Attachment 5 Section 26.45: Overall DBE Three-Year Goal Methodology Fiscal Years

Size: px
Start display at page:

Download "Attachment 5 Section 26.45: Overall DBE Three-Year Goal Methodology Fiscal Years"

Transcription

1 Attachment 5 Section 26.45: Overall DBE Three-Year Methodology Fiscal Years Name of Recipient: Port of Skagit, owner of Skagit Regional Airport Period: FY October 1, 2017 through September 30, 2020 DOT-assisted contract amount: FY ,111 FY FY ,334 Total 944,445 Overall Three-Year : No three-year goal was developed due to the project schedule, and the lack of projects during Instead, we have set annual goals for the two years where federally funded project work is anticipated to occur: Year % 2019 None % Total dollar amount to be expended on DBE s: 22,064 [ % x DOT-assisted amount] Number and Type of Contracts that the airport anticipates awarding: Contracts Fiscal Year #1 1. Master Plan Update - 611,111 Contracts Fiscal Year #2 1. None Contracts Fiscal Year #3 1. Environmental Assessment - 333,334 The local market area includes four counties: Island, Skagit, Snohomish and Whatcom. The market area was determined based upon the location of previous bidders. This is also the are from which a substantial majority of the contractors and subcontractors come from and the area in which the airport spends a substantial majority of its contracting dollars. Port of Skagit DBE i Skagit Regional Airport

2 Step (c) Actual relative availability of DBE s The base figure for the relative availability of DBEs was calculated as follows: - The project work was divided into the appropriate NAICS classifications as shown in Table 1 below. Table 1 PORT OF SKAGIT, SKAGIT REGIONAL AIRPORT FY 2018 Project Description: Master Plan Update Work Description NAICS Code Cost (Federal only) % of Project Engineering , % FY2018 Total: 611, FY 2019 Project Description: NONE Work Description NAICS Code Cost (Federal only) % of Project FY2019 Total: - FY 2020 Project Description: Environmental Assessment Work Description NAICS Code Cost (Federal only) % of Project Environmental Consulting , % FY2020 Total: 333, The total number of qualified firms for each category of work was determined by using the U.S. Census Bureau data from 2015, the most current year available. This data was located at the following website: - Certified DBE firms for these NAICS categories were found by using the State of Washington s online database from the Office of Minority and Women s Business Enterprises (OMWBE). This data was located at the following website: - For each NAICS category, DBE firms were then evaluated based on location and work capabilities. DBE firms were considered ready, willing and able if they met the following conditions: Firm location is within the previously defined market area; Port of Skagit DBE ii Skagit Regional Airport

3 Work capabilities include those necessary for this project. It is assumed that firms will be capable of performing the work included in the category under which they are listed and certified. - The DBE goal for each NAICS work classification was then calculated by dividing the number of ready, willing, and able DBE firms by the total number of ready, willing and able firms. - Lastly, an average DBE goal was then calculated for the entire project, using cost-based weighting. The cost-weighted DBE goal is the percentage of work expected to be performed by each NAICS DBE category divided by the total project cost. Calculations for these figures were derived from our Engineer s preliminary cost estimate for work on the project(s). Table 2 below illustrates these calculations. Step 1 resulted in the following annual goals: FY %, FY %, and FY % Step (d) Adjustments to Step 1 base and weighted figures After calculating a weighted base figure of the relative availability of DBEs, evidence was examined to determine what adjustment (if any) was needed to arrive at the overall goal. a. Past Participation There have been no recent projects of similar character at Skagit Regional Airport that had DBE participation. Based on past participation there is no data to support an adjustment to the weighted base figure. b. Disparity Study There are no disparity studies available for review. The Port will continue to contact FAA, and Washington Department of Transportation and others for records of any recently completed disparity studies. No adjustments will be made on this basis. c. Work Item Analysis Several NAICS codes were overly broad, given the scope of the work anticipated. The DBEs in the market area were reviewed to determine their capability to perform the work items included in these projects. The quantity of able DBEs was adjusted accordingly and the cost estimates for this work were used to calculate a percentage of the total work and is reflected in the DBE goal set in Step 1. d. Other factors The Port has contacted the following business advocacy agencies: Associated Builders and Contractors of Western Washington Association of Washington State Hispanic Chambers of Commerce Bellingham Whatcom Chamber of Commerce Burlington Chamber of Commerce Economic Alliance Snohomish Economic Development Alliance of Skagit Entrepreneurial Institute of Washington Federal Highway Administration, Washington Division Greater Bothell Chamber of Commerce Greater Marysville Tulalip Chamber Lynnwood Chamber of Commerce Mt Vernon Chamber of Commerce National Association of Minority Contractors, WA State Northwest Mountain Minority Supplier Development Council Oak Harbor Chamber of Commerce Port of Skagit DBE iii Skagit Regional Airport

4 Sedro-Woolley Chamber of Commerce Small Business Development Center at Edmonds Community College Small Business Development Center at Western Washington University Snohomish Chamber of Commerce Veteran Business Outreach Center WA DOT Aviation Division, Construction Division, and Tribal Liaison Office WA Secretary of Transportation Washington Asphalt Pavement Association Women s Business Centers All comments received will be addressed and the goal adjusted if applicable. See Consultation: Section (g) (1) below. No evidence was found that would support any adjustment to the Step 1 goal, therefore the Port of Skagit will adopt the goals established in Step 1: FY %, FY %, and FY % Table 2 Percent DBE Calculation - Skagit Regional Airport, Skagit, Burlington, WA includes the following Washington counties: Island, Skagit, Snohomish, Whatcom DBE Buisnesses in the survey area were calculated using data from the The Office of Minority and Women's Business Enterprises available at: Data was obtained on 6/6/2017. Total established firm data was taken from the U.S. Census Bureau website available at data was used for the calculations as it is the most recent available. FY 2018 NAICS Codes from 2015 Census % of Total Project Work Project Work Elements Island Skagit Snohomish Whatcom Totals Base Weighted TotalDBETotalDBE Total DBE TotalDBE Total DBE % Engineering % 1.43% 100.0% % 1.43% FY NO PROJECTS ANTICIPATED % of NAICS Total Codes from Project Work Elements Project 2015 Census Work Island Skagit Snohomish Whatcom Totals TotalDBETotalDBE Total DBE TotalDBE Total DBE % Base Weighted FY 2020 NAICS Codes from 2015 Census % of Total Project Work Project Work Elements Island Skagit Snohomish Whatcom Totals Base Weighted TotalDBETotalDBE Total DBE TotalDBE Total DBE % Environmental Consulting % 4.00% % 4.00% Port of Skagit DBE iv Skagit Regional Airport

