Completion Report. Project Number: Loan Numbers: 1440/1441 July Philippines: Rural Water Supply and Sanitation Sector Project

Size: px
Start display at page:

Download "Completion Report. Project Number: Loan Numbers: 1440/1441 July Philippines: Rural Water Supply and Sanitation Sector Project"

Transcription

1 Completion Report Project Number: Loan Numbers: 1440/1441 July 2006 Philippines: Rural Water Supply and Sanitation Sector Project

2 CURRENCY EQUIVALENTS Currency Unit peso (P) At Appraisal At Project Completion 30 April July 2004 P1.00 = $ $ $1.00 = P26.18 P56.20 ABBREVIATIONS ADB Asian Development Bank BME benefit monitoring and evaluation BWSA barangay waterworks and sanitation association DILG Department of the Interior and Local Government DOF Department of Finance DOH Department of Health DPWH Department of Public Works and Highways EA executing agency EIRR economic internal rate of return HHE health and hygiene education IA implementing agency LGU local government unit MWT municipal water sanitation team NGO nongovernment organization O&M operation and maintenance PCR project completion review PMO project management office PWT provincial water sanitation team SRA sector reform agenda WQS water quality and surveillance WSS water sanitation and supply GLOSSARY barangay the smallest political unit into which cities and municipalities in the Philippines are divided. It is the basic unit of the Philippine political system. It consists of less than 1,000 inhabitants residing within the territorial limit of a city or municipality and administered by a set of elective officials, headed by a barangay chairman (punong barangay). NOTES (i) (ii) The fiscal year (FY) of the Government and its agencies ends on 31 December. In this report, "$" refers to US dollars.

3 Vice President C. Lawrence Greenwood, Jr., Operations Group 2 Director General R. Nag, Southeast Asia Department (SERD) Director S. Lateef, Social Sectors Division, SERD Team leader Team member P. van Klaveren, Urban Development Specialist, SERD R. Alvarez, Assistant Project Analyst, SERD

4 CONTENTS Page BASIC DATA ii MAP vii I. PROJECT DESCRIPTION 1 II. EVALUATION OF DESIGN AND IMPLEMENTATION 2 A. Relevance of Design and Formulation 2 B. Project Outputs 3 C. Project Costs 4 D. Disbursements 5 E. Project Schedule 5 F. Implementation Arrangements 6 G. Conditions and Covenants 7 H. Consultant Recruitment and Procurement 8 I. Performance of Consultants, Contractors, and Suppliers 8 J. Performance of the Borrower and the Executing Agency 9 K. Performance of the Asian Development Bank 10 III. EVALUATION OF PERFORMANCE 10 A. Relevance 10 B. Effectiveness in Achieving Outcome 10 C. Efficiency in Achieving Outcome and Outputs 11 D. Preliminary Assessment of Sustainability 12 E. Impact 13 IV. OVERALL ASSESSMENT AND RECOMMENDATIONS 14 A. Overall Assessment 14 B. Lessons Learned 14 C. Recommendations 15 APPENDIXES 1. Project Framework Physical Accomplishments Revisions in Loan Allocations Project Implementation Schedule Status of Compliance with Loan Covenants Economic Evaluation 30

5 BASIC DATA A. Loan Identification 1. Country 2. Loan Number 3. Project Title 4. Borrower 5. Executing Agency 6. Amount of Loan 7. Project Completion Report Number B. Loan Data 1. Appraisal Date Started Date Completed 2. Loan Negotiations Date Started Date Completed 3. Date of Board Approval 4. Date of Loan Agreement 5. Date of Loan Effectiveness In Loan Agreement Actual Number of Extensions 6. Closing Date In Loan Agreement Actual Number of Extensions 7. Terms of Loan Interest Rate Maturity (number of years) Grace Period (number of years) Philippines 1440/1441 Rural Water Supply and Sanitation Sector Project Republic of the Philippines Department of Public Works and Highways $18.5 million (Loan 1440) SDR million (Loan 1441[SF]) July July April May 1996 (intermittent) 4 June June September November 1997 one 1 February July 2004 (Loan 1440); 23 July 2004 (Loan 1441[SF]) two Loan 1440 Loan 1441(SF) variable 1% Disbursements a. Dates Initial Disbursement 2 June 1998 Final Disbursement 26 May 2004 Time Interval 71 months Effective Date 7 November 1997 Original Closing Date 1 February 2002 Time Interval 50 months Loan 1440 Effective Date 7 November 1997 Revised Closing Date 8 July 2004 Time Interval 80 months Loan 1441(SF) 7 November July months

6 iii b. Amount Loan 1440-PHI ($ million) Category Original Allocation Last Revised Allocation a Amount Cancelled a Net Amount Available Amount Disbursed b Undisbursed Balance b 01 Civil Works (0.082) 02 Equipment and Materials 03 Consulting (0.082) Services 04 Interest and Commitment Charges 05 Institutional Development (0.084) Total a As of 19 March 2002, date of first partial cancellation. b Cancelled on 8 July 2004, date loan account was closed. Loan 1441-PHI(SF) (SDR million) Category Original Allocation Last Revised Allocation a Amount Cancelled a Net Amount Available Amount Disbursed Undisbursed Balance b 01 Civil Works Equipment and Materials Consulting Services (0.076) Interest and Commitment Charges Total Note: Numbers may not sum precisely due to rounding. a As of 3 July 2003, date of first partial cancellation. b Cancelled on 23 July 2004, date loan account was closed. Loan 1441-PHI(SF) ($ million) Category Original Allocation Last Revised Allocation a Amount Cancelled a Net Amount Available b Amount Disbursed Undisbursed Balance b 01 Civil Works Equipment and Materials Consulting Services (0.112) Interest and Commitment Charges Total Note: Numbers may not sum precisely due to rounding. a SDR1.00 = $ as of 3 July 2003, date of first partial cancellation. b SDR1.00 = $ as of 23 July 2004, date of loan account closing.

7 iv C. Project Data 1. Project Cost ($ million) Cost Appraisal Estimate Actual Foreign Exchange Cost Local Currency Cost Total Cost 2. Financing Plan ($ million) Appraisal Estimate Foreign Local Actual Foreign Local A. Implementation Costs ADB National Government Local Government Units Communities B. Interest During Construction ADB Total ADB = Asian Development Bank. 3. Cost Breakdown by Project Component ($ million) Appraisal Actual Component Foreign Local Total Foreign Local Total A. Part A: Institutional Development 1. Capacity Building Program Community Management Program Health and Hygiene Education Program Water Quality Control/Surveillance Program Subtotal (A) B. Part B: Water Supply and Sanitation 1. Land Civil Works Equipment Feasibility Studies and Detailed Design a 5. Project Management/Consulting Services Administration Support Subtotal (B) C. Service Charge and Interest During Construction Total a Cost of feasibility studies was doubled because the costs for the sanitation works and procuring chemicals were charged under this category.

8 v 4. Project Schedule Item Appraisal Estimate Actual Engagement of Institutional Development Consultants October 1996 Not engaged Selection of Implementation Consultants October 1996 June 1998 BWSA Formation and Registration July 1996 May 1998 Capacity Building Program Sector Agencies October 1996 November 1997 LGUs October 1996 April 1998 BWSA October 1996 November 1998 Civil Works Construction or Rehabilitation of Facilities January 1997 June 1999 Completion and Turnover of Facilities to BWSAs September 2001 January 2004 Equipment and Supplies First Procurement October 1996 April 1999 Last Procurement June 1999 August 2003 Completion of Delivery of Equipment June 1999 May 2004 Conduct of BME July 1996 April 1999 Conduct of Health and Hygiene Education July 1996 October 1999 First Year Review October 1997 August 1998 Mid-Term Review March 1999 October 2000 Final Review October 2001 November 2003 BME = benefit, monitoring, and evaluation, BWSA = barangay waterworks and sanitation association, LGU = local government unit. 5. Project Performance Report Ratings Development Objectives Ratings Implementation Progress Implementation Period From 30 November 1998 to 30 November 2000 Satisfactory Satisfactory From 31 December 2000 to 31 August 2001 Partly Satisfactory Partly Satisfactory From 30 September 2001 to 31 July 2002 Partly Satisfactory Satisfactory From 31 August 2002 to 31 December 2004 Satisfactory Satisfactory D. Data on Asian Development Bank Missions Name of Mission Date No. of Persons No. of Person-Days Specialization of Members a Fact-Finding 24 April 12 May a, e, f, g, h, i, Appraisal 3 25 July a, e, g, h, I, k Consultation 5 8 May M Inception November a, e, g, h Review August a, n Review 6 30 April a, d, n Review May a, d, n Mid-Term Review 30 October 30 November a, b, f, i, j, n Review 13 July 18 September c, f, i Review 3 20 December e, n Review 20 November 16 December e, n Project Completion Review b 14 February 10April c, l, n a a = project economist, b = urban environment specialist, c = urban development specialist, d = division manager, e = project engineer, f = senior programs officer, g = programs officer, h = counsel, i = institutional development specialist (staff consultant), j

9 vi = water supply engineer (staff consultant), k = community participation specialist (staff consultant), l = financial/economic analyst (staff consultant), m = department director, n = assistant project analyst. b The project completion report was prepared by Paul van Klaveren, urban development specialist, and Riza-Gloria V. Alvarez, assistant project analyst.

