENTS 2 Executive

More information

Historic Bridge Programmatic Agreements: Best Practices and Examples

Historic Bridge Programmatic Agreements: Best Practices and Examples Historic Bridge Programmatic Agreements: Best Practices and Examples Programmatic Agreements (PAs) are an effective tool for developing and documenting procedures and strategies for managing historic bridges.

More information

Annual Plan

Annual Plan 2015-2020 Annual Plan 712 South Highway 6, Oakland, Iowa 51560 Our mission: Golden Hills Resource Conservation and Development is dedicated to conserving the community, cultural and environmental assets

More information

1. Introduction to the National Fish and Wildlife Foundation and the Angeles National Forest partnership 2. Overview of Wildfires Restoration Program

1. Introduction to the National Fish and Wildlife Foundation and the Angeles National Forest partnership 2. Overview of Wildfires Restoration Program Photo: istock 1. Introduction to the National Fish and Wildlife Foundation and the Angeles National Forest partnership 2. Overview of Wildfires Restoration Program 3. Review of Angeles National Forest

More information

2011 SURVEY OF MUNICIPAL REGULATIONS AND FIRE CODE REGULATIONS AFFECTING CHILD CARE FACILITIES DEVELOPMENT IN SANTA CLARA COUNTY

2011 SURVEY OF MUNICIPAL REGULATIONS AND FIRE CODE REGULATIONS AFFECTING CHILD CARE FACILITIES DEVELOPMENT IN SANTA CLARA COUNTY 2011 Prepared for the Santa Clara County Early Learning Master Plan Facilities Committee Prepared by the Office of the Superintendent, Santa Clara County Office of Education 2011 SURVEY OF MUNICIPAL REGULATIONS

More information

PLANNING DEPARTMENT ADMINISTRATION

PLANNING DEPARTMENT ADMINISTRATION PLANNING DEPARTMENT ADMINISTRATION Support Division Planning & Community Zoning Administration Review & Compliance Land Use & Design Rezoning & Permitting Plan Review Community LDO Management Zoning &

More information

City of Lansing Application #2 River Trail West (Near Elm St) - Wall and Pavement Repair

City of Lansing Application #2 River Trail West (Near Elm St) - Wall and Pavement Repair City of Lansing Application #2 River Trail West (Near Elm St) - Wall and Pavement Repair 1 2 Ingham County Parks and Recreation Commission P.O. Box 178 121 E. Maple Street, Suite 102 Mason, MI 48854 Trails

More information

CITY OF LOS ANGELES INTER-DEPARTMENTAL CORRESPONDENCE

CITY OF LOS ANGELES INTER-DEPARTMENTAL CORRESPONDENCE CITY OF LOS ANGELES INTER-DEPARTMENTAL CORRESPONDENCE Date: May 17, 2016 To: The Honorable City Council c/o City Clerk, Room 395 Attention: Honorable Mike Bonin, Chair, Transportation Committee From: Seleta

More information

BOWLING GREEN - WARREN COUNTY METROPOLITAN PLANNING ORGANIZATION

BOWLING GREEN - WARREN COUNTY METROPOLITAN PLANNING ORGANIZATION BOWLING GREEN - WARREN COUNTY METROPOLITAN PLANNING ORGANIZATION Fiscal Year 2016 Annual Performance and Expenditure Report July 1, 2015 June 30, 2016 September 2016 Prepared and submitted by: Bowling

More information

Amendments to FY Transportation Improvement Program of the Coastal Region Metropolitan Planning Organization (CORE MPO) August 2016

Amendments to FY Transportation Improvement Program of the Coastal Region Metropolitan Planning Organization (CORE MPO) August 2016 Amendments to FY 2015-2018 Transportation Improvement Program of the Coastal Region Metropolitan Planning Organization (CORE MPO) August 2016 The Transportation Improvement Program (TIP) is the MPO s short-range

More information

FUNDING POLICY GUIDELINES

FUNDING POLICY GUIDELINES FUNDING POLICY GUIDELINES Revised and Approved May 25, 2017 Akron Metropolitan Area Transportation Study 806 CitiCenter 146 South High Street Akron, Ohio 44308 This document was prepared by the Akron Metropolitan