5 Basic Calculation Total DBE's/All Firms The Annual Weighted Calculation shown above will be used for our for each applicable year. Breakout of Estimated Race and Gender Neutral (RN) and Race and Gender Conscious (RC) Participation (b) (1-9) The Port anticipates meeting 100% of its goal by using Race Neutral means of facilitating DBE participation, including but not limited to: - Arranging solicitations, times for the presentation of bids, quantities, specifications, and delivery schedules in ways that facilitate DBE and other small businesses participation; - Encouraging prime contractors to subcontract portions of work they might otherwise perform with their own forces; - Ensuring the inclusion of DBEs and other small businesses on recipient mailing lists for bidders; - Advising prime contractors of the State of Washington online DBE directory and website; - Providing assistance in overcoming limitations such as inability to obtain bonding or financing; The Port of Skagit does not have a history of DBE participation or over-achievement of goals to reference and expects to obtain its DBE participation through the use of annual overall goals and communication of opportunities for DBEs. Consistent with key court rulings 1 and USDOT official guidance, we are applying the entire goal to race-neutral participation. Public Participation Fiscal Year Overall DBEs Available / 280 = 1.43% 2019 N / A / 50 = 4.00% Weighted Calculation [%work(dbe/all Firms) + %work(dbe/all Firms)] X 100 Fiscal Year Annual Weighted Calculation % 2019 N/A % Total Anticipated DBE dollars: Consultation: Section 26.45(g)(1). DBE 8, , , In establishing the overall goal, the Port provided for consultation and publication. This included consultation with minority, women s and general contractor groups, community organizations, and other officials or organizations which could be expected to have information concerning the availability of disadvantaged and non-disadvantaged businesses, the effects of discrimination on opportunities for DBEs, and the Port s efforts to establish a level playing field for the participation of DBEs. 1 Western States Paving Co. v. Washington State DOT, 407 F.3d 983, (9 th Cir. 2005), cert. denied, 546 U.S (2006) Until further notice, federally-funded contracts can be awarded without the lowest responsive bidder meeting the goal or demonstrating good faith effort to meet the goal. Port of Skagit DBE v Skagit Regional Airport

6 The consultation included a scheduled, direct, interactive exchange (e.g., a face-to-face meeting, video conference, teleconference) with as many interested stakeholders as possible focused on obtaining information relevant to the Port s goal-setting process, and it occurred before we were required to submit our goal methodology to the operating administration for review pursuant to paragraph (f) of this section. Notwithstanding paragraph (f)(4) of this section, we will not implement our proposed goal until we have complied with this requirement. The Port contacted the agencies listed in Step 2 above with an invitation to attend a consultation meeting at the office of the Port: Meeting date and time: September 11, 2017 at 11:00 am Location of meeting: Skagit Regional Airport, Airport Drive, Burlington, WA Discussion included, but was not limited to, the following items: Review of the Program document and its parts Review of the goals and the methodology used to determine them Past participation of Disadvantaged Business Enterprises Availability of DBE businesses for utilization in projects Solicit input from participants on ways to increase DBE participation and remove barriers to participation Comments from participants included the following concerns: - Contracting opportunities are not easily found; too many data sources. - Previous barriers to participation included capacity, finance (cash flow), bonding, workforce challenges due to large firms - Explicit discrimination in the past has included: stereotypes, assumptions that DBEs are less qualified, perceived manipulations by political insiders - Suggestions to resolve barriers included: Partnering, transparency, small business taskforces, smaller procurement opportunities - Work with organizations like the Entrepreneurial Institute of WA that provide support to DBEs - Notices could all be centralized with the state agencies that do the certification Discussion included interest in the upcoming/ongoing disparity study being performed in Washington State. It was recognized that the results may change the experience for future contracting opportunities. The Port will use these comments, concerns and suggestions to make improvements to the processes we use for procurement on future projects. Upon evaluation, we determined no evidence was found in this consultation meeting to indicate any adjustment to the goal was needed. Public Notice The Port published a notice of the proposed overall goal in the Skagit Valley Herald and the Daily Journal of Commerce, informing the public that the proposed goal and its rationale are available for inspection during normal business hours at the Port office for 30 days following the date of the notice, and informing the public that the Port and DOT would accept comments on the goals for 45 days from the date of the notice. Port of Skagit DBE vi Skagit Regional Airport

7 SAMPLE PUBLIC NOTICE The PORT OF SKAGIT has established a Disadvantaged Business Enterprise (DBE) program in accordance with regulations of the U.S. Department of Transportation, 49 CFR Part 26. The PORT OF SKAGIT has established DBE annual overall goals of 1.43% for FY 2018, and 4.0% for FT 2020, of the federal financial assistance it will receive for improvements to SKAGIT REGIONAL AIRPORT. The PORT OF SKAGIT estimates it will meet these entire goals through race neutral means. NOTE: No goal has been set for 2019 as there are no projects anticipated that year. The Program and rationale used in developing the goal are available for review at: Port of Skagit Administrative Office Airport Drive P. O. Box 348 Burlington, WA (360) The program and rationale will be available for review for 30 days following the date of this publication. The PORT OF SKAGIT and FAA Civil Rights Office will accept comments on the program and rationale for 45 days following the date of this publication. Comments should be sent to: Sara Young, DBELO Port of Skagit Airport Drive PO Box 348 Burlington, WA saray@portofskagit.com OR FAA Civil Rights Office Attn: Sonia Cruz PO Box Los Angeles, CA Sonia.Cruz@faa.gov The Port will submit its three-year goal to DOT as required by the set schedule. Our overall goal submission to DOT includes the following summary of information and comments received during this public participation process and our responses, if any. Summary: No comments were received as a result of the public notice of our three-year goal and its methodology. Contract s The Port will not use contract goals to meet any portion of the overall goal that the recipient does not project being able to meet using RN means. Please refer to in this program document for additional information. Port of Skagit DBE vii Skagit Regional Airport

TRANSIT JOINT POWERS AUTHORITY FOR MERCED COUNTY

TRANSIT JOINT POWERS AUTHORITY FOR MERCED COUNTY TRANSIT JOINT POWERS AUTHORITY FOR MERCED COUNTY Federal Transit Administration (FTA) Overall DBE Goal Setting Methodology FFY 2018 FFY 2020 Submitted in fulfillment of: Title 49 Code of Federal Regulations

More information

Sandpoint Airport. FY Overall Goal Amendment to the Disadvantaged Business Enterprise (DBE) Program

Sandpoint Airport. FY Overall Goal Amendment to the Disadvantaged Business Enterprise (DBE) Program Sandpoint Airport FY 2018-2020 Overall Goal Amendment to the Disadvantaged Business Enterprise () Program Table of Contents OVERALL GOALS ( 26.45)... 2 AMOUNT OF GOAL FY 2018-2020 IMPROVEMENTS... 2 METHOD...

More information

City of Houston Office of Business Opportunity

City of Houston Office of Business Opportunity City of Houston Office of Business Opportunity Proposed Goal for the Participation of Disadvantaged Business Enterprises in Department of Transportation Funded Contracts Federal Fiscal Years 2017-2019

More information

HILLSBOROUGH COUNTY AVIATION AUTHORITY THREE YEAR OVERALL DISADVANTAGED BUSINESS ENTERPRISE GOAL Federal Fiscal Years 2017, 2018 and 2019

HILLSBOROUGH COUNTY AVIATION AUTHORITY THREE YEAR OVERALL DISADVANTAGED BUSINESS ENTERPRISE GOAL Federal Fiscal Years 2017, 2018 and 2019 I. Introduction HILLSBOROUGH COUNTY AVIATION AUTHORITY THREE YEAR OVERALL DISADVANTAGED BUSINESS ENTERPRISE GOAL Federal Fiscal Years 2017, 2018 and 2019 The United States Congress has determined that

More information

The Division expects to let the following FTA/ USDOT-assisted projects in FFYs :