10 125o00'E 119o00'E Babuyan Channel o 'E o 21 00'N PHILIPPINES o 21 00'N RURAL WATER SUPPLY AND SANITATION SECTOR PROJECT Itbayat ILOCOS NORTE BATANES APAYAO Laoag Basco Kabugao CAGAYAN Sabtang o 'E Bangued Tuguegarao KALINGA ABRA ILOCOS SUR MT. PROVINCE Vigan South China Tabuk Bontoc ISABELA Lagawe LA UNION BENGUET San Fernando Cabarroguis Bayombong La Trinidad Baguio N Ilagan IFUGAO Sea NUEVA VIZCAYA QUIRINO Lingayen 16o00'N ZAMBALES Iba Baler NUEVA ECIJA Tarlac 16o00'N Kilometers AURORA PANGASINAN Palayan TARLAC PAMPANGA San Fernando BULACAN Malolos Balanga Manila BATAAN Project Area City/Town CAMARINES SUR Lucena Calapan Boundaries are not necessarily authoritative. Burias Sibuyan Sea ORIENTAL MINDORO Legaspi ALBAY MARINDUQUE OCCIDENTAL MINDORO CATANDUANES Virac Pili Boac Mamburao Provincial Boundary Daet LAGUNA Batangas National Highway OCEAN CAMARINES NORTE Sta. Cruz BATANGAS National Capital QUEZON Binangonan Trece Martires CAVITE PACIFIC Polillo RIZAL Philippine Sorsogon Romblon Catarman Ticao NORTHERN SAMAR Masbate ROMBLON WESTERN SAMAR AKLAN Catbalogan MASBATE Roxas CAPIZ Naval Vi sayan Sea EASTERN SAMAR ANTIQUE LEYTE ILOILO Iloilo CEBU GUIMARAS NEGROS OCCIDENTAL SURIGAO DEL NORTE Maasin BOHOL Puerto Princesa NEGROS ORIENTAL Tagbilaran Dumaguete Siquijor Dipolog ZAMBOANGA DEL NORTE SIQUIJOR Surigao Bohol Sea Mambajao AGUSAN DEL NORTE Butuan CAMIGUIN MISAMIS ORIENTAL Oroquieta MISAMIS OCC.Tubod Sea Prosperidad Cagayan de Oro AGUSAN Kidapawan Shariff Aguak Zamboanga MAGUINDANAO Isabela Moro BASILAN Jolo SULU Panglima Sugala 119o00'E Gulf Isulan SULTAN KUDARAT Davao City Mati Digos Koronadal DAVAO DEL SUR SOUTH COTABATO Alabel SARANGANI Celebes TAWI-TAWI Tandag SURIGAO DEL SUR Malaybalay DEL SUR Marawi ZAMBOANGA LANAO 8 o00'n DEL SUR DEL NORTE LANAO BUKIDNON DAVAO DEL Pagadian DEL SUR Ipil NORTE Nabunturan ZAMBOANGA Tagum COMPOSTELA VALLEY SIBUGAY NORTH COTABATO DAVAO ORIENTAL 8 o00'n Sulu SOURTHERN LEYTE Cebu Panay Gulf PALAWAN Tacloban Leyte Gulf Bacolod Jordan Borongan BILIRAN Kalibo San Jose Sea SORSOGON Sea 125o00'E HR

11 I. PROJECT DESCRIPTION 1. Improved rural water supply and sanitation (WSS) can have wide-ranging health, social, and economic benefits. In rural areas of the Philippines, sanitation-related diseases afflict many people with diarrhea, the main cause of neonatal morbidity and the leading cause of illness among children. The incidence of these diseases can be significantly reduced when WSS services are improved. The most significant improvements in health are usually achieved through a combination of improved WSS services and better personal and household hygiene. The benefits from WSS can be maximized in underserved rural areas when combined with support programs such as health and hygiene education (HHE). Women and children benefit substantially from improved rural WSS as the physical burden of carrying water can be reduced, and the time and energy saved can be put to more productive use. 2. In 1988, the Government launched the national Water Supply, Sewerage, and Sanitation Sector Master Plan covering the period Water supply coverage for the urban population subsequently increased from 63% in 1988 to 70% in Progress in the provision of water supply facilities for rural areas increased from 65% in 1988 to 70% in As the average is only 40% in the poorest rural areas, the provision of WSS facilities for rural areas is an important priority of the Government s program. 3. The major objectives of the Rural Water Supply and Sanitation Sector Project (the Project) 1 were to (i) improve the capacity of sector agencies to enhance the delivery of social services; (ii) provide safe, adequate, and reliable WSS services to selected low-income rural communities in the 20 poorest provinces of the Government s Social Reform Agenda (SRA); and (iii) support HHE, water quality surveillance, and community management activities. The Project framework is included as Appendix The Department of Public Works and Highways (DPWH) was the Executing Agency (EA), which managed and coordinated the Project in partnership with two implementing agencies (IAs): the Department of the Interior and Local Government (DILG) and the Department of Health (DOH). The two major components of the Project were (i) institutional development and (ii) water supply and sanitation. DPWH was responsible for constructing the water supply facilities, while the DOH led the implementation of the sanitation component. Institutional development and capacity building were implemented by DILG. 5. DPWH was responsible for the further refinement of the benefit monitoring and evaluation (BME) system that it had developed in conjunction with earlier projects assisted by the Asian Development Bank (ADB). 6. Part A: Institutional Development consisted of four subcomponents as follows: (i) a capacity-building program for local institutions covering training courses for local government units (LGUs); (ii) a community management program to help the communities design and implement cost-recovery programs and implement operation and maintenance (O&M) activities; (iii) an HHE program focusing on safe drinking water, good habits for personal hygiene, and controlling diarrhea; and 1 ADB Report and Recommendation of the President to the Board of Directors on a Proposed Loan to the Republic of the Philippines for the Rural Water Supply and Sanitation Sector Project. Manila.

12 2 (iv) water quality control and surveillance (WQS) programs covering (a) water source disinfection, (b) water sample collection and testing, (c) the issuance of certificates of water potability, (d) recommendations to install treatment facilities if test results showed water contamination, and (e) periodic water testing at designated sample points. 7. Part B: Water Supply and Sanitation Facilities included (i) constructing and rehabilitating point source water supply systems (level 1); (ii) constructing public, school, and household latrines; and (iii) constructing and equipping district laboratories. II. EVALUATION OF DESIGN AND IMPLEMENTATION A. Relevance of Design and Formulation 8. The Project responded to ADB s Country Assistance Plan (1996), and responds to the current Country Strategy and Program, specifically by improving the delivery of basic social services to rural areas, with the overall objective of reducing poverty, as specified in the Poverty Partnership Agreement. 2, 3 9. The Medium-Term Philippine Development Plan presents several mediumterm goals and strategies for the WSS sector in the Philippines: (i) Provide potable water to the entire country by 2010 through private sector or public investment. (ii) Ensure that all barangays and municipalities that will be provided with water supply services have the corresponding sanitation facilities for proper disposal of wastewater. (iii) Continue to provide capacity-building programs and technical assistance on WSS planning, management, and project implementation for all water service providers needing assistance. 10. The Project was formulated through a sound demand-based process and multiple consultations with the representatives of the Government, LGUs, communities, and funding agencies. A socioeconomic survey among beneficiaries in 12 provinces, covering 400 communities, was carried out and reviewed by ADB. Furthermore, 40 of the 200 prepared subprojects were reviewed, and eight subprojects were appraised in detail. 11. On the basis of lessons learned from previous ADB-financed rural water-supply projects, the Project recognized the need to focus on the sustainability of operations and a strong sense of ownership. Appropriate measures were incorporated in the project design, such as a capacity-building program for sector agencies and communities, a comprehensive water quality control and surveillance program, and clear delineation of responsibilities among the central and local agencies involved. 12. To increase the level of ownership of each subproject, detailed requirements were formulated for site selection. The formation of barangay waterworks and sanitation associations (BWSAs) was a prerequisite, and detailed arrangements for cost recovery and O&M by the communities were outlined. 2 ADB Country Strategy and Program : Republic of the Philippines. Manila Republic of the Philippines Asian Development Bank Poverty Partnership Agreement. Manila. 4 National Economic Development Authority Medium-Term Philippine Development Plan, Manila.

13 3 B. Project Outputs 13. The Project s original target was to improve access to safe water and sanitation in 3,000 barangays in the 20 poorest provinces, by constructing and rehabilitating 8,256 water-supply facilities, and by training 3,000 BWSAs to manage and operate multiple facilities in each barangay. Additionally, in the same 3,000 barangays, 41,380 latrines were to be constructed in 125 public areas, 125 schools, and 40,000 households. To support the WQS program, 50 district water laboratories were to be constructed and equipped. 14. The target at appraisal refers to the number of barangays to be covered by the Project. A barangay is the smallest administrative unit and can consist of 200 to 5,000 people. It was estimated at appraisal that a total of 8,256 facilities in 3,000 barangays needed to be constructed and rehabilitated. With the target set at 2 million beneficiaries, this resulted in an assumed average number of 667 people per barangay and 242 beneficiaries per facility. During implementation, the focus of monitoring shifted to the number of water supply facilities to be constructed and managed, without taking into account the number of barangays nor the number of beneficiaries per facility. As a consequence, the number of beneficiaries covered by the Project was not monitored. 15. During project implementation, the target number of water supply facilities was increased because of requests for additional spring-development projects. The conclusion was reached that each facility should be operated by a separate BWSA, resulting in a new target of 8,575 water supply facilities and the establishment of 8,575 new BWSAs. Later on, it was realized that in some cases it would be more efficient to allow BWSAs to operate more than one water supply facility, and the target number of BWSAs was reduced to 4,453. With the depreciation of the Philippine peso against the US dollar, the targets for the sanitation component could be increased from 40,000 to more than 90,000 latrines. 16. The targets at appraisal, revised targets, and actual physical accomplishments are presented in Tables 1 and 2. The outputs are presented in more detail in Appendix 2. Description Table 1: Targets versus Achieved Output (Part A) (as of 30 June 2004) Target at Appraisal Revised Target Actual % (of revised target) Part A (Institutional Development) 1. Formed BWSAs 3,000 4,453 4, Trained BWSAs 3,000 4,453 3, LGU Training (a) No. of PWTs Trained (b) No. of MWTs Trained (c) No. of PWTs Staff (d) No. of MWTs Staff 1, BWSA = barangay waterworks and sanitation association, MWT = municipal water and sanitation team, No. = number, PWT = provincial water and sanitation team. Source: Department of Public Works and Highways. 17. During site visits, it became clear to the Project Completion Review (PCR) Mission that not all the formed BWSAs were active. BWSA training was in some cases limited to one or two