More information

CITY/COUNTY PLANNING BOARD Serving Billings, Broadview and Yellowstone County

CITY/COUNTY PLANNING BOARD Serving Billings, Broadview and Yellowstone County Board Attendance Roster: Please note: E stands for excused absence, A stands for un-excused absence, 1 stands for present. BYLAWS, YELLOWSTONE COUNTY BOARD OF PLANNING, (Amended. May 25, 2004) Section

More information

MIDPENINSULA REGIONAL OPEN SPACE DISTRICT GENERAL COUNSEL

MIDPENINSULA REGIONAL OPEN SPACE DISTRICT GENERAL COUNSEL MIDPENINSULA REGIONAL OPEN SPACE DISTRICT GENERAL COUNSEL THE DISTRICT Open space lands offer a respite from everyday life, a source of clean air and water, and local agriculture as well as an opportunity

More information

Regional Tourist Association Board of Directors Manual

Regional Tourist Association Board of Directors Manual Regional Tourist Association Board of Directors Manual REGIONAL TOURIST ASSOCIATION PROGRAM Table of Contents Introduction..... How does tourism benefit the local and state economies?.... What is a Regional

More information

5.1 Mitigation Goals and Objectives

5.1 Mitigation Goals and Objectives Chapter 5. The mitigation goals, objectives, and strategies outlined below were developed by both the steering committee and working groups. Prior to the beginning the working group meetings, the steering

More information

Puerto Rico Highways and Transportation Authority

Puerto Rico Highways and Transportation Authority Puerto Rico Highways and Transportation Authority Rubén Hernández Gregorat, MEM, PE Executive Director February 26, 2010 Disclaimer Today s presentation includes certain statements that are not historical

More information

ARLINGTON COUNTY, VIRGINIA

ARLINGTON COUNTY, VIRGINIA ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of April 22, 2006 DATE: March 30, 2006 SUBJECT: Approval of the County s Annual Consolidated Plan for Fiscal Year (FY) 2007, which includes the

More information

TRB Committee AFF60 Tunnels and Underground Structures. Agenda for 2012 Meeting. Tuesday January 15, :30 PM 5:30 PM Marriott Balcony B

TRB Committee AFF60 Tunnels and Underground Structures. Agenda for 2012 Meeting. Tuesday January 15, :30 PM 5:30 PM Marriott Balcony B TRB Committee AFF60 Tunnels and Underground Structures Agenda for 2012 Meeting Tuesday January 15, 2013 1:30 PM 5:30 PM Marriott Balcony B Committee Scope (official approved scope): This committee is concerned

More information

MEMORANDUM. February 12, Interagency Transit Committee Members and Interested Parties. Anthony Zepeda, Associate Regional Planner

MEMORANDUM. February 12, Interagency Transit Committee Members and Interested Parties. Anthony Zepeda, Associate Regional Planner MEMORANDUM February 12, 2014 To: Fr: Re: Interagency Transit Committee Members and Interested Parties Anthony Zepeda, Associate Regional Planner Cancellation of February 19, 2014 ITC Meeting The Interagency

More information

J o i n t T e c h n i c a l C o o r d i n a t i n g C o m m i t t e e a n d G o v e r n i n g B o a r d

J o i n t T e c h n i c a l C o o r d i n a t i n g C o m m i t t e e a n d G o v e r n i n g B o a r d J o i n t T e c h n i c a l C o o r d i n a t i n g C o m m i t t e e a n d G o v e r n i n g B o a r d November 17, 2016 12: Noon (*MPO Board Members to Join at 12:30), Asheville Area Chamber of Commerce

More information

Florida Job Growth Grant Fund Public Infrastructure Grant Proposal

Florida Job Growth Grant Fund Public Infrastructure Grant Proposal Florida Job Growth Grant Fund Public Infrastructure Grant Proposal Proposal Instructions: The Florida Job Growth Grant Fund Proposal (this document) must be completed by the governmental entity applying

More information

PUBLIC INPUT PROCESS GUIDELINES FOR SIX-YEAR TRANSPORTATION PLAN PROJECTS

PUBLIC INPUT PROCESS GUIDELINES FOR SIX-YEAR TRANSPORTATION PLAN PROJECTS PUBLIC INPUT PROCESS GUIDELINES FOR SIX-YEAR TRANSPORTATION PLAN PROJECTS Clallam County.1 PURPOSE The Clallam County Six-Year Transportation Improvement Plan (Six-Year TIP) serves as a multiyear financing

More information