The Division expects to let the following FTA/ USDOT-assisted projects in FFYs : Suffolk County Disadvantaged Business Enterprise (DBE) Overall Goal and Goal Setting Methodology for Federal Transit Administration Assisted Contracts FFY 2017-2019 Amount of goal The Suffolk County Department

More information

NEW ORLEANS AVIATION BOARD (NOAB) DISADVANTAGED BUSINESS ENTERPRISE (DBE) PROGRAM Goal Setting Methodology and Calculations

NEW ORLEANS AVIATION BOARD (NOAB) DISADVANTAGED BUSINESS ENTERPRISE (DBE) PROGRAM Goal Setting Methodology and Calculations NEW ORLEANS AVIATION BOARD (NOAB) DISADVANTAGED BUSINESS ENTERPRISE (DBE) PROGRAM Goal Setting Methodology and Calculations Goal Overview Federal Fiscal Year 2011 (October 1, 2010 to September 30, 2011)

More information

AIRPORT CONCESSIONS DISADVANTAGED BUSINESS ENTERPRISE (ACDBE) PROGRAM

AIRPORT CONCESSIONS DISADVANTAGED BUSINESS ENTERPRISE (ACDBE) PROGRAM AIRPORT CONCESSIONS DISADVANTAGED BUSINESS ENTERPRISE (ACDBE) PROGRAM Non-Car Rental GOAL SETTING METHODOLOGY FFY 2017-2018-2019 49 CFR Part 23 DATED: September 29, 2017 Goal effective October 1, 2016

More information

Disadvantaged Business Enterprise Program and Triennial DBE Goal Setting Methodology and Rationale

Disadvantaged Business Enterprise Program and Triennial DBE Goal Setting Methodology and Rationale Disadvantaged Business Enterprise Program and Triennial DBE Goal Setting Methodology and Rationale Kenn Hardin Senior Manager Civil Rights Division RTD Small Business Office August 14, 2013 Agenda Introductions

More information

Memphis International Airport

Memphis International Airport FY 2017 - FY 2019 DISADVANTAGED BUSINESS ENTERPRISE (DBE) PROGRAM METHODOLOGY for Memphis-Shelby County Airport Authority Memphis International Airport Memphis, Tennessee July 2016 METHODOLOGY for Establishing

More information

Solano County Transit (SolTrans) Overall Disadvantaged Business Enterprise (DBE) Goal FFY through FFY

Solano County Transit (SolTrans) Overall Disadvantaged Business Enterprise (DBE) Goal FFY through FFY Solano County Transit (SolTrans) Overall Disadvantaged Business Enterprise (DBE) Goal FFY 2016 17 through FFY 2018 19 Summary In accordance with the requirements of 49 C.F.R. Part 26 (Participation by

More information

Santa Clara Valley Transportation Authority Disadvantaged Business Enterprise (DBE) Program

Santa Clara Valley Transportation Authority Disadvantaged Business Enterprise (DBE) Program Santa Clara Valley Transportation Authority Disadvantaged Business Enterprise (DBE) Program Three-Year Overall Goal and Methodology Report For Federal Fiscal Years 2017 2019 I. Goal Setting Methodology

More information

August 9, Re: DBE Program Triennial Goal Concurrence - Recipient ID #1674. Dear Mr. Smith:

August 9, Re: DBE Program Triennial Goal Concurrence - Recipient ID #1674. Dear Mr. Smith: U.S. Department of Transportation Federal Transit Administration REGION IX Arizona, California, Hawaii, Nevada, Guam American Samoa, Northern Mariana Islands 201 Mission Street Suite 1650 San Francisco,

More information

ATTACHMENT 5. Section 26.45: Overall DBE Three-Year Goal Methodology

ATTACHMENT 5. Section 26.45: Overall DBE Three-Year Goal Methodology ATTACHMENT 5 Section 26.45: Overall DBE Three-Year Goal Methodology Name of Recipient: Ontario International Airport Authority (OIAA), owner of Ontario International Airport (ONT) Goal Period: FY-2017-2018-2019

More information

APPENDIX A. Definitions of Terms

APPENDIX A. Definitions of Terms APPENDIX A. Definitions of Terms Appendix A defines terms that are useful to understanding the 2017 Los Angeles Metropolitan Transportation Authority (Metro) Disparity Study report. The following definitions

More information

DISADVANTAGED BUSINESS ENTERPRISE (DBE) PROGRAM

DISADVANTAGED BUSINESS ENTERPRISE (DBE) PROGRAM DISADVANTAGED BUSINESS ENTERPRISE (DBE) PROGRAM Updated Port of Seattle Office of Social Responsibility 2711 Alaskan Way Seattle, WA 98121 Port of Seattle Disadvantaged Business Enterprise (DBE) Program

More information

Port Small Business Development Program

Port Small Business Development Program Port Small Business Development Program April 11, 2013 Angela Watkins Small Business Development Program Manager 1 Purpose The purpose of the Port small business development program is to enhance the opportunity

More information

FEDERAL TRANSIT ADMINISTRATION DISADVANTAGED BUSINESS ENTERPRISE OVERALL GOAL APPROVE PROPOSED AMENDMENT TO DBE OVERALL GOAL

FEDERAL TRANSIT ADMINISTRATION DISADVANTAGED BUSINESS ENTERPRISE OVERALL GOAL APPROVE PROPOSED AMENDMENT TO DBE OVERALL GOAL 61 One Gateway Plaza Los Angeles, CA 90012-2952 2 13.922.2000 Tel metro. net EXECUTIVE MANAGEMENT COMMITTEE MARCH 21, 2013 SUBJECT: ACTION: FEDERAL TRANSIT ADMINISTRATION DISADVANTAGED BUSINESS ENTERPRISE

More information

Disadvantaged Business Enterprise (DBE) Program for Federally-Assisted Projects. Federal Fiscal Years

Disadvantaged Business Enterprise (DBE) Program for Federally-Assisted Projects. Federal Fiscal Years JE Disadvantaged Business Enterprise (DBE) Program for Federally-Assisted Projects Federal Fiscal Years 2016-2018 In Compliance With Title 49 Part 26 of the Code of Federal Regulations (49 CFR 26) December

More information

The airport s non-rental car concession opportunities are detailed below.

The airport s non-rental car concession opportunities are detailed below. LAFAYETTE AIRPORT COMMISSION (LAC) AIRPORT CONCESSIONS DISADVANTAGED BUSINESS ENTERPRISE (ACDBE) PROGRAM Non-Car Rental Goal Setting Methodology and Calculations Federal Fiscal Years 2017, 2018 and 2019

More information

AIRPORT CONCESSION DISADVANTAGED BUSINESS ENTERPRISE PLAN. CITY OF PORTLAND, MAINE, dba PORTLAND INTERNATIONAL JETPORT (PWM)

AIRPORT CONCESSION DISADVANTAGED BUSINESS ENTERPRISE PLAN. CITY OF PORTLAND, MAINE, dba PORTLAND INTERNATIONAL JETPORT (PWM) AIRPORT CONCESSION DISADVANTAGED BUSINESS ENTERPRISE PLAN CITY OF PORTLAND, MAINE, dba PORTLAND INTERNATIONAL JETPORT (PWM) Goals - FAA FISCAL YEAR 2015 TABLE OF CONTENTS I. OBJECTIVES AND POLICY STATEMENT