14 4 sessions on the formation of BWSAs. Skills training programs for WSS were provided to provincial water and sanitation teams (PWTs), municipal water and sanitation teams (MWTs), and all registered BWSAs. Capacity building was provided to give the implementers skills in project planning and operation and the proper maintenance of the water supply system and sanitation services. All PWT staff of the 20 provinces were able to attend the training conducted by DILG, while the number of LGU staff (MWT) members required to participate was reduced from five to three staff per municipality, due to financial and manpower constraints on DILG. Description Table 2: Targets versus Achieved Output (Parts B1 and B2) (as of 30 June 2004) Target at Appraisal Revised Target Actual % (of revised target) A. Part B1 (Water Supply ) 1. Shallow Wells 2,500 2,500 1, Deep Wells 2,026 2,000 1, Spring Development 1,600 1,698 1, Rehab (Deep Wells) 2,000 2,000 1, Rehab (Spring Dev.) Subtotal (A) 8,256 8,575 6, B. Part B2 (Sanitation) 1. District Laboratories School Toilets Public Toilets Household Pit Latrines 40,000 91,400 60, Subtotal (B) 40,300 91,816 61, Source: Department of Public Works and Highways. 18. Although DOH reported that 59 district laboratories had been completed, not all of them are operational. Of the 20 water laboratories visited by the PCR Mission in six provinces, only eight were operating. Common issues raised are the (i) unavailability of qualified medical technologist to conduct water analysis, (ii) late delivery of equipment and chemicals, and (iii) lack of power or water supply. C. Project Costs 19. At appraisal, the project cost was estimated at $57.4 million equivalent, with ADB s share estimated at $37.0 million (64%) and the Government s share at $20.4 million (36%). Loan 1440 of $18.5 million was from ADB s ordinary capital resources. Loan 1441, equivalent to $18.5 million, was from ADB s special funds resources (Asian Development Fund). 20. The loan allocation was revised twice to (i) include provision for institutional development, originally envisaged to be entirely funded by the Government, and (ii) increase civil works and equipment categories to finance committed contracts and remaining works. The loan amount was reduced twice due to peso devaluation. The final loan amount was $20.8 million equivalent: Loan 1440 for $9.7 million and Loan 1441 for $11.1 million equivalent. Appendix 3 provides details on loan allocations per category at appraisal and at completion. The actual project cost was $31.3 million equivalent (55% of the appraisal estimate), of which ADB financed $18.6 million (59%) and the Government $12.7 million (41%).

15 5 21. Administration support costs were estimated at $2.7 million. Due to the 17-month delay in loan effectiveness and the 29-month loan extension, the actual administration support costs were $4.3 million, or 160% of the estimate at appraisal. D. Disbursements 22. Loan effectiveness was delayed by more than a year because there was no budget cover for counterpart funding. This delayed the recruitment of consultants to implement the Project. The first disbursement was made on 2 June 1998, when the project implementation consultants were mobilized. There were delays in procuring equipment and materials under the sanitation component due to (i) the reorganization of DOH, which reconstituted the membership of the bids and awards committee, (ii) delays in fund transfers from DPWH to DOH, and (iii) changes in project staff composition. By November 2000, only 15% of the funds had been disbursed against an elapsed time period of 80%. 23. The initial amount of $1 million was established at DPWH, $0.5 million each for the two loans. The midterm review identified the problems experienced in fund transfer from DPWH to DOH. This caused delays in delivering procured equipment and materials. In response, ADB established a separate imprest fund at DOH in early DPWH, DILG, and DOH were constantly urged by ADB to follow up closely with the Department of Budget and Management on the transfer of funds, and with LGUs for the submission of statements of expenditures to allow the timely replenishment of the imprest fund and ensure fast disbursements. 24. The final disbursement was made on 26 May 2004 for the last batch of latrines under the sanitation component. Disbursements at loan closure totaled $18.6 million equivalent, of which 61% was for purchasing equipment and materials and 27% was for civil works. Loan utilization was 89% of the final, reduced loan amount of $20.8 million equivalent. E. Project Schedule 25. The Project was originally planned to be implemented over 5 years from mid-1996 to August 2001 (Appendix 4) (footnote 1). The loan was declared effective only on 7 November 1997 due to lack of budget cover in the Government s annual appropriation. 26. A second delay was encountered in the recruitment of consultants. Project implementation therefore started only in June 1998 after the mobilization of the consultants and the establishment of the project management office (PMO). 27. The Midterm Review Mission 5 of November 2000 found that the overall accomplishment rate of the Project was 11% against an elapsed loan period of 80%. The loan closing date was extended to 31 July 2003 to compensate for the delayed start of the Project. 28. Further delays in implementation necessitated a second extension until 30 April 2004, on condition that no further extensions would be requested. This extension was approved to allow the completion of the Government s ongoing contractual commitments. 5 Wallum, Peter Back-to-Office Report of Midterm Review Mission on Loans 1440/1441(SF)-PHI: Rural Water Supply and Sanitation Sector Project. ADB: Manila. (22 December).

16 6 29. The major causes for the delay in implementation were the (i) lack of counterpart funds, (ii) delayed procurement, (iii) poor coordination of activities, and (iv) institutional and administrative changes within the EA and IAs. F. Implementation Arrangements 30. The EA for this Project was DPWH. Together with the IAs, DILG and DOH, it was responsible for the overall implementation and coordination of the Project through its PMO-WSS. 31. The DPWH was expected to assist with project design and provide construction supervision through the regional director s district engineering offices and municipal engineering offices. 32. DILG was responsible for coordinating and implementing the capacity-building program for LGUs to enhance their ability to assume full responsibility for water and sanitation projects by training PWTs and MWTs. DILG was additionally responsible for implementing the community management training program to help communities organize and prepare for managing their facilities. 33. DOH was responsible for promoting LGU implementation of health and hygiene, as well as for water quality surveillance and control programs. Safe drinking water and personal hygiene were to be promoted through various media. The water quality surveillance and control programs included testing water sources and issuing potability certificates, supported by the construction and equipping of district water laboratories. 34. The mayor, as chief executive of the LGU in municipalities, was responsible for selecting and formulating subproject proposals, as well as their implementation, in coordination with offices of municipal development, municipal health, and the municipal engineer. Subproject proposals were approved at the provincial level by the provincial board, consisting of representatives of the provincial project development office, provincial heath office, and principal engineer s office. 35. The actual mobilization of communities and preparation of subproject proposals was done by barangay councils or the BWSAs that had already been established. The BWSAs were responsible for providing labor and land for constructing the facilities and for their operation and maintenance. 36. Consultants were engaged to support the activities of the PMO and provide assistance in specific matters such as (i) preparing standard designs, (ii) preparing contract packages and documents, (iii) capacity-building programs, and (iv) implementing health and hygiene programs. 37. In general, the implementation arrangements as defined and agreed during appraisal remained unchanged. The implementation arrangements were complex, requiring coordination among three government agencies at three different levels. Weak project coordination, particularly locally, caused delays in implementation and the fragmented, instead of integrated, implementation of the Project. 38. The project design gave nongovernment organizations (NGOs) important roles in (i) community mobilization and training and (ii) monitoring and evaluating subprojects. It was agreed with the Government that DILG would involve NGOs in the community management

17 7 program, but this did not happen due to budget constraints; DILG implemented the program using only government staff. 39. Decentralizing responsibilities for developing water supply and sanitation to autonomous LGUs during project implementation weakened the position of the EA and IAs, as they could not enforce performance targets. 40. Recognizing the need for speedier implementation, the PMO in November 2000 launched a performance-based implementation plan that included reallocating budgets from poor-performing to high-performing provinces. The implementation rate subsequently increased. 41. The EA failed to enhance the existing BME system, which hindered effective project management. G. Conditions and Covenants 42. Of the 24 covenants, 15 are fully complied with, and nine partly so. Appendix 5 gives the status of compliance with loan covenants in detail. 43. Particular Covenants. Of the nine particular covenants, eight were fully complied with. The covenant on sound operation of the facilities was only partly complied with, as not all subproject facilities are operational. 44. Sector Covenants. The covenant pertaining to the Government s undertaking to fully implement RA 6716 (the Accelerated Water Supply Program), 6 was only partly complied with, because BWSA operations remain unsustainable due to uncollected tariffs. The covenant on the availability of funds was also only partly complied with, due to the delays in the release of counterpart funds. The other two sector covenants were complied with. 45. Social Covenants. Of the two social covenants, the covenant on the active encouragement of NGOs and women to participate in the project was partly complied with. While involvement of NGOs did not materialize due to budget constraints, the socioeconomic survey revealed that women were represented on boards as members (30% of the BWSAs), as treasurer (50%), and as secretary (50%). EA reported that no resettlement was required. Required land areas were either public property or donated by private owners to the community. The water laboratories were constructed on governmental hospital premises. All land and riparian rights and privileges required by the Project were provided in a timely manner. The EA was given the right to issue water permits by the National Water Resources Board, through which the riparian rights are regulated. The unrestricted access of waterways was a condition for issuing water permits and acceptance as a subproject under this Project. 46. Financial Covenants. Both financial covenants were partly complied with. There were delays in the submission of audited project accounts and statements by the provinces for lack of institutional capacity to prepare reports and, in some of the provinces, the limited availability of auditors from the Commission on Audit. The Borrower provided 80% of project costs as a grant, though with substantial delays due to the Government s tight fiscal position. 6 The Accelerated Water Supply Program mandated the provision of 100,000 Level I facilities to rural areas and the provision of funds, services, land, and other resources, in addition to the proceeds of the loan.