More information

Florida Department of Transportation (FDOT) Business Participation Plan FY 13/14

Florida Department of Transportation (FDOT) Business Participation Plan FY 13/14 (FDOT) FY 13/14 1. Mission, Vision, and Statement of Commitment for Enhancing Supplier Diversity FDOT is responsible for the state highway systems and public transportation systems including air, transit,

More information

LOWELL REGIONAL TRANSIT AUTHORITY

LOWELL REGIONAL TRANSIT AUTHORITY LOWELL REGIONAL TRANSIT AUTHORITY DISADVANTAGED BUSINESS ENTERPRISE GOAL SETTING METHODOLOGY FFY 2016-2018 October 2015 LOWELL REGIONAL TRANSIT AUTHORITY Disadvantaged Business Enterprise (DBE) Program

More information

ACI-NA SMALL AIRPORTS CONFERENCE FAA CIVIL RIGHTS - DBE REGULATORY UPDATE. Federal Aviation Administration

ACI-NA SMALL AIRPORTS CONFERENCE FAA CIVIL RIGHTS - DBE REGULATORY UPDATE. Federal Aviation Administration ACI-NA SMALL AIRPORTS CONFERENCE FAA CIVIL RIGHTS - DBE REGULATORY UPDATE Presented to: 2011 Small Airports Conference By: Wilbur Barham Director, National Airports Civil Rights Policy and Compliance Date:

More information

Disadvantaged Business Enterprise (DBE) Program and Goals for LSCOG

Disadvantaged Business Enterprise (DBE) Program and Goals for LSCOG Disadvantaged Business Enterprise (DBE) Program and Goals for LSCOG Lower Savannah Council of Governments has an overall goal of DBE participation for the three federal fiscal years of 2017-2019 (beginning

More information

AIRPORT CONCESSION DISADVANTAGED BUSINESS ENTERPRISE (ACDBE)

AIRPORT CONCESSION DISADVANTAGED BUSINESS ENTERPRISE (ACDBE) CITY OF BILLINGS LOGAN INTERNATIONAL AIRPORT AIRPORT CONCESSION DISADVANTAGED BUSINESS ENTERPRISE (ACDBE) PROGRAM NOVEMBER 2015 SUBPART A GENERAL REQUIREMENTS Section 23.1 Objectives The objectives are

More information

NDOT Civil Rights DBE Program Small Business Element

NDOT Civil Rights DBE Program Small Business Element NDOT Civil Rights DBE Program Small Business Element The DBE program improvements regulations that became effective on February 28, 2011, require federal funds recipients such as NDOT must include an SBE

More information

DISADVANTAGED BUSINESS ENTERPRISE RACE-NEUTRAL IMPLEMENTATION AGREEMENT FOR LOCAL AGENCIES

DISADVANTAGED BUSINESS ENTERPRISE RACE-NEUTRAL IMPLEMENTATION AGREEMENT FOR LOCAL AGENCIES DISADVANTAGED BUSINESS ENTERPRISE RACE-NEUTRAL IMPLEMENTATION AGREEMENT FOR LOCAL AGENCIES 1 of 7 DISADVANTAGED BUSINESS ENTERPRISE RACE-NEUTRAL IMPLEMENTATION AGREEMENT For the County of San Mateo, hereinafter

More information

KNOXVILLE KNOX COUNTY METROPOLITAN PLANNING COMMISSION DEPARTMENT OF TRANSPORTATION DBE PROGRAM DISADVANTAGE BUSINESS ENTERPRISE PLAN FY 2012 FY 2014

KNOXVILLE KNOX COUNTY METROPOLITAN PLANNING COMMISSION DEPARTMENT OF TRANSPORTATION DBE PROGRAM DISADVANTAGE BUSINESS ENTERPRISE PLAN FY 2012 FY 2014 KNOXVILLE KNOX COUNTY METROPOLITAN PLANNING COMMISSION DEPARTMENT OF TRANSPORTATION DBE PROGRAM DISADVANTAGE BUSINESS ENTERPRISE PLAN FY 2012 FY 2014 DRAFT 6/13/11 NOTICE Knoxville Knox County Metropolitan

More information

CITY OF SAN ANTONIO AVIATION DEPARTMENT 49 CFR PARTS 26 & 23 DBE AND SBEDA PROGRAMS OVERVIEW

CITY OF SAN ANTONIO AVIATION DEPARTMENT 49 CFR PARTS 26 & 23 DBE AND SBEDA PROGRAMS OVERVIEW CITY OF SAN ANTONIO AVIATION DEPARTMENT 49 CFR PARTS 26 & 23 DBE AND SBEDA PROGRAMS OVERVIEW January 11, 2017 BACKGROUND San Antonio Airport System San Antonio Airport System is composed of the San Antonio

More information

Update on the 2007 Disparity Study February 2011

Update on the 2007 Disparity Study February 2011 Background Update on the 2007 February 2011 In May 2005, the U.S. Ninth Circuit Court ruled that a state department of transportation could not have a race-conscious disadvantaged business program without

More information

Port of Portland FY11-13 Disadvantaged Business Enterprise (DBE) Goal

Port of Portland FY11-13 Disadvantaged Business Enterprise (DBE) Goal Port of FY11-13 Disadvantaged Business Enterprise (DBE) Goal During Federal Fiscal Years FY11, FY12, FY13, October 1, 2010 September 30, 2013, the Port of plans to solicit bids/proposals for the following

More information

LOUIS ARMSTRONG NEW ORLEANS INTERNATIONAL AIRPORT AIRPORT CONCESSIONS DISADVANTAGED BUSINESS ENTERPRISES GOAL SETTING METHODOLOGY

LOUIS ARMSTRONG NEW ORLEANS INTERNATIONAL AIRPORT AIRPORT CONCESSIONS DISADVANTAGED BUSINESS ENTERPRISES GOAL SETTING METHODOLOGY LOUIS ARMSTRONG NEW ORLEANS INTERNATIONAL AIRPORT AIRPORT CONCESSIONS DISADVANTAGED BUSINESS ENTERPRISES GOAL SETTING METHODOLOGY FEDERAL FISCAL YEARS 2014 2016 1 NEW ORLEANS AVIATION BOARD (NOAB) AIRPORT

More information

MUNICIPALITY OF ANCHORAGE DISADVANTAGED BUSINESS ENTERPRISE (DBE) PROGRAM 49 CFR 26

MUNICIPALITY OF ANCHORAGE DISADVANTAGED BUSINESS ENTERPRISE (DBE) PROGRAM 49 CFR 26 MUNICIPALITY OF ANCHORAGE DISADVANTAGED BUSINESS ENTERPRISE (DBE) PROGRAM 49 CFR 26 FOR Projects assisted with funds from the federal Department of Transportation (DOT) including Federal Transit Administration

More information

Disadvantaged Business Enterprise Plan (DBE) For Projects Funded Through the Federal Transit Administration (FTA) FY to FY

Disadvantaged Business Enterprise Plan (DBE) For Projects Funded Through the Federal Transit Administration (FTA) FY to FY Disadvantaged Business Enterprise Plan (DBE) For Projects Funded Through the Federal Transit Administration (FTA) FY 2016-17 to FY 2018-19 TABLE OF CONTENTS 1. GENERAL REQUIREMENTS a. Objectives...4 b.