18 8 47. Other Covenants. Of the seven remaining covenants, four covenants are partly complied, with (i) the submission of the quarterly reports often delayed, (ii) the refinement of the existing BME system complied with only near project completion (serving as a project output rather than as a project management tool), (iii) tariff collection for the maintenance of project facilities and basic accounts by BWSAs not fully implemented, and (iv) some BWSAs failing to maintain basic accounts. H. Consultant Recruitment and Procurement 48. Consultants were engaged by DPWH in accordance with ADB s Guidelines on the Use of Consultants. The contract for project management consultants was signed in January 1998 and the consultants mobilized in June The consultancy contract was amended twice. The first amendment was to include the services of trainers and specialists in community organizing and development. The second amendment was made to allow the consultants to assist remaining project activities during the 9-month loan extension period. The consultants provided 320 person-months of domestic consulting services, compared with 148 person-months of domestic consulting services estimated at appraisal. There was no requirement for international consulting services. 49. All procurement to be financed out of the proceeds of the loan was made in accordance with ADB s Procurement Guidelines. Civil works were awarded through local competitive bidding among pre-qualified contractors in accordance with procedures acceptable to ADB. In cases where the subproject locations were remote and the contract amounts too small to attract competitive bidding, force account (the resources of public agencies) was used by the LGUs. Civil works based on pure contracts accounted for 30% of total works done, force account for 25%, and combined force account and contracts for 45%. 50. Supply contracts for equipment or materials amounting to $500,000 equivalent or more were procured through international competitive bidding, and those of less than the equivalent of $500,000 through international shopping. There were no substantial deviations from supply requirements. I. Performance of Consultants, Contractors, and Suppliers 51. Project management consultants were engaged through local competitive bidding in accordance with ADB s Guidelines on the Use of Consultants. Due to the delay in loan effectiveness, the project management consultants were fielded 19 months after loan approval. This caused significant delay in project activities because the consultants were required to develop the standard WSS designs, prepare contract packages and documents, and provide support to the activities of the project management office. In spite of the delay, once the consultants were fielded, they performed a proactive role in providing support to the PMO for undertaking project activities. The consultants worked well with the staff of the EA and the IAs. The performance of the consultants was satisfactory. 52. The performance of contractors was satisfactory. Generally, facilities were constructed in compliance with the standard designs provided to the LGUs. There were no reports of substantial delays in construction or deviations from standard designs. While water potability is a concern in some subprojects, this is due to poor site identification. 53. In general, equipment was supplied according to the contracts. The performance of suppliers was satisfactory.

19 9 J. Performance of the Borrower and the Executing Agency 54. The performance of the Department of Finance (DOF) as the representative of the Borrower is partly satisfactory. The prolonged delay in loan effectiveness was due to the lack of budget cover for the loan in the Government s appropriations for the year By the time budget cover was provided for in the 1997 appropriations, 15 months had passed. DOF did not exert the required effort to ensure that the loan was provided budget cover upon approval of the loan in DPWH, as the EA, coordinated reasonably well with DILG, DOH, LGUs, and communities to implement the Project. The EA was able to bring the Project to a great number of small communities in remote areas in the 20 poorest provinces. However, the EA should have put more emphasis on developing and using the BME for monitoring and managing the Project, applying the site selection criteria, and strengthening the focus on the integrated approach of providing WSS to selected barangays or communities. Already during the midterm review (October 2000), it was recognized that LGUs lacked the capacity to comply with the reporting requirements of DPWH, causing a delay in the submission of monitoring data required for BME. Following the review, the report forms were simplified, and consultative meetings were held with the LGUs. However, the submission of data remained a problem and DPWH was not able to intensify its efforts to acquire the data due to inadequate government support for training and project management. Consistent application of site criteria and greater focus on the integrated approach would have increased the effectiveness of the Project. The EA s performance was only partly satisfactory. 56. DILG was the IA for the capacity-building and community management programs. The lack of counterpart funds caused considerable delays and prevented the involvement of NGOs, which was identified as essential in the report and recommendation of the President. Furthermore, due to inadequate financial and human resources, the output target for the training components was not met. DILG s performance was only partly satisfactory. 57. DOH was the IA of the HHE and the WQS programs. Regionally, DOH assisted LGUs and communities in the construction of public and household toilet facilities. The May 1998 national elections resulted in the reorganization of DOH, which triggered the reconstitution of the membership of the bids and awards committee and changes in project staff composition. The national sanitation training program for sanitary inspectors in the 20 SRA provinces was conducted, as was the training for medical technologists for the water analysis laboratories. However, the timing of these training programs did not match the construction and establishment of the toilet facilities and water analysis laboratories, so it is unlikely that the programs served their purpose. Most of the medical technologists who were trained have either left government service or moved to a non-sra province. There was no transition program in place to mitigate these departures. As to the implementation of the WQS program, much more needs to be done to institutionalize water sample collection and the issuance of water potability certificates. The sustainability of operations of the water analysis laboratories is a serious concern. DOH s performance was only partly satisfactory. 58. LGUs were responsible for selecting sites, designing subprojects, and selecting suitable technology with the full participation of beneficiary communities. Disagreements among barangay and BWSA officials arose during project implementation, which hampered the growth of BWSA operations and discouraged communities from giving full support and cooperation to their BWSAs. Low rates of tariff collection is a serious issue. Site selection criteria were not

20 10 consistently applied for lack of understanding of the project rationale and its objectives, reducing the effectiveness of the Project. Overall, the performance of LGUs was only partly satisfactory. K. Performance of the Asian Development Bank 59. ADB fielded eight loan review missions and a midterm review mission, involving 336 person-days. The missions were able to highlight urgent issues affecting project implementation and, through their recommendations, helped facilitate subsequent project execution. ADB acted promptly in processing the Government s requests to provide funding for the institutional development component originally planned to receive Government funding. ADB addressed the Government s need to reallocate loan proceeds to meet the project s obligations to contractors. When DOH was experiencing delays in transferring funds from DPWH, ADB set up a separate imprest account allowing DOH to facilitate disbursement. Staff from the EA and DOH participated in ADB-funded procurement seminars to accelerate procurement. While ADB reorganization in 2002 delayed resolution of some procurement issues faced by the Project, the situation lasted only a few months. The performance of ADB was satisfactory. III. EVALUATION OF PERFORMANCE A. Relevance 60. The Project is considered relevant because it is consistent with the Government s development priorities and ADB s Country Strategy and Program (footnote 2). Providing basic services to the poor population is recognized as an essential step in the process of poverty reduction. 61. Focusing on the rural population of the 20 poorest provinces is relevant, as most poverty in the Philippines is rural, with almost three out of four (73%) of the poor residing in rural areas (footnote 4). 62. The design of the Project takes into consideration the lessons learned in previous ADBfinanced rural water supply projects. There was sufficient allocation of resources for capacity building in the agencies involved, not only for implementing this Project, but also for continued development and management of WSS facilities. The issue of the sustainability of project outputs was addressed by formulating a community-based approach with sufficient community consultation and participation to increase community ownership. The criteria for effective site selection were elaborated, and provision was made for water quality testing facilities. B. Effectiveness in Achieving Outcome 63. The outcome of the Project was to provide safe, adequate, and reliable WSS services to selected low-income rural communities in the 20 poorest provinces of the country. The corresponding target was to provide 2 million people, of whom 80% live below poverty line, with safe water by the year The WSS component of the Project was monitored in terms of the number of facilities constructed. No data was collected on the number of beneficiaries and their economic status. 64. The Project design foresaw the implementation of a BME system within 6 months after project start-up. However, only in February 2004 did the PMO produce the first BME report, 7 7 DPWH, DILG, and DOH Benefit Monitoring and Evaluation, RW3SP. Manila.

21 11 which presented valuable information and quantifiable data on the benefits of the Project. The conclusions correspond with the observations made during the PCR field visits. 65. A total of 192 water supply facilities were inspected during BME. This represented about 10% of the facilities that were completed before 21 August Of the inspected facilities, 75% were operational, and the average number of beneficiaries per facility was 135 people. This is substantially less than the projected number of 242 people per facility. 66. Only about 60% of the water supply facilities were actively monitored and disinfected when needed, and about 90% of the facilities provided water 24 hours per day. However, in the perception of nearly all of the local beneficiaries, the facilities provide adequate water and offer health benefits. 67. The sanitation component of the Project consisted of constructing toilet facilities for selected households, schools, and public areas. Although the objective of the Project was an integrated approach to water and sanitation in 3,000 barangays, the sanitary facilities were not necessarily constructed in the same barangays as the water supply facilities. 68. Almost all of the public toilet facilities are operational. In most cases, a small fee is required for using the facility. Some are maintained by a caretaker employed by the municipality or funded directly from the fees. 69. The original design for school toilets as provided in the loan agreement was for separate buildings constructed adjacent to the classrooms. Results of field inspection and monitoring of school toilets constructed under previous projects indicated that facilities with this design were not properly maintained, since responsibility for cleaning the toilets was not clear. DOH, with the assistance of the consultants, revised the school toilet design to a cubicle attached to individual classrooms, complete with a water-sealed toilet bowl and water faucet. 70. The household toilets were popular and well received by the beneficiaries. The main complaint was that not enough toilets were provided. The latrines are well used and maintained. Most beneficiaries have received HHE and are observing basic hygiene. 71. The Project is rated as less effective for the following reasons: (i) only about 75% of the planned water supply facilities were constructed; (ii) not all constructed facilities are operational; 8 (iii) the number of beneficiaries per facility is less than projected; and (iv) the integration of water supply and sanitation facilities was not achieved. C. Efficiency in Achieving Outcome and Outputs 72. The benefits of the Project, as identified at appraisal, were (i) enhanced capacity to implement and manage the WSS sector program and subprojects; (ii) time saved from collecting water, directly benefiting women and children; and (iii) improved health and thus reduced morbidity and mortality rates. Based on a conservative methodology of quantifiable benefits that was not able to incorporate the health benefits, the weighted average economic internal rate of return (EIRR) for eight selected subprojects was estimated at 27%. 73. Evaluation of performance, based on that of individual subprojects, was likewise conducted after project completion to determine the economic viability using the same economic 8 BME shows that, of the 192 facilities, 145 (76%) are operational.

22 12 assumptions as at appraisal. Economic analysis was carried out in another set of eight water supply subprojects to calculate the EIRR. These EIRR results are presented in Table 3 (details of the economic evaluation are shown in Appendix 6). Table 3: Summary of Economic Internal Rate of Return Subproject EIRR (%) 1. Kamog, Sablan, Benguet San Jose, Malitbog, Southern Leyte Ibarra, Maasin City, Southern Leyte Tinabuan, Jordan, Guimaras 3 5. Comian, Nueva Valencia, Guimaras Bulan-bulan, Jordan, Guimaras Locso-on, Borongan, Eastern Samar Salvacion, Sibalom, Antique 53 EIRR = economic internal rate of return. Source: Asian Development Bank. 74. Economic analysis of the subprojects counts the economic cost savings and consumer surplus as the benefit streams, balanced against the investment cost and O&M as the cost streams. The social discount rate used to determine economic viability was 12%. The EIRR of the eight subprojects ranges from 3% to 53% with a weighted average of 27%. Of the eight sample subprojects, Tinabuan was the only one found to be uneconomic. 75. The Project is considered to be less efficient because (i) the water fee is being collected at less than half 9 of the operational water supply facilities, which means that these subprojects generate no revenues to cover O&M and replacement costs; (ii) it was unable to develop a continuous water quality monitoring program and or an integrated approach, which considerably reduced the targeted health benefits; and (iii) implementation was considerably delayed. D. Preliminary Assessment of Sustainability 76. Project design recognized the need for community involvement in selecting and designing subprojects to guarantee sustainability. Effective O&M, including cost recovery, will take place only when the community accepts full ownership of the facility. 77. The sustainability of project outputs was addressed through the incorporation of an elaborate capacity-building program. This program focused on the institutional, technical, and financial aspects of sustaining project outputs. During the midterm review, it became obvious that the training of LGU staff was far behind schedule and that the training program did not cover the relevant areas of project implementation. The reason for the delay was the lack of DILG funds for the training program. A new implementation schedule was agreed, and ADB funds were provided for refresher training. 78. The Project foresaw an essential role for NGOs in mobilizing, organizing, and training the BWSAs. However, DILG decided not to involve NGOs since no funds were available. Consequently, the mobilization and organization of communities trailed the physical construction of the facilities. Due in many cases to time pressure to implement subprojects, no proper community consultation was carried out on project design or site selection. Not all water supply 9 BME shows that, of the 145 operational facilities, 48 (33%) are collecting water fees. The findings of the PCR Mission confirm that the level of collection is low.

Requirements for Old Age Pension (VETERAN)

Requirements for Old Age Pension (VETERAN) Department of National Defense PHILIPPINE VETERANS AFFAIRS OFFICE Camp Gen. Emilio Aguinaldo, Q.C. Requirements for Old Age Pension (VETERAN) 1. Military Service Record from NRD-OTAG with transmittal number

More information

2018 CALENDAR OF INTERNATIONAL/NATIONAL/REGIONAL SCOUTING EVENTS, ACTIVITIES AND OBSERVANCES Theme: Commitment to Excellence

2018 CALENDAR OF INTERNATIONAL/NATIONAL/REGIONAL SCOUTING EVENTS, ACTIVITIES AND OBSERVANCES Theme: Commitment to Excellence 2018 CALENDAR OF INTERNATIONAL/NATIONAL/REGIONAL SCOUTING EVENTS, ACTIVITIES AND OBSERVANCES Theme: Commitment to Excellence JANUARY 01 New Year s Day 04 SLR Council Scout Executives/Officer-in-Charge

More information

PLDT Group and Philippine LGUs. Partners in Digital Nation Building

PLDT Group and Philippine LGUs. Partners in Digital Nation Building PRESENTS PLDT Group and Philippine LGUs Partners in Digital Nation Building Real-time monitoring of vehicle location, status and driver behavior Promote your city s local products in your very own digital

More information

Inter-Agency Task Force on the Harmonization of National Government Performance Monitoring, Information and Reporting Systems

Inter-Agency Task Force on the Harmonization of National Government Performance Monitoring, Information and Reporting Systems 1. Agricultural Credit Policy Council 2. Philippine Fiber Industry Development Authority 3. National Meat Inspection Service 4. Philippine Center for Postharvest Development and Mechanization 5. Government

More information

Inter-Agency Task Force on the Harmonization of National Government Performance Monitoring, Information and Reporting Systems

Inter-Agency Task Force on the Harmonization of National Government Performance Monitoring, Information and Reporting Systems 1. of the President 2. of the Vice President 3. Agricultural Credit Policy Council 4. Bureau of Fisheries and Aquatic Resources 5. National Meat Inspection Service 6. Philippine Center for Postharvest

More information

Nepal: Small Towns Water Supply and Sanitation Sector Project

Nepal: Small Towns Water Supply and Sanitation Sector Project Validation Report Reference Number: PVR 193 Project Number: 31402 Loan Number: 1755(SF) November 2012 Nepal: Small Towns Water Supply and Sanitation Sector Project Independent Evaluation Department ABBREVIATIONS

More information

Sharing the country s conditions and prospects of Construction Market and the Construction Information Use

Sharing the country s conditions and prospects of Construction Market and the Construction Information Use Sharing the country s conditions and prospects of Construction Market and the Construction Information Use Introduction About the Philippines Philippine Road Network Current Road Network Current Investments

More information

FRAMEWORK FINANCING AGREEMENT. (National Highway Development Sector Investment Program Project 1) between ISLAMIC REPUBLIC OF PAKISTAN.

FRAMEWORK FINANCING AGREEMENT. (National Highway Development Sector Investment Program Project 1) between ISLAMIC REPUBLIC OF PAKISTAN. FRAMEWORK FINANCING AGREEMENT (National Highway Development Sector Investment Program Project 1) between ISLAMIC REPUBLIC OF PAKISTAN and ASIAN DEVELOPMENT BANK DATED 29 October 2005 FRAMEWORK FINANCING

More information

Papua New Guinea: Implementation of the Electricity Industry Policy

Papua New Guinea: Implementation of the Electricity Industry Policy Technical Assistance Report Project Number: 46012 December 2012 Papua New Guinea: Implementation of the Electricity Industry Policy The views expressed herein are those of the consultant and do not necessarily

More information

TESDA Assessment Centers (as of November 2013) AUTOMOTIVE SERVICING

TESDA Assessment Centers (as of November 2013) AUTOMOTIVE SERVICING Region Assessment Center Address Contact No. Qualification Title Date Accredited Expiration Date Automotive Servicing NC I Regional Training Center -Baguio 132 Magsaysay Drive, Baguio City 424-8724 Automotive

More information

Local Government Unit Private Infrastructure Project Development Facility (Loan 1729-PHI) in the Philippines

Local Government Unit Private Infrastructure Project Development Facility (Loan 1729-PHI) in the Philippines Project Completion Report PCR: PHI 32485 Local Government Unit Private Infrastructure Project Development Facility (Loan 1729-PHI) in the Philippines June 2005 CURRENCY EQUIVALENTS Currency Unit peso/s

More information

Completion Report. Pakistan: Balochistan Devolved Social Services Program

Completion Report. Pakistan: Balochistan Devolved Social Services Program Completion Report Project Number: 37218 Loan Numbers: 2202, 2203, and 2204 Grant Number: 0028 December 2011 Pakistan: Balochistan Devolved Social Services Program CURRENCY EQUIVALENTS Currency Unit Pakistan

More information

LIST OF PAL TICKET OFFICES

LIST OF PAL TICKET OFFICES LIST OF PAL TICKET OFFICES Ticket Address Contact Number/s Hours METRO MANILA Binondo Ticket G/F 460 Pacific Center Bldg., Quintin Paredes St., Binondo, Tel: (632) 742-8246 Fax: (632) 742-6563 Sundays

More information

The Future of LGU Public-Private Partnerships for the People (P4) and Reclamation

The Future of LGU Public-Private Partnerships for the People (P4) and Reclamation The Future of LGU Public-Private Partnerships for the People (P4) and Reclamation Alberto C. Agra Chairman, Philippine Reclamation Authority Certified PPP and Regulation Specialist TM Adviser to DILG on

More information

Public Storm Warning Signal. PSWS Luzon Visayas Mindanao

Public Storm Warning Signal. PSWS Luzon Visayas Mindanao Public Storm Warning Signal PSWS Luzon Visayas Mindanao #3 (winds of 101-185 kph is expected in at least 24 hours) Catanduanes #2 (winds of 61-100 kph is expected in at least 24 hours) Camarines Norte,

More information

Papua New Guinea: Support for Water and Sanitation Sector Management

Papua New Guinea: Support for Water and Sanitation Sector Management Technical Assistance Report Project Number: 49454-001 Capacity Development Technical Assistance (CDTA) February 2017 Papua New Guinea: Support for Water and Sanitation Sector Management This document is

More information

Philippines: Health Sector Development Program

Philippines: Health Sector Development Program Completion Report Project Number: 33278 Loan Number: 2136/2137 August 2014 Philippines: Health Sector Development Program This document is being disclosed to the public in accordance with ADB's Public

More information

Pakistan: Punjab Community Water Supply and Sanitation Sector Project

Pakistan: Punjab Community Water Supply and Sanitation Sector Project Validation Report Reference Number: PCV: PAK 2009-48 Project Number: 35314 Loan Number: 1950-PAK(SF) December 2009 Pakistan: Punjab Community Water Supply and Sanitation Sector Project Independent Evaluation

More information

People s Republic of China: Strengthening the Role of E-Commerce in Poverty Reduction in Southwestern Mountainous Areas in Chongqing

People s Republic of China: Strengthening the Role of E-Commerce in Poverty Reduction in Southwestern Mountainous Areas in Chongqing Technical Assistance Report Project Number: 51022-001 Knowledge and Support Technical Assistance (KSTA) December 2017 People s Republic of China: Strengthening the Role of E-Commerce in Poverty Reduction

More information

Case study: System of households water use subsidies in Chile.