More information

Membrane Pre-Selection Request For Proposal

Membrane Pre-Selection Request For Proposal Membrane Pre-Selection Request For Proposal City of San Luis Obispo Water Resource Recovery Facility Project Mandatory Pre-proposal Conference - July 7, 2017 Water Resource Recovery Facility Project Community

More information

PROCEDURE Metropolitan Council Underutilized Business (MCUB) Program

PROCEDURE Metropolitan Council Underutilized Business (MCUB) Program PROCEDURE PROCEDURE Metropolitan Council Underutilized Business (MCUB) Program Section/Number: 3-4-6c Total Pages: 3 Dept. Responsible: ODEOOffice of Equal Opportunity Effective Date: 5/7/121/21/2016 Special

More information

Disparity Study Action Plan June 10, 2009 Recommendation: 10-1 Emerging Small Business (ESB) Program Action: Impact: Timeline:

Disparity Study Action Plan June 10, 2009 Recommendation: 10-1 Emerging Small Business (ESB) Program Action: Impact: Timeline: 10-1 Emerging Small Business (ESB) Program - The Port should consider expanding its ESB program. First, broadening the definition of a small business to include other certified small businesses. Second,

More information

Marin County Transit District Overall Disadvantaged Business Enterprise (DBE) Goal Federal Fiscal Years

Marin County Transit District Overall Disadvantaged Business Enterprise (DBE) Goal Federal Fiscal Years Marin County Transit District Overall Disadvantaged Business Enterprise (DBE) Goal Federal Fiscal Years 2017-19 1 Marin Transit Overall Disadvantaged Business Enterprise (DBE) Goal for Federal Fiscal Years

More information

ONTARIO INTERNATIONAL AIRPORT

ONTARIO INTERNATIONAL AIRPORT ONTARIO INTERNATIONAL AIRPORT AIRPORT CONCESSION DISADVANTAGED BUSINESS ENTERPRISE (ACDBE) PROGRAM ONTARIO INTERNATIONAL AIRPORT AUTHORITY 1923 E. Avion Street Ontario, CA 91761 Phone (909) 544-5300 TDD

More information

BUSINESS DIVERSITY OUTREACH PROGRAM

BUSINESS DIVERSITY OUTREACH PROGRAM BUSINESS DIVERSITY OUTREACH PROGRAM December 14, 2011 OVERVIEW OF DPS BUSINESS DIVERSITY OUTREACH PROGRAM The DPS Business Diversity Program was started in 1999 to outreach to minority, women owned and

More information

C (Procedure) Small, Minority, Women and Veteran Owned Business Enterprise Program PURPOSE DEFINITIONS

C (Procedure) Small, Minority, Women and Veteran Owned Business Enterprise Program PURPOSE DEFINITIONS PURPOSE Alamo Colleges District encourages the use of Small, Minority, Women and/or Veteran Owned Business Enterprises (SMWVBEs) as herein below defined to assist in the implementation of this procedure

More information

SUBCONTRACTING ON CDOT CONSTRUCTION PROJECTS Ramp Up Ridgway!

SUBCONTRACTING ON CDOT CONSTRUCTION PROJECTS Ramp Up Ridgway! SUBCONTRACTING ON CDOT CONSTRUCTION PROJECTS Ramp Up Ridgway! Connect2DOT Colorado Small Business Development Center Network (SBDC) program funded by CDOT Free training, consulting, and resources for small

More information

UNION COUNTY MINORITY AND SMALL BUSINESS GUIDELINES AND OUTREACH PLAN

UNION COUNTY MINORITY AND SMALL BUSINESS GUIDELINES AND OUTREACH PLAN UNION COUNTY MINORITY AND SMALL BUSINESS GUIDELINES AND OUTREACH PLAN TABLE OF CONTENTS Definitions. 1 Responsibilities 3 Dispute Procedures... 7 Minority Business Construction Contract Provisions. 8 Minimum

More information

Disadvantaged Business Enterprise Policy and Program

Disadvantaged Business Enterprise Policy and Program Disadvantaged Business Enterprise Policy and Program Prepared by Regional Planning Commission Jefferson, Orleans, Plaquemines, St. Bernard and St. Tammany Parishes August, 2010 Contents Page Policy Statement...

More information

City and County of Denver International Airport. Airport Concession Disadvantaged Business Enterprise Program. Table of Contents

City and County of Denver International Airport. Airport Concession Disadvantaged Business Enterprise Program. Table of Contents City and County of Denver International Airport Airport Concession Disadvantaged Business Enterprise Program Table of Contents Policy Statement SUBPART A Section 23.1 Section 23.3 Section 23.5 Section

More information

Port of Portland Small Business Program FFY16

Port of Portland Small Business Program FFY16 Port of Portland Small Business Program FFY16 June 21, 2017 Kimberly Mitchell-Phillips Small Business Development Program Manager 1 Small Business Development Program MWVESB Program ACDBE Program Small

More information

RATIONALE AND METHODOLOGY FOR AN OVERALL PROJECT-SPECIFIC GOAL FOR DBE PARTICIPATION IN THE METROPOLITAN WASHINGTON AIRPORTS AUTHORITY

RATIONALE AND METHODOLOGY FOR AN OVERALL PROJECT-SPECIFIC GOAL FOR DBE PARTICIPATION IN THE METROPOLITAN WASHINGTON AIRPORTS AUTHORITY RATIONALE AND METHODOLOGY FOR AN OVERALL PROJECT-SPECIFIC GOAL FOR DBE PARTICIPATION IN THE METROPOLITAN WASHINGTON AIRPORTS AUTHORITY DULLES CORRIDOR METRORAIL - PROJECT PHASE 2 AUGUST 2012 (Revised August

More information

Fort Bend Independent School District. Small Business Enterprise Program Procedures

Fort Bend Independent School District. Small Business Enterprise Program Procedures Fort Bend Independent School District Small Business Enterprise Program Procedures Spring 2015 TABLE OF CONTENTS I. Summary Of Fort Bend Independent School District s Small Business Enterprise Program

More information

Historically Underutilized Business (HUB) Strategic Plan

Historically Underutilized Business (HUB) Strategic Plan The University of Texas MD Anderson Cancer Center Historically Underutilized Business (HUB) Strategic Plan Fiscal Years 2011 2012 Prepared June 2010 page 1 of 7 EXTERNAL AND INTERNAL ASSESSMENT The University

More information

DBE/Small Business Workshop. June 12, 2015

DBE/Small Business Workshop. June 12, 2015 DBE/Small Business Workshop June 12, 2015 Learning Objectives Benefits Purpose Eligibility Criteria Procurement Forecasts SunLine s Procurement Process Fostering Small Business What are the benefits of

More information

Small Business Enterprise Program Participation Plan

Small Business Enterprise Program Participation Plan EXHIBIT H Small Business Enterprise Program Participation Plan Version 5.11.2015 www.transportation.ohio.gov ODOT is an Equal Opportunity Employer and Provider of Services TABLE OF CONTENTS I. PURPOSE...