Case study: System of households water use subsidies in Chile. Case study: System of households water use subsidies in Chile. 1. Description In Chile the privatization of public water companies during the 70 s and 80 s resulted in increased tariffs. As a consequence,

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE Appendix 3 11 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The government has identified the priority areas to be covered under the ensuing project. A PPTA is necessary to provide sound

More information

Completion Report. Project Number: Loan Number: 2449-INO(SF) October Indonesia: Rural Infrastructure Support to the PNPM Mandiri Project

Completion Report. Project Number: Loan Number: 2449-INO(SF) October Indonesia: Rural Infrastructure Support to the PNPM Mandiri Project Completion Report Project Number: 40247 Loan Number: 2449-INO(SF) October 2012 Indonesia: Rural Infrastructure Support to the PNPM Mandiri Project CURRENCY EQUIVALENTS Currency Unit rupiah (Rp) At Appraisal

More information

Global Partnership on Output-based Aid Grant Agreement

Global Partnership on Output-based Aid Grant Agreement Public Disclosure Authorized GPOBA GRANT NUMBER TF010757 Public Disclosure Authorized Public Disclosure Authorized Global Partnership on Output-based Aid Grant Agreement (Philippines Public Health Project)

More information

FACTORS AFFECTING THE DEMAND FOR HEALTH SERVICES IN THE PHILIPPINES WORKING PAPER SERIES NO

FACTORS AFFECTING THE DEMAND FOR HEALTH SERVICES IN THE PHILIPPINES WORKING PAPER SERIES NO FACTORS AFFECTING THE DEMAND FOR HEALTH SERVICES IN THE PHILIPPINES Panfila Ching WORKING PAPER SERIES NO. 92-06 June 1992 Philippine Institute for Development Studies TABLE O F CONTENTS I. Introduction...

More information

What the DOH is doing for Rare Disease and its Role in the Proposed Act

What the DOH is doing for Rare Disease and its Role in the Proposed Act What the DOH is doing for Rare Disease and its Role in the Proposed Act Anthony P. Calibo MD, DPPS Officicer-in-Charge Child Health Development Divison Newborn Care Program Manager, Family Health Office

More information

Regional: Supporting the Cities Development Initiative for Asia

Regional: Supporting the Cities Development Initiative for Asia Technical Assistance Report Project Number: 47285 Regional Capacity Development Technical Assistance (R-CDTA) November 2013 Regional: Supporting the Cities Development Initiative for Asia (Cofinanced by

More information

Pacific Urban Development Investment Planning and Capacity Development Facility

Pacific Urban Development Investment Planning and Capacity Development Facility Technical Assistance Report Project Number: 51175-001 Transaction Technical Assistance Facility (F-TRTA) July 2017 Pacific Urban Development Investment Planning and Capacity Development Facility This document

More information

Completion Report. Project Number: Loan Number: 2230-PAK October Pakistan: Rural Enterprise Modernization Project

Completion Report. Project Number: Loan Number: 2230-PAK October Pakistan: Rural Enterprise Modernization Project Completion Report Project Number: 38447 Loan Number: 2230-PAK October 2010 Pakistan: Rural Enterprise Modernization Project CURRENCY EQUIVALENTS Currency Unit Pakistan rupee/s (PRe/PRs) At Appraisal At

More information

OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject.

OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. OM Section E2/BP Page 1 of 3 OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. A. Introduction JAPAN FUND

More information

Lao People s Democratic Republic: Strengthening Urban Water Supply Regulation

Lao People s Democratic Republic: Strengthening Urban Water Supply Regulation Technical Assistance Report Project Number: 45298 Capacity Development Technical Assistance (CDTA) November 2011 Lao People s Democratic Republic: Strengthening Urban Water Supply Regulation The views

More information

REPUBLIC OF THE PHILIPPINES DEPARTMENT OF FINANCE BUREAU OF INTERNAL REVENUE Quezon City. June 30, 2003 REVENUE MEMORANDUM ORDER NO.

REPUBLIC OF THE PHILIPPINES DEPARTMENT OF FINANCE BUREAU OF INTERNAL REVENUE Quezon City. June 30, 2003 REVENUE MEMORANDUM ORDER NO. REPUBLIC OF THE PHILIPPINES DEPARTMENT OF FINANCE BUREAU OF INTERNAL REVENUE Quezon City June 30, 2003 REVENUE MEMORANDUM ORDER NO. 26-2003 Subject: Prescribing Policies and Procedures on the On-Call Repair

More information

GRANT AGREEMENT (ADB Strategic Climate Fund) (Greater Mekong Subregion Biodiversity Conservation Corridors Project Additional Financing)

GRANT AGREEMENT (ADB Strategic Climate Fund) (Greater Mekong Subregion Biodiversity Conservation Corridors Project Additional Financing) GRANT NUMBER 0426-CAM (SCF) GRANT AGREEMENT (ADB Strategic Climate Fund) (Greater Mekong Subregion Biodiversity Conservation Corridors Project Additional Financing) (Cambodia Component) between KINGDOM

More information

Trust Fund Grant Agreement

Trust Fund Grant Agreement Public Disclosure Authorized CONFORMED COPY GRANT NUMBER TF057872-GZ Public Disclosure Authorized Trust Fund Grant Agreement (Palestinian NGO-III Project) Public Disclosure Authorized between INTERNATIONAL

More information

India: Madhya Pradesh State Roads Sector Project II

India: Madhya Pradesh State Roads Sector Project II Completion Report Project Number: 37328-013 Loan Number: 2330 September 2015 India: Madhya Pradesh State Roads Sector Project II This document is being disclosed to the public in accordance with ADB s

More information

Technical Assistance to the Republic of Philippines for the Support for Health Sector Reform

Technical Assistance to the Republic of Philippines for the Support for Health Sector Reform Technical Assistance TAR: PHI 39066 Technical Assistance to the Republic of Philippines for the Support for Health Sector Reform September 2005 CURRENCY EQUIVALENTS (as of 5 August 2005) Currency Unit

More information

People s Republic of China: Strategy for Inclusive and Green Development of Small Cities, Towns, and Villages in Jiangxi Province

People s Republic of China: Strategy for Inclusive and Green Development of Small Cities, Towns, and Villages in Jiangxi Province Technical Assistance Report Project Number: 49024-001 Policy and Advisory Technical Assistance (PATA) December 2015 People s Republic of China: Strategy for Inclusive and Green Development of Small Cities,

More information

Project Administration Instructions

Project Administration Instructions Project Administration Instructions PAI 1.01 Page 1 of 5 INITIAL PROJECT ADMINISTRATION ACTIVITIES A. Introduction 1. The Project Administration Instructions (PAIs) outline ADB s policies and procedures

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK PPA: PAK 26373 PROJECT PERFORMANCE AUDIT REPORT ON THE POPULATION PROJECT (Loan 1277-PAK[SF]) IN PAKISTAN December 2003 CURRENCY EQUIVALENTS Currency Unit Pakistan rupee/s (PRe/PRs)

More information

Investing in the Philippinesʼ Tourism Development. Atty.. GUILLER B. ASIDO Tourism Infrastructure and Enterprise Zone Authority

Investing in the Philippinesʼ Tourism Development. Atty.. GUILLER B. ASIDO Tourism Infrastructure and Enterprise Zone Authority Investing in the Philippinesʼ Tourism Development Atty.. GUILLER B. ASIDO Tourism Infrastructure and Enterprise Zone Authority PHILIPPINE TOURISM 1 The Story of Philippine Tourism. Tourism is emerging

More information

LGU Access to Official Development Assistance (ODA): Status, Issues, and Concerns

LGU Access to Official Development Assistance (ODA): Status, Issues, and Concerns Philippine Institute for Development Studies Surian sa mga Pag-aaral Pangkaunlaran ng Pilipinas LGU Access to Official Development Assistance (ODA): Status, Issues, and Concerns Alex B. Brillantes Jr.,

More information

PPIAF Assistance in Nepal

PPIAF Assistance in Nepal Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PPIAF Assistance in Nepal June 2012 The Federal Democratic Republic of Nepal (Nepal)

More information

Uzbekistan: Woman and Child Health Development Project

Uzbekistan: Woman and Child Health Development Project Validation Report Reference Number: PVR-331 Project Number: 36509 Loan Number: 2090 September 2014 Uzbekistan: Woman and Child Health Development Project Independent Evaluation Department ABBREVIATIONS

More information

Viet Nam: Second Small and Medium-Sized Enterprises Development Program

Viet Nam: Second Small and Medium-Sized Enterprises Development Program Validation Report December 2017 Viet Nam: Second Small and Medium-Sized Enterprises Development Program Reference Number: PVR-544 Program Numbers: 41360-013 and 41360-014 Loan Numbers: 2680 and 3050 ABBREVIATIONS

More information

Public Disclosure Copy. Implementation Status & Results Report Global Partnership for Education Grant for Basic Education Project (P117662)

Public Disclosure Copy. Implementation Status & Results Report Global Partnership for Education Grant for Basic Education Project (P117662) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized AFRICA Liberia Education Global Practice Recipient Executed Activities Specific Investment

More information

FOR OFFICIAL USE ONLY INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT PROJECT APPRAISAL DOCUMENT ON A PROPOSED LOAN

FOR OFFICIAL USE ONLY INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT PROJECT APPRAISAL DOCUMENT ON A PROPOSED LOAN Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY Report No: PAD1278 Public Disclosure Authorized INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT PROJECT APPRAISAL DOCUMENT

More information

Republic of Indonesia: Water Supply and Sanitation Sector Development Project

Republic of Indonesia: Water Supply and Sanitation Sector Development Project Technical Assistance Report Project Number: 43304-022 Capacity Development Technical Assistance (CDTA) November 2011 Republic of Indonesia: Water Supply and Sanitation Sector Development Project (Financed