More information

CITY OF FRESNO AIRPORTS DEPARTMENT REQUEST FOR QUALIFICATIONS (RFQ) FOR CONSULTING SERVICES FRESNO YOSEMITE INTERNATIONAL AIRPORT

CITY OF FRESNO AIRPORTS DEPARTMENT REQUEST FOR QUALIFICATIONS (RFQ) FOR CONSULTING SERVICES FRESNO YOSEMITE INTERNATIONAL AIRPORT CITY OF FRESNO AIRPORTS DEPARTMENT REQUEST FOR QUALIFICATIONS (RFQ) FOR CONSULTING SERVICES FRESNO YOSEMITE INTERNATIONAL AIRPORT Residential Sound Insulation Program A. PROGRAM NARRATIVE The City of Fresno

More information

ABC S of DBE & ACDBE Programs

ABC S of DBE & ACDBE Programs ABC S of DBE & ACDBE Programs Project Take Off: Community Partnerships and Economic Growth Conference Presented to: By: Broward County Aviation Department Anthony W. Brown, FAA Date: Presentation Overview

More information

MASTER SUBCONTRACTING PLAN FOR DEPARTMENT OF DEFENSE CONTRACTS AND SUBCONTRACTS

MASTER SUBCONTRACTING PLAN FOR DEPARTMENT OF DEFENSE CONTRACTS AND SUBCONTRACTS Memorandum of Agreement Regarding the MASTER SUBCONTRACTING PLAN FOR DEPARTMENT OF DEFENSE CONTRACTS AND SUBCONTRACTS Small Business (SB), Small Disadvantaged Business (SDB), Women-Owned Small Business

More information

The DBE Program is an outreach, education, and objectives program designed to increase the participation of DBEs in the CWSRF Program.

The DBE Program is an outreach, education, and objectives program designed to increase the participation of DBEs in the CWSRF Program. California State Water Resources Control Board Division of Financial Assistance (Division) 1001 I Street Sacramento, California 95814 (916) 341-5700 FAX (916) 341-5707 Mailing Address: P. O. Box 944212

More information

SCDOT MINORITY BUSINESS ENTERPRISE UTILIZATION PLAN

SCDOT MINORITY BUSINESS ENTERPRISE UTILIZATION PLAN SCDOT MINORITY BUSINESS ENTERPRISE UTILIZATION PLAN 2016-2017 INTRODUCTION ON JULY 8, 1981, GOVERNOR RICHARD W. RILEY APPROVED THE SOUTH CAROLINA CONSOLIDATED PROCUREMENT CODE THAT PERTAINS TO PROCUREMENT

More information

CONTRACTING AND PURCHASING

CONTRACTING AND PURCHASING CONTRACTING AND PURCHASING 2017 Educational Series CONTRACTING AND PURCHASING INTRODUCTION GOODS AND SERVICES Texas Department of Transportation (TxDOT) contracting activities are established and controlled

More information

SECTION II. Collection and Analysis of Metro Contract Data

SECTION II. Collection and Analysis of Metro Contract Data SECTION II. Collection and Analysis of Metro Contract Data Section II describes the procurement areas and the relevant geographic market area defined for the Metro disparity study. BBC also identifies

More information

UC Berkeley Supplier Diversity Basics. Module 1: Policy and Regulatory Requirements

UC Berkeley Supplier Diversity Basics. Module 1: Policy and Regulatory Requirements UC Berkeley Supplier Diversity Basics Module 1: Policy and Regulatory Requirements Supplier Diversity Basics Curriculum For UC Berkeley Employees What you need to know: Module 1: Policy and Regulatory

More information

KDOT Procurement Guidelines for STP/CMAQ Funded Planning, Education, and Outreach Projects Effective 10/1/12

KDOT Procurement Guidelines for STP/CMAQ Funded Planning, Education, and Outreach Projects Effective 10/1/12 KDOT Procurement Guidelines for STP/CMAQ Funded Planning, Education, and Outreach Projects Effective 10/1/12 Purpose These guidelines are intended to guide the procurement of goods and consultant services

More information

APPENDIX A. DBE Information to be submitted with Proposal

APPENDIX A. DBE Information to be submitted with Proposal REQUEST FOR PROPOSALS TRANSPORTATION DEVELOPMENT ACT (TDA) TRIENNIAL PERFORMANCE AUDIT OF THE PUBLIC TRANSIT SYSTEMS AND THE COUNCIL OF GOVERNMENTS IN STANISLAUS COUNTY APPENDIX A DBE Information to be

More information

ADMINISTRATIVE PROCEDURES FOR M/WBE PARTICIPATION IN PROCUREMENT CONTRACTING. I. Bid Process - Competitive Bid Requirements

ADMINISTRATIVE PROCEDURES FOR M/WBE PARTICIPATION IN PROCUREMENT CONTRACTING. I. Bid Process - Competitive Bid Requirements Minority/Women Contracting 6Gx13-3G-1.04 ADMINISTRATIVE PROCEDURES FOR M/WBE PARTICIPATION IN PROCUREMENT CONTRACTING As stipulated in Board Rule 6Gx13-3G-1.01, Business Development and Assistance Program,

More information

SONOMA-MARIN AREA RAIL TRANSIT DISTRICT DISADVANTAGED BUSINESS ENTERPRISE (DBE) PROGRAM

SONOMA-MARIN AREA RAIL TRANSIT DISTRICT DISADVANTAGED BUSINESS ENTERPRISE (DBE) PROGRAM SONOMA-MARIN AREA RAIL TRANSIT DISTRICT DISADVANTAGED BUSINESS ENTERPRISE (DBE) PROGRAM Submitted To: FEDERAL TRANSIT ADMINISTRATION SAN FRANCISCO FEDERAL BUILDING 90 7TH STREET, SUITE 15-300 SAN FRANCISCO,

More information

Historically Underutilized Business (HUB) Strategic Plan

Historically Underutilized Business (HUB) Strategic Plan The University of Texas MD Anderson Cancer Center Historically Underutilized Business (HUB) Strategic Plan Fiscal Years 2015 2016 Prepared November 2015 FINAL.doc page 1 of 9 FINAL.doc page 2 of 9 EXTERNAL

More information

Submitted by: Demetria P. Scott & Tamika Reynolds

Submitted by: Demetria P. Scott & Tamika Reynolds Small Business Inclusion (SBI) Strategic Plan FY 2016-2017 UAB Enterprise-Wide Submitted by: Demetria P. Scott & Tamika Reynolds UAB Mission To be a research university and academic health center that

More information

Highway Construction Training and Disadvantaged Business Enterprise Program

Highway Construction Training and Disadvantaged Business Enterprise Program Highway Construction Training and Disadvantaged Business Enterprise Program 2015-2016 Biennial report October 2017 Highway Construction Training and Disadvantaged Business Enterprise Program 1 Prepared

More information

REQUEST FOR QUALIFICATIONS CONSULTING SERVICES FOR WALLA WALLA REGIONAL AIRPORT (ALW) WALLA WALLA, WASHINGTON. October 2, 2018

REQUEST FOR QUALIFICATIONS CONSULTING SERVICES FOR WALLA WALLA REGIONAL AIRPORT (ALW) WALLA WALLA, WASHINGTON. October 2, 2018 REQUEST FOR QUALIFICATIONS CONSULTING SERVICES FOR WALLA WALLA REGIONAL AIRPORT (ALW) WALLA WALLA, WASHINGTON October 2, 2018 The Port of Walla Walla, owner and operator of the Walla Walla Regional Airport,

More information

UNIVERSITY OF CALIFORNIA, SANTA BARBARA

UNIVERSITY OF CALIFORNIA, SANTA BARBARA SMALL BUSINESS MASTER SUBCONTRACTING PLAN (SUBMITTED IN Accordance with Public Law 95-507) THE REGENTS OF THE UNIVERSITY OF CALIFORNIA UCSB PROCUREMENT SERVICES, SAASB 3203 SANTA BARBARA, CA 93106-1150

More information

Doing Business. with

Doing Business. with Doing Business with SEPTEMBER 2016 CONTACTING VIA Procurement Department Equipment, Materials, Supplies, Professional Services, Rolling Stock, Construction, Engineering, and Architectural Design 800 W.