More information

ARTICLE I. Grant Regulations; Definitions

ARTICLE I. Grant Regulations; Definitions 3 ARTICLE I Grant Regulations; Definitions Section 1.01. All provisions of the Special Operations Grant Regulations of ADB, dated 7 February 2005 (the Grant Regulations ), are hereby made applicable to

More information

EU Grant Agreement DOC8UMEW. Public Disclosure Authorized GRANT NUMBER TF0A2379. Public Disclosure Authorized. (Access to Sustainable Energy Project)

EU Grant Agreement DOC8UMEW. Public Disclosure Authorized GRANT NUMBER TF0A2379. Public Disclosure Authorized. (Access to Sustainable Energy Project) Public Disclosure Authorized DOC8UMEW GRANT NUMBER TF0A2379 Public Disclosure Authorized Public Disclosure Authorized EU Grant Agreement (Access to Sustainable Energy Project) between INTERNATIONAL BANK

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE Appendix 9 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. There is an urgent need to support the government in the development of the urban water supply and sanitation sector in Cambodia

More information

Mainstreaming Low Carbon Path in the Transport Sector in the National and Local Levels

Mainstreaming Low Carbon Path in the Transport Sector in the National and Local Levels Mainstreaming Low Carbon Path in the Transport Sector in the National and Local Levels By: ANNELI R. LONTOC (Undersecretary, Department of Transportation and Communications) Research Fellow/ Lecturer,

More information

India: Agribusiness Infrastructure Development Investment Program (Tranche 2)

India: Agribusiness Infrastructure Development Investment Program (Tranche 2) Completion Report Project Number: 37091-033 Loan Number: 2837 August 2017 India: Agribusiness Infrastructure Development Investment Program (Tranche 2) This document is being disclosed to the public in

More information

The World Bank Iraq Trust Fund Newsletter

The World Bank Iraq Trust Fund Newsletter The World Bank Iraq Trust Fund Newsletter July 2006 Volume 1, Issue 8 1. Improving Education in Iraq Despite massive degradation and deterioration as a result of three major wars and over a decade of sanctions,

More information

Honduras has achieved a reasonable level of access

Honduras has achieved a reasonable level of access Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Output-Based Aid in Honduras: An OBA Facility for the Water and Sanitation Sector Honduras

More information

IDP PROTECTION ASSESSMENT REPORT

IDP PROTECTION ASSESSMENT REPORT IDP PROTECTION ASSESSMENT REPORT Armed Confrontations and Displacement in Marawi (AFP vs Maute) Issue No. 03 dated 14 July 2017 Incident Date: 23 May 2017 INCIDENT BACKGROUND CURRENT SITUATION (Updates

More information

SECOND MEETING GMS. Urban Development Working Group. 4 5 July 2018 Manila, Philippines

SECOND MEETING GMS. Urban Development Working Group. 4 5 July 2018 Manila, Philippines GMS 4 5 July 2018 Manila, Philippines Working Group Section 2: Review of Concept and Approach to the Ongoing and Planned ipsum GMS que Corridor moluptam Towns sum Development que moluptam Projects sum

More information

SDG Sanitation Donor Group

SDG Sanitation Donor Group National Policy and Financing for Sanitation Examples from Asian Countries National Sanitation Conference (KSN) 2 8 December 2009 Jakarta Indonesia SDG Sanitation Donor Group Outline Success factors for

More information

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB7052

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB7052 Project Name Region Country Sector(s) Lending Instrument Project ID Borrower(s) Implementing Agency Environmental Category Date PID Prepared Estimated Date of Appraisal Completion Estimated Date of Board

More information

Republic of Tajikistan Dushanbe-Uzbekistan Border Road Improvement Project

Republic of Tajikistan Dushanbe-Uzbekistan Border Road Improvement Project PD 0002-TJK June 6, 2016 PROJECT DOCUMENT Republic of Tajikistan Dushanbe-Uzbekistan Border Road Improvement Project This document has a restricted distribution and may be used by recipients only in performance

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE 12 Appendix 5 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The project preparatory technical assistance (PPTA) is needed for preparing the investment program and conducting technical, economic,

More information

Global Partnership on Output-based Aid Grant Agreement

Global Partnership on Output-based Aid Grant Agreement Public Disclosure Authorized CONFORMED COPY GPOBA GRANT NUMBER TF096551-BD Public Disclosure Authorized Global Partnership on Output-based Aid Grant Agreement (Rural Electrification and Renewable Energy

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. A project preparatory technical assistance (PPTA) is required to support the Ministry of New and Renewable Energy (MNRE) and Solar Energy Corporation

More information

GRANT AGREEMENT (Special Operations) (Hairatan to Mazar-e-Sharif Railway Project) between ISLAMIC REPUBLIC OF AFGHANISTAN. and ASIAN DEVELOPMENT BANK

GRANT AGREEMENT (Special Operations) (Hairatan to Mazar-e-Sharif Railway Project) between ISLAMIC REPUBLIC OF AFGHANISTAN. and ASIAN DEVELOPMENT BANK GRANT NUMBER 0161-AFG(SF) GRANT AGREEMENT (Special Operations) (Hairatan to Mazar-e-Sharif Railway Project) between ISLAMIC REPUBLIC OF AFGHANISTAN and ASIAN DEVELOPMENT BANK DATED 30 SEPTEMBER 2009 GAS:

More information

NCMB Directory. Search for 2013 Outstanding LMC Awards For Industrial Peace. Rationale. Objective. Mechanics

NCMB Directory. Search for 2013 Outstanding LMC Awards For Industrial Peace. Rationale. Objective. Mechanics Rationale Search for 2013 Outstanding LMC Awards For Industrial Peace The Outstanding LMC Awards started in 1998 and it continued to benchmark innovative practices and success stories among companies which

More information

THE PHILIPPINES: TYPHOONS

THE PHILIPPINES: TYPHOONS THE PHILIPPINES: TYPHOONS 7 January 2005 The Federation s mission is to improve the lives of vulnerable people by mobilizing the power of humanity. It is the world s largest humanitarian organization and

More information

Trust Fund Grant Agreement

Trust Fund Grant Agreement Public Disclosure Authorized CONFORMED COPY GRANT NUMBER TF094521 GZ Public Disclosure Authorized Trust Fund Grant Agreement (Additional Financing for the Palestinian NGO-III Project) Public Disclosure

More information

Completion Report. Project Number: Loan Number: 1538 March Bangladesh: Urban Primary Health Care Project

Completion Report. Project Number: Loan Number: 1538 March Bangladesh: Urban Primary Health Care Project Completion Report Project Number: 29033 Number: 1538 March 2007 Bangladesh: Urban Primary Health Care Project CURRENCY EQUIVALENTS Currency Unit taka (Tk) At Appraisal At Project Completion (15 July 1997

More information

Financing Agreement CONFORMED COPY CREDIT NUMBER 4201-ET. (Rural Capacity Building Project) between FEDERAL DEMOCRATIC REPUBLIC OF ETHIOPIA.

Financing Agreement CONFORMED COPY CREDIT NUMBER 4201-ET. (Rural Capacity Building Project) between FEDERAL DEMOCRATIC REPUBLIC OF ETHIOPIA. Public Disclosure Authorized CONFORMED COPY CREDIT NUMBER 4201-ET Public Disclosure Authorized Financing Agreement (Rural Capacity Building Project) Public Disclosure Authorized between FEDERAL DEMOCRATIC

More information

DOCUMENTS GPOBA GRANT NUMBER TF Global Partnership on Output-based Aid. Grant Agreement

DOCUMENTS GPOBA GRANT NUMBER TF Global Partnership on Output-based Aid. Grant Agreement GPOBA GRANT NUMBER TF092629 DOCUMENTS Global Partnership on Output-based Aid Grant Agreement (Extending Telecommunications in Rural Indonesia Project) between REPUBLIC OF INDONESIA and INTERNATIONAL BANK

More information

(Financed by the Japan Fund for Poverty Reduction)

(Financed by the Japan Fund for Poverty Reduction) Technical Assistance Report Project Number: 49276-001 Capacity Development Technical Assistance (CDTA) December 2015 India: Supporting Rajasthan s Productive Clusters in the Delhi Mumbai Industrial Corridor

More information

Report and Recommendation of the President to the Board of Directors

Report and Recommendation of the President to the Board of Directors Report and Recommendation of the President to the Board of Directors Project Number: 44304-01 October 2010 Proposed Loan and Administration of Grant Papua New Guinea: Microfinance Expansion Project CURRENCY

More information

Request for Proposals. Endline Evaluation for WaterCredit Project: Safe Water and Sanitation in the Philippines. November 3, 2017 (revised)

Request for Proposals. Endline Evaluation for WaterCredit Project: Safe Water and Sanitation in the Philippines. November 3, 2017 (revised) Request for Proposals Endline Evaluation for WaterCredit Project: Safe Water and Sanitation in the Philippines November 3, 2017 (revised) Response deadline: November 13, 2017 by 5:00pm PHT 1. General instructions

More information

Grant Assistance Republic of the Philippines: Southern Leyte Landslide Disaster Assistance Project (Financed by the Japan Fund for Poverty Reduction)

Grant Assistance Republic of the Philippines: Southern Leyte Landslide Disaster Assistance Project (Financed by the Japan Fund for Poverty Reduction) Grant Assistance Report Project Number: 40217 November 2006 Grant Assistance Republic of the Philippines: Southern Leyte Landslide Disaster Assistance Project (Financed by the Japan Fund for Poverty Reduction)

More information

Rajasthan Urban Sector Development Program

Rajasthan Urban Sector Development Program India: Rajasthan Urban Sector Development Program Project Name Rajasthan Urban Sector Development Program Project Number 42267-026 Country Project Status Project Type / Modality of Assistance Source of

More information

(Energy Development and Access Project) between INTERNATIONAL DEVELOPMENT ASSOCIATION. and ARB APEX BANK LIMITED