More information

Workshop on Small Business Certification at SFO. What You Need to Know and Why You Should Apply

Workshop on Small Business Certification at SFO. What You Need to Know and Why You Should Apply Workshop on Small Business Certification at SFO What You Need to Know and Why You Should Apply Learning Objectives Understand the Different Types of Certifications Learn What Certifications Apply at SFO

More information

Disadvantaged Business Enterprise Program Open House

Disadvantaged Business Enterprise Program Open House Disadvantaged Business Enterprise Program Open House Fiscal Year 2014 Program Update July 25, 2013 FY2014 DBE Program Update Agenda Welcome and Introduction Disadvantaged Business Enterprise Program Overview

More information

SOLANO COMMUNITY COLLEGE DISTRICT GOVERNING BOARD AGENDA ITEM REVISIONS TO MEASURE Q SMALL, LOCAL, AND DIVERSE BUSINESS PROGRAM PILOT PROGRAM

SOLANO COMMUNITY COLLEGE DISTRICT GOVERNING BOARD AGENDA ITEM REVISIONS TO MEASURE Q SMALL, LOCAL, AND DIVERSE BUSINESS PROGRAM PILOT PROGRAM AGENDA ITEM MEETING DATE June 6, 2018 SOLANO COMMUNITY COLLEGE DISTRICT GOVERNING BOARD AGENDA ITEM TO: SUBJECT: Members of the Governing Board REVISIONS TO MEASURE Q SMALL, LOCAL, AND DIVERSE BUSINESS

More information

Naugatuck Valley Council of Governments Disadvantaged Business Enterprises (DBE) Program. Fiscal Years

Naugatuck Valley Council of Governments Disadvantaged Business Enterprises (DBE) Program. Fiscal Years Naugatuck Valley Council of Governments Disadvantaged Business Enterprises (DBE) Program 2016-2018 Prepared by: The Naugatuck Valley Council of Governments Prepared: August 2012 Revised: April 2016 POLICY

More information

BizCentral USA. Benefits of the SBA 8a / MBE / WBE By Presenter Felix Zapata

BizCentral USA. Benefits of the SBA 8a / MBE / WBE By Presenter Felix Zapata Benefits of the SBA 8a / MBE / WBE By Presenter Felix Zapata Key Note Speaker Felix Zapata Director of Operations Administrator Mariana Davila Marketing Coordinator Benefits Agenda Eligibility for SBA

More information

Sheltered Market Program Description Background

Sheltered Market Program Description Background Sheltered Market Program Description (An Intergovernmental Program Implemented by the City of Portland, Multnomah County and Portland Development Commission) Background The United States Supreme Court

More information

THE DISADVANTAGED BUSINESS ENTERPRISE PROGRAM

THE DISADVANTAGED BUSINESS ENTERPRISE PROGRAM 888 17 th Street, NW, 11 th Floor Washington, DC 20006 Tel: (202) 857-1000 Fax: (202) 857-0200 THE DISADVANTAGED BUSINESS ENTERPRISE PROGRAM May 24, 2017 Presented by: Antonio R. Franco Jacqueline K. Unger

More information

BALTIMORE CITY PUBLIC SCHOOLS MINORITY AND WOMEN BUSINESS ENTERPRISE PROGRAM AND PROCEDURES MANUAL FOR STATE FUNDED PROJECTS

BALTIMORE CITY PUBLIC SCHOOLS MINORITY AND WOMEN BUSINESS ENTERPRISE PROGRAM AND PROCEDURES MANUAL FOR STATE FUNDED PROJECTS BALTIMORE CITY PUBLIC SCHOOLS MINORITY AND WOMEN BUSINESS ENTERPRISE PROGRAM AND PROCEDURES MANUAL FOR STATE FUNDED PROJECTS January 2014 MINORITY BUSINESS ENTERPRISE PROCEDURES FOR STATE FUNDED PUBLIC

More information

Small Business Utilization, FY January Legislative Report

Small Business Utilization, FY January Legislative Report Small Business Utilization, FY 2010-11 January 2012 Legislative Report UNIVERSITY of CALIFORNIA Budget and Capital Resources January 2012 UNIVERSITY OF CALIFORNIA Small Business Utilization Report, FY

More information

UNIVERSITY OF CALIFORNIA, SANTA BARBARA SMALL BUSINESS MASTER SUBCONTRACTING PLAN

UNIVERSITY OF CALIFORNIA, SANTA BARBARA SMALL BUSINESS MASTER SUBCONTRACTING PLAN TABLE OF CONTENTS PAGE 1. Background 3 2. Subcontracting Goals 3 3. Method Used to Develop Subcontracting Goals 4 4. Supplier Onboarding, Training & Outreach 5 5. Plan/Program Contacts & Responsibilities

More information

ARE YOU READY FOR PRIMETIME II? & SBE/DBE CERTIFICATION BASICS

ARE YOU READY FOR PRIMETIME II? & SBE/DBE CERTIFICATION BASICS ARE YOU READY FOR PRIMETIME II? & SBE/DBE CERTIFICATION BASICS PHX Small Business Workshop Series April 1, 2014 THE AVIATION DEPARTMENT S COMMITMENT to OUTREACH Valerie Churchwell, Small Business Outreach

More information

Federal Transit Administration (FTA) Overall DBE Goal-Setting Methodology

Federal Transit Administration (FTA) Overall DBE Goal-Setting Methodology Federal Transit Administration (FTA) Overall DBE Goal-Setting Methodology for FFY 2017-2019 Goal Period Submitted in fulfillment of: Title 49 Code of Federal Regulations Part 26 This analysis is prepared

More information

Disadvantaged Business Enterprise (DBE) Utilization on City Projects. Division of Affirmative Action

Disadvantaged Business Enterprise (DBE) Utilization on City Projects. Division of Affirmative Action Disadvantaged Business Enterprise (DBE) Utilization on City Projects Division of Affirmative Action 1 DBE Program Summary Annual gross receipts of: General contractor: $16.6M Specialty contractor: $7M

More information

Memorandum CAPITAL OF SILICON VALLEY

Memorandum CAPITAL OF SILICON VALLEY COUNCIL AGENDA: 10/06/15 ITEM: I CITY OF, SANlOSE Memorandum CAPITAL OF SILICON VALLEY TO: HONORABLE MAYOR AND CITY COUNCIL FROM: Kimberly J. Becker Barry Ng SUBJECT: SEE BELOW DATE: Approved D " e f/23

More information

REQUEST FOR QUALIFICATIONS FOR Energy Services Master Agreement

REQUEST FOR QUALIFICATIONS FOR Energy Services Master Agreement Request for Qualifications for Page 1 of 8 REQUEST FOR QUALIFICATIONS FOR For the RFQ Submittal Deadline: October 17, 2017 at 3:00 PM 1.1 INTRODUCTION: The is soliciting Statements of Qualifications (SOQ)

More information

EQUAL BUSINESS OPPORTUNITY/ CONTRACT COMPLIANCE DIVISION

EQUAL BUSINESS OPPORTUNITY/ CONTRACT COMPLIANCE DIVISION EQUAL BUSINESS OPPORTUNITY/ CONTRACT COMPLIANCE DIVISION VISION To Provide Comprehensive Assistance and Support for the Growth and Development of Jacksonville s Small and Emerging Businesses Jacksonville

More information

FLORIDA DEPARTMENT OF CORRECTIONS

FLORIDA DEPARTMENT OF CORRECTIONS FLORIDA DEPARTMENT OF CORRECTIONS MINORITY, WOMEN AND VETERAN-OWNED BUSINESS PARTICIPATION PLAN FISCAL YEAR 2012 2013 Kenneth S. Tucker Secretary FLORIDA DEPARTMENT OF CORRECTIONS MINORITY, WOMEN AND VETERAN-OWNED

More information

STATE OF CALIFORNIA DEPARTMENT OF TRANSPORTATION REQUEST FOR QUALIFICATIONS NOTICE NUMBER 03A2139

STATE OF CALIFORNIA DEPARTMENT OF TRANSPORTATION REQUEST FOR QUALIFICATIONS NOTICE NUMBER 03A2139 May 28, 2013 RFQ Number 03A2139 Page 1 of 6 STATE OF CALIFORNIA DEPARTMENT OF TRANSPORTATION REQUEST FOR QUALIFICATIONS NOTICE NUMBER 03A2139 Read carefully as the following revision has been made to this

More information

Contract Compliance Program

Contract Compliance Program Contract Compliance Program Including Equal Employment Opportunity Program Disadvantaged Business Enterprise Program Targeted Small Business Program Updated June 2017 The Des Moines City Council adopted

More information

Florida Department of Transportation 605 Suwannee Street Tallahassee, FL

Florida Department of Transportation 605 Suwannee Street Tallahassee, FL RICK SCOTT GOVERNOR Florida Department of Transportation 605 Suwannee Street Tallahassee, FL 32399-0450 JIM BOXOLD SECRETARY October 28, 2016 Ms. Hue T. Reynolds Executive Director Office of Supplier Diversity

More information

Historically Underutilized Business (HUB) Strategic Plan

Historically Underutilized Business (HUB) Strategic Plan The University of Texas MD Anderson Cancer Center Historically Underutilized Business (HUB) Strategic Plan Fiscal Years 2013 2014 Prepared June 2012 F:\Files\My Docs\Documents\HUB\2013 Strategic Plan\Strategic

More information

REQUEST FOR QUALIFICATIONS CONSULTING SERVICES FOR PULLMAN-MOSCOW REGIONAL AIRPORT PULLMAN, WA

REQUEST FOR QUALIFICATIONS CONSULTING SERVICES FOR PULLMAN-MOSCOW REGIONAL AIRPORT PULLMAN, WA July 12, 2018 REQUEST FOR QUALIFICATIONS CONSULTING SERVICES FOR PULLMAN-MOSCOW REGIONAL AIRPORT PULLMAN, WA The Pullman-Moscow Regional Airport (PMRA) is soliciting Statements of Qualifications (SOQ)

More information

APPENDIX B Consultant Title VI Evaluation Form

APPENDIX B Consultant Title VI Evaluation Form APPENDIX B Consultant Title VI Evaluation Form Introduction VDOT is a recipient of federal financial assistance. As a recipient, VDOT is required to comply with Title VI of the Civil Rights Act of 1964,

More information

STATE AID TO AIRPORTS PROGRAM NC DEPARTMENT OF TRANSPORTATION DIVISION OF AVIATION

STATE AID TO AIRPORTS PROGRAM NC DEPARTMENT OF TRANSPORTATION DIVISION OF AVIATION APRIL 2018 STATE AID TO AIRPORTS PROGRAM State Authorization: N.C.G.S. 63 NC DEPARTMENT OF TRANSPORTATION DIVISION OF AVIATION Agency Contact Person Program and Financial Betsy Beam, Grants Administrator

More information

REQUEST FOR QUALIFICATIONS FOR A PROFESSIONAL ARCHITECTURAL FIRM TO PROVIDE ARCHITECTURAL SERVICES FOR THE BZN YELLOWSTONE INTERNATIONAL AIRPORT

REQUEST FOR QUALIFICATIONS FOR A PROFESSIONAL ARCHITECTURAL FIRM TO PROVIDE ARCHITECTURAL SERVICES FOR THE BZN YELLOWSTONE INTERNATIONAL AIRPORT REQUEST FOR QUALIFICATIONS FOR A PROFESSIONAL ARCHITECTURAL FIRM TO PROVIDE ARCHITECTURAL SERVICES FOR THE BZN YELLOWSTONE INTERNATIONAL AIRPORT TERMINAL EXPANSION PROJECT FEBRUARY 2018 MORRISON-MAIERLE,

More information

Business Participation Plan FISCAL YEAR Justin Senior, Interim Secretary

Business Participation Plan FISCAL YEAR Justin Senior, Interim Secretary Business Participation Plan FISCAL YEAR 2016-2017 Justin Senior, Interim Secretary TABLE OF CONTENTS Subject PAGE Mission, Vision and Statement of Commitment.... 1 Officials Responsible for Monitoring

More information

SOUTHERN UTE INDIAN TRIBE REQUEST FOR PROPOSALS (RFP) FOR ENVIRONMENTAL CONSULTING SERVICES FOR

SOUTHERN UTE INDIAN TRIBE REQUEST FOR PROPOSALS (RFP) FOR ENVIRONMENTAL CONSULTING SERVICES FOR SOUTHERN UTE INDIAN TRIBE REQUEST FOR PROPOSALS (RFP) FOR ENVIRONMENTAL CONSULTING SERVICES FOR Asbestos Remediation of the Old Cafeteria Building Date of RFP Release March 21, 2012 April 25, 2012 - Proposals

More information

REQUEST FOR PROPOSAL FOR. Document Management System for a Tribal Governmental Organization PROPOSAL NO. FY2012/041

REQUEST FOR PROPOSAL FOR. Document Management System for a Tribal Governmental Organization PROPOSAL NO. FY2012/041 REQUEST FOR PROPOSAL FOR Document Management System for a Tribal Governmental Organization PROPOSAL NO. FY2012/041 BY SPOKANE TRIBE OF INDIANS PURCHASING/PROPERTY DEPARTMENT 6195 FORD/WELLPINIT RD PO BOX

More information

Annual Supplier Representations & Certifications

Annual Supplier Representations & Certifications Subcontractor Vendor Action Code (A=Add U=Update) Subcontractor/Vendor # Procurement of material, services and supplies for a United States Government Contract requires that prime contractors, subcontractors

More information

COUNTY OF LOS ANGELES

COUNTY OF LOS ANGELES COUNTY OF LOS ANGELES DEPARTMENT OF PUBLIC WORKS JAMES A. NOYES, Director 900 SOUTH FREMONT AVENUE ALHAMBRA, CALIFORNIA 91803-1331 Telephone: (626) 458-5100 ADDRESS ALL CORRESPONDENCE TO: P.O. BOX 1460

More information

Small Business Subcontracting Plans & Reporting

Small Business Subcontracting Plans & Reporting Small Business Subcontracting Plans & Reporting A Pre award Plan with Post Award Ramifications Session Expectations History of this requirement Policy and Regulations behind Small Business Subcontracting

More information