(Energy Development and Access Project) between INTERNATIONAL DEVELOPMENT ASSOCIATION. and ARB APEX BANK LIMITED Public Disclosure Authorized CONFORMED COPY CREDIT NUMBER 4356-GH Public Disclosure Authorized Project Agreement (Energy Development and Access Project) between Public Disclosure Authorized INTERNATIONAL

More information

On May 12, 2009, RA 9593 otherwise known as the Tourism Act of 2009 was signed into law providing for, among others, the reorganization of the PTA as

On May 12, 2009, RA 9593 otherwise known as the Tourism Act of 2009 was signed into law providing for, among others, the reorganization of the PTA as On May 12, 2009, RA 9593 otherwise known as the Tourism Act of 2009 was signed into law providing for, among others, the reorganization of the PTA as the Tourism Infrastructure and Enterprise Zone Authority

More information

Microfinance for Rural Piped Water Services in Kenya

Microfinance for Rural Piped Water Services in Kenya Policy Note No.1 Microfinance for Rural Piped Water Services in Kenya Using an Output-based Aid Approach for Leveraging and Increasing Sustainability by Meera Mehta and Kameel Virjee The water sector in

More information

Developing Cross-Border Economic Zones between the People's Republic of China and Viet Nam

Developing Cross-Border Economic Zones between the People's Republic of China and Viet Nam Technical Assistance Report Project Number: 43077-01 Regional Policy and Advisory Technical Assistance (R-PATA) September 2009 Developing Cross-Border Economic Zones between the People's Republic of China

More information

Lao People s Democratic Republic and Viet Nam: Greater Mekong Subregion: Sustainable Tourism Development Project

Lao People s Democratic Republic and Viet Nam: Greater Mekong Subregion: Sustainable Tourism Development Project Validation Report December 2017 Lao People s Democratic Republic and Viet Nam: Greater Mekong Subregion: Sustainable Tourism Development Project Reference Number: PVR-542 Project Number: 38015-013 Loan

More information

Project Administration Manual. Islamic Republic of Afghanistan: Road Asset Management Project

Project Administration Manual. Islamic Republic of Afghanistan: Road Asset Management Project Project Administration Manual Project Number: 50062-001 Grant Numbers: {GXXXX; GXXXX} Draft as of October 2016 Islamic Republic of Afghanistan: Road Asset Management Project CONTENTS ABBREVIATIONS I. PROJECT

More information

Republic of Indonesia: Scaling Up Energy Efficiency

Republic of Indonesia: Scaling Up Energy Efficiency Sustainable and Inclusive Energy Program (Subprogram 2) (RRP INO 49043-002) Technical Assistance Report Project Number: 49043-006 Transaction Technical Assistance (TRTA) August 2017 Republic of Indonesia:

More information

This document is being disclosed to the public in accordance with ADB s Public Communications Policy 2011.

This document is being disclosed to the public in accordance with ADB s Public Communications Policy 2011. Technical Assistance Report Project Number: 51336-001 Knowledge and Support Technical Assistance (KSTA) February 2018 Capacity Building Support for Asia-Pacific Economic Cooperation Financial Regulators

More information

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY Report No: RES22379 Public Disclosure Authorized Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING

More information

Rural Community Finance Project. Negotiated financing agreement

Rural Community Finance Project. Negotiated financing agreement Document: EB 2015/LOT/P.37/Sup.1 Date: 17 December 2015 Distribution: Public Original: English E Republic of Liberia Rural Community Finance Project Negotiated financing agreement For: Information Negotiated

More information

Output-based Aid: extending water and sanitation services to the poor in periurban

Output-based Aid: extending water and sanitation services to the poor in periurban Output-based Aid: extending water and sanitation services to the poor in periurban Morocco Xavier Chauvot de Beauchêne, World Bank Type of tool: Output-Based Aid Issue: cities Location: Casablanca, Tangier

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK PROJECT ADMINISTRATION MEMORANDUM FOR THE JFPR GRANT ASSISTANCE TO THE LAO PEOPLE S DEMOCRATIC REPUBLIC FOR COMMUNITY ACTION FOR PREVENTING HIV/AIDS 1/ (JFPR: REG-9006) DRAFT 29

More information

Philippines: ASEM Country Strategy Note April 2003

Philippines: ASEM Country Strategy Note April 2003 Philippines: ASEM Country Strategy Note April 2003 1. The ASEM Trust Fund (TF) has played a critical role in supporting government activities to mitigate the adverse effprilects of the Asian financial

More information

Kyrgyz Republic: Investment Climate Improvement Program

Kyrgyz Republic: Investment Climate Improvement Program Validation Report Reference Number: PVR-423 Project Numbers: 41544-022, 41544-082, 41544-084 Grant Numbers: 0120, 0319, and 0393 October 2015 Kyrgyz Republic: Investment Climate Improvement Program Independent

More information

The Rural Household Infrastructure Grant

The Rural Household Infrastructure Grant The Rural Household Infrastructure Grant Presentation to the SC: Appropriations and PC: Human Settlements Presenters: Marissa Moore & Wendy Fanoe National Treasury 17 August 2012 Contents Constitutional

More information

Shrinking the Map of Malaria thru Private-Public Partnerships

Shrinking the Map of Malaria thru Private-Public Partnerships Shrinking the Map of Malaria thru Private-Public Partnerships Background Pilipinas Shell Foundation, Inc. (PSFI) prides itself of 30 years of experience in managing social development programs of national

More information

33 C. General Conference 33rd session, Paris C/74 11 October 2005 Original: English. Item 5.20 of the agenda

33 C. General Conference 33rd session, Paris C/74 11 October 2005 Original: English. Item 5.20 of the agenda U General Conference 33rd session, Paris 2005 33 C 33 C/74 11 October 2005 Original: English Item 5.20 of the agenda PROPOSAL FOR THE ESTABLISHMENT OF THE REGIONAL CENTRE ON URBAN WATER MANAGEMENT FOR

More information

ALABAMA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT PERMITS AND SERVICES DIVISION STATE REVOLVING FUND PROGRAMS DIVISION

ALABAMA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT PERMITS AND SERVICES DIVISION STATE REVOLVING FUND PROGRAMS DIVISION ALABAMA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT PERMITS AND SERVICES DIVISION STATE REVOLVING FUND PROGRAMS DIVISION 335 11 1400 Coliseum Boulevard Montgomery, Alabama 36110 CITE AS ADEM Admin. Code r.

More information

Grant Agreement for Islamic Republic of Pakistan's Readiness Preparation Proposal Readiness Fund of the FCPF Grant No. TF018696

Grant Agreement for Islamic Republic of Pakistan's Readiness Preparation Proposal Readiness Fund of the FCPF Grant No. TF018696 The World Bank INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT INTERNATIONAL DEVELOPMENT ASSOCIATION 1818 H Street N.W. Washington, D.C. 20433 U.S.A. (202) 473-1000 Cable Address: INTBAFRAD Cable

More information

Madhya Pradesh Integrated Urban Sanitation Programme Guidelines, 2009

Madhya Pradesh Integrated Urban Sanitation Programme Guidelines, 2009 Madhya Pradesh Integrated Urban Sanitation Programme Guidelines, 2009 This document is available at ielrc.org/content/e0925.pdf Note: This document is put online by the International Environmental Law

More information

Global Environment Facility Trust Fund Grant Agreement

Global Environment Facility Trust Fund Grant Agreement CONFORMED COPY GEF TRUST FUND GRANT NUMBER TF099857 Global Environment Facility Trust Fund Grant Agreement (Nyika Transfrontier Conservation Area Project) between REPUBLIC OF MALAWI and INTERNATIONAL BANK

More information

VILLAGE OF FOX CROSSING REQUEST FOR PROPOSAL FOR COMPREHENSIVE PLAN

VILLAGE OF FOX CROSSING REQUEST FOR PROPOSAL FOR COMPREHENSIVE PLAN VILLAGE OF FOX CROSSING REQUEST FOR PROPOSAL FOR COMPREHENSIVE PLAN Issuing Department: Community Development Department Village of Fox Crossing 2000 Municipal Dr. Project Officer: George L. Dearborn Jr.,

More information

Global Financing Facility Grant Agreement

Global Financing Facility Grant Agreement Public Disclosure Authorized OFFICIAL DOCUMENTS GFF GRANT NUMBER TF0A2561 Public Disclosure Authorized Global Financing Facility Grant Agreement (Transforming Health Systems for Universal Care Project)

More information

United Nations Peace Building Fund Grant Agreement

United Nations Peace Building Fund Grant Agreement Public Disclosure Authorized OFFICIAL DOCUMENTS Public Disclosure Authorized GRANT NUMBER TF018255 United Nations Peace Building Fund Grant Agreement (Additional Financing for the Productive Social Safety

More information

ASIAN DEVELOPMENT BANK PCR:BAN 18036

ASIAN DEVELOPMENT BANK PCR:BAN 18036 ASIAN DEVELOPMENT BANK PCR:BAN 18036 PROJECT COMPLETION REPORT ON THE SECOND HEALTH AND FAMILY PLANNING SERVICES PROJECT (Loan No. 1074-BAN[SF]) IN BANGLADESH July 2001 CURRENCY EQUIVALENTS Currency Unit

More information

Maldives: Tsunami Emergency Assistance Project

Maldives: Tsunami Emergency Assistance Project Completion Report Project Number: 39099 Loan Number: 2160-MLD(SF) Grant Number: 0001-MLD December 2009 Maldives: Tsunami Emergency Assistance Project CURRENCY EQUIVALENTS Currency Unit rufiyaa (Rf) At

More information

Nigeria: Second National Urban Water Sector Reform Project. Terms of Reference for Non-Governmental Organization Consultancy

Nigeria: Second National Urban Water Sector Reform Project. Terms of Reference for Non-Governmental Organization Consultancy Nigeria: Second National Urban Water Sector Reform Project Terms of Reference for Non-Governmental Organization Consultancy I. Background 1. In order to support the Nigerian Government to provide potable

More information